CN103001324A - Method for optimizing scheduling and handling of power grid accidents - Google Patents

Method for optimizing scheduling and handling of power grid accidents Download PDF

Info

Publication number
CN103001324A
CN103001324A CN2012103528621A CN201210352862A CN103001324A CN 103001324 A CN103001324 A CN 103001324A CN 2012103528621 A CN2012103528621 A CN 2012103528621A CN 201210352862 A CN201210352862 A CN 201210352862A CN 103001324 A CN103001324 A CN 103001324A
Authority
CN
China
Prior art keywords
accident
power grid
tract
user
network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103528621A
Other languages
Chinese (zh)
Inventor
张劲松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Original Assignee
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Shanghai Municipal Electric Power Co filed Critical State Grid Corp of China SGCC
Priority to CN2012103528621A priority Critical patent/CN103001324A/en
Publication of CN103001324A publication Critical patent/CN103001324A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/20Systems supporting electrical power generation, transmission or distribution using protection elements, arrangements or systems

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A method for optimizing scheduling and handling of power grid accidents includes the steps of acquiring power grid account information from a power supply company system; acquiring power grid topological information from the power supply company system; acquiring power grid load information from the power supply company system; managing information of users important to a power grid; subjecting 220KV substations and 110KV substations governed by the power grid of a power supply company and a corresponding power distribution network to accident plan analysis so as to achieve fast accident isolation and optima fast automatic restoration of the power grid after accidents; and subjecting the 220KV substations and 110KV substations governed by the power grid of a power supply company and the corresponding power distribution network to accident reach analysis. Accident handling plans are automatically updated based on a network model of load and user weight and according to data update conditions, so that anti-accident operability is greatly improved. The method is considerably advanced and is applicable to various fields of scheduling and handling of power grid accidents.

Description

A kind of optimization method of power grid accident dispatch deal
Technical field
The present invention relates to a kind of scheduling in breakdown state processing method, relate in particular to a kind of optimization method that is applied to the power grid accident dispatch deal.
Background technology
At present, each electric company transfers the merging of transferring with the district in ground, so that the compass of competency of each network stations improves greatly at present, the managerial skills of dispatching of power netwoks has been had higher requirement.Distribution network from the transformer station of voltage levels to low-voltage, more complicated at the aspect that relates to aspect the scheduling in breakdown state processing, sometimes only depend on the dispatcher to electrical network be in the push to process the consequence that can not imagine that might cause, so require to have unified comprehensive district transfer the ground blending and the optimization method of accident.
Summary of the invention
For the compass of competency that solves each above-mentioned network stations improves the problem that the scheduling in breakdown state that causes is processed increasingly complex greatly, the invention provides a kind of optimization method of power grid accident dispatch deal, by analyzing the Accident Handling Method of present dispatching management scope, can be dispatcher's fast processing fault, restoring electricity provides foundation, when guaranteeing that the electrical network sudden accident occurs, can in time take more effective measures, idiographic flow of the present invention is as described below:
A kind of optimization method of power grid accident dispatch deal may further comprise the steps:
1) from electric company's system acquisition electrical network account information;
2) from electric company's system acquisition power network topology information;
3) from electric company's system acquisition network load information;
Above-mentioned technology has been carried out the whole network modeling to grid equipment account, topology, the load of electric company.Realized the power grid accident analytical method based on segmentation, contact, user's weight.
4) management electrical network responsible consumer information;
Customer information control system has good opening, can support to meet the relevant interface of international standard and industrywide standard, can network and communication with other related systems, supports the application development platform of standard, has good transfer ability.
The 220KV transformer station of 5) electric company's electrical network being administered, 110KV transformer station and corresponding power distribution network carry out the accident prediction analysis, to reach fault fast isolation and optimum fast automatic the restoring electricity of electrical network after the accident;
The 220KV transformer station of 6) electric company's electrical network being administered, individual 110KV transformer station and corresponding power distribution network carry out the accident impact surface analysis.
Optimization method according to a kind of power grid accident dispatch deal of the present invention is characterized in that, described step 1 to the system of electric company in the step 3 all adopts logical layer, presentation layer hierarchical architecture design.
Optimization method according to a kind of power grid accident dispatch deal of the present invention is characterized in that, has adopted the prime minister to carry out the full electric network modeling in described step 5 and the step 6, forms the design of segmentation and contact, this design specific as follows:
1) according to fault point, section, circuit, obtain all subsegments of faulty section, all subsegments of each subsegment and subsegment form a tract collection, need this tract collection of record and fault section boundary (need to open a sluice gate in accident prediction), and tract concentrates the user in all sections to affect the user;
2) search the downstream section boundary, obtain non-the line facility on each border, and supply line and the rated load of searching for this equipment, obtain turning for circuit of this tract, turn for equipment (need in accident prediction, close a floodgate), wherein, the number=tract 1 of accident prediction can turn and counts * tract 2 for circuit and can turn turned confession circuit for circuit * tract X; Operating sequence is that faulty section and upstream boundary are pulled open in each accident prediction, and the tract upstream boundary is pulled open, and tract turns the confession line boundary and closes;
3) the dead electricity user is the faulty section user, the user that the accident impact user concentrates for all tracts.
Use the optimization method of a kind of power grid accident dispatch deal of the present invention, obtained following beneficial effect:
1. the optimization method of a kind of power grid accident dispatch deal of the present invention, the transformer station of administering for present electrical network and corresponding power distribution network carry out accident prediction to be analyzed, and has optimized the dispatch deal scheme;
2. the optimization method of a kind of power grid accident dispatch deal of the present invention, the actual load situation of the next stage power supply transformer station that affects according to each station, from the stability of a system, power supply reliability, the several respects such as loss of supply amount work out optimized corresponding accident prediction (being sub-divided into the 10KV circuit), to reach fault fast isolation and optimum fast automatic the restoring electricity of electrical network after the accident.
Description of drawings
Fig. 1 is the schematic layout pattern of the optimization method of a kind of power grid accident dispatch deal of the present invention;
Fig. 2 is the system configuration schematic diagram of the optimization method of a kind of power grid accident dispatch deal of the present invention.
Embodiment
Be further described below in conjunction with the optimization method of drawings and Examples to a kind of power grid accident dispatch deal of the present invention.
Embodiment
As depicted in figs. 1 and 2, the optimization method of a kind of power grid accident dispatch deal of the present invention comprises following part:
1) from electric company's system acquisition electrical network account information;
2) from electric company's system acquisition power network topology information;
3) from electric company's system acquisition network load information;
Above-mentioned technology has been carried out the whole network modeling to grid equipment account, topology, the load of electric company.Realized the power grid accident analytical method based on segmentation, contact, user's weight.
These information comprise in the present embodiment:
1. faulty equipment input
The input of fault content adopts text search location, figure to click the mode of location, and chosen content comprises station equipment, line sectionalizing, line facility etc.
2. accident treatment prediction scheme content:
It is as follows that fault is turned over the electricity operation:
Distribution Network Failure: comprise the Fault Isolation operation, turn over the electricity operation, line load branch mode, the analysis of load transfer case.
The power transformation fault: the accident treatment of outlet is identical with distribution,
The defencive function because power transformation is autotomyed, the fault on the bus does not need to consider prediction scheme, and list should be presented in the scope of accident impact
The information of accident impact scope: the input of fault content adopts text search location, figure to click the mode of location, and chosen content comprises station equipment, line sectionalizing, line facility etc.
4) management electrical network responsible consumer information;
Customer information control system has good opening, can support to meet the relevant interface of international standard and industrywide standard, can network and communication with other related systems, supports the application development platform of standard, has good transfer ability.
List the interior distribution large user of power failure range of accident impact in the present embodiment, respectively turn over the user profile of electric scheme impact: comprise all power failure large user tabulations (comprising title, classification, load, contact method (can be revised by scheduling) etc.), responsible consumer, duplicate supply user, the electric user of guarantor can import the Excel file by the user and adjust, and list respectively or quantity statistics among the user.
The 220KV transformer station of 5) electric company's electrical network being administered, 110KV transformer station and corresponding power distribution network carry out the accident prediction analysis, to reach fault fast isolation and optimum fast automatic the restoring electricity of electrical network after the accident;
The 220KV transformer station of 6) electric company's electrical network being administered, individual 110KV transformer station and corresponding power distribution network carry out the accident impact surface analysis.
The subordinate power station that power transformation accident in the present embodiment the causes action of autotomying
The 35KV Above Transmission Lines has system's action of autotomying, and system should list the action (comprising switchyard) of autotomying in all subordinate power stations that accident causes: electric system is operating as bar cutter, looped network cabinet switch operation.
Demonstration information after the power transformation accident is selected:
Comprise automatic transfer case 1.220KV accident must be listed coverage information, responsible consumer (important, two electricity, guarantor's electricity) situation user can by selecting electric pressure, limit the displaying contents scope.
2.35KV accident must be listed coverage information and list content request consistent (showing that coverage is to switchyard rank, bar cutter problem) with the 220KV accident.
3.10KV the coverage information that line fault is listed is listed content request consistent (the demonstration coverage need be considered ring main unit) with the 220KV accident
Above-mentioned turning over electric scheme electrical network final result explanation only need to being provided of providing, the action sequence of concrete protection operation is by the scheduling artificial treatment.
Carry out at last data importing.
Optimization method according to a kind of power grid accident dispatch deal of the present invention is characterized in that, described step 1 to the system of electric company in the step 3 all adopts logical layer, presentation layer hierarchical architecture design.
Optimization method according to a kind of power grid accident dispatch deal of the present invention is characterized in that, has adopted the prime minister to carry out the full electric network modeling in described step 5 and the step 6, forms the design of segmentation and contact, this design specific as follows:
1) according to fault point, section, circuit, obtain all subsegments of faulty section, all subsegments of each subsegment and subsegment form a tract collection, need this tract collection of record and fault section boundary (need to open a sluice gate in accident prediction), and tract concentrates the user in all sections to affect the user;
2) search the downstream section boundary, obtain non-the line facility on each border, and supply line and the rated load of searching for this equipment, obtain turning for circuit of this tract, turn for equipment (need in accident prediction, close a floodgate), wherein, the number=tract 1 of accident prediction can turn and counts * tract 2 for circuit and can turn turned confession circuit for circuit * tract X; Operating sequence is that faulty section and upstream boundary are pulled open in each accident prediction, and the tract upstream boundary is pulled open, and tract turns the confession line boundary and closes;
3) the dead electricity user is the faulty section user, the user that the accident impact user concentrates for all tracts.
The optimization method of a kind of power grid accident dispatch deal of the present invention can also be set up the whole network model based on load and user's weight in the PMS system, and automatically upgrades the accident treatment prediction scheme according to the update status of data, has greatly increased the operability of anti-accident.Traffic department of most domestic electric company accident treatment emergency planning method static state or manual analysis and maintenance has suitable advance relatively, is applicable to various power grid accident dispatch deals field.

Claims (3)

1. the optimization method of a power grid accident dispatch deal may further comprise the steps:
1) from electric company's system acquisition electrical network account information;
2) from electric company's system acquisition power network topology information;
3) from electric company's system acquisition network load information;
4) management electrical network responsible consumer information;
The 220KV transformer station of 5) electric company's electrical network being administered, 110KV transformer station and corresponding power distribution network carry out the accident prediction analysis, to reach fault fast isolation and optimum fast automatic the restoring electricity of electrical network after the accident;
The 220KV transformer station of 6) electric company's electrical network being administered, individual 110KV transformer station and corresponding power distribution network carry out the accident impact surface analysis.
2. the optimization method of a kind of power grid accident dispatch deal as claimed in claim 1 is characterized in that, described step 1 to the system of electric company in the step 3 all adopts logical layer, presentation layer hierarchical architecture design.
3. the optimization method of a kind of power grid accident dispatch deal as claimed in claim 1 is characterized in that, has adopted the prime minister to carry out the full electric network modeling in described step 5 and the step 6, forms the design of segmentation and contact, this design specific as follows:
1) according to fault point, section, circuit, obtain all subsegments of faulty section, all subsegments of each subsegment and subsegment form a tract collection, need this tract collection of record and fault section boundary (need to open a sluice gate in accident prediction), and tract concentrates the user in all sections to affect the user;
2) search the downstream section boundary, obtain non-the line facility on each border, and supply line and the rated load of searching for this equipment, obtain turning for circuit of this tract, turn for equipment (need in accident prediction, close a floodgate), wherein, the number=tract 1 of accident prediction can turn and counts * tract 2 for circuit and can turn turned confession circuit for circuit * tract X; Operating sequence is that faulty section and upstream boundary are pulled open in each accident prediction, and the tract upstream boundary is pulled open, and tract turns the confession line boundary and closes;
3) the dead electricity user is the faulty section user, the user that the accident impact user concentrates for all tracts.
CN2012103528621A 2012-09-19 2012-09-19 Method for optimizing scheduling and handling of power grid accidents Pending CN103001324A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103528621A CN103001324A (en) 2012-09-19 2012-09-19 Method for optimizing scheduling and handling of power grid accidents

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103528621A CN103001324A (en) 2012-09-19 2012-09-19 Method for optimizing scheduling and handling of power grid accidents

Publications (1)

Publication Number Publication Date
CN103001324A true CN103001324A (en) 2013-03-27

Family

ID=47929585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103528621A Pending CN103001324A (en) 2012-09-19 2012-09-19 Method for optimizing scheduling and handling of power grid accidents

Country Status (1)

Country Link
CN (1) CN103001324A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104166937A (en) * 2013-11-26 2014-11-26 贵州黔驰电力信息技术有限公司 Automatic power grid ice melting maintenance schedule arranging method
CN111814999A (en) * 2020-07-08 2020-10-23 上海燕汐软件信息科技有限公司 Fault work order generation method, device and equipment
CN113451988A (en) * 2021-06-02 2021-09-28 合占电力有限公司 Modeling based on upgrading and transforming system equipment

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104166937A (en) * 2013-11-26 2014-11-26 贵州黔驰电力信息技术有限公司 Automatic power grid ice melting maintenance schedule arranging method
CN104166937B (en) * 2013-11-26 2017-08-04 贵州电网公司电力调度控制中心 A kind of power network ice-melt repair schedule automatic editing method
CN111814999A (en) * 2020-07-08 2020-10-23 上海燕汐软件信息科技有限公司 Fault work order generation method, device and equipment
CN111814999B (en) * 2020-07-08 2024-01-16 上海燕汐软件信息科技有限公司 Fault work order generation method, device and equipment
CN113451988A (en) * 2021-06-02 2021-09-28 合占电力有限公司 Modeling based on upgrading and transforming system equipment
CN113451988B (en) * 2021-06-02 2022-05-27 合占电力有限公司 Modeling method based on upgrading and modifying system equipment

Similar Documents

Publication Publication Date Title
Yuan et al. Smart grids in China
CN102521398B (en) Modeling method for substation-dispatching center two-level distributed type power grid
CN102236841B (en) Method for handling accidents of electric power system
CN102522819B (en) Record wave pattern modeling method for fault record device of intelligent transformer substation
CN104821662B (en) A kind of various dimensions intelligent error preventing system and method
CN103199521B (en) Power network planning construction method based on network reconstruction and optimized load-flow simulating calculation
CN109560543A (en) Dynamic contingency prediction scheme analysis method and system based on main distribution Integrated Model
CN110674282B (en) Expert knowledge rule base-based one-key sequential control operation order intelligent simulation method
CN102931727A (en) Topological anti-error check method of power dispatching master station type integrated intelligent anti-error system
CN104184207A (en) Integrated control method of digitalized traction substation of electrified railway
CN102723780B (en) Energy management system for distribution network of power system
CN103093391A (en) City power distribution network arranging method
Quiros-Tortos et al. Geo-information is power: Using geographical information systems to assess rooftop photovoltaics in Costa Rica
CN103872770A (en) Different power supply region feeder automation collocation method based on wiring mode
CN103001324A (en) Method for optimizing scheduling and handling of power grid accidents
Chai et al. Application of Digital Twin and Hologram Technology to Achieve Distribution Network Reliability Forecast
CN202584219U (en) A power distribution production and business integrated system with integration, intelligentization, and visualization
CN103647279B (en) A kind of forecast failure set creation method based on plant stand wiring information
CN105259751B (en) A kind of electric power thematic map update method based on Real-Time Switch action
CN114841627B (en) Maintenance plan checking method, device, equipment and storage medium
CN102957206B (en) Many granularities off-line model joining method of smart grid-oriented
CN204679830U (en) A kind of anti-error and intend the off-line type scheduling operation bill system of ticket training based on scene
Qiuling China Southern Power Grid’s power supply reliability development strategy under digital transformation
CN202886976U (en) Region-county integrated intelligent operating ticket system
CN111697573A (en) Power grid section power supply range analysis method based on topology tracking

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130327