CN102995670B - Soil excavation rectification construction monitoring method of existing building - Google Patents
Soil excavation rectification construction monitoring method of existing building Download PDFInfo
- Publication number
- CN102995670B CN102995670B CN201210376889.4A CN201210376889A CN102995670B CN 102995670 B CN102995670 B CN 102995670B CN 201210376889 A CN201210376889 A CN 201210376889A CN 102995670 B CN102995670 B CN 102995670B
- Authority
- CN
- China
- Prior art keywords
- building
- formula
- rectification
- value
- correction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The invention belongs to the technical field of a reinforcement project of a building structure, and particularly relates to a monitoring method in soil excavation rectification construction of the existing building. The monitoring method comprises the following steps of: comparing and verifying the building inclination and sedimentation variation of the building actually measured in the rectification process of the building with the theoretically calculated inclination and sedimentation variation, carrying out soil excavation rectification on the building according to the change degree when the numerical values are consistent; checking and finding out the reasons for difference when the difference of the numerical values is large, retesting and retrying until the numerical values are consistent; carrying out soil excavation rectification on the building according to the inclination degree consistence value until the building accords with the vertical standard request, wherein the actually measured value is obtained by testing the inclination degree of the building by a total station, and the theoretically calculated value is obtained according to the method and equation. By adopting the soil excavation rectification construction monitoring method of the existing building, the scientificity and accuracy of the soil excavation rectification are improved; and the rectification efficiency is higher, and the rectification quality is better.
Description
Technical field
The invention belongs to building structure strengthening field of engineering technology, specifically relate to a kind of method for supervising existing building carried out in soil digging Deviation Correction Construction.
Background technology
Soil digging correction is by the little side soil digging of building deformation, remove the local stress in foundation soil, cause the stresses re-distribution of the soil body, the side foundation stress little at foundation settlement increases, thus produce larger compressive strain, make building reach the object of slowly correction.
Soil digging method for correcting error is generally used for the building of shallow foundation, and foundation soil is advisable with soil such as cohesive soil, silt, plain fill, mucky soil, sandy soils.
The engineering object that soil digging correction is suitable for mainly contains:
Ground soil property is uneven, and the inclination that there is soft layer or the dark pool is transfinited house.
Base foundation design and type selecting improper, position of centre of gravity, settlement joint etc. arrange the improper building causing tilting to transfinite.
Construction technology is improper or construction quality is inferior, and the too fast ground that causes of constructing is extruded, and a large amount of preloading in building side causes certain to roll the building tiltedly transfinited.
Mud or soft clay region, the building demolition adjacent with certain building, local off-load causes ground lateral compression to cause the building tilting to transfinite.
Building foundation groundwater table changes, and underflow takes away the soil body below building, causes land subsidence, subsides and building inclination is transfinited.
The building inclination that when landslide, earthquake, the natural calamity such as liquefaction of soil mass causes transfinites.
The applicable requirement of soil digging correction to building: building is approximately a rigid body, is out of shape with base integral.Relative contour of building size, sedimentation, inclination etc. are small deformation.
Conventional soil digging deviation correcting technology can only for the numerical value of the sedimentation of certain single observation point, tilt quantity in soil digging process, by virtue of experience judging that the deflection that the structural strain's amount and needing afterwards of building is corrected, final correction reach criterion of acceptability is the restriction that the tilt quantity of each observation point of building all reaches regulation and stipulation.Measuring error or error that this kind of reinforcement and rectification flow process is difficult to seeing time keeping instrument judge, and cannot hold in overall aspect building, easily cause erroneous judgement, easily cause irrational soil digging, increase soil digging number of times.
Summary of the invention
The object of this invention is to provide a kind of existing building soil digging Deviation Correction Construction method for supervising, cannot the deflection of building be held in overall aspect to overcome existing soil digging deviation correcting technology and easily cause the problem of erroneous judgement.
The object of the invention is to be achieved through the following technical solutions:
A kind of existing building soil digging Deviation Correction Construction method for supervising, is characterized in that:
Described method for supervising comprises and contrasting the actual test value of the building inclination in rectifying of leaned building process and calculated value, examines;
When both numerical value are consistent: by inclined degree, soil digging correction is carried out to building;
When both numerical value difference are larger: check and find difference reason, repetition measurement, double calculation are consistent to both, carry out soil digging correction by inclined degree homogeneity value to building;
Until building to meet standard-required vertical;
Described actual test value is tested by the inclined degree of total powerstation to building;
Described calculated value obtains by following method and formula:
In the corner of structure foundation, corner and sudden change place, at least 10 observation points are set,
Inclination building rectification by horizontal control network is measured, measurement of the level records each settlement observation point plane coordinates and elevation, is set to A before correction starts
11(x
11, y
11, z
11), A
12(x
12, y
12, z
12) ... A
1n(x
1n, y
1n, z
1n), get the Z-direction value of relative initial observation coordinate
As the datum π 1 before correction,
Settlement observation point coordinates then after adjustment is A
11(x
11, y
01, z
0), A
12(x
12, y
12, z
0) ... A
1n(x
1n, y
1n, z
0), their z have modified s1=z respectively to relief displacement
11-z
0, s2=z
12-z
0sn=z
1n-z
0, s=(s1, s2 ... sn)
tbe called index vector, wherein si moves down for just representing, and si is for negative representative moves, and so, the initial elevation of all settlement observation points is all corrected to an initial water plane π
1(z=z
0) on;
After correction starts, building is rectified a deviation, and relative initial plane changes to π i plane, if π i equation is:
π
i: a x+b y-z+c=0(formula 4.1-2)
Construct a function F:
F=[(z
i1-s1)-(a x
i1+b y
i1+c)]
2+[(z
i2-s2)-(a x
i2+b y
i2+c)]
2+……
[(z
in-sn)-(a x
in+ b
yin+c)]
2(formula 4.1-3)
F gets minimum value season
Solve formula 4.1-5 ternary system of linear equations, if a, b, c solve, then the clinoplain that i-th observed result is determined is
π
i: ax+by-z+c=0(formula 4.1-6)
Itself and z0 plane intersection line L1 are:
Angle between L1 and x-axis
ε=atan(-a/b) (formula 4.1-7)
This plane normal and z-axis angle γ are
Then
△ K=tan γ (formula 4.1-9)
△ K
x=△ Kcos (ε+pi/2) (formula 4.1-10)
△ K
y=△ Ksin (ε+pi/2) (formula 4.1-11)
Wherein
△ K
xfor this x-axis to slope change
△ Ky be this y-axis to slope change
△ K is the total slope change of this point.
Further, at least 16 observation points are set.
Further, think that difference is larger when the difference of described actual test value and calculated value numerical value is more than or equal to 10% of a less value in both numerical value.
The present invention is according to the above-mentioned △ K calculated
x, △ Ky and △ K slope change, contrast the gradient of actual building, when both numerical value are consistent, by inclined degree, soil digging correction carried out to building; When both numerical value difference are larger, check and find difference reason, repetition measurement, double calculation are consistent to both, carry out soil digging correction by inclined degree homogeneity value to building.
Beneficial effect of the present invention: the invention provides a kind of new soil digging correction monitoring and Numerical Methods, building inclination axle and each tilt quantity, settling amount put can be calculated, and determine the arrangement in follow-up soil digging amount and soil digging hole with this, thus work progress is optimized.By the science, the accuracy that invention increases soil digging correction, correction efficiency is higher, correction better quality, and this method proposes the method that digital quantization weighs inclined degree first, significant for soil digging deviation correcting technology.
Accompanying drawing explanation
Fig. 1 is an embodiment of existing building soil digging Deviation Correction Construction method for supervising of the present invention, and the ground of building arranges the arrangement diagram of multiple observation point;
Fig. 2 is that building is rectified a deviation, and relative initial plane π changes to the structural representation of π 1 plane, shows the intersection of two planes in figure;
Fig. 3 is the ground arrangement diagram of one embodiment of the invention building;
Fig. 4 is showing building former and later two positions in soil digging process, the elevational schematic view that horizontal direction is observed;
Fig. 5 is that display one embodiment calculates the building inclination face of gained and the intersection schematic diagram of initial plane π after observation;
Fig. 6 is one group of sloping shaft floor map that an embodiment draws as calculated afterwards;
Fig. 7 is an embodiment structure foundation plane correction change schematic diagram.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is described in further detail:
Embodiment 1, in the corner of structure foundation, corner and sudden change place, arranges 20 observation points, and by observation, the observation data of front 5 phases is as shown in table 1:
Table 1 example 1 observation data
Period | X | Y | Z1 | Z2 | Z3 | Z4 | Z5 |
A1 | 158.400 | 103.518 | 10.0809 | 10.0760 | 10.0398 | 10.0250 | 10.0250 |
A2 | 159.140 | 101.300 | 10.1010 | 10.0948 | 10.0496 | 10.0312 | 10.0312 |
A3 | 198.892 | 101.300 | 10.0749 | 10.0703 | 10.0368 | 10.0231 | 10.0151 |
A4 | 200.400 | 102.557 | 10.0622 | 10.0584 | 10.0306 | 10.0192 | 10.0112 |
A5 | 200.400 | 116.249 | 9.9352 | 9.9392 | 9.9682 | 9.9800 | 9.9670 |
A6 | 198.892 | 117.300 | 9.9265 | 9.9310 | 9.9639 | 9.9773 | 9.9723 |
A7 | 191.186 | 117.300 | 9.9319 | 9.9361 | 9.9665 | 9.9790 | 9.9799 |
A8 | 190.400 | 116.658 | 9.9380 | 9.9418 | 9.9695 | 9.9809 | 9.9828 |
A9 | 189.702 | 113.259 | 9.9700 | 9.9718 | 9.9853 | 9.9907 | 9.9914 |
A10 | 185.210 | 113.259 | 9.9729 | 9.9746 | 9.9867 | 9.9917 | 9.9917 |
A11 | 184.400 | 116.436 | 9.9440 | 9.9474 | 9.9725 | 9.9827 | 9.9842 |
A12 | 183.725 | 117.300 | 9.9364 | 9.9403 | 9.9688 | 9.9804 | 9.9824 |
A13 | 175.144 | 117.300 | 9.9421 | 9.9456 | 9.9715 | 9.9821 | 9.9831 |
A14 | 174.400 | 115.951 | 9.9551 | 9.9578 | 9.9779 | 9.9861 | 9.9861 |
A15 | 173.660 | 113.300 | 9.9802 | 9.9814 | 9.9902 | 9.9939 | 9.9948 |
A16 | 169.208 | 113.259 | 9.9831 | 9.9841 | 9.9917 | 9.9948 | 9.9958 |
A17 | 168.400 | 116.475 | 9.9542 | 9.9570 | 9.9775 | 9.9859 | 9.9852 |
A18 | 167.406 | 117.300 | 9.9472 | 9.9504 | 9.9740 | 9.9837 | 9.9849 |
A19 | 159.350 | 117.300 | 9.9524 | 9.9554 | 9.9766 | 9.9853 | 9.9853 |
A20 | 158.400 | 116.255 | 9.9628 | 9.9651 | 9.9817 | 9.9885 | 9.9885 |
Note: 1. in table, the unit of X, Y, Zi is m;
2. be the observation data of front 6 phases in table, with the Z1 phase for reference.
After calculating by the technology of the present invention method, the conclusion drawn is as follows:
Table 2 embodiment 1 result of calculation
Z1 | Z2 | Z3 | Z4 | Z5 | |
a | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 |
b | 0.000 | 0.001 | 0.005 | 0.006 | 0.007 |
c | 9.978 | 9.907 | 9.395 | 9.186 | 9.187 |
Kx(‰) | 0.000 | 0.040 | 0.333 | 0.453 | 0.295 |
Ky(‰) | 0.000 | 0.568 | 4.717 | 6.412 | 6.641 |
Total K (‰) | 0.000 | 0.570 | 4.729 | 6.428 | 6.647 |
The related conclusions drawn by table 2 is see seeing Fig. 6, Fig. 7
The difference maximum value of data and actual measurement is 9.2mm as calculated, and difference is 3%, is less than 10%, can think that data are reliable, namely presses calculated value and continues soil digging.
Embodiment 2, in the corner of structure foundation, corner and sudden change place, arranges 16 observation points, and by observation, the observation data of front 5 phases is as shown in table 2:
Table 3 embodiment 2 observation data
Period | X | Y | Z1 | Z2 | Z3 | Z4 | Z5 |
A1 | 184.7863 | 128.5912 | 15.0398 | 15.0224 | 15.0180 | 15.0128 | 15.0087 |
A2 | 185.1013 | 126.6317 | 15.0496 | 15.0279 | 15.0225 | 15.0160 | 15.0109 |
A3 | 224.7331 | 127.7570 | 15.0368 | 15.0207 | 15.0167 | 15.0118 | 15.0081 |
A4 | 225.7910 | 129.0991 | 15.0306 | 15.0172 | 15.0139 | 15.0098 | 15.0067 |
A5 | 226.1995 | 142.3721 | 14.9682 | 14.9821 | 14.9856 | 14.9898 | 14.9930 |
A6 | 225.5165 | 143.9643 | 14.9639 | 14.9797 | 14.9836 | 14.9884 | 14.9921 |
A7 | 217.6655 | 142.4591 | 14.9665 | 14.9812 | 14.9848 | 14.9892 | 14.9927 |
A8 | 216.5650 | 143.0229 | 14.9695 | 14.9829 | 14.9862 | 14.9902 | 14.9933 |
A9 | 214.9326 | 138.4853 | 14.9853 | 14.9917 | 14.9933 | 14.9953 | 14.9968 |
A10 | 210.2731 | 138.7426 | 14.9867 | 14.9925 | 14.9940 | 14.9957 | 14.9971 |
A11 | 209.4968 | 142.6816 | 14.9725 | 14.9845 | 14.9875 | 14.9912 | 14.9940 |
A12 | 210.1986 | 143.5231 | 14.9688 | 14.9824 | 14.9859 | 14.9900 | 14.9932 |
A13 | 201.4223 | 143.4795 | 14.9715 | 14.9840 | 14.9871 | 14.9908 | 14.9938 |
A14 | 199.4374 | 141.7330 | 14.9779 | 14.9876 | 14.9900 | 14.9929 | 14.9952 |
A15 | 200.0100 | 138.6697 | 14.9902 | 14.9945 | 14.9956 | 14.9969 | 14.9979 |
A16 | 194.2928 | 139.7977 | 14.9917 | 14.9953 | 14.9962 | 14.9973 | 14.9982 |
After calculating by the technology of the present invention method, the conclusion drawn is as follows: table 4 embodiment 2 result of calculation
Z1 | Z2 | Z3 | Z4 | Z5 | |
a | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 |
b | 0.000 | 0.002 | 0.002 | 0.003 | 0.004 |
c | 14.992 | 14.701 | 14.628 | 14.541 | 14.472 |
Kx(‰) | 0.000 | 0.103 | 0.129 | 0.160 | 0.184 |
Ky(‰) | 0.000 | 1.976 | 2.470 | 3.062 | 3.527 |
Total K (‰) | 0.000 | 1.978 | 2.473 | 3.067 | 3.531 |
The related conclusions drawn by table 2 is see seeing Fig. 6, Fig. 7.
The difference maximum value of data and actual measurement is 3.2mm as calculated, and difference is 4.5%, is less than 10%, can think that data are reliable, namely press calculated value and continue soil digging.
Also can show that example 1 is too fast in the rate of settling change of the 3rd, 4,5 phases by example 1,2 contrast, should less soil digging amount.
Claims (2)
1. an existing building soil digging Deviation Correction Construction method for supervising, is characterized in that:
Described method for supervising comprises and contrasting the actual test value of the building inclination in rectifying of leaned building process and calculated value, examines;
When both numerical value are consistent: by inclined degree, soil digging correction is carried out to building;
When the difference of both numerical value is more than or equal to 10% of a less value in both numerical value: check and find difference reason, repetition measurement, double calculation are consistent to both, carry out soil digging correction by inclined degree homogeneity value to building;
Until building to meet standard-required vertical;
Described actual test value is tested by the inclined degree of total powerstation to building;
Described calculated value obtains by following method and formula:
In the corner of structure foundation, corner and sudden change place, at least 10 observation points are set,
Inclination building rectification by horizontal control network is measured, measurement of the level records each settlement observation point plane coordinates and elevation, is set to A before correction starts
11(x
11, y
11, z
11), A
12(x
12, y
12, z
12) ... A
1n(x
1n, y
1n, z
1n), get the Z-direction value of relative initial observation coordinate
As the datum π 1 before correction,
Settlement observation point coordinates then after adjustment is A
11(x
11, y
01, z
0), A
12(x
12, y
12, z
0) ... A
1n(x
1n, y
1n, z
0), their z have modified s1=z respectively to relief displacement
11-z
0, s2=z
12-z
0sn=z
1n-z
0, s=(s1, s2 ... sn)
tbe called index vector, wherein si moves down for just representing, and si is for negative representative moves, and so, the initial elevation of all settlement observation points is all corrected to an initial water plane π
1(z=z
0) on;
After correction starts, building is rectified a deviation, and relative initial plane changes to π i plane, if π i equation is:
π
i: a x+b y-z+c=0 (formula 4.1-2)
Construct a function F:
F=[(z
i1-s1)-(a x
i1+b y
i1+c)]
2+[(z
i2-s2)-(a x
i2+b y
i2+c)]
2+……
[(z
in-sn)-(a x
in+ b y
in+ c)]
2(formula 4.1-3)
F gets minimum value season
a∑x
ik 2+b∑x
ik*y
ik+c∑x
ik=∑(z
ik-sk)*x
ik}
A ∑ x
ik* y
ik+ b ∑ y
ik 2+ c ∑ y
ik=∑ (z
ik-sk) * y
ik---(formula 4.1-5)
a∑x
ik+b∑y
ik+c*n=∑(z
ik-sk)
Solve formula 4.1-5 ternary system of linear equations, if a, b, c solve, then the clinoplain that i-th observed result is determined is
π
i: ax+by-z+c=0 (formula 4.1-6)
Itself and z0 plane intersection line L1 are:
Angle between L1 and x-axis
ε=atan (-a/b) (formula 4.1-7)
This plane normal and z-axis angle γ are
Then
△ K=tan γ (formula 4.1-9)
△ K
x=△ Kcos (ε+pi/2) (formula 4.1-10)
△ K
y=△ Ksin (ε+pi/2) (formula 4.1-11)
Wherein
△ K
xfor this x-axis to slope change
△ Ky be this y-axis to slope change
△ K is the total slope change of this point.
2. existing building soil digging Deviation Correction Construction method for supervising according to claim 1, is characterized in that arranging at least 16 observation points.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210376889.4A CN102995670B (en) | 2012-09-28 | 2012-09-28 | Soil excavation rectification construction monitoring method of existing building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210376889.4A CN102995670B (en) | 2012-09-28 | 2012-09-28 | Soil excavation rectification construction monitoring method of existing building |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102995670A CN102995670A (en) | 2013-03-27 |
CN102995670B true CN102995670B (en) | 2015-04-01 |
Family
ID=47924726
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210376889.4A Active CN102995670B (en) | 2012-09-28 | 2012-09-28 | Soil excavation rectification construction monitoring method of existing building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102995670B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105569099A (en) * | 2014-10-13 | 2016-05-11 | 湖南征驰工程技术咨询有限公司 | Method for correcting building inclination caused by pile inclination |
CN111967176B (en) * | 2020-08-18 | 2024-03-01 | 扬州大学 | Deviation correcting load prediction method for external flashing wood frame |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010248744A (en) * | 2009-04-14 | 2010-11-04 | Higashio Mech Co Ltd | Method for restoring differentially settled house |
-
2012
- 2012-09-28 CN CN201210376889.4A patent/CN102995670B/en active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010248744A (en) * | 2009-04-14 | 2010-11-04 | Higashio Mech Co Ltd | Method for restoring differentially settled house |
Non-Patent Citations (1)
Title |
---|
超大结构倾斜度监测系统设计与应用;周仕仁等人;《施工技术》;20100228;第39卷(第2期);30-32 * |
Also Published As
Publication number | Publication date |
---|---|
CN102995670A (en) | 2013-03-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107893437B (en) | Large open caisson foundation construction real-time monitoring system based on remote wireless transmission technology | |
CN110849322B (en) | High-precision monitoring method for three-dimensional displacement track of power transmission line tower footing | |
CN109101774B (en) | Earthquake soil pressure calculation method for gravity type embankment retaining wall | |
CN106529150B (en) | Compound stratum shield tunnel vault load calculation method | |
CN110806192B (en) | Method for monitoring internal deformation of high rock-fill dam | |
CN104613932A (en) | Method for determining quasigeoid models by utilizing deviation of plumb line and gravity anomaly | |
CN210154614U (en) | Foundation pit and settlement monitoring device of peripheral stratum thereof based on BIM | |
CN109460589A (en) | It is a kind of based on the Tunnel dynamic design approach of deformation-Structure Method | |
CN109583116A (en) | Underground engineering primary stress field dynamic playback method based on multi-source real measured data | |
Roman et al. | Geodesy, geoids, and vertical datums: A perspective from the US National Geodetic Survey | |
CN111551438B (en) | Method for evaluating large deformation anchoring control effect of soft rock of large buried depth tunnel | |
CN106597504A (en) | Measurement system and method for building construction | |
CN103744128A (en) | Comprehensive forecasting method for underground cavity rockburst intensity grade | |
CN102561293B (en) | Water-soil pressure test method for soft-soil deep foundation pits | |
CN104294860A (en) | P-Y curve measuring device in pile-soil interaction shaking table test | |
CN101591988A (en) | The base stabilization appraisal procedure in mining influence district and upright tower method | |
CN102995670B (en) | Soil excavation rectification construction monitoring method of existing building | |
CN113882441B (en) | Earthquake instability early warning method for high and steep slope and application thereof | |
CN112035917A (en) | Method and device for predicting ultimate vertical displacement of earth surface in shield tunneling construction | |
CN105586974A (en) | Design method for foundation pit retaining structure | |
CN106017444A (en) | Independent monitoring method for construction verticality of super-high building | |
CN114969922B (en) | Method for acquiring vertical load of newly built station for underpass construction and construction method | |
CN112431236B (en) | Novel method for judging dangerous points of support piles | |
WANG et al. | Gravity Change Detected by Repeated Absolute Gravity Measurements in Western Yunnan and Lhasa, China and Its Implication | |
Kostoglodov et al. | Deformation in the Guerrero seismic gap, Mexico, from leveling observations |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |