CN102995670B - Soil excavation rectification construction monitoring method of existing building - Google Patents

Soil excavation rectification construction monitoring method of existing building Download PDF

Info

Publication number
CN102995670B
CN102995670B CN201210376889.4A CN201210376889A CN102995670B CN 102995670 B CN102995670 B CN 102995670B CN 201210376889 A CN201210376889 A CN 201210376889A CN 102995670 B CN102995670 B CN 102995670B
Authority
CN
China
Prior art keywords
building
formula
rectification
value
correction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210376889.4A
Other languages
Chinese (zh)
Other versions
CN102995670A (en
Inventor
梁幸福
阳刚
周仕仁
校迎春
罗文�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Engineering Technology Co Ltd
Original Assignee
Shanghai Baoye Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Engineering Technology Co Ltd filed Critical Shanghai Baoye Engineering Technology Co Ltd
Priority to CN201210376889.4A priority Critical patent/CN102995670B/en
Publication of CN102995670A publication Critical patent/CN102995670A/en
Application granted granted Critical
Publication of CN102995670B publication Critical patent/CN102995670B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention belongs to the technical field of a reinforcement project of a building structure, and particularly relates to a monitoring method in soil excavation rectification construction of the existing building. The monitoring method comprises the following steps of: comparing and verifying the building inclination and sedimentation variation of the building actually measured in the rectification process of the building with the theoretically calculated inclination and sedimentation variation, carrying out soil excavation rectification on the building according to the change degree when the numerical values are consistent; checking and finding out the reasons for difference when the difference of the numerical values is large, retesting and retrying until the numerical values are consistent; carrying out soil excavation rectification on the building according to the inclination degree consistence value until the building accords with the vertical standard request, wherein the actually measured value is obtained by testing the inclination degree of the building by a total station, and the theoretically calculated value is obtained according to the method and equation. By adopting the soil excavation rectification construction monitoring method of the existing building, the scientificity and accuracy of the soil excavation rectification are improved; and the rectification efficiency is higher, and the rectification quality is better.

Description

A kind of existing building soil digging Deviation Correction Construction method for supervising
Technical field
The invention belongs to building structure strengthening field of engineering technology, specifically relate to a kind of method for supervising existing building carried out in soil digging Deviation Correction Construction.
Background technology
Soil digging correction is by the little side soil digging of building deformation, remove the local stress in foundation soil, cause the stresses re-distribution of the soil body, the side foundation stress little at foundation settlement increases, thus produce larger compressive strain, make building reach the object of slowly correction.
Soil digging method for correcting error is generally used for the building of shallow foundation, and foundation soil is advisable with soil such as cohesive soil, silt, plain fill, mucky soil, sandy soils.
The engineering object that soil digging correction is suitable for mainly contains:
Ground soil property is uneven, and the inclination that there is soft layer or the dark pool is transfinited house.
Base foundation design and type selecting improper, position of centre of gravity, settlement joint etc. arrange the improper building causing tilting to transfinite.
Construction technology is improper or construction quality is inferior, and the too fast ground that causes of constructing is extruded, and a large amount of preloading in building side causes certain to roll the building tiltedly transfinited.
Mud or soft clay region, the building demolition adjacent with certain building, local off-load causes ground lateral compression to cause the building tilting to transfinite.
Building foundation groundwater table changes, and underflow takes away the soil body below building, causes land subsidence, subsides and building inclination is transfinited.
The building inclination that when landslide, earthquake, the natural calamity such as liquefaction of soil mass causes transfinites.
The applicable requirement of soil digging correction to building: building is approximately a rigid body, is out of shape with base integral.Relative contour of building size, sedimentation, inclination etc. are small deformation.
Conventional soil digging deviation correcting technology can only for the numerical value of the sedimentation of certain single observation point, tilt quantity in soil digging process, by virtue of experience judging that the deflection that the structural strain's amount and needing afterwards of building is corrected, final correction reach criterion of acceptability is the restriction that the tilt quantity of each observation point of building all reaches regulation and stipulation.Measuring error or error that this kind of reinforcement and rectification flow process is difficult to seeing time keeping instrument judge, and cannot hold in overall aspect building, easily cause erroneous judgement, easily cause irrational soil digging, increase soil digging number of times.
Summary of the invention
The object of this invention is to provide a kind of existing building soil digging Deviation Correction Construction method for supervising, cannot the deflection of building be held in overall aspect to overcome existing soil digging deviation correcting technology and easily cause the problem of erroneous judgement.
The object of the invention is to be achieved through the following technical solutions:
A kind of existing building soil digging Deviation Correction Construction method for supervising, is characterized in that:
Described method for supervising comprises and contrasting the actual test value of the building inclination in rectifying of leaned building process and calculated value, examines;
When both numerical value are consistent: by inclined degree, soil digging correction is carried out to building;
When both numerical value difference are larger: check and find difference reason, repetition measurement, double calculation are consistent to both, carry out soil digging correction by inclined degree homogeneity value to building;
Until building to meet standard-required vertical;
Described actual test value is tested by the inclined degree of total powerstation to building;
Described calculated value obtains by following method and formula:
In the corner of structure foundation, corner and sudden change place, at least 10 observation points are set,
Inclination building rectification by horizontal control network is measured, measurement of the level records each settlement observation point plane coordinates and elevation, is set to A before correction starts 11(x 11, y 11, z 11), A 12(x 12, y 12, z 12) ... A 1n(x 1n, y 1n, z 1n), get the Z-direction value of relative initial observation coordinate
z 0 = 1 n Σ 1 n Z 1 i (formula 4.1-1)
As the datum π 1 before correction,
Settlement observation point coordinates then after adjustment is A 11(x 11, y 01, z 0), A 12(x 12, y 12, z 0) ... A 1n(x 1n, y 1n, z 0), their z have modified s1=z respectively to relief displacement 11-z 0, s2=z 12-z 0sn=z 1n-z 0, s=(s1, s2 ... sn) tbe called index vector, wherein si moves down for just representing, and si is for negative representative moves, and so, the initial elevation of all settlement observation points is all corrected to an initial water plane π 1(z=z 0) on;
After correction starts, building is rectified a deviation, and relative initial plane changes to π i plane, if π i equation is:
π i: a x+b y-z+c=0(formula 4.1-2)
Construct a function F:
F=[(z i1-s1)-(a x i1+b y i1+c)] 2+[(z i2-s2)-(a x i2+b y i2+c)] 2+……
[(z in-sn)-(a x in+ b yin+c)] 2(formula 4.1-3)
F gets minimum value season
∂ F ∂ a = 0 ; ∂ F ∂ b = 0 ; ∂ F ∂ c = 0 (formula 4.1-4) solves
aΣ x ik 2 + bΣ x ik * y ik + cΣ x ik = Σ ( z ik - sk ) * x ik aΣ x ik * y ik + bΣ y ik 2 + cΣ y ik = Σ ( z ik - sk ) * y ik aΣ x ik + bΣ y ik + c * n = Σ ( z ik - sk ) ---(formula 4.1-5)
Solve formula 4.1-5 ternary system of linear equations, if a, b, c solve, then the clinoplain that i-th observed result is determined is
π i: ax+by-z+c=0(formula 4.1-6)
Itself and z0 plane intersection line L1 are:
ax + by + c = 0 z = z 0
Angle between L1 and x-axis
ε=atan(-a/b) (formula 4.1-7)
This plane normal and z-axis angle γ are
cos γ = | ( a , b , - 1 ) x ( 0,0,1 ) a 2 + b 2 + 1 | = 1 a 2 + b 2 + 1 (formula 4.1-8)
Then
△ K=tan γ (formula 4.1-9)
△ K x=△ Kcos (ε+pi/2) (formula 4.1-10)
△ K y=△ Ksin (ε+pi/2) (formula 4.1-11)
Wherein
△ K xfor this x-axis to slope change
△ Ky be this y-axis to slope change
△ K is the total slope change of this point.
Further, at least 16 observation points are set.
Further, think that difference is larger when the difference of described actual test value and calculated value numerical value is more than or equal to 10% of a less value in both numerical value.
The present invention is according to the above-mentioned △ K calculated x, △ Ky and △ K slope change, contrast the gradient of actual building, when both numerical value are consistent, by inclined degree, soil digging correction carried out to building; When both numerical value difference are larger, check and find difference reason, repetition measurement, double calculation are consistent to both, carry out soil digging correction by inclined degree homogeneity value to building.
Beneficial effect of the present invention: the invention provides a kind of new soil digging correction monitoring and Numerical Methods, building inclination axle and each tilt quantity, settling amount put can be calculated, and determine the arrangement in follow-up soil digging amount and soil digging hole with this, thus work progress is optimized.By the science, the accuracy that invention increases soil digging correction, correction efficiency is higher, correction better quality, and this method proposes the method that digital quantization weighs inclined degree first, significant for soil digging deviation correcting technology.
Accompanying drawing explanation
Fig. 1 is an embodiment of existing building soil digging Deviation Correction Construction method for supervising of the present invention, and the ground of building arranges the arrangement diagram of multiple observation point;
Fig. 2 is that building is rectified a deviation, and relative initial plane π changes to the structural representation of π 1 plane, shows the intersection of two planes in figure;
Fig. 3 is the ground arrangement diagram of one embodiment of the invention building;
Fig. 4 is showing building former and later two positions in soil digging process, the elevational schematic view that horizontal direction is observed;
Fig. 5 is that display one embodiment calculates the building inclination face of gained and the intersection schematic diagram of initial plane π after observation;
Fig. 6 is one group of sloping shaft floor map that an embodiment draws as calculated afterwards;
Fig. 7 is an embodiment structure foundation plane correction change schematic diagram.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is described in further detail:
Embodiment 1, in the corner of structure foundation, corner and sudden change place, arranges 20 observation points, and by observation, the observation data of front 5 phases is as shown in table 1:
Table 1 example 1 observation data
Period X Y Z1 Z2 Z3 Z4 Z5
A1 158.400 103.518 10.0809 10.0760 10.0398 10.0250 10.0250
A2 159.140 101.300 10.1010 10.0948 10.0496 10.0312 10.0312
A3 198.892 101.300 10.0749 10.0703 10.0368 10.0231 10.0151
A4 200.400 102.557 10.0622 10.0584 10.0306 10.0192 10.0112
A5 200.400 116.249 9.9352 9.9392 9.9682 9.9800 9.9670
A6 198.892 117.300 9.9265 9.9310 9.9639 9.9773 9.9723
A7 191.186 117.300 9.9319 9.9361 9.9665 9.9790 9.9799
A8 190.400 116.658 9.9380 9.9418 9.9695 9.9809 9.9828
A9 189.702 113.259 9.9700 9.9718 9.9853 9.9907 9.9914
A10 185.210 113.259 9.9729 9.9746 9.9867 9.9917 9.9917
A11 184.400 116.436 9.9440 9.9474 9.9725 9.9827 9.9842
A12 183.725 117.300 9.9364 9.9403 9.9688 9.9804 9.9824
A13 175.144 117.300 9.9421 9.9456 9.9715 9.9821 9.9831
A14 174.400 115.951 9.9551 9.9578 9.9779 9.9861 9.9861
A15 173.660 113.300 9.9802 9.9814 9.9902 9.9939 9.9948
A16 169.208 113.259 9.9831 9.9841 9.9917 9.9948 9.9958
A17 168.400 116.475 9.9542 9.9570 9.9775 9.9859 9.9852
A18 167.406 117.300 9.9472 9.9504 9.9740 9.9837 9.9849
A19 159.350 117.300 9.9524 9.9554 9.9766 9.9853 9.9853
A20 158.400 116.255 9.9628 9.9651 9.9817 9.9885 9.9885
Note: 1. in table, the unit of X, Y, Zi is m;
2. be the observation data of front 6 phases in table, with the Z1 phase for reference.
After calculating by the technology of the present invention method, the conclusion drawn is as follows:
Table 2 embodiment 1 result of calculation
Z1 Z2 Z3 Z4 Z5
a 0.000 0.000 0.000 0.000 0.000
b 0.000 0.001 0.005 0.006 0.007
c 9.978 9.907 9.395 9.186 9.187
Kx(‰) 0.000 0.040 0.333 0.453 0.295
Ky(‰) 0.000 0.568 4.717 6.412 6.641
Total K (‰) 0.000 0.570 4.729 6.428 6.647
The related conclusions drawn by table 2 is see seeing Fig. 6, Fig. 7
The difference maximum value of data and actual measurement is 9.2mm as calculated, and difference is 3%, is less than 10%, can think that data are reliable, namely presses calculated value and continues soil digging.
Embodiment 2, in the corner of structure foundation, corner and sudden change place, arranges 16 observation points, and by observation, the observation data of front 5 phases is as shown in table 2:
Table 3 embodiment 2 observation data
Period X Y Z1 Z2 Z3 Z4 Z5
A1 184.7863 128.5912 15.0398 15.0224 15.0180 15.0128 15.0087
A2 185.1013 126.6317 15.0496 15.0279 15.0225 15.0160 15.0109
A3 224.7331 127.7570 15.0368 15.0207 15.0167 15.0118 15.0081
A4 225.7910 129.0991 15.0306 15.0172 15.0139 15.0098 15.0067
A5 226.1995 142.3721 14.9682 14.9821 14.9856 14.9898 14.9930
A6 225.5165 143.9643 14.9639 14.9797 14.9836 14.9884 14.9921
A7 217.6655 142.4591 14.9665 14.9812 14.9848 14.9892 14.9927
A8 216.5650 143.0229 14.9695 14.9829 14.9862 14.9902 14.9933
A9 214.9326 138.4853 14.9853 14.9917 14.9933 14.9953 14.9968
A10 210.2731 138.7426 14.9867 14.9925 14.9940 14.9957 14.9971
A11 209.4968 142.6816 14.9725 14.9845 14.9875 14.9912 14.9940
A12 210.1986 143.5231 14.9688 14.9824 14.9859 14.9900 14.9932
A13 201.4223 143.4795 14.9715 14.9840 14.9871 14.9908 14.9938
A14 199.4374 141.7330 14.9779 14.9876 14.9900 14.9929 14.9952
A15 200.0100 138.6697 14.9902 14.9945 14.9956 14.9969 14.9979
A16 194.2928 139.7977 14.9917 14.9953 14.9962 14.9973 14.9982
After calculating by the technology of the present invention method, the conclusion drawn is as follows: table 4 embodiment 2 result of calculation
Z1 Z2 Z3 Z4 Z5
a 0.000 0.000 0.000 0.000 0.000
b 0.000 0.002 0.002 0.003 0.004
c 14.992 14.701 14.628 14.541 14.472
Kx(‰) 0.000 0.103 0.129 0.160 0.184
Ky(‰) 0.000 1.976 2.470 3.062 3.527
Total K (‰) 0.000 1.978 2.473 3.067 3.531
The related conclusions drawn by table 2 is see seeing Fig. 6, Fig. 7.
The difference maximum value of data and actual measurement is 3.2mm as calculated, and difference is 4.5%, is less than 10%, can think that data are reliable, namely press calculated value and continue soil digging.
Also can show that example 1 is too fast in the rate of settling change of the 3rd, 4,5 phases by example 1,2 contrast, should less soil digging amount.

Claims (2)

1. an existing building soil digging Deviation Correction Construction method for supervising, is characterized in that:
Described method for supervising comprises and contrasting the actual test value of the building inclination in rectifying of leaned building process and calculated value, examines;
When both numerical value are consistent: by inclined degree, soil digging correction is carried out to building;
When the difference of both numerical value is more than or equal to 10% of a less value in both numerical value: check and find difference reason, repetition measurement, double calculation are consistent to both, carry out soil digging correction by inclined degree homogeneity value to building;
Until building to meet standard-required vertical;
Described actual test value is tested by the inclined degree of total powerstation to building;
Described calculated value obtains by following method and formula:
In the corner of structure foundation, corner and sudden change place, at least 10 observation points are set,
Inclination building rectification by horizontal control network is measured, measurement of the level records each settlement observation point plane coordinates and elevation, is set to A before correction starts 11(x 11, y 11, z 11), A 12(x 12, y 12, z 12) ... A 1n(x 1n, y 1n, z 1n), get the Z-direction value of relative initial observation coordinate
z 0 = 1 n Σ 1 n z 1 i (formula 4.1-1)
As the datum π 1 before correction,
Settlement observation point coordinates then after adjustment is A 11(x 11, y 01, z 0), A 12(x 12, y 12, z 0) ... A 1n(x 1n, y 1n, z 0), their z have modified s1=z respectively to relief displacement 11-z 0, s2=z 12-z 0sn=z 1n-z 0, s=(s1, s2 ... sn) tbe called index vector, wherein si moves down for just representing, and si is for negative representative moves, and so, the initial elevation of all settlement observation points is all corrected to an initial water plane π 1(z=z 0) on;
After correction starts, building is rectified a deviation, and relative initial plane changes to π i plane, if π i equation is:
π i: a x+b y-z+c=0 (formula 4.1-2)
Construct a function F:
F=[(z i1-s1)-(a x i1+b y i1+c)] 2+[(z i2-s2)-(a x i2+b y i2+c)] 2+……
[(z in-sn)-(a x in+ b y in+ c)] 2(formula 4.1-3)
F gets minimum value season
∂ F ∂ a = 0 ; ∂ F ∂ b = 0 ; ∂ F ∂ c = 0 (formula 4.1-4) solves
a∑x ik 2+b∑x ik*y ik+c∑x ik=∑(z ik-sk)*x ik}
A ∑ x ik* y ik+ b ∑ y ik 2+ c ∑ y ik=∑ (z ik-sk) * y ik---(formula 4.1-5)
a∑x ik+b∑y ik+c*n=∑(z ik-sk)
Solve formula 4.1-5 ternary system of linear equations, if a, b, c solve, then the clinoplain that i-th observed result is determined is
π i: ax+by-z+c=0 (formula 4.1-6)
Itself and z0 plane intersection line L1 are:
ax + by + c = 0 z = z 0
Angle between L1 and x-axis
ε=atan (-a/b) (formula 4.1-7)
This plane normal and z-axis angle γ are
cos γ = | ( a , b , - 1 ) × ( 0,0,1 ) a 2 + b 2 + 1 | = 1 a 2 + b 2 + 1 (formula 4.1-8)
Then
△ K=tan γ (formula 4.1-9)
△ K x=△ Kcos (ε+pi/2) (formula 4.1-10)
△ K y=△ Ksin (ε+pi/2) (formula 4.1-11)
Wherein
△ K xfor this x-axis to slope change
△ Ky be this y-axis to slope change
△ K is the total slope change of this point.
2. existing building soil digging Deviation Correction Construction method for supervising according to claim 1, is characterized in that arranging at least 16 observation points.
CN201210376889.4A 2012-09-28 2012-09-28 Soil excavation rectification construction monitoring method of existing building Active CN102995670B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210376889.4A CN102995670B (en) 2012-09-28 2012-09-28 Soil excavation rectification construction monitoring method of existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210376889.4A CN102995670B (en) 2012-09-28 2012-09-28 Soil excavation rectification construction monitoring method of existing building

Publications (2)

Publication Number Publication Date
CN102995670A CN102995670A (en) 2013-03-27
CN102995670B true CN102995670B (en) 2015-04-01

Family

ID=47924726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210376889.4A Active CN102995670B (en) 2012-09-28 2012-09-28 Soil excavation rectification construction monitoring method of existing building

Country Status (1)

Country Link
CN (1) CN102995670B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105569099A (en) * 2014-10-13 2016-05-11 湖南征驰工程技术咨询有限公司 Method for correcting building inclination caused by pile inclination
CN111967176B (en) * 2020-08-18 2024-03-01 扬州大学 Deviation correcting load prediction method for external flashing wood frame

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010248744A (en) * 2009-04-14 2010-11-04 Higashio Mech Co Ltd Method for restoring differentially settled house

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010248744A (en) * 2009-04-14 2010-11-04 Higashio Mech Co Ltd Method for restoring differentially settled house

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
超大结构倾斜度监测系统设计与应用;周仕仁等人;《施工技术》;20100228;第39卷(第2期);30-32 *

Also Published As

Publication number Publication date
CN102995670A (en) 2013-03-27

Similar Documents

Publication Publication Date Title
CN107893437B (en) Large open caisson foundation construction real-time monitoring system based on remote wireless transmission technology
CN110849322B (en) High-precision monitoring method for three-dimensional displacement track of power transmission line tower footing
CN109101774B (en) Earthquake soil pressure calculation method for gravity type embankment retaining wall
CN106529150B (en) Compound stratum shield tunnel vault load calculation method
CN110806192B (en) Method for monitoring internal deformation of high rock-fill dam
CN104613932A (en) Method for determining quasigeoid models by utilizing deviation of plumb line and gravity anomaly
CN210154614U (en) Foundation pit and settlement monitoring device of peripheral stratum thereof based on BIM
CN109460589A (en) It is a kind of based on the Tunnel dynamic design approach of deformation-Structure Method
CN109583116A (en) Underground engineering primary stress field dynamic playback method based on multi-source real measured data
Roman et al. Geodesy, geoids, and vertical datums: A perspective from the US National Geodetic Survey
CN111551438B (en) Method for evaluating large deformation anchoring control effect of soft rock of large buried depth tunnel
CN106597504A (en) Measurement system and method for building construction
CN103744128A (en) Comprehensive forecasting method for underground cavity rockburst intensity grade
CN102561293B (en) Water-soil pressure test method for soft-soil deep foundation pits
CN104294860A (en) P-Y curve measuring device in pile-soil interaction shaking table test
CN101591988A (en) The base stabilization appraisal procedure in mining influence district and upright tower method
CN102995670B (en) Soil excavation rectification construction monitoring method of existing building
CN113882441B (en) Earthquake instability early warning method for high and steep slope and application thereof
CN112035917A (en) Method and device for predicting ultimate vertical displacement of earth surface in shield tunneling construction
CN105586974A (en) Design method for foundation pit retaining structure
CN106017444A (en) Independent monitoring method for construction verticality of super-high building
CN114969922B (en) Method for acquiring vertical load of newly built station for underpass construction and construction method
CN112431236B (en) Novel method for judging dangerous points of support piles
WANG et al. Gravity Change Detected by Repeated Absolute Gravity Measurements in Western Yunnan and Lhasa, China and Its Implication
Kostoglodov et al. Deformation in the Guerrero seismic gap, Mexico, from leveling observations

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant