CN102994892A - Preparation method of swing check valve plate - Google Patents

Preparation method of swing check valve plate Download PDF

Info

Publication number
CN102994892A
CN102994892A CN2012103734968A CN201210373496A CN102994892A CN 102994892 A CN102994892 A CN 102994892A CN 2012103734968 A CN2012103734968 A CN 2012103734968A CN 201210373496 A CN201210373496 A CN 201210373496A CN 102994892 A CN102994892 A CN 102994892A
Authority
CN
China
Prior art keywords
valve plate
treatment
hour
blank
hours
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103734968A
Other languages
Chinese (zh)
Other versions
CN102994892B (en
Inventor
许国荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mecco Valve Co.,Ltd.
Original Assignee
TONGLING GUOFANG PLUMBING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TONGLING GUOFANG PLUMBING TECHNOLOGY Co Ltd filed Critical TONGLING GUOFANG PLUMBING TECHNOLOGY Co Ltd
Priority to CN201210373496.8A priority Critical patent/CN102994892B/en
Publication of CN102994892A publication Critical patent/CN102994892A/en
Application granted granted Critical
Publication of CN102994892B publication Critical patent/CN102994892B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a preparation method of a swing check valve plate. The preparation method comprises the following steps of: molding a valve plate blank by pouring, cooling the blank molded by pouring to 300 DEG C, reheating the blank to 650-760 DEG C, preserving heat for 3-5 hours, furnace-cooling the blank to 300 DEG C, preserving heat for 4 hours, reheating the blank to 650-760 DEG C, preserving heat for 17 hours, cooling the blank to 450 DEG C at a speed of 50 DEG C/h and then cooling the blank to 140 DEG C at a speed of 20 DEG C/h, wherein each component comprises the following chemical components by weight percent: 2.85-3.20% of C, 1.2-1.5% of Si, 0.8-1.2% of Mn, 0.6-0.8% of P, 0.05-0.07% of S, 0.24-0.35% of Cr and 0.7-0.9% of Cu. The preparation method has the beneficial effects that the powder metallurgy material and the manufacturing process have higher production continuity; the material utilization rate is high; the powder metallurgy material is suitable for volume production; and the cost is reduced.

Description

A kind of swing check valve valve plate preparation method
Technical field
The present invention relates to a kind of preparation method of butterfly valve valve rod, specifically belong to a kind of swing check valve valve plate preparation method.
Background technology
Vacuum breaker is useful in chloroazotic acid, sulfuric acid, hydrochloric acid, hydrofluoric acid and various organic acid, strong acid, the strong oxidizer of-50~150 ℃ various concentration, also is applicable to highly basic organic solvent and other corrosive gases of various concentration, uses on the pipeline of liquid medium.
At present, preparation vacuum breaker industry, domestic ball non-return valve flap all adopts common rapid steel material, or the stainless steel material is by machining ball non-return valve flap.Compare with the powder metallurgy seat of stop valve, the ball non-return valve flap process velocity that common rapid steel material or the machining of stainless steel material are made is slower, material use efficiency is not high, and powder metallurgical technique is made stopping valve, not only material use efficiency is high, and be suitable for producing in enormous quantities, before assembling is used, need the powder metallurgy valve body is carried out a small amount of ground finish.
Summary of the invention
Technical problem to be solved by this invention is for vacuum breaker valve plate Technology present situation, and a kind of swing check valve valve plate preparation method that a kind of production efficiency is high, manufacturing cost is lower who provides.
The technical solution used in the present invention is as follows:
A kind of swing check valve valve plate preparation method includes following steps:
A, casting valve plate blank, each component chemical composition weight percent is: C:2.85-3.20%, Si:1.2-1.5%, Mn:0.8-1.2%, P:0.6-0.8%, S:0.05-0.07%, Cr 0.24-0.35%, Cu 0.7-0.9%, the blank temperature of casting is down to 300 ℃, reheats to 650-760 ℃, be incubated 3-5 hour, stove is chilled to 300 ℃, is incubated 4 hours, reheats to 650-760 ℃, be incubated 17 hours, be cooled to 450 ℃ with 50 ℃/hour, again with 20 ℃/hour, be cooled to 140 ℃;
B, above-mentioned starting material are heated to 1400-1500 ℃, are fused into molten metal, detect the content of chemical ingredients, then in above-mentioned molten metal, add the metal element of corresponding shortage, mix, form potting syrup;
c, in sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the vacuum breaker valve plate after taking out, described steam treatment is the water atomization steam treatment, the treatment time is 4-5 hour, temperature is 550-650 ℃;
D, quench treatment: the vacuum breaker valve plate sent into be heated to 850-890 ℃ in the heat treatment furnace, and insulation 2-3 hour; Then, cool off with quenching oil;
E, temper: the vacuum breaker valve plate after will quenching is sent into and is heated to 300-400 ℃ in the tempering stove, insulation 50-70min;
F, bonderizing, be 180-200 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1-2min, adopt phosphorization agent to process 15-20min, after dripping empty 1-2min, adopt clear water to clean 1-2min again, after dripping again empty 1-2min, process 0.5-1min workpiece is placed 78-100 ℃ hot water;
G, sub-zero treatment: with the container of packing into of valve plate part behind the bonderizing, add liquid nitrogen and carry out sub-zero treatment, the time is 10-12 hour.
In step c, in sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the vacuum breaker valve plate after taking out, and described steam treatment is the water atomization steam treatment, and the treatment time is 4.5 hours, and temperature is 600 ℃.
Compared with prior art, the invention has the advantages that:
Compared with prior art, the inventive method is by the cast operation, and by quenching, tempering, phosphatization, sub-zero treatment, the tensile strength sigma b (MPa) of the vacuum breaker valve plate that obtains: 〉=1080 (110), yield strength σ s (MPa): 〉=930 (95), elongation δ 5 (%): 〉=12, relative reduction in area ψ (%): 〉=45, Impact energy Ak v (J): 〉=63, notched bar impact strength α kv (J/cm2): 〉=78.
The present invention makes blank obtain rational distribution, thereby reduced the size of overlap, so that material use efficiency has brought up to 70% from original about 30%, improved 40%, because blank reduces, the equipment hitting power also reduces accordingly, and the life-span that causes mould is brought up to 9000 from original 5000, improves nearly about one times.After the blank properly distributed, because the minimizing of overlap, metal reflow causes the phenomenons such as the sufficient and part of folder dirt and forging part is inabundant to improve.
Embodiment
A kind of swing check valve valve plate preparation method includes following steps:
A, casting valve plate blank, each component chemical composition weight percent is: C:2.85-3.20%, Si:1.2-1.5%, Mn:0.8-1.2%, P:0.6-0.8%, S:0.05-0.07%, Cr 0.24-0.35%, Cu 0.7-0.9%, the blank temperature of casting is down to 300 ℃, reheats to 650-760 ℃, be incubated 3-5 hour, stove is chilled to 300 ℃, is incubated 4 hours, reheats to 650-760 ℃, be incubated 17 hours, be cooled to 450 ℃ with 50 ℃/hour, again with 20 ℃/hour, be cooled to 140 ℃;
B, above-mentioned starting material are heated to 1400-1500 ℃, are fused into molten metal, detect the content of chemical ingredients, then in above-mentioned molten metal, add the metal element of corresponding shortage, mix, form potting syrup;
c, in sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the vacuum breaker valve plate after taking out, described steam treatment is the water atomization steam treatment, the treatment time is 4.5 hours, temperature is 600 ℃;
D, quench treatment: the vacuum breaker valve plate sent into be heated to 850-890 ℃ in the heat treatment furnace, and insulation 2-3 hour; Then, cool off with quenching oil;
E, temper: the vacuum breaker valve plate after will quenching is sent into and is heated to 300-400 ℃ in the tempering stove, insulation 50-70min;
F, bonderizing, be 180-200 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1-2min, adopt phosphorization agent to process 15-20min, after dripping empty 1-2min, adopt clear water to clean 1-2min again, after dripping again empty 1-2min, process 0.5-1min workpiece is placed 78-100 ℃ hot water;
G, sub-zero treatment: with the container of packing into of valve plate part behind the bonderizing, add liquid nitrogen and carry out sub-zero treatment, the time is 10-12 hour.

Claims (2)

1. swing check valve valve plate preparation method is characterized in that including following steps:
A, casting valve plate blank, each component chemical composition weight percent is: C:2.85-3.20%, Si:1.2-1.5%, Mn:0.8-1.2%, P:0.6-0.8%, S:0.05-0.07%, Cr 0.24-0.35%, Cu 0.7-0.9%, the blank temperature of casting is down to 300 ℃, reheats to 650-760 ℃, be incubated 3-5 hour, stove is chilled to 300 ℃, is incubated 4 hours, reheats to 650-760 ℃, be incubated 17 hours, be cooled to 450 ℃ with 50 ℃/hour, again with 20 ℃/hour, be cooled to 140 ℃;
B, above-mentioned starting material are heated to 1400-1500 ℃, are fused into molten metal, detect the content of chemical ingredients, then in above-mentioned molten metal, add the metal element of corresponding shortage, mix, form potting syrup;
c, in sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the vacuum breaker valve plate after taking out, described steam treatment is the water atomization steam treatment, the treatment time is 4-5 hour, temperature is 550-650 ℃;
D, quench treatment: the vacuum breaker valve plate sent into be heated to 850-890 ℃ in the heat treatment furnace, and insulation 2-3 hour; Then, cool off with quenching oil;
E, temper: the vacuum breaker valve plate after will quenching is sent into and is heated to 300-400 ℃ in the tempering stove, insulation 50-70min;
F, bonderizing, be 180-200 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1-2min, adopt phosphorization agent to process 15-20min, after dripping empty 1-2min, adopt clear water to clean 1-2min again, after dripping again empty 1-2min, process 0.5-1min workpiece is placed 78-100 ℃ hot water;
G, sub-zero treatment: with the container of packing into of valve plate part behind the bonderizing, add liquid nitrogen and carry out sub-zero treatment, the time is 10-12 hour.
2. swing check valve valve plate preparation method according to claim 1 is characterized in that:
In step c, in sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the vacuum breaker valve plate after taking out, and described steam treatment is the water atomization steam treatment, and the treatment time is 4.5 hours, and temperature is 600 ℃.
CN201210373496.8A 2012-09-29 2012-09-29 A kind of swing check valve valve plate preparation method Active CN102994892B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210373496.8A CN102994892B (en) 2012-09-29 2012-09-29 A kind of swing check valve valve plate preparation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210373496.8A CN102994892B (en) 2012-09-29 2012-09-29 A kind of swing check valve valve plate preparation method

Publications (2)

Publication Number Publication Date
CN102994892A true CN102994892A (en) 2013-03-27
CN102994892B CN102994892B (en) 2016-04-06

Family

ID=47923996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210373496.8A Active CN102994892B (en) 2012-09-29 2012-09-29 A kind of swing check valve valve plate preparation method

Country Status (1)

Country Link
CN (1) CN102994892B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114273617A (en) * 2021-12-24 2022-04-05 福建贝得阀门有限公司 Rapid casting molding process for valve body of soft and hard sealing ball valve

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85107725A (en) * 1985-10-17 1986-07-23 陕西机械学院 Make the vermicular cast iron of mould for glass bottle
CN1045280A (en) * 1989-02-28 1990-09-12 陕西机械学院 Bainite and martensite mottled nodular cast iron grinding ball
CN1054621A (en) * 1990-03-02 1991-09-18 柳州市都乐企业集团 Iron pan corrosiron and manufacturing process thereof
CN101081432A (en) * 2007-06-04 2007-12-05 天乾(无锡)科技有限公司 Method for founding main regulation valve body of steam turbine
CN101618508A (en) * 2009-07-30 2010-01-06 扬州东升汽车零部件制造有限公司 Method for producing vehicle-used stabilizer bar with high corrosion resistance
US20100239451A1 (en) * 2007-06-26 2010-09-23 Incorporated National University Iwate University Flake Graphite Cast Iron And Production Method Thereof
CN102092417A (en) * 2010-12-06 2011-06-15 十堰合骏实业有限公司 Integrated valve bush and powder metallurgy process method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85107725A (en) * 1985-10-17 1986-07-23 陕西机械学院 Make the vermicular cast iron of mould for glass bottle
CN1045280A (en) * 1989-02-28 1990-09-12 陕西机械学院 Bainite and martensite mottled nodular cast iron grinding ball
CN1054621A (en) * 1990-03-02 1991-09-18 柳州市都乐企业集团 Iron pan corrosiron and manufacturing process thereof
CN101081432A (en) * 2007-06-04 2007-12-05 天乾(无锡)科技有限公司 Method for founding main regulation valve body of steam turbine
US20100239451A1 (en) * 2007-06-26 2010-09-23 Incorporated National University Iwate University Flake Graphite Cast Iron And Production Method Thereof
CN101618508A (en) * 2009-07-30 2010-01-06 扬州东升汽车零部件制造有限公司 Method for producing vehicle-used stabilizer bar with high corrosion resistance
CN102092417A (en) * 2010-12-06 2011-06-15 十堰合骏实业有限公司 Integrated valve bush and powder metallurgy process method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114273617A (en) * 2021-12-24 2022-04-05 福建贝得阀门有限公司 Rapid casting molding process for valve body of soft and hard sealing ball valve
CN114273617B (en) * 2021-12-24 2024-02-27 福建贝得阀门有限公司 Rapid casting molding process for valve body of soft and hard sealing ball valve

Also Published As

Publication number Publication date
CN102994892B (en) 2016-04-06

Similar Documents

Publication Publication Date Title
CN102994907A (en) Casting method of check valve body
CN102965576B (en) Preparation method of pump shaft of oil feed pump
CN102978486A (en) Aluminum alloy casting forming method for valve clack of sluice valve
CN102703652B (en) Heat treatment process of hot-work-die steel for aluminum die-casting mould
CN104084587A (en) Manufacturing method of powder metallurgical hub bearing unit
CN102994906B (en) A kind of method of ball valve body
CN103060698B (en) A kind of preparation technology of corrosion resistant mould steel
CN102979938B (en) Casting method of valve body of check valve
CN102994890B (en) A kind of valve body of anti-explosion valve castmethod
CN107201475A (en) A kind of casting preparation method of valve body
CN102994910A (en) Casting method of gate valve rod
CN102994892B (en) A kind of swing check valve valve plate preparation method
CN102974771A (en) Casting forming preparation method of pressure reducing valve body
CN102994718B (en) Method for preparing gate valve disc through casting molding
CN102994861B (en) A kind of castmethod of spherical check valve rod
CN102994891A (en) Method for preparing valve rod of plug valve
CN103060666A (en) Casting method of alloy body of spherical check valve
CN102994886B (en) A kind of method of casting stopping valve valve plate processed
CN102994867B (en) A kind of casting preparation method of reverse checkvalve spool
CN103060672A (en) Preparation process for die steel
CN107828992A (en) A kind of preparation method of the aluminium alloy wheel hub of low scrappage
CN102994868B (en) A kind of casting preparation method of wafer type valve flap
CN102996865B (en) Method for casting valve body of ball check valve
CN102979956B (en) A kind of warm forging forming method of throttle valve stem
CN102978554A (en) Titanium alloy valve rod preparation method of plug valve

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160303

Address after: 244100 new road, West Lake Town Development Zone, lion mountain, Tongling, Anhui

Applicant after: Anhui Mingzhu Pigment Technology Co., Ltd.

Address before: 244121 Tongling Jinqiao Industrial Park, Tongling, Anhui

Applicant before: Tongling Guofang Plumbing Technology Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Zhang Chengzhong

Inventor before: Xu Guorong

CB03 Change of inventor or designer information
TR01 Transfer of patent right

Effective date of registration: 20180522

Address after: No. 3858, Shanghai Bao Qian highway, Jiading District, Shanghai

Patentee after: Shanghai Mecco Valve Co.,Ltd.

Address before: 244100 New Town Road, West Lake Town Development Zone, Tongling, Anhui

Patentee before: Tongling Guofang Plumbing Technology Co., Ltd.

TR01 Transfer of patent right