CN102994890A - Casting method of valve body of anti-explosion valve - Google Patents

Casting method of valve body of anti-explosion valve Download PDF

Info

Publication number
CN102994890A
CN102994890A CN2012103729527A CN201210372952A CN102994890A CN 102994890 A CN102994890 A CN 102994890A CN 2012103729527 A CN2012103729527 A CN 2012103729527A CN 201210372952 A CN201210372952 A CN 201210372952A CN 102994890 A CN102994890 A CN 102994890A
Authority
CN
China
Prior art keywords
valve body
equal
hour
dripping
empty
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103729527A
Other languages
Chinese (zh)
Other versions
CN102994890B (en
Inventor
许国荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Hongfan Special Equipment Engineering Co ltd
Original Assignee
TONGLING GUOFANG PLUMBING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TONGLING GUOFANG PLUMBING TECHNOLOGY Co Ltd filed Critical TONGLING GUOFANG PLUMBING TECHNOLOGY Co Ltd
Priority to CN201210372952.7A priority Critical patent/CN102994890B/en
Publication of CN102994890A publication Critical patent/CN102994890A/en
Application granted granted Critical
Publication of CN102994890B publication Critical patent/CN102994890B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a casting method of a valve body of an anti-explosion valve. The method comprises the following steps: pouring the valve body and controlling the weight percentages of chemical components in the valve body as follows: less than or equal to 2.32% but greater than or equal to 4.15% of C, less than or equal to 0.40% but greater than or equal to 1.40% of Si, less than or equal to 0.30% but greater than or equal to 1.30% of Mn, less than or equal to 0.010% but greater than or equal to 0.030% of P, less than or equal to 0.010% but greater than or equal to 0.030% of S, less than or equal to 1.50% but greater than or equal to 2.50% of Cr, less than or equal to trace but greater than or equal to 0.0018% of B, and the balance of iron and avoidless impurities; cooling the poured and moulded valve body to 350 DEG C, then heating to 670-760 DEG C, insulating for 3-5h, cooling the furnace to 300 DEG C, insulating for 4h, then heating to 650-760 DEG C, insulating for 17h, cooling to 400 DEG C at 50 DEG C/h, and then cooling to 140 DEG C at 20 DEG C/h. According to the powder metallurgy material and manufacturing process provided by the invention, higher production continuity is obtained and the material utilization rate is high. The method provided by the invention is suitable for production in a large scale, and the cost is lowered.

Description

A kind of explosion trap valve body castmethod
Technical field
The present invention relates to a kind of preparation method of explosion trap, specifically belong to a kind of explosion trap valve body castmethod.
Background technology
Explosion trap is the function unit in the fluid delivery system, has the functions such as shunting or overflow pressure relief.The valve that is used for fluid control system, from the simplest stopping valve to very complicated robot control system(RCS) used various valves, its kind and specification are quite various.Valve can be used for controlling flowing of all kinds fluids such as air, water, steam, various corrosive medium, mud, oil product, liquid metal and radiating medium.Not only the material manufacture craft is poor for explosion trap at present, and is suitable for producing in enormous quantities, needs valve body is carried out a small amount of ground finish before assembling is used.
Summary of the invention
Technical problem to be solved by this invention is for explosion trap Technology present situation, and a kind of explosion trap valve body castmethod that a kind of production efficiency is high, manufacturing cost is lower that provides.
The technical solution used in the present invention is as follows:
A kind of explosion trap valve body castmethod includes following steps:
A, cast valve body, chemical component weight per-cent is in the application valve body: 2.32%≤C≤4.15%, 0.40%≤Si≤1.40%, 0.30%≤Mn≤1.30%, 0.010%≤P≤0.030%, 0.010%≤S≤0.030%.1.50%≤Cr≤2.50%, trace≤B≤0.0018%, surplus is iron and inevitable impurity; The valve body temperature of casting is down to 350 ℃, reheats to 670-760 ℃, is incubated 3-5 hour, and stove is chilled to 300 ℃, is incubated 4 hours, reheats to 650-760 ℃, is incubated 17 hours, is cooled to 400 ℃ with 50 ℃/hour, again with 20 ℃/hour, is cooled to 140 ℃;
b, in the valve body sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the explosion trap valve body after taking out, described steam treatment is the water atomization steam treatment, the treatment time is 4-5 hour, temperature is 550-650 ℃;
C, quench treatment: the explosion trap valve body sent into be heated to 850-890 ℃ in the heat treatment furnace, and insulation 2-3 hour; Then cool off with quenching oil;
D, temper: the explosion trap valve body after will quenching is sent into and is heated to 300-400 ℃ in the tempering stove, insulation 50-70min;
E, bonderizing, be 180-200 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1-2min, adopt phosphorization agent to process 15-20min, after dripping empty 1-2min, adopt clear water to clean 1-2min again, after dripping again empty 1-2min, process 0.5-1min workpiece is placed 78-100 ℃ hot water.
Bonderizing, be 190 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1.5min, adopt phosphorization agent to process 17min, after dripping empty 1.5min, adopt clear water to clean 1.5min again, after dripping again empty 1.5min, process 0.7min workpiece is placed 90 ℃ hot water.
Compared with prior art, the invention has the advantages that:
The present invention passes through technique scheme, one-piece construction is scientific and reasonable, the corresponding energy consumption that reduced has reduced materials consumption and cost and has dropped into, and working accuracy improves greatly, compared with prior art material use efficiency is brought up to more than 90% by present 65%, power consumption reduces about 70%, and recruitment reduces 3/4ths, and a machine tool two people operate the malleable workpiece of split run more than 550, improve about 4 times of work efficiency, the positively effect highly significant of generation.
It is as follows that mechanical property of the present invention detects data:
Tensile strength sigma b (MPa): 〉=1080 (110)
Yield strength σ s (MPa): 〉=930 (95)
Elongation δ 5 (%): 〉=12
Relative reduction in area ψ (%): 〉=55
Impact energy Ak v (J): 〉=65
Notched bar impact strength α kv (J/cm2): 〉=78 (8)
Hardness :≤223HB
Embodiment
A kind of explosion trap valve body castmethod includes following steps:
A, cast valve body, chemical component weight per-cent is in the application valve body: 2.32%≤C≤4.15%, 0.40%≤Si≤1.40%, 0.30%≤Mn≤1.30%, 0.010%≤P≤0.030%, 0.010%≤S≤0.030%.1.50%≤Cr≤2.50%, trace≤B≤0.0018%, surplus is iron and inevitable impurity; The valve body temperature of casting is down to 350 ℃, reheats to 670-760 ℃, is incubated 3-5 hour, and stove is chilled to 300 ℃, is incubated 4 hours, reheats to 650-760 ℃, is incubated 17 hours, is cooled to 400 ℃ with 50 ℃/hour, again with 20 ℃/hour, is cooled to 140 ℃;
b, in the valve body sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the explosion trap valve body after taking out, described steam treatment is the water atomization steam treatment, the treatment time is 4-5 hour, temperature is 550-650 ℃;
C, quench treatment: the explosion trap valve body sent into be heated to 850-890 ℃ in the heat treatment furnace, and insulation 2-3 hour; Then cool off with quenching oil;
D, temper: the explosion trap valve body after will quenching is sent into and is heated to 300-400 ℃ in the tempering stove, insulation 50-70min;
E, bonderizing, be 190 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1.5min, adopt phosphorization agent to process 17min, after dripping empty 1.5min, adopt clear water to clean 1.5min again, after dripping again empty 1.5min, process 0.7min workpiece is placed 90 ℃ hot water.

Claims (2)

1. explosion trap valve body castmethod is characterized in that including following steps:
A, cast valve body, chemical component weight per-cent is in the application valve body: 2.32%≤C≤4.15%, 0.40%≤Si≤1.40%, 0.30%≤Mn≤1.30%, 0.010%≤P≤0.030%, 0.010%≤S≤0.030%;
1.50%≤Cr≤2.50%, trace≤B≤0.0018%, surplus is iron and inevitable impurity; The valve body temperature of casting is down to 350 ℃, reheats to 670-760 ℃, is incubated 3-5 hour, and stove is chilled to 300 ℃, is incubated 4 hours, reheats to 650-760 ℃, is incubated 17 hours, is cooled to 400 ℃ with 50 ℃/hour, again with 20 ℃/hour, is cooled to 140 ℃;
b, in the valve body sand mold, pour into a mould potting syrup by cast gate, cooled and solidified, steam treatment namely gets the explosion trap valve body after taking out, described steam treatment is the water atomization steam treatment, the treatment time is 4-5 hour, temperature is 550-650 ℃;
C, quench treatment: the explosion trap valve body sent into be heated to 850-890 ℃ in the heat treatment furnace, and insulation 2-3 hour; Then cool off with quenching oil;
D, temper: the explosion trap valve body after will quenching is sent into and is heated to 300-400 ℃ in the tempering stove, insulation 50-70min;
E, bonderizing, be 180-200 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1-2min, adopt phosphorization agent to process 15-20min, after dripping empty 1-2min, adopt clear water to clean 1-2min again, after dripping again empty 1-2min, process 0.5-1min workpiece is placed 78-100 ℃ hot water.
2. a kind of explosion trap valve body castmethod according to claim 1 is characterized in that: described
Bonderizing, be 190 ℃ with workpiece at showing tremendous enthusiasm closure temperature at normal temperatures, the employing pH value is 8 surface conditioner processing 1min, after dripping empty 1.5min, adopt phosphorization agent to process 17min, after dripping empty 1.5min, adopt clear water to clean 1.5min again, after dripping again empty 1.5min, process 0.7min workpiece is placed 90 ℃ hot water.
CN201210372952.7A 2012-09-29 2012-09-29 A kind of valve body of anti-explosion valve castmethod Active CN102994890B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210372952.7A CN102994890B (en) 2012-09-29 2012-09-29 A kind of valve body of anti-explosion valve castmethod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210372952.7A CN102994890B (en) 2012-09-29 2012-09-29 A kind of valve body of anti-explosion valve castmethod

Publications (2)

Publication Number Publication Date
CN102994890A true CN102994890A (en) 2013-03-27
CN102994890B CN102994890B (en) 2016-03-02

Family

ID=47923994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210372952.7A Active CN102994890B (en) 2012-09-29 2012-09-29 A kind of valve body of anti-explosion valve castmethod

Country Status (1)

Country Link
CN (1) CN102994890B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532115A (en) * 2014-12-31 2015-04-22 铜陵市经纬流体科技有限公司 Hydrogen-embrittlement-resistant high-strength soft sealing sluice valve body and preparation method thereof
CN106591693A (en) * 2016-12-20 2017-04-26 铜陵市经纬流体科技有限公司 High-sealing type valve rod for gate valve
CN106678408A (en) * 2016-12-20 2017-05-17 铜陵市经纬流体科技有限公司 Check valve body suitable for acid solutions
CN114273617A (en) * 2021-12-24 2022-04-05 福建贝得阀门有限公司 Rapid casting molding process for valve body of soft and hard sealing ball valve

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4103866A (en) * 1977-01-10 1978-08-01 Milwaukee Valve Company, Inc. Butterfly valve
JPH09511020A (en) * 1994-03-25 1997-11-04 ブリコ・エンジニアリング・リミテッド Sintered product manufacturing method
CN101081432A (en) * 2007-06-04 2007-12-05 天乾(无锡)科技有限公司 Method for founding main regulation valve body of steam turbine
CN101476085A (en) * 2009-01-08 2009-07-08 辽宁福鞍铸业集团有限公司 Method for foundry production of ultra-supercritical main steam control valve for nuclear power unit
CN101618508A (en) * 2009-07-30 2010-01-06 扬州东升汽车零部件制造有限公司 Method for producing vehicle-used stabilizer bar with high corrosion resistance
CN101745606A (en) * 2009-12-29 2010-06-23 上海应用技术学院 Casting technology method for high-rigidity gray iron hydraulic valve body
US20120160376A1 (en) * 2010-12-28 2012-06-28 The Japan Steel Works, Ltd. Heat resistant cast steel, manufacturing method thereof, cast parts of steam turbine, and manufacturing method of cast parts of steam turbine

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4103866A (en) * 1977-01-10 1978-08-01 Milwaukee Valve Company, Inc. Butterfly valve
JPH09511020A (en) * 1994-03-25 1997-11-04 ブリコ・エンジニアリング・リミテッド Sintered product manufacturing method
CN101081432A (en) * 2007-06-04 2007-12-05 天乾(无锡)科技有限公司 Method for founding main regulation valve body of steam turbine
CN101476085A (en) * 2009-01-08 2009-07-08 辽宁福鞍铸业集团有限公司 Method for foundry production of ultra-supercritical main steam control valve for nuclear power unit
CN101618508A (en) * 2009-07-30 2010-01-06 扬州东升汽车零部件制造有限公司 Method for producing vehicle-used stabilizer bar with high corrosion resistance
CN101745606A (en) * 2009-12-29 2010-06-23 上海应用技术学院 Casting technology method for high-rigidity gray iron hydraulic valve body
US20120160376A1 (en) * 2010-12-28 2012-06-28 The Japan Steel Works, Ltd. Heat resistant cast steel, manufacturing method thereof, cast parts of steam turbine, and manufacturing method of cast parts of steam turbine

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532115A (en) * 2014-12-31 2015-04-22 铜陵市经纬流体科技有限公司 Hydrogen-embrittlement-resistant high-strength soft sealing sluice valve body and preparation method thereof
CN106591693A (en) * 2016-12-20 2017-04-26 铜陵市经纬流体科技有限公司 High-sealing type valve rod for gate valve
CN106678408A (en) * 2016-12-20 2017-05-17 铜陵市经纬流体科技有限公司 Check valve body suitable for acid solutions
CN114273617A (en) * 2021-12-24 2022-04-05 福建贝得阀门有限公司 Rapid casting molding process for valve body of soft and hard sealing ball valve
CN114273617B (en) * 2021-12-24 2024-02-27 福建贝得阀门有限公司 Rapid casting molding process for valve body of soft and hard sealing ball valve

Also Published As

Publication number Publication date
CN102994890B (en) 2016-03-02

Similar Documents

Publication Publication Date Title
CN104439219B (en) A kind of casting technique of steel loop base based on casting and rolling composite forming
CN102936692B (en) Cold punching die mold steel processing method
CN102965576B (en) Preparation method of pump shaft of oil feed pump
CN102978486A (en) Aluminum alloy casting forming method for valve clack of sluice valve
CN102994890B (en) A kind of valve body of anti-explosion valve castmethod
CN102994907A (en) Casting method of check valve body
CN102994910A (en) Casting method of gate valve rod
CN102979938B (en) Casting method of valve body of check valve
CN102965571B (en) Powder metallurgy method for pump body of hydraulic pump
CN102703652A (en) Heat treatment process of hot-work-die steel for aluminum die-casting mould
CN102994906B (en) A kind of method of ball valve body
CN107893198A (en) Air bleeding valve and its casting technique in a kind of pipe-line system
CN102979956B (en) A kind of warm forging forming method of throttle valve stem
CN107201475A (en) A kind of casting preparation method of valve body
CN104404370A (en) Non-return valve casting technology
CN102974771A (en) Casting forming preparation method of pressure reducing valve body
CN102994861B (en) A kind of castmethod of spherical check valve rod
CN103060666A (en) Casting method of alloy body of spherical check valve
CN102994718A (en) Method for preparing gate valve disc through casting molding
CN102994886B (en) A kind of method of casting stopping valve valve plate processed
CN102994892B (en) A kind of swing check valve valve plate preparation method
CN104741586A (en) Valve body casting method of explosion-proof valve
CN102978554A (en) Titanium alloy valve rod preparation method of plug valve
CN102994891A (en) Method for preparing valve rod of plug valve
CN102996865B (en) Method for casting valve body of ball check valve

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160126

Address after: 244000 Anhui Tongling lion mountain eastern suburbs Office union residents committee

Applicant after: TONGLING JINGWEI FLUID SCIENCE & TECHNOLOGY Co.,Ltd.

Address before: 244121 Tongling Jinqiao Industrial Park, Tongling, Anhui

Applicant before: TONGLING GUOFANG PLUMBING TECHNOLOGY Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20171229

Address after: 541004 Dongyuan building, Seven Star District, Guilin City, Guangxi 801

Patentee after: Qiu Deliang

Address before: 244000 Anhui Tongling lion mountain eastern suburbs Office union residents committee

Patentee before: TONGLING JINGWEI FLUID SCIENCE & TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180604

Address after: 730100 Chiang Kai Ying 252, Dingyuan Industrial Park, Yuzhong County, Lanzhou, Gansu

Patentee after: GANSU ZHUDUN CIVIL DEFENSE ENGINEERING Co.,Ltd.

Address before: 510000 Guangdong science and Technology Industrial Development Zone, Guangzhou, 231 and 233 podium B1B2 Building 1, two, three, four

Patentee before: BOAO ZONGHENG NETWORK TECHNOLOGY Co.,Ltd.

Effective date of registration: 20180604

Address after: 510000 Guangdong science and Technology Industrial Development Zone, Guangzhou, 231 and 233 podium B1B2 Building 1, two, three, four

Patentee after: BOAO ZONGHENG NETWORK TECHNOLOGY Co.,Ltd.

Address before: 541004 Dongyuan building, Seven Star District, Guilin City, Guangxi 801

Patentee before: Qiu Deliang

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230804

Address after: 637200 section 2, Fenghuang Avenue, Duofu Industrial Park, Xichong County, Nanchong City, Sichuan Province

Patentee after: SICHUAN HONGFAN SPECIAL EQUIPMENT ENGINEERING Co.,Ltd.

Address before: 730100 Chiang Kai Ying 252, Dingyuan Industrial Park, Yuzhong County, Lanzhou, Gansu

Patentee before: GANSU ZHUDUN CIVIL DEFENSE ENGINEERING Co.,Ltd.

TR01 Transfer of patent right