CN102982658A - Electric capital construction meteorological disaster warning method based on refined weather forecast information and system - Google Patents

Electric capital construction meteorological disaster warning method based on refined weather forecast information and system Download PDF

Info

Publication number
CN102982658A
CN102982658A CN201210462641XA CN201210462641A CN102982658A CN 102982658 A CN102982658 A CN 102982658A CN 201210462641X A CN201210462641X A CN 201210462641XA CN 201210462641 A CN201210462641 A CN 201210462641A CN 102982658 A CN102982658 A CN 102982658A
Authority
CN
China
Prior art keywords
information
value
weather forecast
geographic position
disaster
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210462641XA
Other languages
Chinese (zh)
Inventor
戴彦
吴臻
张俊
姜巍
周海松
丁雨恒
黄海平
贺鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Nanjing NARI Group Corp
Zhejiang Electric Power Co
Original Assignee
State Grid Corp of China SGCC
Nanjing NARI Group Corp
Zhejiang Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Nanjing NARI Group Corp, Zhejiang Electric Power Co filed Critical State Grid Corp of China SGCC
Priority to CN201210462641XA priority Critical patent/CN102982658A/en
Publication of CN102982658A publication Critical patent/CN102982658A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses an electric capital construction meteorological disaster warning method based on refined weather forecast information. The electric capital construction meteorological disaster warning method based on refined weather forecast information includes receiving the refined weather forecast information, calculating corresponded weather forecast value from the refined weather forecast information based on the geographic position of a capital construction, comparing a meteorological environment value to a disaster prevention parameter threshold value and generating meteorological disaster information, querying disaster prevention strategy information from a disaster prevention expectation data base based on the meteorological disaster information and sending meteorological disaster warning information and disaster prevention strategy information. The invention further provides a warning system for the meteorological disaster warning method. With the help of refined weather forecast information and through rasterized data calculation, a meteorological environment around a specific capital construction project construction site can be forecasted and early warned in a relatively exact mode and powerful information assurance of weather forecast aspect can be provided for the safe and smooth conduction of the electric construction.

Description

Electric Power Capital Construction meteorological disaster method for early warning and system based on the Weather Forecast Information that becomes more meticulous
Technical field
The present invention relates to the meteorological disaster early warning technology, particularly a kind of Electric Power Capital Construction meteorological disaster method for early warning and system based on the Weather Forecast Information that becomes more meticulous.
Background technology
Electric Power Capital Construction is the Utilities Electric Co.s at different levels major tasks contents in every year, electric power capital construction projects at present mostly in the open and field work, the construction safety of construction project and construction speed are subject to the larger impact of meteorological disaster, and have directly affected thus construction object and the economic benefit of Utilities Electric Co..
For ensureing construction safety and the construction speed of electric power capital construction projects, bouw/infra of Utilities Electric Co. can unite local observatory at present, provide some forecast informations and weather warning information by observatory, these information generally are dealt into construction project with the note form and manage and handle mobile phone, arrange the honest jump progress by project manager or management again.
This weather information has shortcoming as follows to the meteorological disaster early warning of electric power capital construction projects construction:
1) information that sends with the note form, the information that having limited observatory provides can only be some daily public informations, such as the weather warning of key cities' forecast or compartmentalization, these information do not have specific aim to construction project, weak effect;
2) project manager who receives information or management, meteorological knowledge is limited, can only give an order by artificial judgment to the processing of meteorological disaster, and the easy like this guidance that makes the mistake has larger danger;
3) weather data does not have Data Collection, and history inversion and the condition of a disaster of disaster are assessed without any directive significance;
4) can't carry out unified meteorological disaster early warning to all across the entire province construction projects;
Summary of the invention
Therefore, the present invention proposes a kind of Electric Power Capital Construction meteorological disaster method for early warning and system based on the Weather Forecast Information that becomes more meticulous, the present invention has mainly solved following technical matters: 1) substitute the forecast short message with the Weather Forecast Information that becomes more meticulous, the expression of the data by rasterizing, in conjunction with the electric power Geographic Information System, can carry out comparatively accurate forecast and early warning to specifying construction project building site weather environment on every side.2) use computer system integrated, automatic data acquisition, automatically construction project meteorological disaster identification, emergency measure is sent in automatic matching calamity emergency storehouse, has avoided the amateur artificial commander's of project manager error.3) each weather data typing local data base has Data support to history inversion and the condition of a disaster assessment of disaster.4) can carry out unified monitoring and early warning to regional all construction projects.
Electric Power Capital Construction meteorological disaster method for early warning based on the Weather Forecast Information that becomes more meticulous of the present invention is characterized in that, may further comprise the steps:
Step 1 receives the Weather Forecast Information that becomes more meticulous;
Step 2 according to the geographic position in capital construction place, is calculated corresponding weather forecast value from the described Weather Forecast Information that becomes more meticulous;
Step 3, the parameter threshold of taking precautions against natural calamities of more described weather environment value and construction project generates meteorological disaster information;
Step 4 is inquired about the policy information of taking precautions against natural calamities according to meteorological disaster information from meteorological disaster anticipation database;
Step 5 sends meteorological disaster early warning information and the policy information of taking precautions against natural calamities.
Preferably, the Weather Forecast Information that becomes more meticulous described in the step 1 is the environment parament value of grid format.
Further preferably, described step 2 adopts the distance weighting sciagraphy to calculate the corresponding weather forecast value in described geographic position based on the environment parament value of described grid format.
Further preferably, the described employing distance weighting sciagraphy step of calculating the corresponding weather forecast value in described geographic position specifically comprises:
Obtain positional value and the environment parament value of described geographic position grid point on every side;
Calculate distance and the weight proportion of described geographic position and each grid point;
Utilize the described environment parament value of described weight proportion and each grid point, calculate the environment parament value in described geographic position by weighted average, digital average or vector method;
Comprehensive above result of calculation generates the corresponding weather forecast value in described geographic position.
Further preferably, the environment parament value of described geographic position grid point on every side comprises temperature, humidity, rainfall amount, wind speed, wind direction value; And calculate the temperature and humidity value in described geographic position by weighted average; Calculate the rainfall value in described geographic position by the digital average method; Calculate wind speed, the wind direction value in described geographic position by vector method; Comprehensive above result of calculation generates the corresponding weather forecast value in described geographic position.
The weather forecast value typing local data base in the described geographic position of further preferably, described step 2 being calculated.
In order to carry out said method, the invention allows for a kind of Electric Power Capital Construction meteorological disaster prewarning system based on the Weather Forecast Information that becomes more meticulous, it is characterized in that, comprising:
The information access part receives the Weather Forecast Information that becomes more meticulous;
The practical part of weather data according to the geographic position in capital construction place, is calculated corresponding weather forecast value from the described Weather Forecast Information that becomes more meticulous;
Disaster is differentiated part, and the parameter threshold of taking precautions against natural calamities of more described weather environment value and construction project is obtained meteorological disaster information;
The disaster alarm part is inquired about the policy information of taking precautions against natural calamities according to meteorological disaster information from meteorological disaster anticipation database;
Information release component divides, and sends meteorological disaster early warning information and the policy information of taking precautions against natural calamities.
Preferably, the described Weather Forecast Information that becomes more meticulous that partly receives of the described information access environment parament value that is grid format.
Further preferably, the practical part of described weather data adopts the distance weighting sciagraphy to calculate the corresponding weather forecast value in described geographic position based on the environment parament value of described grid format.
Further preferably, the practical part of the described weather data step that adopts the distance weighting sciagraphy to calculate the corresponding weather forecast value in described geographic position specifically comprises:
Obtain positional value and the environment parament value of described geographic position grid point on every side;
Calculate distance and the weight proportion of described geographic position and each grid point;
Utilize the described environment parament value of described weight proportion and each grid point, calculate the environment parament value in described geographic position by weighted average, digital average or vector method;
Comprehensive above result of calculation generates the corresponding weather forecast value in described geographic position.
Further preferably, the environment parament value of described geographic position grid point on every side comprises temperature, humidity, rainfall amount, wind speed, wind direction value; And
Calculate the temperature and humidity value in described geographic position by weighted average;
Calculate the rainfall value in described geographic position by the digital average method;
Calculate wind speed, the wind direction value in described geographic position by vector method;
Comprehensive above result of calculation generates the corresponding weather forecast value in described geographic position.
Further preferably, described Electric Power Capital Construction meteorological disaster prewarning system also comprises local data base, is used for the weather forecast value in the described geographic position of typing.
As seen, the present invention also calculates by the data of rasterizing by the Weather Forecast Information that becomes more meticulous, can carry out to the weather environment around the specific construction project building site comparatively accurate forecast and early warning, and realized that computer system is integrated, automatic data acquisition, automatically construction project meteorological disaster identification, automatic matching calamity emergency storehouse, send emergency measure, the foundation of science is provided for the condition of a disaster reply, broken away from the dependence to the personal experience, and each weather data typing local data base, history inversion and the condition of a disaster assessment of disaster there is Data support, realized that regional all construction projects carry out unified monitoring and early warning.
Description of drawings
Fig. 1 is the disaster early warning system one-piece construction synoptic diagram according to the embodiment of the invention.
Fig. 2 is the process flow diagram that adopts the calculating of distance weighting sciagraphy and the corresponding weather forecast value in geographic position in the embodiment of the invention.
Fig. 3 is the process flow diagram that generates meteorological disaster information in the embodiment of the invention.
Embodiment
With reference to the accompanying drawings the present invention is described more fully, exemplary embodiment of the present invention wherein is described.
Fig. 1 is the disaster early warning system one-piece construction synoptic diagram according to the embodiment of the invention.The present invention is a kind of Electric Power Capital Construction meteorological disaster prewarning system based on the Weather Forecast Information that becomes more meticulous, it comprises that information access part 1, the practical part 2 of weather data, disaster differentiation part 3, disaster alarm part 4, information release component divide 5, and above each several part is electrically connected successively.
Information access part 1 receives the Weather Forecast Information that becomes more meticulous that observatory provides by communication line.The content of Weather Forecast Information of becoming more meticulous can comprise radar Doppler 1-3 hour heavy showers short forecasting, radar Doppler thunderbolt in 1 hour potentiality short forecasting, 1-72 hour lattice point numerical forecasting, by the time typhoon forecast information, these forecast informations are environment parament values of the raster data form that produces after being processed by observatory's processing.Wherein two radar Doppler information are by a hour issue, raster data interval 5*5 kilometer range; Twice issue lattice point numerical value forecast information every day, the forecast interval by hour, forecast duration 1-72 hour uses the ground floor data, content is temperature, wind speed, wind direction.Typhoon forecast information is pursued a hour issue when pursuing behind Landed Typhoon, content distributed current location wind speed and direction, following 12,24 hours shift positions of comprising.The environment parament value of described rasterizing accesses the native system that is positioned at Electric Power Capital Construction department by information access part 1, and data deposit the meteorogical phenomena database of native system in.
The practical part 2 of weather data is according to residing geographic position, actual capital construction place, environment parament value based on described grid format, adopt the distance weighting sciagraphy to calculate the corresponding weather forecast value in described geographic position, thereby be the weather environment forecast of construction project by hour definite its geographic location, differentiating for next step meteorological disaster provides data.Fig. 2 shows the process flow diagram that adopts the calculating of distance weighting sciagraphy and the corresponding weather forecast value in geographic position.The practical part 2 of weather data obtains the residing geographic position data in capital construction place from Geographic Information System 6, then the rasterizing data projection is arrived the capital construction website, extract four the grid point positions nearest with the geographic position in capital construction place, thereby obtain positional value and the corresponding environment parament value of each location point of four grid points around the described geographic position, described parameter value comprises the data such as temperature, humidity, rainfall amount, wind speed, wind direction value; Then the practical part of weather data 2 is calculated the distance of four grid points and capital construction website, and than as the weight ratio coefficient, directly corresponding temperature, the humidity value with four grid points is multiplied by weight ratio coefficient calculations capital construction website temperature, humidity take distance; For rainfall, because grid point reaches the 5*5 kilometer, directly use the rainfall value mean value calculation of four grid points.To wind speed, wind direction wind speed, the wind direction vector quantization with four grid points, take wind direction as direction, wind speed is the vector size, calculate the value of making a concerted effort of four vectors at the capital construction website, be wind speed, the wind direction value of capital construction website; Comprehensive above result of calculation generates the corresponding weather forecast value in described geographic position.
All kinds of weather environments are according to the impact on construction project, its type is divided into the harm such as strong wind, heavy rain, high temperature, thunderbolt, strong convection, corresponding with it, there is the maximum parameter threshold of taking precautions against natural calamities at the capital construction scene, such as the windproof rank in capital construction building site, heavy rain rank, high-temperature levels etc., reflected that the gas such as maximum wind power that the capital construction building site can bear, rainfall amount, temperature are as environmental threshold value.Disaster is differentiated the parameter threshold of taking precautions against natural calamities that part 3 obtains construction project, and this parameter threshold of taking precautions against natural calamities can be inputted by hand or automatically transfer from the parameter database 7 of taking precautions against natural calamities of construction project.Disaster is differentiated the weather environment value of taking precautions against natural calamities parameter threshold and being exported by the practical part 2 of weather data of part 3 more described construction projects, obtains meteorological disaster information, comprises disaster kind, disaster time of origin, disaster duration, disaster rank etc.Fig. 3 shows disaster and differentiates the process flow diagram that part 3 execution are relatively judged, comprise the weather forecast value that reads capital construction point, and the described parameter threshold of taking precautions against natural calamities of reading, then carry out respectively the judgement to high temperature, heavy rain, typhoon, thunderbolt and strong convection, comprise the temperature forecast value whether out-of-limit value, rainfall predicted value whether cross limit value, whether the typhoon influence scope, whether lightning risk is arranged, whether have strong convective weather and produce, generate described meteorological disaster information if one of above type meets.
Disaster alarm part 4 is according to above-mentioned meteorological disaster information, automatic matching is applicable to the policy information of taking precautions against natural calamities of disaster kind, rank, time from meteorological disaster anticipation database 8, thereby generate disaster anticipation scheme, comprise disaster alarm mode, disaster prevention method, the prophylactico-therapeutic measures of capital construction building site etc.
Information release component divides 5, receive meteorological disaster early warning information and the policy information of taking precautions against natural calamities, and report to the police by different way by power grid GIS, note system, provide corresponding disaster prevention method, the prophylactico-therapeutic measures of capital construction building site and historical disaster information inquiry at query interface simultaneously.The present invention also is that local data base is separately set up in each capital construction place, thereby with the weather forecast value typing local data base of geographic location, capital construction place, judges the reference frame of research as local meteorologic analysis.
As seen, the present invention also calculates by the data of rasterizing by the Weather Forecast Information that becomes more meticulous, can carry out to the weather environment around the specific construction project building site comparatively accurate forecast and early warning, and realized that computer system is integrated, automatic data acquisition, automatically construction project meteorological disaster identification, automatic matching calamity emergency storehouse, send emergency measure, the foundation of science is provided for the condition of a disaster reply, broken away from the dependence to the personal experience, and each weather data typing local data base, history inversion and the condition of a disaster assessment of disaster there is Data support, realized that regional all construction projects carry out unified monitoring and early warning.
Above content is preferred embodiment of the present invention only, for those of ordinary skill in the art, according to thought of the present invention, all will change in specific embodiments and applications, and this description should not be construed as limitation of the present invention.

Claims (10)

1. the Electric Power Capital Construction meteorological disaster method for early warning based on the Weather Forecast Information that becomes more meticulous is characterized in that, may further comprise the steps:
Step 1 receives the Weather Forecast Information that becomes more meticulous;
Step 2 according to the geographic position in capital construction place, is calculated corresponding weather forecast value from the described Weather Forecast Information that becomes more meticulous;
Step 3, the parameter threshold of taking precautions against natural calamities of more described weather environment value and construction project generates meteorological disaster information;
Step 4 is inquired about the policy information of taking precautions against natural calamities according to meteorological disaster information from meteorological disaster anticipation database;
Step 5 sends meteorological disaster early warning information and the policy information of taking precautions against natural calamities.
2. method according to claim 1 is characterized in that, the Weather Forecast Information that becomes more meticulous described in the step 1 is the environment parament value of grid format.
3. method according to claim 2 is characterized in that, described step 2 adopts the distance weighting sciagraphy to calculate the corresponding weather forecast value in described geographic position based on the environment parament value of described grid format.
4. method according to claim 3 is characterized in that, the step that described employing distance weighting sciagraphy calculates the corresponding weather forecast value in described geographic position specifically comprises:
Obtain positional value and the environment parament value of described geographic position grid point on every side;
Calculate distance and the weight proportion of described geographic position and each grid point;
Utilize the described environment parament value of described weight proportion and each grid point, calculate the environment parament value in described geographic position by weighted average, digital average or vector method;
Comprehensive above result of calculation generates the corresponding weather forecast value in described geographic position.
5. method according to claim 1 is characterized in that, described method also comprises the weather forecast value typing local data base in the described geographic position that described step 2 is calculated.
6. the Electric Power Capital Construction meteorological disaster prewarning system based on the Weather Forecast Information that becomes more meticulous is characterized in that, comprising:
The information access part receives the Weather Forecast Information that becomes more meticulous;
The practical part of weather data according to the geographic position in capital construction place, is calculated corresponding weather forecast value from the described Weather Forecast Information that becomes more meticulous;
Disaster is differentiated part, and the parameter threshold of taking precautions against natural calamities of more described weather environment value and construction project is obtained meteorological disaster information;
The disaster alarm part is inquired about the policy information of taking precautions against natural calamities according to meteorological disaster information from meteorological disaster anticipation database;
Information release component divides, and sends meteorological disaster early warning information and the policy information of taking precautions against natural calamities.
7. early warning system according to claim 6 is characterized in that, the environment parament value that the described Weather Forecast Information that becomes more meticulous that described information access partly receives is grid format.
8. early warning system according to claim 7 is characterized in that, the practical part of described weather data adopts the distance weighting sciagraphy to calculate the corresponding weather forecast value in described geographic position based on the environment parament value of described grid format.
9. early warning system according to claim 8 is characterized in that, the step that the practical part of described weather data adopts the distance weighting sciagraphy to calculate the corresponding weather forecast value in described geographic position specifically comprises:
Obtain positional value and the environment parament value of described geographic position grid point on every side;
Calculate distance and the weight proportion of described geographic position and each grid point;
Utilize the described environment parament value of described weight proportion and each grid point, calculate the environment parament value in described geographic position by weighted average, digital average or vector method;
Comprehensive above result of calculation generates the corresponding weather forecast value in described geographic position.
10. early warning system according to claim 6 is characterized in that, described early warning system also comprises local data base, is used for the weather forecast value in the described geographic position of typing.
CN201210462641XA 2012-11-16 2012-11-16 Electric capital construction meteorological disaster warning method based on refined weather forecast information and system Pending CN102982658A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210462641XA CN102982658A (en) 2012-11-16 2012-11-16 Electric capital construction meteorological disaster warning method based on refined weather forecast information and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210462641XA CN102982658A (en) 2012-11-16 2012-11-16 Electric capital construction meteorological disaster warning method based on refined weather forecast information and system

Publications (1)

Publication Number Publication Date
CN102982658A true CN102982658A (en) 2013-03-20

Family

ID=47856582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210462641XA Pending CN102982658A (en) 2012-11-16 2012-11-16 Electric capital construction meteorological disaster warning method based on refined weather forecast information and system

Country Status (1)

Country Link
CN (1) CN102982658A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103854234A (en) * 2014-03-03 2014-06-11 国网河南省电力公司 Coal-fired power plant fire coal storage early warning method taking rainfall influence into account
CN105069558A (en) * 2015-07-28 2015-11-18 江苏励维逊电气科技有限公司 Warning and analyzing method for power facility damage based on meteorological data
CN105447770A (en) * 2015-12-10 2016-03-30 国网四川省电力公司电力科学研究院 Assessment method for applying power grid monitoring data to refined weather forecast
CN106707372A (en) * 2016-12-30 2017-05-24 山东鲁能软件技术有限公司 Fine weather forecast method based on power grid GIS
CN107608982A (en) * 2016-07-11 2018-01-19 中国四维测绘技术有限公司 Method, Meteorological Services platform and the system of the weather information service of object-oriented
CN112285807A (en) * 2019-11-12 2021-01-29 北京嘉韵楷达气象科技有限公司 Meteorological information prediction method and device
CN115240362A (en) * 2022-06-30 2022-10-25 江西大正智能信息技术有限公司 Monitoring alarm system and method of intelligent construction site management and control platform

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
中国气象局预测减灾司: "《天气预报技术文集(2008)》", 30 November 2008 *
国家环境保护总局: "《小城镇环境规划编制技术指南》", 31 December 2002, 中国环境科学出版社 *
宋健 等: "地质灾害精细化气象临近预警系统的设计与实现", 《浙江气象》 *
邓兴旺: "利用数值预报产品制作夏季降水分县分级预报试验", 《气象》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103854234A (en) * 2014-03-03 2014-06-11 国网河南省电力公司 Coal-fired power plant fire coal storage early warning method taking rainfall influence into account
CN103854234B (en) * 2014-03-03 2017-01-25 国网河南省电力公司 Coal-fired power plant fire coal storage early warning method taking rainfall influence into account
CN105069558A (en) * 2015-07-28 2015-11-18 江苏励维逊电气科技有限公司 Warning and analyzing method for power facility damage based on meteorological data
CN105447770A (en) * 2015-12-10 2016-03-30 国网四川省电力公司电力科学研究院 Assessment method for applying power grid monitoring data to refined weather forecast
CN107608982A (en) * 2016-07-11 2018-01-19 中国四维测绘技术有限公司 Method, Meteorological Services platform and the system of the weather information service of object-oriented
CN106707372A (en) * 2016-12-30 2017-05-24 山东鲁能软件技术有限公司 Fine weather forecast method based on power grid GIS
CN112285807A (en) * 2019-11-12 2021-01-29 北京嘉韵楷达气象科技有限公司 Meteorological information prediction method and device
CN112285807B (en) * 2019-11-12 2023-11-07 北京嘉韵楷达气象科技有限公司 Meteorological information prediction method and device
CN115240362A (en) * 2022-06-30 2022-10-25 江西大正智能信息技术有限公司 Monitoring alarm system and method of intelligent construction site management and control platform

Similar Documents

Publication Publication Date Title
CN102982658A (en) Electric capital construction meteorological disaster warning method based on refined weather forecast information and system
TWI338143B (en) Electric utility storm outage management
KR101809629B1 (en) Method and system for forecasting detailed information of urban heat using the um ldaps
CN103337133B (en) Based on the electrical network Thunderstorm early warning system and the method that identify forecasting technique
Zhou et al. Forecast of low visibility and fog from NCEP: Current status and efforts
JP5940922B2 (en) Renewable energy prediction device
CN110908014B (en) Galloping refined correction forecasting method and system
CN105069558A (en) Warning and analyzing method for power facility damage based on meteorological data
CN104951993A (en) Comprehensive monitoring and early warning system based on meteorology and power grid GIS and method thereof
CN104950348B (en) The correlating method of a kind of weather data and electrical network facilities and system
CN102254239A (en) Power grid wind damage early warning system based on micro-landform wind field distribution and typhoon superimposed effect
US11105958B2 (en) Systems and methods for distributed-solar power forecasting using parameter regularization
CN103700032A (en) Construction method of power grid regulation and control integration panoramic data platform
CN109541602A (en) A kind of fine early warning of Doppler radar meteorology vector quantization power grid and regulator control system
CN116780583B (en) Intelligent energy storage method, system, equipment and medium for photovoltaic power generation
CN115549292A (en) Power grid operation monitoring system and method thereof
CN109471205B (en) Monitoring and early warning method based on gridding meteorological data in power grid operation
KR102134861B1 (en) Climate information based electrical equipment degradation diagnosis system
CN114518612A (en) Thunderstorm risk early warning method and system and electronic equipment
CN111027827A (en) Method and device for analyzing operation risk of bottom-preserving communication network and computer equipment
CN111371484B (en) Unmanned aerial vehicle base station control method, device and system and computer readable storage medium
CN106773813B (en) Power consumption control method and device
Raschke et al. Vulnerability of the Swiss electric power transmission grid against natural hazards
CN114186726A (en) Meteorological data processing method, and prompting method and device based on meteorological data
CN113609406A (en) High-altitude operation trend information sharing method, system and equipment based on geocoding

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130320