sintering
raw material
inner rotating
alloy powder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104917877A
Other languages
Chinese (zh)
Other versions
CN102962459B (en
Inventor
申建中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang fire Polytron Technologies Inc
Original Assignee
ZHEJIANG YIHUO TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG YIHUO TECHNOLOGY Co Ltd filed Critical ZHEJIANG YIHUO TECHNOLOGY Co Ltd
Priority to CN201210491787.7A priority Critical patent/CN102962459B/en
Publication of CN102962459A publication Critical patent/CN102962459A/en
Application granted granted Critical
Publication of CN102962459B publication Critical patent/CN102962459B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Powder Metallurgy (AREA)

Abstract

The invention discloses a method for manufacturing a rotating shuttle inner shuttle through an injection molding method. The rotating shuttle inner shuttle adopts the following alloy material: Fe2NiMo, FeCrMo or FeCr; and the manufacturing method of the rotating shuttle inner shuttle comprises the following steps: firstly, performing segregation-free mixing on raw material alloy powder, secondly, performing alloying treatment on the raw material alloy powder, thirdly, grinding and screening the raw material alloy powder, fourthly, performing feed preparation on the raw material alloy powder, fifthly, performing injection molding on feed, sixthly, sintering a molded rotating shuttle inner shuttle, seventhly, performing surface shaping treatment, so as to achieve the required size, and eighthly, performing sandblasting or polishing treatment on the surface of the rotating shuttle inner shuttle. The method has the advantages that Fe2NiMo, FeCrMo or FeCr is adopted as raw material, so that composition segregation and unnecessary internal impurities are eliminated, and the sintering and shrinkage uniformity of the product is good.

Description

A kind of method of utilizing injection moulding to make inner rotating-shuttle
Technical field
The present invention relates to the sewing machine accessory, relate in particular to the inner rotating-shuttle in the sewing machine.
Background technology
Inner rotating-shuttle is one of main accessory in the rotating shuttle.The tatting structure is complicated in being somebody's turn to do, and makes meticulous.Existing preparation method generally adopts cold extrusion and car, mill machining process makes, and it is loaded down with trivial details to make manufacturing procedure, and complex process (up to 300 multiple working procedures) can't large-scale production, and the metal material utilization rate is low.
Summary of the invention
Technical problem to be solved by this invention just provides a kind of method of utilizing injection moulding to make inner rotating-shuttle, and technique is simple, and production efficiency is high, and the metal material utilization rate is high.
For solving the problems of the technologies described above, the present invention adopts following technical scheme: a kind of method of utilizing injection moulding to make inner rotating-shuttle, it is characterized in that: the alloy material that described inner rotating-shuttle adopts is Fe2Ni Mo, FeCrMo or FeCr, and the manufacture method of this inner rotating-shuttle comprises the steps:
(1) raw material alloy powder being carried out segregation-free mixes;
(2) raw material alloy powder is carried out Alloying Treatment;
(3) raw material alloy powder is ground sieve,
(4) raw material alloy powder is carried out feedstock preparation;
(5) feeding is carried out injection moulding;
(6) inner rotating-shuttle carries out sintering after the moulding;
(7) surperficial Shape correction reaches required size;
(8) sandblast or polishing are carried out in the surface.
Preferably, to contain by weight 0.2~0.3%Mo powder, 1.5~2.5% carbonyl nickel powders, surplus be carbonyl iron dust to the raw material alloy powder of described Fe2Ni Mo.
Preferably, to contain by weight 0.2~0.3%Mo powder, 1.5~2.5%Cr powder, surplus be carbonyl iron dust to the raw material alloy powder of described FeCrMo.
Preferably, the raw material alloy powder of described FeCr contains 0.5~1.5%Cr powder by weight, surplus is carbonyl iron dust.
Preferably, the granularity behind the described raw material alloy powder mill sieve is 0.5 ~ 80 micron.
Preferably, 200 ~ 800 ℃ of the temperature of described Alloying Treatment, alloying time 0.2 ~ 6 hour.
Preferably, described injection molding condition is 140 ~ 180 ℃ of injection temperatures, injection pressure 80 ~ 100MPa, 10 ~ 60 ℃ of mold temperatures.
Preferably, the condition of described sintering is 800~1300 ℃ of sintering temperatures, and sintering time is 20 ~ 3600min, and atmosphere is vacuum-sintering or protective atmosphere sintering.
Preferably, sintering adopts continuous sintering furnace, this continuous sintering furnace comprises a combined type body of heater, the burner of described body of heater is provided with liftable fire door and charging aperture, the stove tail is provided with liftable fire door and discharging opening, described body of heater is disposed with the degreasing section from burner to the stove tail, sintering stage, the slow cooling section, cooling section, described degreasing section is provided with at least one inert gas pipeline, the gas outlet subsection setup of described inert gas pipeline is in degreasing section burner hearth, simultaneously degreasing section is provided with at least one control carbon gas pipeline, the gas outlet subsection setup of described control carbon gas pipeline is in degreasing section burner hearth, described inert gas pipeline enters burner hearth from degreasing section left end, described control carbon gas pipeline enters burner hearth from degreasing section right-hand member, and described inert gas pipeline and control carbon gas pipeline are provided with flow control valve.
Preferably, described degreasing section is provided with at least two cooling passages that are communicated with flue and body of heater outer air, and this cooling passage is for closing and regulate the adjustable passage of throughput.
It is raw material that the present invention adopts Fe2Ni Mo, FeCrMo or FeCr, has eliminated component segregation and unnecessary intrinsic contaminants, product sintering shrinkage high conformity; Raw material powder particle size carries out proportioning as required between nanometer to 80 micron regulates, and cost of material is significantly reduced, and product density, performance are satisfied the demand.
In addition, the present invention sets up the shaping step, eliminates the product rejection that causes because of micro-deformation, improves product percent of pass, reduces product rejection rate.
Thereby technique of the present invention is simple, and production efficiency is high, and the metal material utilization rate is high.
Description of drawings
The invention will be further described below in conjunction with the drawings and specific embodiments:
Fig. 1 is the used sintering furnace structural representation of sintering;
Fig. 2 is degreasing section inert gas pipeline structural representation;
Fig. 3 is degreasing section cooling vent hole structure schematic diagram;
Fig. 4 is the long-pending wax jar structure schematic diagram of degreasing section;
Fig. 5 is the slow cooling section structural representation;
Fig. 6 is the cooling section structural representation;
Fig. 7 is cooling section admission line structural representation;
Fig. 8 is gas distribution pipe structural representation in the cooling section admission line;
Fig. 9 is the temperature alarming device structural representation;
Figure 10 is temperature alarming device control principle schematic diagram.
The specific embodiment
The below specifies the embodiment of inner rotating-shuttle manufacture method of the present invention.
Embodiment 1:
Alloy material is Fe2Ni Mo, and its raw material consists of: 2% carbonyl nickel powder, 0.25%Mo powder, remaining powder are carbonyl iron dust, 0.5 ~ 80 micron of raw material granularity.At first alloy powder carries out segregation-free and mixes, and then alloy powder is placed in the stove Alloying Treatment under protective atmosphere.200 ~ 800 ℃ for the treatment of temperatures, alloying time 0.2 ~ 6 hour, it is vacuum drying oven that Alloying Treatment adopts body of heater, have continuous oven or batch stove of logical protective gas (inert gas, reducibility gas).After the Alloying Treatment, powder grinds sieve.The raw alloy Powder Particle Size that obtains behind the mill sieve is 0.5 ~ 80 micron.Then raw material alloy powder is carried out feedstock preparation, again feeding is carried out injection moulding; Inner rotating-shuttle carries out sintering after the moulding.
The comparing embodiment of embodiment 1 is to inject with equigranular atomizing 20Cr material; Under the equal conditions, behind the sintering, Fe2Ni material scantling first-time qualification rate 90%, 20Cr material, first-time qualification rate 60%; Atomizing 20Cr scantling shows the size abnormal deformation, and shrinkage factor is inconsistent.
Embodiment 2:
Alloy material is FeCrMo, and its raw material consists of: 1%Cr powder, 0.25%Mo powder, all the other are carbonyl iron dust, 0.5 ~ 80 micron of raw material granularity.At first carry out segregation-free and mix, then raw material alloy powder is placed in the stove Alloying Treatment under protective atmosphere.200 ~ 800 ℃ for the treatment of temperatures, alloying time 0.2 ~ 6 hour.After the Alloying Treatment, powder grinds sieve.The raw alloy Powder Particle Size that obtains behind the mill sieve is 0.5 ~ 80 micron.Then raw material alloy powder is carried out feedstock preparation, again feeding is carried out injection moulding; Inner rotating-shuttle carries out sintering after the moulding.
The comparing embodiment of embodiment 2 is injected with equigranular atomizing 20Cr material; Under the equal conditions, behind the sintering, Fe2Ni material scantling first-time qualification rate 92%, 20Cr material, first-time qualification rate 61.5%; Atomizing 20Cr scantling shows the size abnormal deformation, and shrinkage factor is inconsistent.
Embodiment 3:
Alloy material is FeCr, and its raw material consists of: the 1%Cr powder, remaining is carbonyl iron dust, 0.5 ~ 80 micron of raw material granularity.At first carry out segregation-free and mix, then raw material alloy powder is placed in the stove Alloying Treatment under protective atmosphere.200 ~ 800 ℃ of Alloying Treatment temperature, alloying time 0.2 ~ 6 hour.After the Alloying Treatment, powder grinds sieve.The raw alloy Powder Particle Size that obtains behind the mill sieve is 0.5 ~ 80 micron.Then raw material alloy powder is carried out feedstock preparation, again feeding is carried out injection moulding; Inner rotating-shuttle carries out sintering after the moulding.
The comparing embodiment of embodiment 3 is injected with equigranular atomizing 20Cr material; Under the equal conditions, behind the sintering, FeCr scantling first-time qualification rate 90.2%, 20Cr material, first-time qualification rate 61.2%; Atomizing 20Cr scantling shows the size abnormal deformation, and shrinkage factor is inconsistent.
Among above-mentioned three embodiment, inner rotating-shuttle needs surperficial Shape correction to reach required size behind the sintering, and then sandblast or polishing are carried out in the surface.
Above-mentioned comparative example fully shows, adopts raw material of the present invention, carries out injection moulding, and the first-time qualification rate of product is greatly improved behind the sintering, and raw material of the present invention and manufacture method have significant superiority.
The below to moulding after inner rotating-shuttle carry out the used sintering furnace of sintering and make and specifying.
As shown in Figure 1, continuous sintering furnace for the present invention's employing, it comprises a combined type body of heater, the burner of described body of heater is provided with the liftable fire door and charging aperture 6, stove tail are provided with liftable fire door and discharging opening 60, and described body of heater is disposed with degreasing section 1, sintering stage 2, slow cooling section 3, cooling section 4 from burner to the stove tail.Described furnace binding is meshbeltfurnace or stepping beam type continuous oven; When employing pushed away boat structure sintering furnace, material boat size and fire box temperature were the integral multiple relation.
Adopt external cycling mechanism between described charging aperture 6 and the discharging opening 60.This outer circulation mechanism adopts sprocket wheel, belt or gear drive to realize.
Described body of heater is provided with sample tap 150 at the linkage section 15 of degreasing section and sintering stage, and described sample tap adopts upper shed or side opening mode.This sample tap adopts mechanical pull bar or bolted mode to open or close sample tap.
Such as Fig. 2 to the concrete structure that Figure 4 shows that the degreasing section, described degreasing section is provided with at least one inert gas pipeline 11, the gas outlet subsection setup of described inert gas pipeline is in degreasing section burner hearth 13, simultaneously degreasing section is provided with at least one control carbon gas pipeline 12, and the gas outlet subsection setup of described control carbon gas pipeline is in degreasing section burner hearth 13.Inert gas pipeline 11 and control carbon gas pipeline 12 can arrange a row or multi-row gas outlet vertically.Inert gas pipeline 11 is provided with three among Fig. 2, is respectively the first inert gas pipeline 110, the second inert gas pipeline 111, the 3rd inert gas pipeline 112, and its length that stretches into burner hearth 13 inside is different.Control carbon gas pipeline 12 also can adopt the structure identical with inert gas pipeline 11.The adjusting of control carbon gas flow direction can be undertaken by rotating control carbon gas pipeline 12, control carbon gas pipeline two ends are rotatably connected on the tuning movable joint, specifically can adopt thread connection, control carbon gas pipeline is provided with handle, turning handle, then the gas outlet direction is rotated with control carbon gas pipeline 12 and is changed, certainly, for the adjusting of the gas outlet direction that realizes inert gas pipeline 11, it also can adopt the tuning movable joint structure.
Described degreasing section is provided with at least two cooling passages 131 that are communicated with flue and body of heater outer air, and this cooling passage is for closing and regulate the adjustable passage of throughput.This cooling passage 131 passes heat-insulation layer 130 and is communicated with degreasing section flue.Passage 131 adopts the natural ventilation mode.When needs are regulated zone temperatures, can realize that by the openings of sizes of opening this section upper shed can cover opening with a rotating baffle plate, flap shutter can be regulated openings of sizes.
Control carbon gas in the described control carbon gas pipeline adopts decarburization atmosphere, and this decarburization atmosphere is H 2Perhaps H 2O or decomposed ammonia body or CO 2Perhaps O 2Also or the combination of above-mentioned gas.
Described degreasing section front end below arranges long-pending wax tank 14, and described long-pending wax tank is provided with grafting wax mouth 140, inert gas entrance 141 and exhaust-valve 142.
Be illustrated in figure 5 as the concrete structure of slow cooling section, described slow cooling section 3 arranges air-cooled jacket structured, be about to the slow cooling section and be set to the jacket pipe structure, outer tube sleeve on inner pipe, have certain space to form air-cooled chuck inner chamber 30 between outer tube and the inner tube, described air-cooled chuck inner chamber 30 is inwardly dried by an air blast 31.
Such as Fig. 6 to Figure 8 shows that the cooling section concrete structure, described cooling section arranges a liftable separated door 40 cooling section is separated, described cooling section in liftable separated door front side and rear side be respectively equipped with admission line 41, the admission line of described separated door front side is used for carrying reducibility gas, and the admission line of described separated door rear side is used for carrying inert gas.
Wherein, described admission line 41 comprises that one extends transversely into the gas distribution pipe 411 of cooling section, and these gas distribution pipe two ends are slip-knot 413, and gas distribution pipe is provided with several gas outlets 412.Slip-knot and gas distribution pipe adopt spiral marking connection, when needs are adjusted airflow direction, realize by rotating the gas distribution pipe angle.
As shown in Figure 9 and Figure 10, temperature alarming device on the degreasing section describes as example, degreasing section burner hearth 13 outer heat-insulation layers 130 are provided with a main temperature thermocouple 51 and a tracking and temperature testing thermocouple 50, described main temperature thermocouple and tracking and temperature testing thermocouple are connected with switch board 5, and switch board is provided with one and follows the tracks of overtemperature alarm 52.Switch board 5 internal controller judge whether overtemperature according to the data that main temperature thermocouple 51 and a tracking and temperature testing thermocouple 50 record, if overtemperature, then control is followed the tracks of overtemperature alarm 52 and reported to the police.
Temperature alarming device on the sintering stage is identical with temperature alarming device structure on the above-mentioned degreasing section.
In addition, the heater of described degreasing section and sintering stage adopts silicon carbide heater, and described sintering furnace arranges the sintered dimensions image acquistion system at degreasing section, sintering stage.This system has photoelectric coupling mechanism, has optical system, signal processing system, sintering shrinkage curve setting program and pushes away the compositions such as boat time setting program.
The slow cooling section is provided with protective gas admission line 32, and as the usefulness that passes into sintering gas shield gas, the slow cooling section arranges thermocouple temperature measuring apparatus, is used for the temperature of monitoring slow cooling section, is convenient in time adjust cooling velocity, reduces deformation of products.
Beneficial effect of the present invention is:
1, set up the inert gas pipeline in the segmentation of degreasing section, pipeline can carry out flow and airflow direction adjusting at different warm areas as required;
2, for avoiding the uniformity in airflow influence temperature field, establish the cooling passage in the degreasing section flue outside, avoid the burner hearth internal temperature uncontrollable;
3, in the degreasing section control carbon gas pipeline is set, control carbon gas can be adjusted at different sections as required, and airflow direction was adjustable after control carbon gas entered burner hearth inside;
4, control carbon gas adopts decarburization atmosphere, and these atmosphere comprise H 2, H 2O, decomposed ammonia body, CO 2, O 2And their combination, to adapt to control carbon needs.Contain O 2The mist gas ratio is controlled at non-explosive range.
5, for guaranteeing size uniform, adopt meshbeltfurnace, stepping beam type continuous oven; When pushing away boat structure sintering furnace, material boat size and fire box temperature are the integral multiple relation.
6, (sintering stage and cooling section) air inlet arranges the temperature control means in the slow cooling section, and the control cooling velocity reduces deformation of products;
7, at cooling section separated door is set, separated door leading portion configuration reducibility gas pipeline, the current potential during with the cooling of assurance product;
8, for guaranteeing to separate sneaking into of oxidizing gas when door opened, the inert gas seal measure is set, oxidation when causing the product cooling to avoid oxidizing atmosphere to enter the separated door leading portion separating the fire door back segment.
9, be the inhomogeneous deformation of products that causes in the temperature field of avoiding product degreasing and sintering process, in the preferred high-quality Temperature Control Measures, the control accuracy section temperature difference of temperature ± 5 ℃.These measures comprise that high-quality carborundum heater, symmetrically arranged TEMP detect the tracking measure;
10, be to realize that effectively the sintering process size is controlled, at degreasing section, sintering stage the sintered dimensions image acquistion system be set, from motion tracking product sintered dimensions situation of change, to adjust degreasing, sintering process system;
11, for avoiding burner to amass wax, long-pending wax tank body is set under burner; On the long-pending wax tank body inert gas pipeline is set, does not need the blowing out operation to guarantee the de-waxing process, nonoxidizing gas destroys system balancing;
12, be the implementation procedure continuous production, adopt external cycling mechanism, guarantee system's continuous circulation operation.
13, at the follow-up sample tap that arranges of degreasing section, be convenient to sample analysis skimming processes situation and adjust.
The present invention is applicable to the continuous degreasing sintering of cerul, plasticity system, and sintering process can realize that carbon is controlled, and atmosphere is controlled, temperature is controlled, and product size is controlled, and Product Precision is high, can match in excellence or beauty with the vacuum drying oven sintered products.

Claims (10)

1. method of utilizing injection moulding to make inner rotating-shuttle, it is characterized in that: the alloy material that described inner rotating-shuttle adopts is Fe2Ni Mo, FeCrMo or FeCr, and the manufacture method of this inner rotating-shuttle comprises the steps:
(1) raw material alloy powder being carried out segregation-free mixes;
(2) raw material alloy powder is carried out Alloying Treatment;
(3) raw material alloy powder is ground sieve,
(4) raw material alloy powder is carried out feedstock preparation;
(5) feeding is carried out injection moulding;
(6) inner rotating-shuttle carries out sintering after the moulding;
(7) surperficial Shape correction reaches required size;
(8) sandblast or polishing are carried out in the surface.
2. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1 is characterized in that: it is carbonyl iron dust that the raw material alloy powder of described Fe2Ni Mo contains 0.2~0.3%Mo powder, 1.5~2.5% carbonyl nickel powders, surplus by weight.
3. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1 is characterized in that: it is carbonyl iron dust that the raw material alloy powder of described FeCrMo contains 0.2~0.3%Mo powder, 1.5~2.5%Cr powder, surplus by weight.
4. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1, it is characterized in that: the raw material alloy powder of described FeCr contains 0.5~1.5%Cr powder by weight, surplus is carbonyl iron dust.
5. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1, it is characterized in that: the granularity behind the described raw material alloy powder mill sieve is 0.5 ~ 80 micron.
6. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1 is characterized in that: 200 ~ 800 ℃ of the temperature of described Alloying Treatment, alloying time 0.2 ~ 6 hour.
7. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1, it is characterized in that: described injection molding condition is 140 ~ 180 ℃ of injection temperatures, injection pressure 80 ~ 100MPa, 10 ~ 60 ℃ of mold temperatures.
8. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1, it is characterized in that: the condition of described sintering is 800 ~ 1300 ℃ of sintering temperatures, and sintering time is 20 ~ 3600min, atmosphere is vacuum-sintering or protective atmosphere sintering.
9. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 1, it is characterized in that: sintering adopts continuous sintering furnace, this continuous sintering furnace comprises a combined type body of heater, the burner of described body of heater is provided with liftable fire door and charging aperture, the stove tail is provided with liftable fire door and discharging opening, described body of heater is disposed with the degreasing section from burner to the stove tail, sintering stage, the slow cooling section, cooling section, described degreasing section is provided with at least one inert gas pipeline, the gas outlet subsection setup of described inert gas pipeline is in degreasing section burner hearth, simultaneously degreasing section is provided with at least one control carbon gas pipeline, the gas outlet subsection setup of described control carbon gas pipeline is in degreasing section burner hearth, described inert gas pipeline enters burner hearth from degreasing section left end, described control carbon gas pipeline enters burner hearth from degreasing section right-hand member, and described inert gas pipeline and control carbon gas pipeline are provided with flow control valve.
10. the method for utilizing injection moulding to make inner rotating-shuttle according to claim 9, it is characterized in that: described degreasing section is provided with at least two cooling passages that are communicated with flue and body of heater outer air, and this cooling passage is for closing and regulate the adjustable passage of throughput.
CN201210491787.7A 2012-11-27 2012-11-27 Method for manufacturing rotating shuttle inner shuttle through injection molding method Active CN102962459B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210491787.7A CN102962459B (en) 2012-11-27 2012-11-27 Method for manufacturing rotating shuttle inner shuttle through injection molding method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210491787.7A CN102962459B (en) 2012-11-27 2012-11-27 Method for manufacturing rotating shuttle inner shuttle through injection molding method

Publications (2)

Publication Number Publication Date
CN102962459A true CN102962459A (en) 2013-03-13
CN102962459B CN102962459B (en) 2015-02-04

Family

ID=47793053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210491787.7A Active CN102962459B (en) 2012-11-27 2012-11-27 Method for manufacturing rotating shuttle inner shuttle through injection molding method

Country Status (1)

Country Link
CN (1) CN102962459B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103381482A (en) * 2013-08-01 2013-11-06 兰州金浩机械制造有限公司 Injection forming method for preparing helical gear
CN104338928A (en) * 2014-01-10 2015-02-11 宁波市睿科金属粉末注射成型有限公司 Cutter bit of glass cutter and machining method thereof
CN104561800A (en) * 2013-10-11 2015-04-29 浙江一火科技有限公司 Wear-resistant inner shuttle of rotating shuttle
CN104975232A (en) * 2014-04-04 2015-10-14 浙江一火科技有限公司 Wear-resistant alloy rotating shuttle
CN107584124A (en) * 2016-07-10 2018-01-16 浙江火科技股份有限公司 A kind of metal injection moulding production method of shuttle frame new alloy material
CN109468547A (en) * 2019-01-06 2019-03-15 浙江火科技股份有限公司 A kind of high-ductility abrasion-proof inner rotating-shuttle and preparation method thereof
CN109877324A (en) * 2019-03-19 2019-06-14 湖南恒基粉末科技有限责任公司 A kind of preparation method of kovar alloy Package boxes

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0456707A (en) * 1990-06-26 1992-02-24 Daido Steel Co Ltd Continuous type vacuum furnace
JPH07665A (en) * 1993-06-21 1995-01-06 Hirose Mfg Co Ltd Part of sewing machine
JPH09220395A (en) * 1996-02-19 1997-08-26 Toshiba Corp Rotating vessel of dewatering-and-washing machine
JP2003328006A (en) * 2002-05-13 2003-11-19 Ishikawajima Harima Heavy Ind Co Ltd Continuous baking unit for porous body sheet of heat- resistant alloy, and method for manufacturing the same
CN201311177Y (en) * 2008-10-16 2009-09-16 济南大学 Multi-stage continuous sintering furnace
CN102500757A (en) * 2011-11-09 2012-06-20 崔敏娟 Method for manufacturing inner shuttle of rotating shuttle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0456707A (en) * 1990-06-26 1992-02-24 Daido Steel Co Ltd Continuous type vacuum furnace
JPH07665A (en) * 1993-06-21 1995-01-06 Hirose Mfg Co Ltd Part of sewing machine
JPH09220395A (en) * 1996-02-19 1997-08-26 Toshiba Corp Rotating vessel of dewatering-and-washing machine
JP2003328006A (en) * 2002-05-13 2003-11-19 Ishikawajima Harima Heavy Ind Co Ltd Continuous baking unit for porous body sheet of heat- resistant alloy, and method for manufacturing the same
CN201311177Y (en) * 2008-10-16 2009-09-16 济南大学 Multi-stage continuous sintering furnace
CN102500757A (en) * 2011-11-09 2012-06-20 崔敏娟 Method for manufacturing inner shuttle of rotating shuttle

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103381482A (en) * 2013-08-01 2013-11-06 兰州金浩机械制造有限公司 Injection forming method for preparing helical gear
CN104561800A (en) * 2013-10-11 2015-04-29 浙江一火科技有限公司 Wear-resistant inner shuttle of rotating shuttle
CN104338928A (en) * 2014-01-10 2015-02-11 宁波市睿科金属粉末注射成型有限公司 Cutter bit of glass cutter and machining method thereof
CN104975232A (en) * 2014-04-04 2015-10-14 浙江一火科技有限公司 Wear-resistant alloy rotating shuttle
CN107584124A (en) * 2016-07-10 2018-01-16 浙江火科技股份有限公司 A kind of metal injection moulding production method of shuttle frame new alloy material
CN109468547A (en) * 2019-01-06 2019-03-15 浙江火科技股份有限公司 A kind of high-ductility abrasion-proof inner rotating-shuttle and preparation method thereof
CN109877324A (en) * 2019-03-19 2019-06-14 湖南恒基粉末科技有限责任公司 A kind of preparation method of kovar alloy Package boxes
CN109877324B (en) * 2019-03-19 2021-06-15 湖南恒基粉末科技有限责任公司 Preparation method of kovar alloy packaging box body

Also Published As

Publication number Publication date
CN102962459B (en) 2015-02-04

Similar Documents

Publication Publication Date Title
CN102962459B (en) Method for manufacturing rotating shuttle inner shuttle through injection molding method
CN102941345B (en) Method for manufacturing outer shuttle of rotating shuttle by injection molding
CN102962461B (en) Metal injection molded continuous sintering furnace
CN203044898U (en) Continuous sintering furnace for metal injection molding
CN107716918A (en) A kind of AlSi10Mg dusty materials and preparation method thereof and its application
CA3059299A1 (en) Method for producing metal powders by means of gas atomization and production plant of metal powders according to such method
CN107695338A (en) A kind of AlSi7Mg dusty materials and preparation method thereof and its application
CN203356596U (en) Metal powder injection-molding vacuum-degreasing sintering furnace with partial pressure sintering control device
CN102962458A (en) Degreasing section structure of metal injection molded continuous sintering furnace
CN109211655A (en) Device and method that is a kind of high-throughput and continuously quickly preparing alloy sample
CN102728844A (en) Method for preparing superfine iron powder at low cost
CN109877330A (en) A kind of device and application method producing 3D printing spherical metal powder
CN102962462B (en) Method for manufacturing rotating shuttle through injection molding method
CN102962456B (en) Method for manufacturing rotating shuttle lock door wrench through injection molding method
CN102941347B (en) Method for manufacturing rotating shuttle door wrench by utilizing flow temperature-pressure molding method
CN102962460B (en) Method for manufacturing rotating shuttle inner shuttle through warm flow compaction forming method
CN102962457B (en) Method for manufacturing rotating shuttle through warm flow compaction forming method
US2384971A (en) Apparatus for producing metal powder
CA1057509A (en) Metal powder production by direct reduction in an arc heater
CN108405872A (en) Preparation method and application of Fe-36Ni iron-based alloy powder
JP5601426B2 (en) Raw material charging method to blast furnace
CN102974827B (en) Method for manufacturing outer shuttle of rotating shuttle by flowing warm pressing forming method
CA1057508A (en) Metal powder production by direct reduction in an arc heater
CN108262485A (en) A kind of industrialization in-situ synthetic method of W base composite powders for adding WC hardening constituents
CN202984665U (en) Cooling zone structure of metal injection molding continuous type sintering furnace

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 321001 Zhejiang Province, Jinhua city Wucheng District Youth Industrial Zone

Patentee after: Zhejiang fire Polytron Technologies Inc

Address before: 321001 Zhejiang Province, Jinhua city Wucheng District Youth Industrial Zone

Patentee before: Zhejiang Yihuo Technology Co., Ltd.