CN102938532A - Control cable connection construction method without needs of line calibration - Google Patents

Control cable connection construction method without needs of line calibration Download PDF

Info

Publication number
CN102938532A
CN102938532A CN2012104451330A CN201210445133A CN102938532A CN 102938532 A CN102938532 A CN 102938532A CN 2012104451330 A CN2012104451330 A CN 2012104451330A CN 201210445133 A CN201210445133 A CN 201210445133A CN 102938532 A CN102938532 A CN 102938532A
Authority
CN
China
Prior art keywords
core
cable
control cables
wire size
size pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104451330A
Other languages
Chinese (zh)
Inventor
刘光武
戚双成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN ELECTRIC POWER CONSTRUCTION Co OF CHINA ENERGY ENGINEERING GROUP
Original Assignee
TIANJIN ELECTRIC POWER CONSTRUCTION Co OF CHINA ENERGY ENGINEERING GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN ELECTRIC POWER CONSTRUCTION Co OF CHINA ENERGY ENGINEERING GROUP filed Critical TIANJIN ELECTRIC POWER CONSTRUCTION Co OF CHINA ENERGY ENGINEERING GROUP
Priority to CN2012104451330A priority Critical patent/CN102938532A/en
Publication of CN102938532A publication Critical patent/CN102938532A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The invention discloses a control cable connection construction method which comprises firstly checking insulation resistance before a control cable is paved and arranging temporary cable plate on the control cable to mark specific cable information; secondly peeling and cutting a cable outer sheath at a cable terminal, sequencing according to cable core arrangement rules, and penetrating in a line size tube; and finally conducting two end connection on the control cable according to marks of the line size tube. Compared with a prior construction method, the technical scheme optimizes control cable connection construction procedures, can effectively save operation labor and time, obviously improves efficiency of construction and reduces using quantity of line calibration tools.

Description

The control cables wiring does not need the construction method of school line
Technical field
The present invention relates to electric device installing engineering cable construction field, more particularly, relate to the construction method of control cables wiring.
Background technology
In control cables terminal connection construction in the past, universal law is to select cable than the position of comparatively dense, as dish, screen cabinet place connect end as head, does not need the school line, when connecing the other end, needs the school line.The school lineman does to coordinate and carry out by two people, and both sides use intercom or the contact of school line phone, uses universal instrument or dry cell school line lamp (being commonly called as the examination lamp) school line, as shown in Figure 1, all cores is proofreaded successively, finally uses not every core of secondary wire size area under control.Concrete grammar is: two people determine public core or earth connection for the line of school at the cable two ends respectively, the every core number marking tube that connects end with cable head is as the criterion, all cores are searched successively with head and connect the corresponding core of each core of end with universal instrument or school line lamp at the cable other end, and put on corresponding wire size pipe.For avoiding getting lines crossed by electric loop, also head should be connect to the wire that end connected and pull down from terminal.After the school line completes, can carry out the operations such as wire harness colligation, terminal separated time and wiring.Take that to proofread 10 core control cables be example, from starting to connect universal instrument or school line lamp calculates, through searching each core to all having worn the wire size pipe, the required comprehensive duration of two people was approximately about 15 minutes.The control cables radical of a generating set, if calculate by 6500, average 10 cores, that is petty, and only cable checking one procedure just needs 3250 hours consuming time of accumulation, amounts to: and 3250 ÷ 8=406.25 are artificial/day.This has caused the waste in personnel and man-hour undoubtedly, the urgent need improvement of will being correlated with.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, by the critical process to before the control cables wiring, control effectively, grasp and utilize distinguishing mark and the core arrangement regulation on the control cables insulated wire cores, remove the operation of school line from control cables wiring work progress, thus reach save operation manpower and time, the purpose of raising efficiency of construction.For engineering construction, economic benefit wherein and social benefit are apparent.
Technical purpose of the present invention is achieved by following technical proposals:
The control cables wiring does not need the construction method of school line, according to following step, carries out:
At first, check insulation resistance before control cables lays, and the temporary cable board is set on control cables, to mark concrete cable information;
Secondly, the cable jacket of stripping cable terminal, sorted and penetrated the wire size pipe according to the core arrangement regulation of control cables;
Finally, carry out two terminated lines of control cables according to wire size pipe mark.
Control cables during fabrication, all adopts Arabic numerals or color (solid color or combined colors) to distinguish the different insulative core of multicore cable or indicates the function of insulated wire cores.The cable insulation core is arranged evenly with one heart by certain manufacture rule radially layered from inside to outside, as shown in accompanying drawing 2-6.
The all cores of multi-core controlled cable are all to turn round towards same direction strand during fabrication, and between all cores, (containing between each group pair twist wire) is all opposing parallel, and the mutual alignment of each core in the cable arbitrary cross-section is all constant.When confirming this end line core of cable by clockwise sequence, those ends should be by counterclockwise sequence.
When insulated wire cores adopts numeral flag, core insulate for same color, as shown in Figure 2, by internal layer, to outer, since 1, by natural numerical order clockwise (seeing in the cable opposite end for counterclockwise) direction, is arranged.A complete numeral flag is comprised of numeral and following dash, and the every upper any two groups of figure blanks of core insulation are not more than 50mm, as shown in Figure 3.
Insulated wire cores adopts when color-coded, and every one deck (being each circle) is all had any different in the standard core of same layer line core color, and other cores except the standard core are same color.Determine that outermost layer standard core is 1, sequence confirms as 2,3,4~27 by the root core in the direction of the clock, then on every core, puts on respectively secondary wire size pipe (indicating numeral 1,2,3,4~27 wire size pipes of being distinguished), as shown in Figure 4.The outermost layer standard core with distinct color of still take in the cable opposite end is 1, by counterclockwise sequence, by the root core, confirms as 2,3,4~27, puts on respectively secondary wire size pipe.As shown in Figure 5.
If all insulated wire cores are color-coded, but while not being all unique color, wherein arranging situation uniqueness and one easy to remember are defined as 1(two red folders one are blue or two red folders one are black as shown in Figure 6).Then, sequence confirms as 2,3,4~10 by the root core in the direction of the clock, puts on respectively secondary wire size pipe.Still with this rule, by counterclockwise sequence, by the root core, confirm as 2,3,4~10 in the cable opposite end, put on respectively secondary wire size pipe.
In order to distinguish control cables each core that insulate, be mainly Arabic numerals and color-coded two kinds of methods, because numeral flag is more easily identified, when at present a lot of cables manufacturing factory does not propose special the requirement the user, the control cables of production adopts the ink printing technology to carry out numeral flag to insulated wire cores mostly.For color-coded cable core, after having grasped principle and rule described above, can find out the identification rule of each core.The core quantity of control cables generally is divided into: 2,3,4,5,7,8,10,12,14,16,19,24,27,30,37,44,48,52,61, and totally 19 specifications.2,3,4,5,1-6,1-7,2-8,3-9,4-10,5-11,1-6-12,2-8-14,3-9-15,4-10-16,1-6-12-18,2-8-14-20,3-9-15-21,4-10-16-22,1-6-12-18-24 structure level number from inside to outside and the arrangement of answering in contrast are respectively:.As shown in accompanying drawing 7 and 8, the core identification that the core insulation is 19 color-coded core control cables, wherein Fig. 7 is that every layer line core color is inconsistent, selecting 1 of the unique red sign of outermost layer is the standard core, clockwise mark to 12, core below the standard core 1 of red sign is decided to be 13, then carries out clockwise mark; In Fig. 8, one of core of outermost layer different colours is decided to be to the standard core, clockwise mark, then the core below choice criteria core 1 is decided to be 13, then carries out clockwise mark.
Can remove the school line procedures from by the operation of above-mentioned main points, directly penetrate secondary wire size pipe and carry out wiring, thus reach save operation manpower and time, the purpose of raising efficiency of construction.For engineering construction, economic benefit wherein and social benefit are apparent.
In technical scheme of the present invention; by the critical process to before the control cables wiring, control effectively; grasp and utilize distinguishing mark and the core arrangement regulation on the control cables insulated wire cores; the operation of in control cables wiring work progress, removing the school line from; the method has been optimized control cables wiring working procedure; can effectively save operation manpower and time, significantly improve efficiency of construction; reduced the use amount of school lineman's utensil, reduce costs, technology maturation, easy and simple to handle, construction easily, protection of the environment, meet standard.
The accompanying drawing explanation
Carry out the loop schematic diagram of control cables school line in Fig. 1 prior art.
The 30 core control cables cores that the insulation of Fig. 2 core is numeral flag are arranged schematic diagram.
Numeral flag example schematic diagram in the insulation of Fig. 3 core.
The insulation of Fig. 4 core is for color-coded, and head connects end by clockwise sequence schematic diagram.
Fig. 5 core insulation is for color-coded, after connect end by counterclockwise sequence schematic diagram.
Fig. 6 insulated wire cores is color-coded, but is not all the identification schematic diagram of unique color.
The core identification schematic diagram that the insulation of Fig. 7 core is 19 color-coded core control cables.
The core identification schematic diagram that the insulation of Fig. 8 core is 19 color-coded core control cables.
Fig. 9 control cables lays the construction schematic diagram of front inspection insulation resistance.
Figure 10 temporary cable board is pasted schematic diagram is set.
Figure 11 insulated wire cores schematic diagram corresponding with terminal board.
Embodiment
Further illustrate technical scheme of the present invention below in conjunction with concrete enforcement.
1. good for each core insulation of control cables that guarantees to lay, before laying, control cables should check insulation resistance (as shown in Figure 9, using 500V megohm meter to measure)
For the cable that metallic sheath, screen or armouring are arranged:
Multicore cable, should be respectively be connected and be measured all the other cores and metallic sheath or screen or armour with regard to each core; Measure insulation resistance between multicore cable core and shielding, should will be measured shielding after all core parallel connections.
Non metallic sheath, non-shielding or without the cable of armouring:
Multicore cable is measured after should connecting all the other cores with regard to each core respectively.
The 10 core cables of the Digital ID shown in Fig. 9 of take are example: by 2~No. 10 line core with after the shielding drainage thread is in parallel and measure between the Line 1 core; By 3~No. 10 line core with the shielding drainage thread in parallel after and between No. 2 cores, measure, get rid of the single line core at every turn, by that analogy, until all be completed.The insulation measurement result all should be more than 200M Ω, otherwise should search reason.
2. control cables is pasted the temporary cable board before and after laying
In the past, carrying out before and after the cable laying construction is all to be tied formal cable card, the one, easily cable card is hung and caused loss in the cable laying process, the 2nd, when making cable termination stripping cable, cable card is tied position in the stripping scope and removes and cause confusion or lose.Therefore, employing is printed on large-scale Indexing tab by cable number, model, specification, voltage, the beginning and the end place device name or, on the A4 copy paper, at least the same form is two, sticks on respectively the control cables two ends of laying, as shown in figure 10.Longer cable also need be pasted in middle part, then uses the tight looping of wide adhesive tape two-layer, to cement and to estimate clear being as the criterion.The particular location of pasting should be two ends and deducts the additional length place, is positioned at outside the stripping scope.The additional length of cable is with reference to table 1.The main consideration that the temporary cable board sticks on herein is, at cable laying, cable termination stripping, terminals, makes, cable tie is fixed and the overall process of wiring can be not destroyed and lose, to the last of formal cable card replacement.Correct for guaranteeing the stickup of temporary cable board, should be responsible for by the special messenger.
Additional length when table 1 35kV and following cable laying tolerance
Figure BDA00002371084800041
Cable terminal stripping cable jacket, penetrate the wire size pipe
Control cables has laid put in place (dish, screen or equipment place), and the cable arrange-line before terminals are made completes and colligation is temporarily fixed, and it is reserved that cable length meets the longest standby core, cuts unnecessary length.
As the control cables insulated wire cores is numeral flag, can along continuous, carry out according to normal cable connection operation, make (comprise earth connection draw), cable as stripping cable, terminals and fix, wire harness colligation etc., need be in strict accordance with cable core since 1 natural numerical order from small to large when arriving the school line and wearing wire size plumber order, with the terminal board natural numerical order from small to large corresponding wire size pipe that penetrates one by one, as shown in figure 11.Then carry out following operation, as terminal separated time, wiring, ground connection, list, the work progress such as arrangement.
When the control cables wiring, head connect an end and did not need the school line in the past, and it is larger that the taking out of core connects randomness, when connecing the other end and head connect end and carry out the school line, connect end secondary wire size pipe with head and be as the criterion.If do not need the school line while making other end wiring, firstly connect an end and must penetrate according to certain rule the wire size pipe, handle and get final product by this rule during other end wiring.
As the multi-core controlled cable insulated wire cores is every layer of standard core with distinct color, when most of cores are the same color (as shown in Figure 4), at first long to cable socket stripping oversheath, steel armour and inner covering 50~80mm, expose whole cores, but must keep the original arrangement of cable core, must not be loose, to keep the original arrangement of cable core.The standard core that has distinct color with outermost layer penetrates wire size pipe 1, and sequence penetrates wire size pipe 2, wire size pipe 3 by the root core in the direction of the clock, until this layer line core has all been worn, natural number is again from second layer standard core, by that analogy until all worn.When connecing the cable other end, the standard core that still with outermost layer, has a distinct color penetrates wire size pipe 1, and penetrate wire size pipe 2, wire size pipe 3 by counterclockwise sequence by the root core, by that analogy until all worn, worn the core of wire size pipe and all made a call to turning one's head of an about 10mm, come off to avoid the wire size pipe.
The numeral flag cable core is by 1,2,3 ... natural numerical order, corresponding one by one with terminal board natural numerical order from small to large, and penetrate the secondary wire size pipe of answering in contrast.Color-coded cable core, the core that the outermost layer of take has distinct color is 1, in cable socket core 2,3, the 4 natural orders arrangements in the direction of the clock of central station of floating dock side, dish cabinet side, mains side, control side; At the cable socket core of equipment side, power side, controlled side on the spot, by 2,3,4 natural orders counterclockwise, arrange.
While running into different types of multi-core controlled cable, can adopt the method be explained by reference to the accompanying drawings in summary of the invention to position and number.
While being color-coded, after all cores are put on the wire size pipe, just can start follow-up operation when the cable insulation core, as continue stripping cable jacket, terminals making etc., after the terminal separated time completes, the wire size pipe need be smoothed out with the fingers to suitable position, cut the core of unnecessary length, finally complete wiring work.
Above the present invention has been done to exemplary description; should be noted that; in the situation that do not break away from core of the present invention, the replacement that is equal to that any simple distortion, modification or other those skilled in the art can not spend creative work all falls into protection scope of the present invention.

Claims (4)

1. the control cables wiring does not need the construction method of school line, it is characterized in that, according to following step, carries out:
At first, check insulation resistance before control cables lays, and the temporary cable board is set on control cables, to mark concrete cable information;
Secondly, the cable jacket of stripping cable terminal, sorted and penetrated the wire size pipe according to the core arrangement regulation of control cables;
Finally, carry out two terminated lines of control cables according to wire size pipe mark.
2. control cables wiring according to claim 1 does not need the construction method of school line, it is characterized in that, when described core adopts numeral flag, arrange and penetrate wire size pipe since 1 by the natural numerical order clockwise direction to outer by internal layer, in the cable opposite end, with counter clockwise direction, arrange and penetrate the wire size pipe.
3. control cables wiring according to claim 1 does not need the construction method of school line, it is characterized in that, described core adopts when color-coded, every one deck is all had any different in the standard core of same layer line core color, determine that outermost layer standard core is 1, sequence is pursued the confirmation of root core and put on respectively the wire size pipe on every core in the direction of the clock, and the outermost layer standard core with distinct color of still take in the cable opposite end is 1, by counterclockwise sorting by the confirmation of root core and putting on respectively the wire size pipe.
4. control cables wiring according to claim 1 does not need the construction method of school line, it is characterized in that, described core is color-coded, but while not being all unique color, be defined as 1 with arranging situation uniqueness wherein and one easy to remember, sequence is pursued the confirmation of root core and is put on respectively the wire size pipe in the direction of the clock, in the cable opposite end, still with this rule, by counter clockwise direction, sorts by the confirmation of root core and puts on respectively the wire size pipe.
CN2012104451330A 2012-11-08 2012-11-08 Control cable connection construction method without needs of line calibration Pending CN102938532A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104451330A CN102938532A (en) 2012-11-08 2012-11-08 Control cable connection construction method without needs of line calibration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104451330A CN102938532A (en) 2012-11-08 2012-11-08 Control cable connection construction method without needs of line calibration

Publications (1)

Publication Number Publication Date
CN102938532A true CN102938532A (en) 2013-02-20

Family

ID=47697412

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104451330A Pending CN102938532A (en) 2012-11-08 2012-11-08 Control cable connection construction method without needs of line calibration

Country Status (1)

Country Link
CN (1) CN102938532A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105448408A (en) * 2015-11-25 2016-03-30 国网辽宁省电力有限公司锦州供电公司 Cable recognition bar and method for recognizing maintenance cable through employing same
CN108173167A (en) * 2017-11-13 2018-06-15 武汉船用机械有限责任公司 A kind of electrical-optical cable laying method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH097434A (en) * 1995-06-23 1997-01-10 Mitsubishi Cable Ind Ltd Multiconductor cable
CN101950608A (en) * 2010-09-30 2011-01-19 安徽宏源特种电缆集团有限公司 Three-color or four-color spiral fluoroplastic extruded insulation installating line

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH097434A (en) * 1995-06-23 1997-01-10 Mitsubishi Cable Ind Ltd Multiconductor cable
CN101950608A (en) * 2010-09-30 2011-01-19 安徽宏源特种电缆集团有限公司 Three-color or four-color spiral fluoroplastic extruded insulation installating line

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《1000MW超超临界火电机组施工技术丛书》编委会: "《热控工程施工》", 31 March 2012, article "热控电缆敷设施工措施", pages: 219-223 *
何升: "《远动自动化(初级工)》", 31 October 1999, article "接线", pages: 177-178 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105448408A (en) * 2015-11-25 2016-03-30 国网辽宁省电力有限公司锦州供电公司 Cable recognition bar and method for recognizing maintenance cable through employing same
CN108173167A (en) * 2017-11-13 2018-06-15 武汉船用机械有限责任公司 A kind of electrical-optical cable laying method

Similar Documents

Publication Publication Date Title
CN208521482U (en) A kind of rural power grids distribution business work skill operation training cabinet
CN111308264A (en) Power distribution network single-phase earth fault section positioning method based on cosine similarity
CN107271831A (en) A kind of novel transformer substation secondary cable alignment device and method
CN112540259A (en) Distribution network disconnection fault identification method and system suitable for intelligent power distribution terminal
CN205248761U (en) Single core cable cross -bonding case
CN102938532A (en) Control cable connection construction method without needs of line calibration
CN101854017B (en) Secondary wiring method in power engineering
CN205429680U (en) Cable cross -bonding case
CN108153946B (en) Automatic export method of prefabricated cabin cable list based on standard wiring
CN201319045Y (en) Ground impedance testing cable in large-scale ground grid
CN205882178U (en) Power cable connector lug
CN102360053A (en) Method for finding out specific reticule from middle of wiring harnesses
CN202602184U (en) Special clamp for secondary wire connecting
CN201859680U (en) Spiral double-color insulated wire
CN204632563U (en) A kind of platform district test flexible current mutual inductor
CN201859682U (en) Spiral double-color insulating wire core
CN203491593U (en) Quick wire butt-joining device for multi-strand control cable
CN105353180A (en) Strong current generator with multiple uniformly distributed conductors
CN108414886A (en) A kind of mutual table method of power distribution network
CN206833970U (en) A kind of lv power cable with protection copper strips
CN204142760U (en) The general line concentrator of transformer test
CN202352398U (en) Cable special for secondary circuit for electric energy metering
CN202548265U (en) Multi-channel cable aligner
CN212410832U (en) High-efficient type secondary cable digit is to line ware
CN208596196U (en) It is a kind of intelligence armored cable to core apparatus

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Liu Guangwu

Inventor after: Qi Shuangcheng

Inventor after: Xie Zuowen

Inventor before: Liu Guangwu

Inventor before: Qi Shuangcheng

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LIU GUANGWU QI SHUANGCHENG TO: LIU GUANGWU QI SHUANGCHENG XIE ZUOWEN

C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130220