CN102912985A - Short-distance pumping method of concrete pump truck - Google Patents

Short-distance pumping method of concrete pump truck Download PDF

Info

Publication number
CN102912985A
CN102912985A CN2011102176245A CN201110217624A CN102912985A CN 102912985 A CN102912985 A CN 102912985A CN 2011102176245 A CN2011102176245 A CN 2011102176245A CN 201110217624 A CN201110217624 A CN 201110217624A CN 102912985 A CN102912985 A CN 102912985A
Authority
CN
China
Prior art keywords
jib
pumping
cantilever crane
distance pumping
short
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102176245A
Other languages
Chinese (zh)
Other versions
CN102912985B (en
Inventor
董连城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201110217624.5A priority Critical patent/CN102912985B/en
Priority claimed from CN201110217624.5A external-priority patent/CN102912985B/en
Publication of CN102912985A publication Critical patent/CN102912985A/en
Application granted granted Critical
Publication of CN102912985B publication Critical patent/CN102912985B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a short-distance pumping method of a concrete pump truck. The short-distance pumping method can be realized by utilizing a part of a cantilever crane at the tail end without unfolding the whole cantilever crane when the concrete pump truck pumps in short distance during construction. In the prior art, pumping is realized by unfolding the cantilever crane long in few tens of meters, and winding a part of the cantilever crane at the tail end when in short-distance pumping and additionally arranging an assisting discharging device and a discharging hose. The short-distance pumping method of additionally arranging the discharging device and winding the cantilever crane at the tail end is complicated in structure and difficult to realize, and severe affection can be caused on stress of the cantilever crane. In order to overcome the above defects, the invention provides a method which enables the cantilever crane to realize short-distance pumping in a reasonable stress state by utilizing a part of the cantilever crane without winding the cantilever crane at the tail end and additionally arranging the assisting discharging device and the discharging hose on the cantilever crane. By arranging a pipeline switching device at a rotating tower of the cantilever crane, assorted pipes of the cantilever crane can be switched, so that construction in a manner that the whole cantilever crane is used in long-distance pumping and only a part of the cantilever crane is used in short-distance pumping is more reasonable and practical.

Description

The method of concrete mixer short distance pumping
Technical field
The present invention relates to concrete mixer, specifically relate to the method for concrete mixer short distance pumping of concrete.
Background technology
Be widely used in now the pump truck of concreting when pumpdown, launch tens meters jib.Concrete by being installed in the jib pipe arrangement on the jib, is pumped to the place to use under the High Pressure of pumping system.Because the jointed shaft between jib and the pipe bent position in the jib pipe arrangement be on same axis, so jib and jib pipe arrangement can be curled up and received or launch under the control of arm support oil cylinder.
Concrete mixer will launch tens meters jibs and realize pumping construction when carrying out elevation or the larger pumping construction of span.When pumping of concrete elevation or span are little, only need to use a part jib to construct.This moment part end arm support receipts of curling up, concrete is by the jib pipeline on the part jib that launches and be installed in auxiliary discharging device and the additional discharging flexible pipe realization pumping construction that launches arm support tail end.Thisly can reduce pumping line length, reduce the pumping mode that jib is holded up height, reduce system pressure, pumping pressure and pipe wear, can effectively reduce use cost.
Although the short distance pumping mode can produce above good effect.But complex structure realizes that difficulty is larger.The end arm support of particularly curling up and receiving increases the pumping method that adds discharging flexible pipe and subsidiary conduit switching mechanism, weight is all concentrated acted on the ends that launch jib.To the stressed very adverse influence that produced of jib.
Summary of the invention
The present invention is directed to the deficiency that existing concrete pump truck short distance pumping construction exists, provide and to have made concrete mixer when realizing the operation of short distance pumping concrete construction, the receipts of needn't curling up end arm support, and not be used in and the subsidiary conduit switching mechanism is set on the deploying portion jib and needn't increases additional discharging flexible pipe, in the situation of jib reasonable stress, can carry out the method for short distance pumping construction.
The present invention is on the head end jib pipe arrangement of distance head end jib and the suitable distance of capstan head pedestal jointed shaft, the jib pipe arrangement is disconnected, and this section is to part jib pipe arrangement and the rotatable head end operating rocker pipe of bend pipe formation centered by capstan head jointed shaft axis of jointed shaft.Equally on the second section jib pipe arrangement of distance second section jib and the suitable distance of the 3rd joint jib jointed shaft, the jib pipe arrangement is disconnected, cleaved facet consists of the rotatable terminal operating rocker pipe centered by second, third joint jib jointed shaft axis to part jib pipe arrangement and the bend pipe of this jointed shaft.This moment, all the jib pipe arrangement was comprised of two parts: part between two switching pipelines; The terminal afterwards part of pipeline of switching.
At the jib of concrete mixer and the hinged place of jib capstan head the concrete duct switching device shifter is set.This device can be big or small apart from ground according to the pumping concrete construction operation, and the jib pipe arrangement is switched.During the long term distance pumping, the whole jibs of choice for use and corresponding jib pipe arrangement.During short closely pumping, curl up and receive the part head end jib of close jib brick tower, choice for use part end arm support and corresponding jib pipe arrangement satisfy the requirement of pumping concrete construction operation.
The objective of the invention is to realize like this ground:
Pipeline switching device is installed on the head end jib at jib capstan head place, can rotate centered by jib and jib capstan head hinge axes with the head end jib.This device is made of drive sprocket, head end sprocket wheel, terminal sprocket, terminal gear, driving chain, locking hook.Wherein the rotatable switching pipeline of head end sprocket wheel and head end coaxial line is fixedly linked, and driving chain links to each other it with drive sprocket.Terminal gear and terminal rotatable switching pipeline coaxial line are fixedly linked.During the short distance pumping, head end jib and second section, the 3rd joint jib are in the receipts state of curling up, and it is constant that locking hook guarantees that first, second two joints jib is in the receipts state relative position of curling up.Terminal sprocket and the engagement of terminal gear, driving chain links to each other terminal sprocket with drive sprocket.
In the pipe end junction sealing device is set, guarantees to connect reliable.
The present invention compares with prior art, has following good effect:
1. simple in structure, be easy to realize, make the short distance pumping reduce pressure, reduce wear, the positive effect such as energy-saving and cost-reducing obtains embodying.
2. can change the framework form of short distance pumping construction, minimizing additional facilities and they are on the stressed impact of jib.
3. in the process that short distance pumping selection jib is constructed, improve work efficiency, the pump truck job stability is obviously promoted.
Description of drawings
Fig. 1 is the working state schematic representation of pump truck short distance pumping of concrete before the invention process.
Fig. 2 is the working state schematic representation of pump truck short distance pumping of concrete after the invention process.
Fig. 3 is pipeline switching device operating principle schematic diagram.
Fig. 4 is the pump truck closely pumping jib capstan head place working state schematic representation of receiving portions jib of curling up.
Fig. 5 is that pump truck launches whole jib long distance pumping jib capstan heads place working state schematic representation.
1 is the jib capstan head among the figure, the 2nd, and head end jib, the 3rd, the jib pipe arrangement of head end jib, 4 is the 3rd joint jibs, and 5 is jib pipe arrangements of the 3rd joint jib, the 6th, and the second section jib, the 7th, the jib pipe arrangement of second section jib, the 8th, end portion jib, the 9th, the jib pipe arrangement of end portion jib, 10 pipeline switching devices, the 11st, the changeable arm pipe of head end, the 12nd, terminal changeable arm pipe, the 13rd, drive sprocket, the 14th, head end sprocket wheel, the 15th, terminal sprocket, the 16th, terminal gear, 17 driving chains, the 18th, locking hook.
The specific embodiment
The present invention will be further described below in conjunction with accompanying drawing
Fig. 1 is the working state schematic representation of pump truck short distance pumping of concrete before the invention process.
Show among the figure, implement the present invention before, when carrying out the short distance pumping or launch whole jib pumping constructions, perhaps curl up and receive the state that end arm support uses auxiliary discharging device and additional discharging flexible pipe to construct.
Fig. 2 is the working state schematic representation of pump truck short distance pumping of concrete after the invention process.
Show among the figure that behind enforcement the present invention, when carrying out the short distance pumping, the receipts of only part head end jib need being curled up utilize the part end arm support to carry out the duty of Concrete Pumping Construction.
Fig. 3 is pipeline switching device operating principle schematic diagram.
Show among the figure, when carrying out the short distance pumping construction, the head end jib 2 of concrete mixer, second section jib 6, the three joint jibs 4 are in the receipts state of curling up.Locking hook makes head end two joint jibs be in relative static conditions.At this moment, be installed in the terminal sprocket 15 on the pipeline switching device 10 on the head end jib, be in engagement with terminal gear 6.Drive sprocket 13 drives the changeable arm pipe 11 of head end, terminal changeable arm pipe 12 rotation docking.Concrete pumps from the capstan head bend pipe, and through the changeable arm pipe 11 of head end, the terminal changeable arm pipe 12 directly jib pipe arrangement 9 of the part end arm support of the jib pipe arrangement 5 by the 3rd joint jib and back is pumped to the job location.
Also show among the figure, when the whole jibs of expansion carry out the long term distance pumping, at first utilize the drive sprocket 13 of switching device shifter, drive the changeable arm pipe 11 of head end, terminal changeable arm pipe 12 rotations.The changeable arm pipe 11 of head end is docked, the state that terminal changeable arm pipe 12 docks with the jib pipe arrangement 5 of the 3rd joint jib with jib pipe arrangement 3 to the head end jib.
Fig. 4 is that pump truck is curled up the receiving portions jib closely during pumping concrete construction, jib capstan head place working state schematic representation.
Show among the figure that when the short distance pumping construction, head end jib 2 and the second jib 6, the 3rd joint jib 4 are in the receipts state of curling up.The jib pipe arrangement 3 of head end jib, the jib pipe arrangement 7 of second section jib is not participated in the state of pumping construction.
Fig. 5 is pump truck when launching whole jib long distance pumping concrete construction, jib capstan head place working state schematic representation.
Show among the figure that when long-distance pumping was constructed, head end jib 2 and the second jib 6, the 3rd joint jib 4 were in deployed condition.All the jib pipe arrangement is participated in the state of pumping construction successively.At this moment, locking hook 18 discharges, head end jib 2, second section jib 6, the three joint jibs 4, and part end arm support 8 sequential deployments.Terminal gear 16 also breaks away from engagement with terminal sprocket 15.Concrete pumps from the capstan head bend pipe, successively through the changeable arm pipe 11 of head end, the jib pipe arrangement 3 of head end jib, the jib pipe arrangement 7 of second section jib, the jib pipe arrangement 5 of terminal changeable arm pipe 12, the three joint jibs, the jib pipe arrangement 9 by the part end arm support is pumped to the job location.

Claims (3)

1. the method for concrete mixer short distance pumping, comprise concrete pumping structure, pumping line, jib capstan head, jib, jib pipe arrangement, discharging flexible pipe, concrete needs to be pumped to the place to use by whole jib pipe arrangements or part jib pipe arrangement during construction, it is characterized in that, when the short distance pumping construction, utilize pipeline switching device only to use the part end arm support that concrete pump is delivered to the place to use.
2. the method for concrete mixer short distance pumping as claimed in claim 1, it is characterized in that, curl head end part jib during the short distance pumping, the changeable arm pipe of head end (11) perforation that is connected with terminal changeable arm pipe (12) launches the end portion jib and carries out pumping construction.
3. the method for concrete mixer short distance pumping as claimed in claim 1, it is characterized in that, pipeline switching device is arranged on head end jib and the jib capstan head place that is articulated and connected, by drive sprocket (13) through chain (17) drive respectively be fixedly mounted on the changeable arm pipe of head end (11) and with sprocket (14) and the sprocket (13) of its coaxial rotating, sprocket (13) is meshed with terminal gear (16) before jib launches or during the short distance pumping, terminal gear (16) be fixedly connected with terminal changeable arm pipe (12) and with its coaxial rotating.
CN201110217624.5A 2011-08-01 The method of concrete mixer short distance pumping Active CN102912985B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110217624.5A CN102912985B (en) 2011-08-01 The method of concrete mixer short distance pumping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110217624.5A CN102912985B (en) 2011-08-01 The method of concrete mixer short distance pumping

Publications (2)

Publication Number Publication Date
CN102912985A true CN102912985A (en) 2013-02-06
CN102912985B CN102912985B (en) 2016-12-14

Family

ID=

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022205640A1 (en) * 2021-03-31 2022-10-06 三一汽车制造有限公司 Engineering machine

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1140480A (en) * 1994-11-08 1997-01-15 乌尔里克·赫德尔梅尔 Concrete pumping device
CN101078298A (en) * 2007-04-25 2007-11-28 董连城 Method and device for transmitting concrete by concrete pump vehicle
JP4120905B2 (en) * 1999-03-31 2008-07-16 石川島建機株式会社 Operation control device for boom-equipped concrete pump car
EP2067911A1 (en) * 2006-09-30 2009-06-10 Sany Heavy Industry Co., Ltd. Method and apparatus for suppressing vibration of boom of concrete pump vehicle
CN201460228U (en) * 2009-05-07 2010-05-12 三一重工股份有限公司 Arm support system and pump truck containing same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1140480A (en) * 1994-11-08 1997-01-15 乌尔里克·赫德尔梅尔 Concrete pumping device
JP4120905B2 (en) * 1999-03-31 2008-07-16 石川島建機株式会社 Operation control device for boom-equipped concrete pump car
EP2067911A1 (en) * 2006-09-30 2009-06-10 Sany Heavy Industry Co., Ltd. Method and apparatus for suppressing vibration of boom of concrete pump vehicle
CN101078298A (en) * 2007-04-25 2007-11-28 董连城 Method and device for transmitting concrete by concrete pump vehicle
CN201460228U (en) * 2009-05-07 2010-05-12 三一重工股份有限公司 Arm support system and pump truck containing same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022205640A1 (en) * 2021-03-31 2022-10-06 三一汽车制造有限公司 Engineering machine

Similar Documents

Publication Publication Date Title
EP2439357B1 (en) Concrete pump truck and boom device thereof
CN102359278B (en) Arm support of concrete pump truck and concrete pump truck
CN201598834U (en) Concrete pump truck and arm support device thereof
CN201458605U (en) Turnover weight balance mechanism for lorry-mounted crane
CN202245841U (en) Synchronous telescoping mechanism for five-stage telescopic boom automobile crane
CN201635407U (en) Folding ejecting reversing device of concrete ejection machine
CN109667721B (en) Tower drum unit erecting tool
CN202496332U (en) Highly-efficient and rapid spraying rod folding and unfolding mechanism of broad-width spraying machine
CN215908537U (en) Water supply and drainage pipeline optimizes laying device
CN102296970B (en) Concrete sprayer
CN102400696A (en) Timbering machine and tunneling machine applying same
WO2014108055A1 (en) Conveying pipeline, boom system and operating equipment
CN102912985A (en) Short-distance pumping method of concrete pump truck
CN109914809A (en) A kind of concrete arm tail house and concrete pumping equipment
CN101078298B (en) Method for selecting arm support accroding to the pumping distance in concrete pump vehicle
CN105569686A (en) Tunnel sidewall concrete injection construction method
CN102912985B (en) The method of concrete mixer short distance pumping
CN204163410U (en) A kind of concrete pumping system
CN105317220A (en) Material conveying hose protection device, material distribution mechanism and concrete pumping equipment
CN203188632U (en) Arm support structure of concrete pump truck
CN113586093B (en) Mining concrete wet spraying machine
CN201587356U (en) Concrete pump truck and arm support device thereof
CN102720363B (en) Arm support device and concrete pump truck
CN209289148U (en) Coal mining machinery is driven quick change connection structure
CN202279551U (en) Pipe reeling device and engineering machinery

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant