CN102861998B - Sealing structure for titanium steel or zirconium titanium steel composite board device lining - Google Patents

Sealing structure for titanium steel or zirconium titanium steel composite board device lining Download PDF

Info

Publication number
CN102861998B
CN102861998B CN201210363157.1A CN201210363157A CN102861998B CN 102861998 B CN102861998 B CN 102861998B CN 201210363157 A CN201210363157 A CN 201210363157A CN 102861998 B CN102861998 B CN 102861998B
Authority
CN
China
Prior art keywords
vertical
coating metal
strip
filler strip
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210363157.1A
Other languages
Chinese (zh)
Other versions
CN102861998A (en
Inventor
徐鑫磊
李方
史从俊
王春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING MAICI TITANIUM CO Ltd
Original Assignee
NANJING MAICI TITANIUM CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING MAICI TITANIUM CO Ltd filed Critical NANJING MAICI TITANIUM CO Ltd
Priority to CN201210363157.1A priority Critical patent/CN102861998B/en
Publication of CN102861998A publication Critical patent/CN102861998A/en
Application granted granted Critical
Publication of CN102861998B publication Critical patent/CN102861998B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Arc Welding In General (AREA)

Abstract

A sealing structure for a titanium steel or zirconium titanium steel composite board device lining is characterized in that a sealing structure at connection of a longitudinal welding seam and an annular welding seam comprises the annular welding seam (1) and the longitudinal welding seam (2). Detecting holes (3) are arranged in the longitudinal welding seam (2). An annular filler strip is disposed in the annular welding seam (1) in a spot welding manner. A longitudinal filler strip (5) and a longitudinal filler block (6) are disposed in the longitudinal welding seam (2). A gap (7) is reserved between the longitudinal filler strip (5) and the longitudinal filler block (6). Coating metal stickers (8) are welded on the annular welding seam (1) and the longitudinal welding seam (2) in a sealed manner. A support block (9) is filled on the upper portion of the gap (7). A cover plate (10) covering the coating metal stickers (8) on the annular welding seam (1) and the longitudinal welding seam (2) is welded on the support block (9) in a sealed manner. Leaking liquid from the longitudinal welding seam is prevented from entering the annular welding seam, leaking liquid from the annular welding seam is prevented from entering the longitudinal welding seam, and leakage can be detected in corresponding detecting holes (3) conveniently and timely. In addition, the sealing structure is capable of prolonging service lives of devices and improving detecting and maintenance efficiency.

Description

Titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure
Technical field
the present invention relates to a kind of connection hermetically-sealed construction of composite cylindrical shell, especially can find in time that breakthrough and breakthrough can not have influence on the titanium steel of adjacent weld seam and adjacent leak detection point or a hermetically-sealed construction for titanium feature cylindrical shell, specifically a kind of titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure.
Background technology
At present, height corrosion occasion in chemical plant installations all needs to select non-ferrous metal, but select nonferrous metal price very high, so the important and big-and-middle-sized equipment in chemical plant installations all adopts composite plate: adopt blast form, carbon steel and non-ferrous metal are fit together, non-ferrous metal is thinner, and carbon steel is thicker.Non-ferrous metal can be anticorrosive, carbon steel energy proof strength, as titanium steel and zirconium titanium steel composite board, because steel and zirconium material or titanium material do not possess good solderability, the equipment that cannot guarantee is normally worked, so all adopt in the world at present joint strip form, first makes base material be weldingly connected, in weld seam, install again titanium or zirconium material filler strip additional, then at weld seam, around weld joint strip filler strip and the sealing of base material weld seam are covered.When corrosion occurs joint strip circumferential weld, reveal, chemical medium will enter filler strip from leak source, and the gap by filler strip flows into leak hunting aperture, because of longitudinal joint with circumferential weld without blocking quarantine measures, medium will corrode base steel layer, as shown in Figure 1.When maintenance, from leak hunting aperture, pass into compressed air, because vertical circumferential weld communicates, compressed air passes through backing plate two side clearances seepage everywhere, the position that location defect is revealed fast.
In addition, because equipment volume is large, maintenance difficulty is large, therefore often a plurality of leak detection points need to be set in same longitudinal seam or girth joint, but owing to communicating between same joint strip, therefore there will be a plurality of detection of place's seepage Kong Junneng to detect the phenomenon of seepage, be difficult to locate fast breakthrough, to maintenance, cause difficulty.
Summary of the invention
The object of the invention is can flow into annular joint strip place for the breakthrough outside longitudinal joint strip in existing coating metallic plate chemical reaction container, the breakthrough at annular joint strip place also can flow to the problem that longitudinal joint strip and breakthrough determine that difficulty is large, design a kind of can the vertical girth joint of blocking-up between seepage flow and can locate fast titanium steel or the zirconium equipment made of titanium-steel clad plate liner seal structure of breakthrough.
Technical scheme of the present invention is:
Sealing technical scheme of the present invention for the T junction of longitudinal seam and girth joint junction is:
A kind of titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure, it comprises the hermetically-sealed construction of longitudinal seam and girth joint junction, it is characterized in that described longitudinal seam and the hermetically-sealed construction of girth joint junction comprise girth joint 1 and longitudinal seam 2, in described longitudinal seam 2, be provided with and detect hole 3, at described girth joint 1 mid point, be welded with ring filler strip 4, vertical filler strip 5 and vertical cushion block 6 are installed in longitudinal seam 2, and vertical cushion block 6 arranges near girth joint 1, between vertical filler strip 5 and vertical cushion block 6, leaves gap 7, the one side that described vertical filler strip 5 is relative with vertical cushion block 6 is tightly connected by silver brazing and base material, the dual-side of vertical cushion block 6 is welded to connect with coating metal sealing respectively, vertical filler strip 5 is welded to connect near both sides, end and the coating metal sealing of vertical cushion block 6, and remainder is connected with the spot welding of coating metal, on described girth joint 1 and longitudinal seam 2, all seal weld is connected to coating metal joint strip 8, a part for described vertical cushion block 6 is exposed outside the coating metal joint strip 8 on girth joint 1, the end of vertical filler strip 5 and the part that weld seam two side cladding metal sealings are weldingly connected are also exposed outside the coating metal joint strip 8 on longitudinal seam, on 7 tops, described gap, between coating metal joint strip 8 on longitudinal seam and the coating metal joint strip 8 on girth joint 1, pad is equipped with back-up block 9, on back-up block 9, seal weld is connected to the cover plate 10 of the coating metal joint strip 8 on the coating metal joint strip 8 that can cover on longitudinal seam and girth joint 1, thereby prevent that the leakage fluid that the leakage fluid on longitudinal seam enters in girth joint or on girth joint from entering in vertical girth joint, to detect in corresponding leak hunting aperture 3 in time.
For the quick location of breakthrough on girth joint, technical scheme of the present invention is:
A kind of titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure, it comprises the hermetically-sealed construction of girth joint junction, the hermetically-sealed construction of described girth joint junction comprises the ring filler strip 4 being arranged in girth joint 1 and is opened in the leak hunting aperture 3 in base material weld seam, the centre that it is characterized in that the ring filler strip 4 between two described leak hunting apertures 3 is provided with cut-off point, between cut-off point, form a seal clearance 7, relative two ends and the base material silver brazing of ring filler strip 4 cut-off points is tightly connected, cut-off point dual-side end and coating metal sealing are weldingly connected, simultaneously, all expose outside coating metal joint strip 8 at the two ends of the ring filler strip 4 at cut-off point place, on the top in described gap 7, add size and encircle filler strip 4 ends and expose the ring back-up block 11 that size matches, on described ring back-up block 11, seal weld is connected to the ring cowling plate 12 that can cover cut-off point place coating metal joint strip 8.
For the quick location of breakthrough on longitudinal seam, technical scheme of the present invention is:
A kind of titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure, it comprises the hermetically-sealed construction of longitudinal seam junction, the hermetically-sealed construction of described longitudinal seam junction comprises the vertical filler strip 5 being arranged in longitudinal seam 2 and is opened in the leak hunting aperture 3 in base material weld seam, the centre that it is characterized in that the vertical filler strip 5 between two described leak hunting apertures 3 is provided with cut-off point, between cut-off point, form a seal clearance, vertical relative two ends and the base material silver brazing of filler strip 5 cut-off points is tightly connected, cut-off point dual-side end and coating metal sealing are weldingly connected, simultaneously, all expose outside coating metal joint strip 8 at the two ends of the vertical filler strip 5 at cut-off point place, on the top in described gap, add that size and vertical filler strip 5 ends expose the vertical back-up block that size matches, on described vertical back-up block, seal weld is connected to the vertical cover plate that can cover cut-off point place coating metal joint strip 8.
Beneficial effect of the present invention:
The invention solves the equipment that titanium steel composite board or zirconium titanium steel composite board are manufactured, a difficult problem for sealing between welding of longitudinal seam and circumferential seam basic unit and multiple layer, isolation and fast detecting.Improved the service life of equipment and detected maintenance efficiency.
Accompanying drawing explanation
Fig. 1 is existing sealed structural representation.
Fig. 2 is sealed structural representation of the present invention, and in figure, left side is the hermetically-sealed construction of vertical girth joint, the hermetically-sealed construction that right side is girth joint.
Fig. 3 is one of hermetically-sealed construction manufacture process decomposing schematic representation of the present invention.
Fig. 4 is two of hermetically-sealed construction manufacture process decomposing schematic representation of the present invention.
Fig. 5 is three of hermetically-sealed construction manufacture process decomposing schematic representation of the present invention.
Fig. 6 is four of hermetically-sealed construction manufacture process decomposing schematic representation of the present invention.
Fig. 7 is five of hermetically-sealed construction manufacture process decomposing schematic representation of the present invention.
Fig. 1~Fig. 7 is the plane after inner barrel is launched.
The specific embodiment
Below in conjunction with drawings and Examples, the present invention is further illustrated.
Embodiment mono-.
As shown in Fig. 1-7.
A kind of titanium steel or zirconium equipment made of titanium-steel clad plate lining T word welded seal structure, it is positioned at the junction of longitudinal seam 2 and girth joint 1, as shown in Figure 3, in A-A cutaway view Amplified image in Fig. 3, parent metal 13 is the carbon steel that weldability is good, coating metal 14 is titanium or zirconium material explosive clad plate, and in junction, being provided with and picking edge regions 15,16 is base material weld seam.In described longitudinal seam 2, be provided with and detect hole 3, at described girth joint 1 mid point, be welded with ring filler strip 4, vertical filler strip 5 and vertical cushion block 6 are installed in longitudinal seam 2, vertical cushion block 6 arranges near girth joint 1, adopt filler strip structure to be because parent metal and coating metal do not possess good solderability, between vertical filler strip 5 and vertical cushion block 6, leave gap 7, as Fig. 4, the one side that described vertical filler strip 5 is relative with vertical cushion block 6 is tightly connected by silver brazing 17 and base material, the dual-side of vertical cushion block 6 adopts titanium soldering and sealing (or zirconium soldering and sealing) seal welding to be connected with coating metal respectively, in Fig. 5,17 is silver brazing position, 18 is titanium (or zirconium) soldering and sealing position, vertical filler strip 5 adopts titanium (zirconium) soldering and sealing seal welding to be connected (position as in figure 18) near the both sides, end of vertical cushion blocks 6 and coating metal, and remainder is connected with the spot welding of coating metal employing titanium (zirconium), on described girth joint 1 and longitudinal seam 2, all adopt titanium (zirconium) soldering and sealing seal weld to be connected to coating metal joint strip 8, a part for described vertical cushion block 6 is exposed outside the coating metal joint strip 8 on girth joint 1, the end of vertical filler strip 5 and the part that weld seam two side cladding metal sealings are weldingly connected are also exposed outside the coating metal joint strip 8 on longitudinal seam 2, top in described gap 7, between coating metal joint strip 8 on longitudinal seam and the coating metal joint strip 8 on girth joint 1, pad is equipped with back-up block 9, as shown in Figure 6, on back-up block 9, seal weld is connected to the cover plate 10 of the coating metal joint strip 8 on the coating metal joint strip 8 that can cover on longitudinal seam and girth joint 1, as shown in Figure 7.Thereby prevent that the leakage fluid that the leakage fluid on longitudinal seam enters in girth joint or on girth joint from entering in vertical girth joint, to detect in time in corresponding leak hunting aperture 3.
When corrosion occurs coating metal joint strip 8 circumferential welds, reveal, chemical medium will enter vertical filler strip 5 from leak source, by indulging the gap of filler strip 5, flow into leak hunting aperture 3.Because installing vertical filler strip 5 additional at T font joint and the employing of banjo fixing butt jointing place, vertical filler strip 5 both sides, end adopt titanium (zirconium) soldering and sealing, end adopts 2 road silver brazing, so the chemical medium of revealing can only flow out by the leak hunting aperture of appointment, because be, adopt 2 road silver brazing sealings, even if wherein lost efficacy together, also have second can guarantee its sealing property.During maintenance, can from leak hunting aperture 3, pass into tooled joint air body, carry out air-tight test, with suds, at device interior, enter leak detection.Also can from leak hunting aperture 3, pass into helium, from device interior, carry out helium leak check.Because the use of double sealing can be increased work efficiency and preparation rate greatly.In the manufacture process of equipment, save a large amount of helium.
Embodiment bis-.
As shown in Figure 6,7.
A kind of titanium steel or zirconium equipment made of titanium-steel clad plate lining girth joint hermetically-sealed construction, as shown in right side in Fig. 2, it comprises the ring filler strip 4 being arranged in girth joint 1 and is opened in the leak hunting aperture 3 in base material weld seam, the centre of the ring filler strip 4 between two described leak hunting apertures 3 is provided with cut-off point, between cut-off point, form a seal clearance 7, relative two ends and the base material silver brazing of ring filler strip 4 cut-off points is tightly connected, cut-off point dual-side end and coating metal sealing are weldingly connected, simultaneously, all expose outside coating metal joint strip 8 at the two ends of the ring filler strip 4 at cut-off point place, as Fig. 6, on the top in described gap 7, add size and encircle filler strip 4 ends and expose the ring back-up block 11 that size matches, on described ring back-up block 11, seal weld is connected to the ring cowling plate 12 that can cover cut-off point place coating metal joint strip 8, as Fig. 7.
Embodiment tri-.
The structure of the present embodiment and embodiment bis-safety are identical, and can not residing position different, embodiment be girth joint, and the present embodiment is longitudinal seam.
The part that the present invention does not relate to all prior art that maybe can adopt same as the prior art is realized.

Claims (3)

1. a titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure, it comprises the hermetically-sealed construction of longitudinal seam and girth joint junction, it is characterized in that described longitudinal seam and the hermetically-sealed construction of girth joint junction comprise girth joint (1) and longitudinal seam (2), in described longitudinal seam (2), be provided with and detect hole (3), at described girth joint (1) mid point, be welded with ring filler strip (4), vertical filler strip (5) and vertical cushion block (6) are installed in longitudinal seam (2), vertical cushion block (6) arranges near girth joint (1), between vertical filler strip (5) and vertical cushion block (6), leave gap (7), the one side that described vertical filler strip (5) is relative with vertical cushion block (6) is tightly connected by silver brazing and base material, the dual-side of vertical cushion block (6) is welded to connect with coating metal sealing respectively, vertical filler strip (5) is welded to connect near both sides, end and the coating metal sealing of vertical cushion block (6), and remainder is connected with the spot welding of coating metal, at described girth joint (1) and the upper equal seal weld of longitudinal seam (2), be connected to coating metal joint strip (8), a part for described vertical cushion block (6) is exposed outside the coating metal joint strip (8) on girth joint (1), the end of vertical filler strip (5) and the part that weld seam two side cladding metal sealings are weldingly connected are also exposed outside the coating metal joint strip (8) on longitudinal seam, on top, described gap (7), between coating metal joint strip (8) on longitudinal seam and the coating metal joint strip (8) on girth joint (1), pad is equipped with back-up block (9), in the upper seal weld of back-up block (9), be connected to the cover plate (10) of the coating metal joint strip (8) on the coating metal joint strip (8) that can cover on longitudinal seam and girth joint (1), thereby prevent that the leakage fluid that the leakage fluid on longitudinal seam enters in girth joint or on girth joint from entering in vertical girth joint, to detect in corresponding leak hunting aperture (3) in time.
2. a titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure, it comprises the hermetically-sealed construction of girth joint junction, the hermetically-sealed construction of described girth joint junction comprises the ring filler strip (4) being arranged in girth joint (1) and is opened in the leak hunting aperture (3) in base material weld seam, the centre that it is characterized in that the ring filler strip (4) between described two leak hunting apertures (3) is provided with cut-off point, between cut-off point, form a seal clearance (7), relative two ends and the base material silver brazing of ring filler strip (4) cut-off point is tightly connected, cut-off point dual-side end and coating metal sealing are weldingly connected, simultaneously, all expose outside coating metal joint strip (8) at the two ends of the ring filler strip (4) at cut-off point place, on the top of described gap (7), add size and encircle filler strip (4) end and expose the ring back-up block (11) that size matches, in the upper seal weld of described ring back-up block (11), be connected to the ring cowling plate (12) that can cover cut-off point place coating metal joint strip (8).
3. a titanium steel or zirconium equipment made of titanium-steel clad plate liner seal structure, it comprises the hermetically-sealed construction of longitudinal seam junction, the hermetically-sealed construction of described longitudinal seam junction comprises the vertical filler strip (5) being arranged in longitudinal seam (2) and is opened in the leak hunting aperture (3) in base material weld seam, the centre that it is characterized in that the vertical filler strip (5) between described two leak hunting apertures (3) is provided with cut-off point, between cut-off point, form a seal clearance, vertical relative two ends and the base material silver brazing of filler strip (5) cut-off point is tightly connected, cut-off point dual-side end and coating metal sealing are weldingly connected, simultaneously, all expose outside coating metal joint strip (8) at the two ends of the vertical filler strip (5) at cut-off point place, on the top in described gap, add that size and vertical filler strip (5) end expose the vertical back-up block that size matches, on described vertical back-up block, seal weld is connected to the vertical cover plate that can cover cut-off point place coating metal joint strip (8).
CN201210363157.1A 2012-09-26 2012-09-26 Sealing structure for titanium steel or zirconium titanium steel composite board device lining Active CN102861998B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210363157.1A CN102861998B (en) 2012-09-26 2012-09-26 Sealing structure for titanium steel or zirconium titanium steel composite board device lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210363157.1A CN102861998B (en) 2012-09-26 2012-09-26 Sealing structure for titanium steel or zirconium titanium steel composite board device lining

Publications (2)

Publication Number Publication Date
CN102861998A CN102861998A (en) 2013-01-09
CN102861998B true CN102861998B (en) 2014-07-23

Family

ID=47441269

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210363157.1A Active CN102861998B (en) 2012-09-26 2012-09-26 Sealing structure for titanium steel or zirconium titanium steel composite board device lining

Country Status (1)

Country Link
CN (1) CN102861998B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106975859A (en) * 2017-05-18 2017-07-25 上海森松化工成套装备有限公司 The strengthening of welded seam structure of composite board equipment
CN111571124A (en) * 2020-05-06 2020-08-25 九江市永信制罐设备有限公司 Flower basket barrel production process

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201140884Y (en) * 2007-12-11 2008-10-29 西安核设备有限公司 Soldering structure of container housing made by zirconium steel composite board
CN201289423Y (en) * 2008-11-19 2009-08-12 南京宝色股份公司 Leak detection structure for composite board equipment
CN201745974U (en) * 2009-07-07 2011-02-16 上海贤达罗兰压力容器制造有限公司 Protective and leak detecting structure of weld joint of container taking active metal and steel composite board as liner
CN201606591U (en) * 2010-03-03 2010-10-13 南京斯迈柯特种金属装备股份有限公司 Leakproof double-layered protection structure for adapter lining of zirconium steel compound plate equipment
CN101929547A (en) * 2010-08-04 2010-12-29 南京宝色股份公司 Double-integrated sealing structure for pressure container of composite board
CN201988379U (en) * 2011-03-10 2011-09-28 南京斯迈柯特种金属装备股份有限公司 Double-layered protecting structure for preventing leakage of weld of joint strip of titanium-steel or zirconium-steel composite plate barrel
CN202763303U (en) * 2012-09-26 2013-03-06 南京麦驰钛业有限公司 Lining sealing structure of titanium steel or zirconium titanium steel composite plate equipment

Also Published As

Publication number Publication date
CN102861998A (en) 2013-01-09

Similar Documents

Publication Publication Date Title
CN204677934U (en) A kind of novel alloy flange
CN102861998B (en) Sealing structure for titanium steel or zirconium titanium steel composite board device lining
CN202763303U (en) Lining sealing structure of titanium steel or zirconium titanium steel composite plate equipment
CN101929547A (en) Double-integrated sealing structure for pressure container of composite board
CN201745974U (en) Protective and leak detecting structure of weld joint of container taking active metal and steel composite board as liner
CN201289423Y (en) Leak detection structure for composite board equipment
CN201606591U (en) Leakproof double-layered protection structure for adapter lining of zirconium steel compound plate equipment
CN204879137U (en) Anticorrosive bimetal of antiseep transition coupling
CN203606079U (en) Seal test tool for double-layer pipeline fuel nozzle
CN202963799U (en) Leak detection separating structure at container welding joint of active metal and steel composite plate
CN203258202U (en) Sealing structure at outlet position of inner coil of equipment
CN201606592U (en) Leakproof double-layered protection structure for adapter sealing ring of zirconium steel compound plate equipment
KR102541108B1 (en) flange assembly
CN203216360U (en) Connection structure between heat exchange tube and tube plate and capable of preventing corrosion of clearance on shell pass side
CN202582839U (en) Vacuum cap used for detecting welding quality of containment vessel for nuclear power station
CN208902342U (en) A kind of joint strip weld seam divides chamber double leakage detecting structures
CN205483420U (en) Double -deck leak hunting structure of composite sheet equipment
CN210442067U (en) Leak detection device for pressure container
CN202914924U (en) Flange structure of thrust-stop ring
CN209432370U (en) For fuel tank upper plate air-tightness detection device
CN107023723A (en) A kind of flange and preparation method thereof
RU141409U1 (en) DEVICE FOR PROTECTION AGAINST CORROSION OF WELDED JOINT OF PIPES WITH INTERNAL COATING
CN202555242U (en) High-pressure reaction vessel
CN202983663U (en) Multilayer coating structure of reaction tower
CN201802858U (en) Dual-integral type sealing structure of composite board pressure vessel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Sealing structure for titanium steel or zirconium titanium steel composite board device lining

Effective date of registration: 20191010

Granted publication date: 20140723

Pledgee: Nanjing Bank Co., Ltd. Chengnan Branch

Pledgor: Nanjing Maici Titanium Co.,Ltd.

Registration number: Y2019980000236

PE01 Entry into force of the registration of the contract for pledge of patent right