CN102843879A - Container data center - Google Patents

Container data center Download PDF

Info

Publication number
CN102843879A
CN102843879A CN2011101730968A CN201110173096A CN102843879A CN 102843879 A CN102843879 A CN 102843879A CN 2011101730968 A CN2011101730968 A CN 2011101730968A CN 201110173096 A CN201110173096 A CN 201110173096A CN 102843879 A CN102843879 A CN 102843879A
Authority
CN
China
Prior art keywords
counter
rack
data center
built
side plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101730968A
Other languages
Chinese (zh)
Other versions
CN102843879B (en
Inventor
萧胜中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cloud Frame Co ltd
Original Assignee
Hongfujin Precision Industry Shenzhen Co Ltd
Hon Hai Precision Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hongfujin Precision Industry Shenzhen Co Ltd, Hon Hai Precision Industry Co Ltd filed Critical Hongfujin Precision Industry Shenzhen Co Ltd
Priority to CN201110173096.8A priority Critical patent/CN102843879B/en
Priority claimed from CN201110173096.8A external-priority patent/CN102843879B/en
Publication of CN102843879A publication Critical patent/CN102843879A/en
Application granted granted Critical
Publication of CN102843879B publication Critical patent/CN102843879B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Vibration Prevention Devices (AREA)

Abstract

The invention relates to a container data center which comprises a container and an equipment cabinet arranged in the container, wherein a damping device is arranged at the bottom of the equipment cabinet, a supporting device is arranged at the top of the equipment cabinet and consists of a sleeve and a connecting mechanism, the sleeve is fixed at the top of the equipment cabinet, one end of the connecting mechanism is fixed at the top wall of the container, and the other end of the connecting mechanism is slidably contained in the sleeve along the vertical direction. According to the container data center, a cover body arranged at the top wall of the container can be slidably contained and installed in the sleeve at the top of the equipment cabinet along the vertical direction, so that the damping device at the bottom of the equipment cabinet can more effectively isolate the shock and impact of the outside transmitted to the equipment cabinet, thus protecting an electronic device in the equipment cabinet from being damaged.

Description

Counter data center
Technical field
The present invention relates to a kind of counter data center.
Background technology
Counter data center is in transportation or meet when shaking doughtily, and the rack counter data center in can wave, tilt, and might damage the interior electronic equipment of this rack, influences the operate as normal of data center.
Summary of the invention
Seeing that more than, be necessary to provide a kind of shockproof counter data center.
A kind of counter data center; Comprise a counter and be installed on the rack in this counter; The bottom of this rack is provided with a damping device, and the top of this rack is provided with a bracing or strutting arrangement, and this bracing or strutting arrangement comprises that one is fixed in the sleeve and a bindiny mechanism at the top of this rack; One end of this bindiny mechanism is fixed in the roof of this counter, and the other end vertically slides and is contained in this sleeve.
The bindiny mechanism of the roof that is installed on counter of counter of the present invention data center can vertically be contained in the sleeve at the top that is installed on this rack slidably; Make vibrations and the impact that rack is imported in the more effectively isolated external world of damping device of bottom of rack into, protect the electronic installation in this rack to avoid damaging.
Description of drawings
Combine embodiment that the present invention is done further description with reference to the accompanying drawings.
Fig. 1 is the three-dimensional exploded view of the preferred embodiments of counter of the present invention data center, and this counter data center comprises a bracing or strutting arrangement.
Fig. 2 is the three-dimensional exploded view of the bracing or strutting arrangement among Fig. 1.
Fig. 3 is the assembly drawing of Fig. 1.
Fig. 4 is the cutaway view of Fig. 3 along IV-IV.
The main element symbol description
Counter 300
Built-in beam 310
Connector 320
Connecting hole 302
Rack 10
Sleeve 12
Installing hole 102
Damping device 14
Supporter 142
Shock absorber part 144
Bracing or strutting arrangement 20
Body 244
Through hole 245
Bindiny mechanism 24
Connecting rod 242
Nut 246
Fixture 26
Top board 261
First side plate 262
Lug 263
Second side plate 265
Base plate 267
Accepting groove 268
Locking hole 269
Following embodiment will combine above-mentioned accompanying drawing to further specify the present invention.
Embodiment
Please with reference to Fig. 1, the preferred embodiments of counter of the present invention data center comprises a counter 300, is installed in the some racks 10 in this counter 300.Be respectively equipped with two damping devices 14 and a bracing or strutting arrangement 20 between the diapire of the bottom of each rack 10 and top and counter 300 and the roof.Some through holes are offered in the bottom of each rack 10, and the top of each rack 10 is provided with an installing hole 102 near its two short limit respectively.
Each damping device 14 comprises that a cross section is the supporter 142 and a shock absorber part 144 of " worker " type.This supporter 142 is offered some through holes.
The bar shape that this shock absorber part 144 is processed by vibration-absorptive materials such as rubber or plastics, its length roughly length with this supporter 142 are suitable.This first shock absorber part 144 is offered some through holes.
Please consult Fig. 2 in the lump, this bracing or strutting arrangement 20 comprises a built-in beam 310, a pair of sleeve 12, a pair of bindiny mechanism 24 and a pair of fixture 26.
Each sleeve 12 is the cylinder that two ends are respectively equipped with the hollow of an opening.
The cross section of this built-in beam 310 generally takes the shape of the letter U, and it comprises that a base plate reaches the upwardly extending biside plate of two opposed side edges by this base plate.Wherein the side of side plate is provided with the two inboard connectors 320 of roof that can this built-in beam 310 be fixed in this counter 300.The base plate of this built-in beam 310 is provided with two connecting holes 302 (as shown in Figure 4).
Each bindiny mechanism 24 comprises a connecting rod 242, a body 244 and a pair of nut 246.This body 244 is cylinders of being processed by vibration-absorptive materials such as rubber or plastics, and this body 244 is offered the through hole 245 that a confession connecting rod 242 passes vertically.The two ends of this connecting rod 242 are equipped with screw thread.
Each fixture 26 is the rectangle framework of a both ends open, and it comprises the top board 261 of a rectangle and one first side plate 262 and one second side plate 265 that is extended downward vertically by these top board 261 relative dual-sides.Terminal outwards vertical extent one lug 263 of this first side plate 262, the end of this second side plate 265 extends a base plate 267 to first side plate 262, and the free end of this base plate 267 is close to the bottom surface of this lug 263.This top board 261, first side plate 262, second side plate 265 and this base plate 267 surround the accepting groove 268 of a rectangle.The top board 261 of this fixture 26 and base plate 267 are offered a relative locking hole 269 respectively.The lug 263 of this fixture 26 and base plate 267 are offered a relative through hole respectively.
Please consult Fig. 3 and Fig. 4 in the lump; When two damping devices 14 are assembled in rack 10; Some screws pass the through hole of these rack 10 bottoms, the through hole of this two shock absorber part 144 and the through hole of this two supporter 142 respectively successively and are bolted in some nuts, thereby this two damping device 14 is installed on the bottom of this rack 10 along the length direction of rack 10.This bracing or strutting arrangement 20 is assembled in rack 10, two sleeves 12 are fixed in the installing hole 102 of rack 10 with the mode of welding respectively.This two fixture 26 is sheathed on built-in beam 310, and the locking hole 269 that makes this two fixture 26 is respectively over against two connecting holes 302 of this built-in beam 310.Two screws pass respectively this two fixture 26 lug 263 and base plate 267 through hole and be bolted in two nuts, thereby this two fixture 26 is fixed in this built-in beam 310.One end of each connecting rod 242 is passed the through hole 245 of a nut 246 and this body 244 and is bolted in another nut 246, from this body 244 is locked in this connecting rod 242.Then the body of this connecting rod 242 244 is inserted in the corresponding sleeve 12, these connecting rod 242 other ends are passed the base plate 267 of a nut 246, this fixture 26 locking hole 269, this built-in beam 310 connecting hole 302 and this fixture 26 top board 261 locking hole 269 and be bolted in another nut 246.The top board 261 of this fixture 26 and two nuts 246 of base plate 267 both sides are close in adjusting, and the body 244 of this bracing or strutting arrangement 20 is contained in the sleeve 12 of this rack 10 fully, lock this two nut 246 again and get final product.At this moment, two bodies 244 of this bracing or strutting arrangement 20 are contained in two sleeves 12 slidably, and the motion of these two bodies, 244 horizontal directions is suffered restraints.
Through being spirally connected or riveted way is fixed in two damping devices 14 diapire of this counter 300.
The body 244 that is installed on the roof of counter 300 can vertically be contained in the sleeve 12 at the top that is installed on this rack 10 slidably; Make vibrations and the impact that rack 10 is imported in the more effectively isolated external world of damping device 14 of bottom of rack 10 into, protect the electronic installations in this rack 10 to avoid damaging; Because two bodies 244 slide and are contained in the sleeve 12, can avoid rack 10 in the horizontal direction bigger lateral movement and make between the rack 10 bump each other, can make the structure of counter data center more stable.
In other embodiments, can save fixture 26, built-in beam 310, the end that body 244 is not installed of each connecting rod 242 directly locked the roof of counter 300.
In other embodiments, this bracing or strutting arrangement 20 also can only be installed a bindiny mechanism 24 in the middle part of built-in beam 310, and the middle position at the top of this rack 10 only is provided with an installing hole 102 accordingly with a fixing sleeve 12.

Claims (7)

1. counter data center; Comprise a counter and be installed on the rack in this counter; The bottom of this rack is provided with a damping device, and the top of this rack is provided with a bracing or strutting arrangement, and this bracing or strutting arrangement comprises that one is fixed in the sleeve and a bindiny mechanism at the top of this rack; One end of this bindiny mechanism is fixed in the roof of this counter, and the other end vertically slides and is contained in this sleeve.
2. counter as claimed in claim 1 data center; It is characterized in that: this bindiny mechanism comprises the body that a connecting rod and is processed by vibration-absorptive material; This bracing or strutting arrangement comprises that one is fixed in the built-in beam of this counter roof; One end of this connecting rod connects this built-in beam, and the other end is connected in this body, and this body slides and is contained in this sleeve.
3. counter as claimed in claim 2 data center; It is characterized in that: this body is a cylinder; This body is offered a through hole vertically; The two ends of this connecting rod are equipped with screw thread, and an end of this connecting rod passes the through hole of a nut and this body and is bolted in another nut so that this body is connected in connecting rod.
4. counter as claimed in claim 2 data center; It is characterized in that: this bracing or strutting arrangement comprises that also one is sheathed on the fixture of this built-in beam; The cross section of this built-in beam generally takes the shape of the letter U; The base plate of this built-in beam is offered a connecting hole, and this fixture is provided with an accepting groove, this fixture is offered this connecting rod of locking hole respectively in the relative both sides of accepting groove the other end pass a nut, this fixture locking hole and this built-in beam connecting hole and be bolted in another nut.
5. counter as claimed in claim 4 data center; It is characterized in that: this fixture is the rectangle framework of both ends open; It comprises that the top board of a rectangle reaches by vertically extending in the same way first side plate of the relative dual-side of this top board and second side plate; The end of this second side plate extends a base plate to first side plate, and this accepting groove is surrounded by this top board, first side plate, second side plate and this base plate, and this two locking hole lays respectively at this top board and base plate.
6. counter as claimed in claim 5 data center; It is characterized in that: the end of this first side plate lug that stretches out; The free end of this base plate is close to the bottom surface of this lug, and this lug and base plate are offered a relative through hole respectively, and a screw passes this two through hole and is bolted in a nut.
7. counter as claimed in claim 1 data center; It is characterized in that: the bottom of this rack is provided with two damping devices; The shock absorber part that each damping device comprises that the supporter and of one " worker " type is arranged between rack and the supporter and processed by vibration-absorptive material, bottom, each shock absorber part and supporter that some screws pass this rack successively are bolted in some nuts.
CN201110173096.8A 2011-06-24 Container data center Active CN102843879B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110173096.8A CN102843879B (en) 2011-06-24 Container data center

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110173096.8A CN102843879B (en) 2011-06-24 Container data center

Publications (2)

Publication Number Publication Date
CN102843879A true CN102843879A (en) 2012-12-26
CN102843879B CN102843879B (en) 2016-12-14

Family

ID=

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110854693A (en) * 2019-11-22 2020-02-28 广州市顺承电气设备有限公司 Volume-adjustable power distribution cabinet

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200986681Y (en) * 2006-12-26 2007-12-05 深圳市同洲电子股份有限公司 Hard disk shock-absorbing device
US20080060790A1 (en) * 2006-09-13 2008-03-13 Sun Microsystems, Inc. Server rack service utilities for a data center in a shipping container
CN201491422U (en) * 2009-08-26 2010-05-26 中国人民解放军63961部队 On-board reinforced case

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080060790A1 (en) * 2006-09-13 2008-03-13 Sun Microsystems, Inc. Server rack service utilities for a data center in a shipping container
CN200986681Y (en) * 2006-12-26 2007-12-05 深圳市同洲电子股份有限公司 Hard disk shock-absorbing device
CN201491422U (en) * 2009-08-26 2010-05-26 中国人民解放军63961部队 On-board reinforced case

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110854693A (en) * 2019-11-22 2020-02-28 广州市顺承电气设备有限公司 Volume-adjustable power distribution cabinet

Similar Documents

Publication Publication Date Title
US8045343B2 (en) Server carrier assembly
US8419328B2 (en) Container data center
US10420247B2 (en) Connecting assembly for rack system
US20140055934A1 (en) Server
US8500377B2 (en) Container data center
RU158613U1 (en) COMPUTER CASE CONNECTION DEVICE WITH VIBRATION-PROTECTING PLATFORM
CN104735930A (en) Server cabinet
CN102843879A (en) Container data center
CN103493505A (en) Sub-rack mounting bracket and assembly
US8322679B2 (en) Container data center
CN102843879B (en) Container data center
CN105813418B (en) Electrical control cabinet
US20140060915A1 (en) Server cabinet
CN103185814A (en) Test fixture
GB2483756B (en) Positioning device used on rack
CN100518456C (en) Electric cabinet
CN102811574B (en) Container data center
CN102841656A (en) Goods cabinet data center
CN103068190A (en) Container data center
CN204055599U (en) A kind of automobile sensor support
CN102833965A (en) Container data center
TW201302018A (en) Container data center
CN205213166U (en) Electric control cabinet
CN109152265B (en) Bracket assembly for cabinet
CN117154570B (en) Vibration-resistant electrical cabinet

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160601

Address after: 518000 Guangdong Province, Shenzhen New District of Longhua City, Dalang street, Hua Sheng Lu Yong Jingxuan commercial building 1608

Applicant after: Jinyang Shenzhen sea Network Intelligent Technology Co.,Ltd.

Address before: 518109 Guangdong city of Shenzhen province Baoan District Longhua Town Industrial Zone tabulaeformis tenth East Ring Road No. 2 two

Applicant before: HONG FU JIN PRECISION INDUSTRY (SHENZHEN) Co.,Ltd.

Applicant before: HON HAI PRECISION INDUSTRY Co.,Ltd.

C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Zeng Shanghuai

Inventor before: Xiao Shengzhong

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20161017

Address after: 401320 Chongqing District of Banan City Jinzhu Industrial Park

Applicant after: Chongqing Jiewei Mold Manufacturing Co.,Ltd.

Address before: Tianhe District Tong East Road Guangzhou city Guangdong province 510665 B-101 No. 5, room B-118

Applicant before: GUANGDONG GAOHANG INTELLECTUAL PROPERTY OPERATION Co.,Ltd.

Effective date of registration: 20161017

Address after: Tianhe District Tong East Road Guangzhou city Guangdong province 510665 B-101 No. 5, room B-118

Applicant after: GUANGDONG GAOHANG INTELLECTUAL PROPERTY OPERATION Co.,Ltd.

Address before: 518000 Guangdong Province, Shenzhen New District of Longhua City, Dalang street, Hua Sheng Lu Yong Jingxuan commercial building 1608

Applicant before: Jinyang Shenzhen sea Network Intelligent Technology Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191212

Address after: 214063 307-517, Guangnan Road, Liangxi District, Wuxi City, Jiangsu Province

Patentee after: Wuxi Senlan Intellectual Property Agency Co.,Ltd.

Address before: 401320 Chongqing District of Banan City Jinzhu Industrial Park

Patentee before: Chongqing Jiewei Mold Manufacturing Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191224

Address after: Room d2-622, China Sensor Network International Innovation Park, No. 200, Linghu Avenue, Taihu International Science and Technology Park, Wuxi New District, 214000, Jiangsu Province

Patentee after: CLOUD FRAME CO.,LTD.

Address before: 214063 307-517, Guangnan Road, Liangxi District, Wuxi City, Jiangsu Province

Patentee before: Wuxi Senlan Intellectual Property Agency Co.,Ltd.