A kind of modular activity flood-control wall
Technical field
The present invention relates to a kind of flood-control wall, be specifically related to a kind of modular activity flood-control wall.
Background technology
The typhoon season of the early June of China's Coastal Areas to mid-July plum rain season and mid-July to mid-September is prone to take place flood damage.Interim in flood season, the lower units of physical features such as many facilities such as underground garage, market, sub-district will guarantee that not only drainage system is good, also will pile up some sand hills on the doorway, cause vehicle or other property damage to stop the excess surface water inflow.Can play waterproof effect preferably though pile up sand hill, because sand hill weight is big, it is more in banking process, to expend muscle power and time, and the filler of putting off until some time later in the sand hill is more, add muscle power required in the banking process and time, so cost is higher.In case the words of the defective tightness of sand hill accumulation simultaneously also can cause drainage, in addition, after flood season, the sand hill of using is handled also pretty troublesome.Some interim lock gate for flood protection have also appearred on the existing market; But before installation, need do a large amount of civil engineering work mostly; So cause the installation period of gate to increase, and the raising of cost, problems such as inefficiency caused; And the most installation that need be independent of existing lock gate for flood protection weather strip, the time of causing gate to open is longer.The combination flood-control wall that also has a kind of movable type will be transported in flood season temporarily and to carry out aggregate erection on the former dykes and dams, removes and transports in the back in the past in flood season, therefore will increase cost of transportation.
Summary of the invention
The purpose of this invention is to provide a kind of modular activity flood-control wall, it need not to do in advance a large amount of civil engineering work, can carry out aggregate erection and in light weight apace in flood season temporarily, and transportation and cost of manufacture are low, can effectively carry out the flood control in flood season.
The technical scheme that realizes above-mentioned purpose is: a kind of modular activity flood-control wall; Be installed between the two stifled construction walls; Said modular activity flood-control wall comprises some standard modules and pair of end portions module; Wherein, said standard module is the T-shaped hollow block of cross section, the side of each standard module respectively the side through bindiny mechanism and adjacent standard module with positively and invertedly connecting method be connected form in the middle part of waterwall; Said end module is the L-shaped hollow block of cross section, and the shape of the thickness of said end module, right and wrong side and size respectively correspondingly with the shape of the thickness of said standard module, side and measure-alike; The flat side of a pair of said end module is connected with the medial surface of said construction wall through retention mechanism, and the right and wrong side of a pair of said end module right and wrong side through bindiny mechanism and waterwall two, said middle part respectively is connected with positively and invertedly connecting method and forms whole section waterwall; The top and the bottom of the top and the bottom of the front end face of each said standard module and the front end face of each said end module offer respectively one have a plug water injection hole.
Above-mentioned modular activity flood-control wall; Wherein, Said flood-control wall comprises that also second pair of said end module and is connected second pair of adjusting module between the said end module through retention mechanism; This adjusting module is the quadrangular hollow block, and the thickness of this adjusting module and the size of side be measure-alike with the thickness of said end module and flat side correspondingly respectively, the top and the bottom of the front end face of this adjusting module offer respectively one have a plug water injection hole; Said whole section waterwall is split as left side waterwall and right side waterwall, and the right and wrong side that the right and wrong side of second pair of said end module is passed through right and wrong side and the said right side waterwall left end of bindiny mechanism and said left side waterwall right-hand member respectively is connected with positively and invertedly connecting method.
Above-mentioned modular activity flood-control wall; Wherein, Said flood-control wall also comprises an adjusting module; This adjusting module is a four-prism hollow block, and the thickness of this adjusting module and the size of side be measure-alike with the thickness of said end module and flat side correspondingly respectively, the top and the bottom of the front end face of this adjusting module be provided with respectively one have a plug water injection hole;
Said adjusting module is connected through retention mechanism between one of the said whole waterwall said construction wall with a corresponding side.
Above-mentioned modular activity flood-control wall, wherein, said standard module and said end module are made by polyvinyl-chloride plate material; The two sides of each said standard module and each said end module and the middle part of upper and lower end face are respectively equipped with a band, the width of sealing band be standard module or end module thickness 1/2nd, the thickness of sealing band is 2~5mm.
Above-mentioned modular activity flood-control wall, wherein, said adjusting module is made by polyvinyl-chloride plate material; The two sides of said adjusting module and the middle part of upper and lower end face are respectively equipped with a band, the width of sealing band be adjusting module thickness 1/2nd, the thickness of sealing band is 2~5mm.
Above-mentioned modular activity flood-control wall; Wherein, said bindiny mechanism is on some flange strap and the another side that is opened in said standard module accordingly on the right and wrong side that is located on the side of said standard module with a said end module and some the caulking grooves adaptive with flange strap on the right and wrong side of another said end module.
Above-mentioned modular activity flood-control wall, wherein, said bindiny mechanism is a screw bolt and nut.
Above-mentioned modular activity flood-control wall, wherein, said retention mechanism is a screw bolt and nut.
The technical scheme of modular activity flood-control wall of the present invention; Adopt the lighter polyvinyl-chloride plate material of weight to make each module; Transportation and cost of manufacture are low; Easy for installation, and can carry out aggregate erection apace in flood season temporarily, gain in weight with the excess surface water that stops that heavy rain forms by water filling then.Modular activity flood-control wall of the present invention need not to do in advance a large amount of civil engineering work, can effectively carry out the flood control in flood season.
Description of drawings
Fig. 1 is the elevation of first kind of embodiment of modular activity flood-control wall of the present invention;
Fig. 2 is the phantom drawing of a kind of standard module in the modular activity flood-control wall of the present invention;
Fig. 3 is the phantom drawing of the another kind of standard module in the modular activity flood-control wall of the present invention;
Fig. 4 is the phantom drawing of the end module in the modular activity flood-control wall of the present invention;
Fig. 5 is the phantom drawing of second kind of embodiment of modular activity flood-control wall of the present invention;
Fig. 6 is the phantom drawing of the adjusting module in the modular activity flood-control wall of the present invention;
Fig. 7 is the elevation of the third embodiment of modular activity flood-control wall of the present invention.
The specific embodiment
For the technician who makes the present technique field can understand technical scheme of the present invention better, its specific embodiment is at length explained below in conjunction with accompanying drawing:
See also Fig. 1 to Fig. 3, a kind of modular activity flood-control wall of the present invention is installed in two stifled construction walls 100, between 200.Modular activity flood-control wall comprises some standard module 1, pair of end portions module 2,2 ', some retention mechanisms 5 and some bindiny mechanisms, wherein:
Standard module 1 is made by polyvinyl-chloride plate material and is the T-shaped hollow block of cross section; The two sides of each standard module 1 and the middle part of upper and lower end face are respectively equipped with a band 10; The width of sealing band 10 be standard module 1 thickness 1/2nd, the thickness of sealing band 10 is 2~5mm; The top and the bottom of the front end face of standard module 1 offer respectively one have a plug water injection hole 11,12; The side of each standard module 1 respectively the side through bindiny mechanism and adjacent standard module 1 with positively and invertedly connecting method be connected form in the middle part of waterwall; 10 of bands be used between the standard module 1 and and ground between sealing; Bindiny mechanism is located at the some flange strap 51 on the side of standard module 1 and is opened in some caulking groove 52 (see figure 4)s adaptive with flange strap on the another side of standard module 1 accordingly; Bindiny mechanism can also be a screw bolt and nut;
End module 2 is made by polyvinyl-chloride plate material and is the L-shaped hollow block of cross section; The two sides of each end module 2 and the middle part of upper and lower end face are respectively equipped with a band 20; The width of sealing band 20 be end module 2 thickness 1/2nd, the thickness of sealing band 20 is 2~5mm; The height of end module 2 and thickness respectively with the thickness of standard module 1 and highly identical, and the shape of the right and wrong side of end module 2 and size respectively with the shape of the side of standard module 1 and measure-alike; The top and the bottom of the front end face of each end module 2 offer respectively one have a plug water injection hole 21,22;
Pair of end portions module 2,2 ' flat side are connected with the medial surface of construction wall 100,200 through retention mechanism 4; Retention mechanism 4 is a screw bolt and nut; Pair of end portions module 2,2 ' right and wrong the side right and wrong side through bindiny mechanism and waterwall two, middle part respectively are connected with positively and invertedly connecting method and form whole section waterwall; 20 of bands be used between end module 2 and the standard module 1 and between the ground and with the medial surface of building wall 100,200 between sealing; Offer some the flange strap 51 that the caulking groove 52 on the side with standard module 1 is adaptive on the right and wrong side of an end module 2 in the pair of end portions module 2,2 '; Offer the adaptive caulking groove 52 of flange strap 51 on the side of some and standard module 1 on the right and wrong side of another end module 2 '; Flange strap 51 and the caulking groove on the standard module 1 52 on the end module 2 form bindiny mechanisms, or the flange strap on caulking groove on the end module 2 52 and the standard module 1 51 forms bindiny mechanisms.
Because standard module 1 all is in advance according to the sized of setting with end module 2; And the whole section waterwall that the assembling back forms has certain length; If two stifled construction walls 100, the distance between 200 do not match with the size of whole section waterwall, therefore also need adjust the length of whole section waterwall through an adjusting module 3.
See also Fig. 5 and Fig. 6 again; Another kind of modular activity flood-control wall of the present invention; Comprise that also second pair of end module 2,2 ' and is connected second pair of end module 2, adjusting module 3 between 2 ' through retention mechanism 4; This adjusting module 3 is made by the lighter polyvinyl-chloride plate material of weight, and is a four-prism hollow block, and the two sides of adjusting module 3 and the middle part of upper and lower end face are respectively equipped with a band 30; The width of sealing band 30 be adjusting module 3 thickness 1/2nd, the thickness of sealing band 30 is 2~5mm; Sealing band 30 is used for and pair of end portions module 2, between 2 ' and and ground between sealing; The thickness of the thickness of adjusting module 3 and this adjusting module 3 and the size of side and end module 2 and puts down the measure-alike of side, the top and the bottom of the front/rear end of this adjusting module 3 offer respectively one have a plug water injection hole 31,32;
In view of the foregoing; Need whole section waterwall is split as left side waterwall and right side waterwall, the right and wrong side that makes second pair of end module 2,2 ' right and wrong side pass through right and wrong side and the right side waterwall left end of bindiny mechanism and left side waterwall right-hand member respectively is connected with positively and invertedly connecting method.
Certainly; The mode that also has the length of whole section waterwall of another kind of adjustment; Promptly can adjusting module 3 be connected (see figure 7) between one of the whole waterwall construction wall 100 with a corresponding side through retention mechanism, band 30 be used for and end module 2 between and between the ground and and the medial surface of construction wall 100 between sealing.
The top water injection hole 31 of the front end face of adjusting module 3 both can be used for water filling, also can be used to breathe freely.The bottom water injection hole 32 of the front end face of adjusting module 3 both can be used for introducing bottom surface ponding, also was used for discharging water.
Because standard module 1, end module 2 and adjusting module 3 are made by the lighter polyvinyl-chloride plate material of weight; Transportation and installation are all very convenient; But it is lighter with the flood-control wall weight that end module 2 constitutes to depend merely on standard module 1; Be not enough to stop the excess surface water of heavy rain formation; Therefore in actual use, the front end face that standard module 1, end module 2 and adjusting module 3 is provided with the top and the bottom water injection hole is assembled into whole section waterwall as upstream face, when the water level of local area water is low; Need be to the water injection hole that is positioned at whole section waterwall top to standard module 1, end module 2 and adjusting module 3 artificial recharges, so that standard module 1, end module 2 and adjusting module 3 reach certain weight.When the water level of local area water is higher; Make excess surface water introduce standard module 1, end module 2 and adjusting module 3 from the water injection hole that is positioned at whole section waterwall bottom; At this moment; The water injection hole that is positioned at whole section waterwall top is as air-vent, so that standard module 1, end module 2 and adjusting module 3 reach certain weight.In the time will removing whole section waterwall in the past flood season, open the plug of the water injection hole that is positioned at whole section waterwall bottom earlier, the water in standard module 1, end module 2 and the adjusting module 3 is bled off, can disassemble easily then, and can transport like a cork.
Modular activity flood-control wall of the present invention, owing to adopt the lighter polyvinyl-chloride plate material of weight to make each module, transportation and installation are all very convenient.Can carry out aggregate erection apace in flood season temporarily, gain in weight with the excess surface water that stops that heavy rain forms by water filling then.
Those of ordinary skill in the art will be appreciated that; Above embodiment is used for explaining the present invention; And be not to be used as qualification of the present invention; As long as in connotation scope of the present invention, all will drop in claims scope of the present invention variation, the modification of the above embodiment.