CN102819636B - 基于逻辑关系的建模系统和建模方法 - Google Patents

基于逻辑关系的建模系统和建模方法 Download PDF

Info

Publication number
CN102819636B
CN102819636B CN2012102731479A CN201210273147A CN102819636B CN 102819636 B CN102819636 B CN 102819636B CN 2012102731479 A CN2012102731479 A CN 2012102731479A CN 201210273147 A CN201210273147 A CN 201210273147A CN 102819636 B CN102819636 B CN 102819636B
Authority
CN
China
Prior art keywords
increment
model
modeling
correcting module
operand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2012102731479A
Other languages
English (en)
Other versions
CN102819636A (zh
Inventor
李建英
赵生传
刘远龙
罗鲁东
王强
张媛
王文刚
王超
张瑞鹏
王黎
王泽众
王公仆
杨欣
杨慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Sifang Automation Co Ltd
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN201310309659.0A priority Critical patent/CN103530811B/zh
Priority to CN201310309622.8A priority patent/CN103544336B/zh
Priority to CN2012102731479A priority patent/CN102819636B/zh
Priority to CN201310309625.1A priority patent/CN103530810B/zh
Publication of CN102819636A publication Critical patent/CN102819636A/zh
Priority to US13/956,831 priority patent/US9507884B2/en
Priority to GB1313780.7A priority patent/GB2507149A/en
Application granted granted Critical
Publication of CN102819636B publication Critical patent/CN102819636B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/18Network design, e.g. design based on topological or interconnect aspects of utility systems, piping, heating ventilation air conditioning [HVAC] or cabling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/04Power grid distribution networks

Abstract

本发明提供一种基于逻辑关系的建模系统,包括操作任务集成模块、任务解释器、图形布局修正模块、图形布线修正模块和数据库模型增量修正模块,所述数据库模型增量修正模块包括图形增量计算单元、模型增量计算单元;同时提供一种使用该建模系统的建模方法。该系统利用逻辑关系描述,基于自动布线技术的支持,以图形化的方式实现基于逻辑关系描述的电力系统新的电网模型图模一体化生成,完全在“一张网”上定义与修改电网模型,而不是在无数张片网图上建立电力系统模型,从而实现和帮助电网运行管理人员能够准确且快速地建立、修改全系统电网模型,这种建模系统直观明了、可靠准确,也更容易。

Description

基于逻辑关系的建模系统和建模方法
技术领域
本发明涉及电力系统电网模型构建领域,具体涉及一种基于逻辑关系的建模系统和建模方法。
背景技术
电网模型是一切电力系统有关的分析、决策与管理的基础,模型是否有、是否完整、是否准确、是否容易建立应该说都非常重要,传统的电网模型定义方法采用图模库一体化方法,也就是先画图、然后生成模型、再写入关系数据库中。画图是手工绘制,采用基于物理节点的方法,及每个设备对象都有一个或多个关节点,通过绘制关节点之间的连接线,实现拓扑描述;图形绘制的范围通常是以厂站图形为单元,站与站之间通过线路建立连接关系,从而生成整个系统的电网模型。该方法在电网规模不大且站外设备较少、分支较少时有其优点,但当系统规模大、接线复杂时,以厂站图为单元时,系统模型涉及的厂站图达到几百个甚至更多,管理维护困难,容易出错,且基于物理节点的“点对点联接”方式操作步骤太多、容易因为人工操作失误造成模型描述错误,此外当站外设备多、分支多时以厂站图为单元的建模方式边界切割复杂,这些因素都造成了电网模型的定义困难,严重影响了对电力系统应用分析决策的支持与可靠性。
发明内容
为此,本发明所要解决的是现有建模系统采用手工绘图操作步骤太多、容易出错的技术问题,从而提供一种操作简单、运行可靠的基于逻辑关系的建模系统和建模方法。
为解决上述技术问题,本发明采用的技术方案如下:
一种基于逻辑关系的建模系统,包括
操作任务集成模块,将操作任务集成分为不同类别,所述类别包括增加操作对象、删除操作对象、修改操作对象;
任务解释器,获取所述操作任务集成模块的命令信息,并对所述命令信息进行任务拆分;
图形布局修正模块,采用矩形点阵描述,将操作对象放置于网格节点上,当新增加一个或多个空间点操作对象时,相邻区域关联的空间点需要自动移位;
图形布线修正模块,根据最少交叉与最短路径进行布线,并对布线路径上关联的对象进行修正;
数据库模型增量修正模块,根据所述图形布局修正模块和所述图形布线修正模块的动作,相对应地进行模型增删改动作,包括:
图形增量计算单元,根据所述图形布局修正模块和所述图形布线修正模块的动作,计算当前的图形增量,所述图形增量包括电网图元对象增量与拓扑关系变化增量;
模型增量计算单元,根据所述图形增量计算单元得到的当前的图形增量,计算当前的模型增量;
关系型数据库,存储所述图形增量对应的模型增量修正后的电网模型。
所述的建模系统,所述任务解释器进行任务拆分,采用集成任务拆分机制,符合IEC61968/61970标准。
所述的建模系统,所述最短路径为不采用斜线的情况下,不超越双节点组成的矩形区域的水平垂直走线。
所述的建模系统,所述最少交叉通过局部区域的换位与换向模拟计算得到。
所述的建模系统,所述操作对象包括容器类对象、容器类对象内部主接线、容器类对象与容器类对象之间的连接。
所述的建模系统,所述容器类对象包括厂站、开闭所、环网柜、分支箱、箱变。
一种使用所述建模系统的建模方法,包括如下步骤:
一、将操作任务集成分为不同类别,所述类别包括增加操作对象、删除操作对象、修改操作对象;
二、对操作任务的命令信息进行任务拆分;
三、对所述操作对象进行图形自动布局修正,采用矩形点阵描述,将操作对象放置于网格节点上,当新增加一个或多个空间点操作对象时,相邻区域关联的空间点需要自动移位;
四、对所述操作对象进行图形自动布线修正,根据最少交叉与最短路径进行布线,并对布线路径上关联的对象进行修正;
五、根据图形布局修正的结果和图形布线的修正结果,计算当前的图形增量;
六、根据得到的当前的图形增量,计算当前的模型增量;
七、对图形增量对应的模型增量进行相应的增删改动作并存储。
本发明的上述技术方案相比现有技术具有以下优点:
本发明提供一种基于逻辑关系的建模系统,包括操作任务集成模块、任务解释器、图形布局修正模块、图形布线修正模块和数据库模型增量修正模块,同时提供一种使用该建模系统的建模方法。该系统利用逻辑关系描述,基于自动布线技术的支持,以图形化的方式实现基于逻辑关系描述的电力系统新的电网模型图模一体化生成,完全在“一张网”上定义与修改电网模型,而不是在无数张片网图上建立电力系统模型,从而实现和帮助电网运行管理人员能够准确且快速地建立、修改全系统电网模型,这种建模系统直观明了、可靠准确,也更容易。相对于现有技术而言,该系统采用逻辑化描述,将逻辑关系描述语言变换为空间拓扑描述信息,进而形成空间点与线的图形化语言描述,将过去多步骤操作融合为单一任务型操作,利用自动布局布线技术,实现点线之间的连接,点线连接采用最短路径与最少交叉原则;实现了对逻辑化建模语言的图形化表述,模型中的对象与库对象的增量部分自动计算并增删,实现图形对象与网络数据库模型中的对象一一对应,解决了电力系统长久存在的模型定义难题,简化电力系统网络模型的定义方法,用描述性的逻辑语言方法,提交模型定义内容,提高了模型定义的速度,降低了模型定义的难度,提高了模型定义的准确度,保证了对复杂大系统模型的定义生成。
本发明提供一种使用该系统的建模方法,可运用于输电网以及配电网模型的生成,特别适合规模较大的输电网或接线关系复杂的配电网模型定义与生成。
本发明提供的建模系统和建模方法,解决大规模电网与复杂接线关系电网模型建立过程繁琐、容易出错、难以维护的问题,只要采用了这项技术,在一张图上建立模型,模型大小、范围一目了然,不用在几百张片网图形上修补,提高了模型建立的直观性;将原来基于物理节点的操作过程逻辑化描述为单一任务型,由程序完成多步骤操作,简化了电网模型的建立过程;在一张图上增量化建立模型,维护了图模的严格一致,解决了一直困扰电力部门的全局一体化建模困境。
附图说明
为了使本发明的内容更容易被清楚的理解,下面根据本发明的具体实施例并结合附图,对本发明作进一步详细的说明,其中
图1为本发明所述的基于逻辑关系的建模系统的一个实施例的结构示意图;
图2为图1所示实施例的基于逻辑关系的建模系统的连接关系逻辑定义图;
图3为图1所示实施例的基于逻辑关系的建模系统的站内拓扑逻辑定义图;
图4为图1所示实施例的基于逻辑关系的建模系统的容器类对象增加图;
图5为图1所述的基于逻辑关系的建模系统的自由布局布线图。
图中附图标记表示为:1-操作任务集成模块;2-任务解释器;3-图形布局修正模块;4-图形布线修正模块;5-数据库模型增量修正模块;51-图形增量计算单元;52-模型增量计算单元;53-关系型数据库。
具体实施方式
实施例:
下面给出本发明所述的一种基于逻辑关系的建模系统的一个具体的实施方式,参见图1所示,一种基于逻辑关系的建模系统,包括:操作任务集成模块1、任务解释器2、图形布局修正模块3、图形布线修正模块4和数据库模型增量修正模块5。具体内容如下:
操作任务集成模块1,包括增加操作对象、删除操作对象、修改操作对象,本实施例中,所述操作对象包括容器类对象、容器类对象内部主接线、容器类对象与容器类对象之间的连接,其中,所述容器类对象包括厂站、开闭所、环网柜、分支箱、箱变,图2、图3分别为所述建模系统的连接关系逻辑定义图和站内拓扑逻辑定义图,图4为所述建模系统的容器类对象增加图。
任务解释器2,获取所述操作任务集成模块1的命令信息,并对所述命令信息进行任务拆分,拆分成图形布局修正、图形布线修正、计算图形增量、计算模型增量、存储模型增量修正后的电网模型五步任务;例如:命令信息为厂站1与厂站2之间增加一条线路,拆分的任务为:(1)计算厂站1间隔及出线方位和顺序;(2)计算厂站2间隔及出线方位和顺序;(3)计算厂站1与厂站2矩形区域内对象移动数据;(4)计算增加厂站1与厂站2之间的布线通道及移动位置数据;(5)图形增量为厂站1与厂站2内部主接线变化、外部厂站移位数据以及布线通道,修正图形并刷新显示;(6)模型增量为新线路、线路开关、新增节点;修正支路-节点-电压等级-厂站容器之间的关系,修正模型至关系数据库。本实施例中,所述任务解释器进行任务拆分,采用集成任务拆分机制,符合IEC61968/61970标准。
图形布局修正模块3,采用矩形点阵描述,将操作对象放置于网格节点上,当新增加一个或多个空间点操作对象时,相邻区域关联的空间点需要自动移位。
图形布线修正模块4,根据最少交叉与最短路径进行布线,并对布线路径上关联的对象进行修正,本实施例中,所述最少交叉通过局部区域的换位与换向模拟计算得到,所述最短路径为不采用斜线的情况下,不超越双节点组成的矩形区域的水平垂直走线,图5为所述建模系统的自由布局布线图;容器类对象内部主接线的修正,以环网柜内部主接线分裂为例:(1)计算环网柜内部母线出线方位与间隔大小、并计算最少交叉出线顺序;(2)计算环网柜外部对象布局移位数据;(3)布局图形修正;(4)移位后布线图形修正;(5)模型增量为环网柜内部新增母线以及分段开关。
数据库模型增量修正模块5,根据所述图形布局修正模块3和所述图形布线修正模块4的动作,相对应地进行模型增删改动作。所述数据库模型修正模块5包括:图形增量计算单元51,根据所述图形布局修正模块3和所述图形布线修正模块4的动作,计算当前的图形增量,所述图形增量包括电网图元对象增量与拓扑关系变化增量,以删除某条线路为例:图形增量为线路本身包含的线段、关联厂站1内部主接线以及关联厂站2内部主接线;模型增量为删除线路以及删除线路上的关联开关、刀闸、物理节点;模型增量计算单元52,根据所述图形增量计算单元51得到的当前的图形增量,计算当前的模型增量;关系型数据库53,存储所述图形增量对应的模型增量修正后的电网模型。
本实施例中,此系统的硬件主要由带图形加速芯片的UNIX/LINUX工作站组成。
同时,提供一种使用上述建模系统的建模方法,包括如下步骤:
一、将操作任务集成分成不同类别,所述类别包括增加操作对象、删除操作对象、修改操作对象;
二、对操作任务的命令信息进行任务拆分;
三、对所述操作对象进行图形自动布局修正,采用矩形点阵描述,将操作对象放置于网格节点上,当新增加一个或多个空间点操作对象时,相邻区域关联的空间点需要自动移位;
四、对所述操作对象进行图形自动布线修正,根据最少交叉与最短路径进行布线,并对布线路径上关联的对象进行修正;
五、根据图形布局修正的结果和图形布线的修正结果,计算当前的图形增量;
六、根据得到的当前的图形增量,计算当前的模型增量;
七、对图形增量对应的模型增量进行相应的增删改动作并存储。
显然,上述实施例仅仅是为清楚地说明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明创造的保护范围之中。

Claims (7)

1.一种基于逻辑关系的建模系统,其特征在于:包括
操作任务集成模块,将操作任务集成分为不同类别,所述类别包括增加操作对象、删除操作对象、修改操作对象;
任务解释器,获取所述操作任务集成模块的命令信息,并对所述命令信息进行任务拆分;
图形布局修正模块,采用矩形点阵描述,将操作对象放置于网格节点上,当新增加一个或多个空间点操作对象时,相邻区域关联的空间点需要自动移位;
图形布线修正模块,根据最少交叉与最短路径进行布线,并对布线路径上关联的对象进行修正;
数据库模型增量修正模块,根据所述图形布局修正模块和所述图形布线修正模块的动作,相对应地进行模型增删改动作,包括:
图形增量计算单元,根据所述图形布局修正模块和所述图形布线修正模块的动作,计算当前的图形增量,所述图形增量包括电网图元对象增量与拓扑关系变化增量;
模型增量计算单元,根据所述图形增量计算单元得到的当前的图形增量,计算当前的模型增量;
关系型数据库,存储所述图形增量对应的模型增量修正后的电网模型。
2.根据权利要求1所述的建模系统,其特征在于:所述任务解释器进行任务拆分,采用集成任务拆分机制,符合IEC61968/61970标准。
3.根据权利要求2所述的建模系统,其特征在于:所述最短路径为不采用斜线的情况下,不超越双节点组成的矩形区域的水平垂直走线。
4.根据权利要求3所述的建模系统,其特征在于:所述最少交叉通过局部区域的换位与换向模拟计算得到。
5.根据权利要求1-4所述的建模系统,其特征在于:所述操作对象包括容器类对象、容器类对象内部主接线、容器类对象与容器类对象之间的连接。
6.根据权利要求5所述的建模系统,其特征在于:所述容器类对象包括厂站、开闭所、环网柜、分支箱、箱变。
7.一种使用权利要求1-6所述建模系统的建模方法,其特征在于:包括如下步骤:
一、将操作任务集成分为不同类别,所述类别包括增加操作对象、删除操作对象、修改操作对象;
二、对操作任务的命令信息进行任务拆分;
三、对所述操作对象进行图形自动布局修正,采用矩形点阵描述,将操作对象放置于网格节点上,当新增加一个或多个空间点操作对象时,相邻区域关联的空间点需要自动移位;
四、对所述操作对象进行图形自动布线修正,根据最少交叉与最短路径进行布线,并对布线路径上关联的对象进行修正;
五、根据图形布局修正的结果和图形布线的修正结果,计算当前的图形增量;
六、根据得到的当前的图形增量,计算当前的模型增量;
七、对图形增量对应的模型增量进行相应的增删改动作并存储。
CN2012102731479A 2012-03-23 2012-08-02 基于逻辑关系的建模系统和建模方法 Active CN102819636B (zh)

Priority Applications (6)

Application Number Priority Date Filing Date Title
CN201310309659.0A CN103530811B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模系统
CN201310309622.8A CN103544336B (zh) 2012-03-23 2012-08-02 基于逻辑关系的电网模型的建模系统
CN2012102731479A CN102819636B (zh) 2012-03-23 2012-08-02 基于逻辑关系的建模系统和建模方法
CN201310309625.1A CN103530810B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模方法
US13/956,831 US9507884B2 (en) 2012-03-23 2013-08-01 Modeling system and modeling method based on logical relation
GB1313780.7A GB2507149A (en) 2012-08-02 2013-08-01 Modeling system based on a logical relation

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201210090887 2012-03-23
CN201210090887.9 2012-03-23
CN2012102731479A CN102819636B (zh) 2012-03-23 2012-08-02 基于逻辑关系的建模系统和建模方法

Related Child Applications (3)

Application Number Title Priority Date Filing Date
CN201310309659.0A Division CN103530811B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模系统
CN201310309625.1A Division CN103530810B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模方法
CN201310309622.8A Division CN103544336B (zh) 2012-03-23 2012-08-02 基于逻辑关系的电网模型的建模系统

Publications (2)

Publication Number Publication Date
CN102819636A CN102819636A (zh) 2012-12-12
CN102819636B true CN102819636B (zh) 2013-08-21

Family

ID=47303747

Family Applications (4)

Application Number Title Priority Date Filing Date
CN201310309659.0A Active CN103530811B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模系统
CN201310309625.1A Active CN103530810B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模方法
CN201310309622.8A Active CN103544336B (zh) 2012-03-23 2012-08-02 基于逻辑关系的电网模型的建模系统
CN2012102731479A Active CN102819636B (zh) 2012-03-23 2012-08-02 基于逻辑关系的建模系统和建模方法

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201310309659.0A Active CN103530811B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模系统
CN201310309625.1A Active CN103530810B (zh) 2012-03-23 2012-08-02 电力系统基于逻辑关系的建模方法
CN201310309622.8A Active CN103544336B (zh) 2012-03-23 2012-08-02 基于逻辑关系的电网模型的建模系统

Country Status (2)

Country Link
US (1) US9507884B2 (zh)
CN (4) CN103530811B (zh)

Families Citing this family (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103473714A (zh) * 2013-09-06 2013-12-25 国家电网公司 一种配网系统中图模自动维护方法
CN104133943B (zh) * 2014-07-08 2017-06-20 国家电网公司 基于目标导向的配网图形自动生成方法
CN104268801A (zh) * 2014-10-10 2015-01-07 东方电子股份有限公司 电力系统环网潮流计算的可视化调试方法
CN104408555A (zh) * 2014-11-12 2015-03-11 国家电网公司 一种电能质量评估模型的创建方法和电能质量评估方法
CN104573209B (zh) * 2014-12-30 2018-07-06 国家电网公司 一种配网厂站及设备容器内部细节按需动态显示方法
CN104598110B (zh) * 2015-01-12 2018-01-30 中国南方电网有限责任公司 超大规模输电网潮流图动态视口显示方法
CN105140919B (zh) * 2015-09-18 2017-09-19 国网山东省电力公司菏泽供电公司 一种基于图论的快速拓扑分析及拓扑岛建立的方法
CN105260556B (zh) * 2015-10-28 2017-11-24 浙江大学 发夹变异操作rna遗传算法的桥式吊车建模方法
CN105354379B (zh) * 2015-11-02 2017-12-05 浙江大学 发夹交叉操作rna遗传算法的桥式吊车支持向量机建模方法
CN105740543A (zh) * 2016-01-29 2016-07-06 山东鲁能智能技术有限公司 基于qml图形化的电力系统建模方法及建模系统
CN105930575B (zh) * 2016-04-19 2019-03-01 国网重庆市电力公司电力科学研究院 一种psasp数据模型转换为pscad数据模型的自动转换方法
CN106651144B (zh) * 2016-11-25 2020-12-18 南京南瑞继保电气有限公司 一种带有同杆并架线路信息的杆塔与线路关系建模方法
CN106600457B (zh) * 2016-12-06 2020-08-14 国网福建省电力有限公司 一种变电站微机五防主接线图分析系统
US10606565B2 (en) * 2017-01-31 2020-03-31 Stackery, Inc. Visual devops systems and methods
US11343352B1 (en) * 2017-06-21 2022-05-24 Amazon Technologies, Inc. Customer-facing service for service coordination
CN107515977A (zh) * 2017-08-17 2017-12-26 南京国电南自电网自动化有限公司 基于g语言的继电保护主接线图设计方法
CN109947859B (zh) * 2017-08-25 2023-12-05 南方电网科学研究院有限责任公司 配电网绘图建模方法、系统、存储介质和计算机设备
CN108521123B (zh) * 2018-04-26 2020-02-14 福建积微科技有限公司 一种可视化的多联络点配电网故障区段关联方法
CN111211557B (zh) * 2019-12-30 2024-04-16 中国电力科学研究院有限公司 一种多层级多分支的电网结构规划方法与系统
CN111460595A (zh) * 2020-03-12 2020-07-28 广西电网有限责任公司电力科学研究院 一种配电网真型试验系统中图形维护的方法及装置
CN113538164B (zh) * 2020-04-13 2023-04-25 电力规划总院有限公司 一种电力系统生产模拟模型的建模方法、装置和电子设备
US11941413B2 (en) 2020-06-29 2024-03-26 Amazon Technologies, Inc. Managed control plane service
US11948005B2 (en) 2020-06-29 2024-04-02 Amazon Technologies, Inc. Managed integration of constituent services of multi-service applications
CN112383145B (zh) * 2020-11-12 2022-09-02 山东鲁软数字科技有限公司 一种改善配电环网图成图效果的线路拆分方法及系统
CN112436602A (zh) * 2020-11-12 2021-03-02 单新文 一种电网图形及模型扩展方法
CN112417626B (zh) * 2020-11-12 2023-04-14 山东鲁软数字科技有限公司 配电自动化系统环网图中分支排序方法及装置
CN112765134A (zh) * 2020-12-29 2021-05-07 广东电网有限责任公司电力科学研究院 一种电力物联层级对象模型的生成方法及系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040236620A1 (en) * 2003-05-19 2004-11-25 Chauhan S. K. Automated utility supply management system integrating data sources including geographic information systems (GIS) data
CN101436790A (zh) * 2008-12-26 2009-05-20 北京市电力公司调度通信中心 包含复杂t接线路的电网模型在线拼接与合并方法
CN101789042A (zh) * 2010-01-29 2010-07-28 华东电网有限公司 电网企业cim模型增量比较工具
CN102262758A (zh) * 2011-08-17 2011-11-30 国电南瑞科技股份有限公司 基于cime文件的时空多维电网模型统一建模和管理方法
CN102375827A (zh) * 2010-08-16 2012-03-14 北京国科恒通电气自动化科技有限公司 一种对版本化的电网模型数据库进行快速加载的方法

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003332429A (ja) * 2002-05-09 2003-11-21 Renesas Technology Corp 半導体装置の製造方法および半導体装置
JP4250540B2 (ja) * 2004-01-30 2009-04-08 キヤノン株式会社 レイアウト調整方法および装置およびレイアウト調整プログラム
JP4047308B2 (ja) * 2004-08-06 2008-02-13 キヤノン株式会社 レイアウト処理方法、情報処理装置及びコンピュータプログラム
CN101499109A (zh) * 2008-07-24 2009-08-05 杨志华 配电生产管理信息图形系统
CN101799837A (zh) * 2009-12-31 2010-08-11 杭州电子科技大学 一种调度大屏输电网单线图厂站布局后的自动布线方法
JP5284403B2 (ja) * 2011-03-28 2013-09-11 株式会社東芝 オントロジ更新装置、方法、およびシステム
CN102201129B (zh) * 2011-04-25 2013-04-17 西安理工大学 一种三维可视化地铁综合管线运营维护系统及维护方法
US9362746B2 (en) * 2011-10-07 2016-06-07 Cisco Technology, Inc. Communication network topology management based on an associated electric grid topology

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040236620A1 (en) * 2003-05-19 2004-11-25 Chauhan S. K. Automated utility supply management system integrating data sources including geographic information systems (GIS) data
CN101436790A (zh) * 2008-12-26 2009-05-20 北京市电力公司调度通信中心 包含复杂t接线路的电网模型在线拼接与合并方法
CN101789042A (zh) * 2010-01-29 2010-07-28 华东电网有限公司 电网企业cim模型增量比较工具
CN102375827A (zh) * 2010-08-16 2012-03-14 北京国科恒通电气自动化科技有限公司 一种对版本化的电网模型数据库进行快速加载的方法
CN102262758A (zh) * 2011-08-17 2011-11-30 国电南瑞科技股份有限公司 基于cime文件的时空多维电网模型统一建模和管理方法

Also Published As

Publication number Publication date
CN103544336B (zh) 2016-02-03
CN102819636A (zh) 2012-12-12
CN103544336A (zh) 2014-01-29
US20140039865A1 (en) 2014-02-06
CN103530810A (zh) 2014-01-22
CN103530810B (zh) 2015-10-28
CN103530811A (zh) 2014-01-22
US9507884B2 (en) 2016-11-29
CN103530811B (zh) 2015-11-18

Similar Documents

Publication Publication Date Title
CN102819636B (zh) 基于逻辑关系的建模系统和建模方法
CN107292003B (zh) 一种电网厂站接线图自动生成方法
CN102957205B (zh) 一种建立配电网模型的方法及系统
CN102411764B (zh) 电网设备的数据管理系统及管理方法
CN102402634B (zh) 电网地理信息系统中配电单线图的自动布局方法
CN106021684B (zh) 一种模块电源标准化设计系统及其设计方法、应用
CN104218673B (zh) 电网自动化智能分区方法
CN101937435B (zh) 面向电力系统的分布式实时数据库在线同步方法
CN102289548B (zh) 一种基于AutoCAD配网图到单线图的自动转换方法
CN110866320A (zh) 一种智能台区图形自动生成方法及系统
CN102867091B (zh) 一种电网潮流图增量化修正方法
CN105807658A (zh) 一种智能变电站与调度主站图模信息共享的方法
CN103020335A (zh) 一种配电网地理接线图到区域正交图的自动转换方法
CN102254056A (zh) 一种核电站电缆路径设计方法
CN107948008B (zh) 一种用于低压配电网监控系统的建模方法
CN106202662A (zh) 一种配电网网架图自动绘制映射方法
CN111585349A (zh) 一种电网模型管理及监视系统
CN106021632A (zh) 基于拓扑关系变电站一次接线图生成全网图方法
CN104239589A (zh) 一种配电网业扩报装智能分析系统的实现方法
CN106777686A (zh) 基于地理信息的电网中配电单线的自动分布法局方法
CN105373008A (zh) 一种电力系统用全物理模型仿真方法
CN102708258B (zh) 一种PSS/E至SimPowerSys的电力网络系统数据转换方法
CN103441988B (zh) 跨gis平台数据迁移方法
CN104808549B (zh) 带电网模型拼接功能的测控装置
CN104598110B (zh) 超大规模输电网潮流图动态视口显示方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: Shinan District 266003 Shandong city of Qingdao province Liujiaxia Road No. 17 in Qingdao power supply company

Applicant after: Qingdao Power Supply Co., Ltd., Shandong Electric Power Corporation

Address before: 266000 Shandong city in Qingdao Province Southern Xuejiadao hub village Huangdao District Xuejiadao Wawushan station

Applicant before: Qingdao Power Supply Co., Ltd., Shandong Electric Power Corporation

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP. BEIJING SIFANG JIBAO AUTO

Effective date: 20131111

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Li Jianying

Inventor after: Wang Li

Inventor after: Wang Zezhong

Inventor after: Wang Gongpu

Inventor after: Yang Xin

Inventor after: Yang Hui

Inventor after: Wang Min

Inventor after: Zhang Bin

Inventor after: Zhao Shengchuan

Inventor after: Liu Yuanlong

Inventor after: Luo Ludong

Inventor after: Wang Qiang

Inventor after: Zhang Yuan

Inventor after: Wang Wengang

Inventor after: Wang Chao

Inventor after: Zhang Ruipeng

Inventor before: Li Jianying

Inventor before: Wang Li

Inventor before: Wang Zezhong

Inventor before: Wang Gongpu

Inventor before: Yang Xin

Inventor before: Yang Hui

Inventor before: Zhao Shengchuan

Inventor before: Liu Yuanlong

Inventor before: Luo Ludong

Inventor before: Wang Qiang

Inventor before: Zhang Yuan

Inventor before: Wang Wengang

Inventor before: Wang Chao

Inventor before: Zhang Ruipeng

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LI JIANYING ZHAO SHENGCHUAN LIU YUANLONG LUO LUDONG WANG QIANG ZHANG YUAN WANG WENGANG WANG CHAO ZHANG RUIPENG WANG LI WANG ZEZHONG WANG GONGPU YANG XIN YANG HUI TO: LI JIANYING ZHAO SHENGCHUAN LIU YUANLONG LUO LUDONG WANG QIANG ZHANG YUAN WANG WENGANG WANG CHAO ZHANG RUIPENG WANG LI WANG ZEZHONG WANG GONGPU YANG XIN YANG HUI WANG MIN ZHANG BIN

TR01 Transfer of patent right

Effective date of registration: 20131111

Address after: Shinan District 266003 Shandong city of Qingdao province Liujiaxia Road No. 17 in Qingdao power supply company

Patentee after: Qingdao Power Supply Co., Ltd., Shandong Electric Power Corporation

Patentee after: State Grid Corporation of China

Patentee after: Beijing Sifang Jibao Automation Co., Ltd.

Address before: Shinan District 266003 Shandong city of Qingdao province Liujiaxia Road No. 17 in Qingdao power supply company

Patentee before: Qingdao Power Supply Co., Ltd., Shandong Electric Power Corporation