CN102808977B - High exhaust check valve of critical and supercritical thermal power generating set valve - Google Patents

High exhaust check valve of critical and supercritical thermal power generating set valve Download PDF

Info

Publication number
CN102808977B
CN102808977B CN201210292893.2A CN201210292893A CN102808977B CN 102808977 B CN102808977 B CN 102808977B CN 201210292893 A CN201210292893 A CN 201210292893A CN 102808977 B CN102808977 B CN 102808977B
Authority
CN
China
Prior art keywords
cylinder
force
valve
nut
strong
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210292893.2A
Other languages
Chinese (zh)
Other versions
CN102808977A (en
Inventor
陈力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DALIAN DV VALVE Co Ltd
Original Assignee
DALIAN DV VALVE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DALIAN DV VALVE Co Ltd filed Critical DALIAN DV VALVE Co Ltd
Priority to CN201210292893.2A priority Critical patent/CN102808977B/en
Publication of CN102808977A publication Critical patent/CN102808977A/en
Application granted granted Critical
Publication of CN102808977B publication Critical patent/CN102808977B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Check Valves (AREA)

Abstract

临界、超临界火电机组阀门高排逆止阀,本发明涉及临界、超临界火电发电机组系统用的火电阀门领域,其特征是强开轴左轴套键安装于阀体左侧轴销孔内,与摇臂组件连接,在阀体轴销孔右侧插入强关轴、右轴套;右支架上旋入右填料压板螺柱,装右填料压板、填料、压套右填料压板螺母、导向套、轴承、轴承压盖、油杯、缠绕垫片一同套入强关轴,与阀体配紧;左侧强开轴处压入填料、填料压套,左支架、轴承、轴承压盖、导向套组装后和开关压板同时插入强开轴;两侧安装强开传动柄、强关传动柄,安装气缸体内,然后安装气缸后盖、强开缸后盖O形圈;气缸组合后,分别安装强开气缸、强关气缸。本发明高排逆止阀可以自动开启,遇紧急情况强关气缸能在小于0.5秒内迅速自动关闭阀门。

Figure 201210292893

Critical and supercritical thermal power unit valve high-row check valve, the invention relates to the field of thermal power valves used in critical and supercritical thermal power generating unit systems, characterized in that the left shaft sleeve key of the forced opening shaft is installed in the shaft pin hole on the left side of the valve body , to connect with the rocker arm assembly, insert the strong closing shaft and the right bushing on the right side of the shaft pin hole of the valve body; screw the right packing pressure plate stud into the right bracket, install the right packing pressure plate, packing, pressure sleeve, right packing pressure plate nut, guide Sleeves, bearings, bearing glands, oil cups, and spiral wound gaskets are inserted into the strong closing shaft together, and are tightly matched with the valve body; packing, packing gland, left bracket, bearing, bearing gland, After the guide sleeve is assembled and the switch pressure plate is inserted into the forced opening shaft at the same time; the forced opening drive handle and the forced closing drive handle are installed on both sides, and the cylinder body is installed, and then the cylinder rear cover and the forced opening cylinder rear cover O-ring are installed; after the cylinder is assembled, respectively Install the forced opening cylinder and forced closing cylinder. The high-row non-return valve of the present invention can be automatically opened, and the closed cylinder can be quickly and automatically closed in less than 0.5 seconds in case of an emergency.

Figure 201210292893

Description

临界、超临界火电机组阀门高排逆止阀Critical and supercritical thermal power unit valve high discharge check valve

技术领域 technical field

本发明涉及临界、超临界火电发电机组系统用的火电阀门领域,具体地说是涉及一种一千兆瓦临界、超临界火电机组阀门高排逆止阀。  The invention relates to the field of thermal power valves used in critical and supercritical thermal power generating set systems, in particular to a high-discharge check valve for one gigawatt critical and supercritical thermal power generating set valves. the

背景技术 Background technique

临界、超临界燃煤发电机组相关阀门高排逆止阀,即旋启式止回阀外加执行机构,该阀安装在高压缸与再热器之间管道上,防止气流不稳定而引起再热器介质倒流进高压缸,起到关键设备的保护作用。现有技术中该类阀门外没有执行机构,不能自动开启,关闭时间没有保证。遇紧急情况不能在小于0.5秒内迅速自动关闭阀门。阀门关闭可以防止因气流不稳定而引起的再热器介质倒流进高压缸,起到对关键设备的保护作用。  Critical and supercritical coal-fired generating sets related valves are high discharge check valves, that is, swing check valves with additional actuators. This valve is installed on the pipeline between the high pressure cylinder and the reheater to prevent reheating caused by unstable air flow. The device medium flows back into the high-pressure cylinder, which plays a protective role for key equipment. In the prior art, there is no actuator outside this type of valve, so it cannot be opened automatically, and the closing time is not guaranteed. In case of emergency, the valve cannot be closed automatically within less than 0.5 seconds. Closing the valve can prevent the reheater medium from flowing back into the high-pressure cylinder due to unstable air flow, and protect key equipment. the

发明内容 Contents of the invention

为了解决上述现有技术存在的问题,本发明提供了高排逆止阀,可以自动开启,遇紧急情况强关气缸能在小于0.5秒内迅速自动关闭阀门。 In order to solve the above-mentioned problems in the prior art, the present invention provides a high-row non-return valve, which can be opened automatically, and the valve can be quickly and automatically closed within less than 0.5 seconds when the cylinder is forced to close in case of emergency.

本发明解决其技术问题所采用的技术方案是: The technical solution adopted by the present invention to solve its technical problems is:

(1)摇臂、阀瓣、开口销、阀瓣螺母、阀瓣螺母垫圈、防转销组装成组件置于阀体内,阀座焊接在阀体上; (1) The rocker arm, disc, cotter pin, disc nut, disc nut washer and anti-rotation pin are assembled into components and placed in the valve body, and the valve seat is welded on the valve body;

(2)强开轴左轴套键安装于阀体左侧轴销孔内(见图2),与摇臂组件连接。在阀体轴销孔右侧插入强关轴、右轴套; (2) The left sleeve key of the forced opening shaft is installed in the shaft pin hole on the left side of the valve body (see Figure 2), and is connected with the rocker arm assembly. Insert the strong closing shaft and the right bushing on the right side of the shaft pin hole of the valve body;

(3)阀体两侧轴销孔内装填料,阀体两侧拧入右支架螺柱、左支架螺柱。右支架上旋入右填料压板螺柱,装右填料压板、填料、压套右填料压板螺母、导向套、轴承、轴承压盖、油杯、缠绕垫片一同套入强关轴,与阀体配紧,放上右支架防松垫片,拧紧右支架螺母; (3) Filling is installed in the shaft pin holes on both sides of the valve body, and the right bracket studs and left bracket studs are screwed into both sides of the valve body. Screw in the studs of the right packing pressure plate on the right bracket, install the right packing pressure plate, packing, pressure sleeve, right packing pressure plate nut, guide sleeve, bearing, bearing gland, oil cup, winding gasket and insert them into the strong closing shaft together with the valve body Fit it tightly, put the anti-loosening washer on the right bracket, and tighten the nut on the right bracket;

(4)左侧强开轴处压入填料、填料压套,拧入压板螺柱,放入左填料压板,拧上压板螺母。左支架、轴承、轴承压盖、导向套组装后和开关压板同时插入强开轴,加左支架防松垫片,拧紧左支架螺母 ;两侧安装强开传动柄、强关传动柄,锁紧螺母及左支架平垫圈;拧上紧钉螺钉。安装上开槽盘头螺钉、下开槽盘头螺钉、内开关固定板、外开关固定板、行程开关; (4) Press packing and packing gland into the forced opening shaft on the left side, screw in the pressure plate stud, put in the left packing pressure plate, and screw on the pressure plate nut. After the left bracket, bearing, bearing gland, and guide sleeve are assembled, insert the strong opening shaft at the same time as the switch pressure plate, add the left bracket anti-loosening washer, and tighten the left bracket nut; install the strong opening drive handle and the strong close drive handle on both sides, and lock them Nut and left bracket flat washer; tighten the set screw. Install the upper slotted pan head screw, the lower slotted pan head screw, the inner switch fixing plate, the outer switch fixing plate, and the travel switch;

(5)安装强开气缸、强关气缸(见图4、5),强开弹簧缸、强关弹簧缸镶入强开缸活塞杆O形圈、强开缸后盖O形圈,安装气缸体。强开活塞杆、强关活塞杆镶入强开活塞杆O形圈,分别安装强开活塞、强关活塞,镶入强开活塞O形圈,拧紧缓冲螺母,分别套入强开弹簧、强关弹簧后安装气缸体内,然后安装气缸后盖、强开缸后盖O形圈,拧紧强开缸螺母、强开缸螺柱、弹簧垫圈; (5) Install the forced opening cylinder and forced closing cylinder (see Figure 4 and 5), insert the forced opening spring cylinder and forced closing spring cylinder into the forced opening cylinder piston rod O-ring, the forced opening cylinder rear cover O-ring, and install the cylinder body. The forced opening piston rod and the forced closing piston rod are inserted into the forced opening piston rod O-ring, respectively installed the forced opening piston and the forced closing piston, inserting the forced opening piston O-ring, tightening the buffer nut, and inserting the forced opening spring, forced closing piston respectively. After closing the spring, install the cylinder body, then install the cylinder back cover, the O-ring of the back cover of the forced opening cylinder, and tighten the forced opening cylinder nut, the forced opening cylinder stud, and the spring washer;

(6)气缸组合后,分别安装阀体两侧,用强关气缸支撑板、强开气缸支撑板的内六角圆柱头螺钉固定,分别安装强开气缸、强关气缸这两个气缸并连接气动元件减压过滤器、电磁阀、快速排气阀、手动试验阀(见图6); (6) After the cylinders are combined, install the two sides of the valve body respectively, and fix them with the hexagonal socket head screws of the support plate of the strong closing cylinder and the support plate of the strong opening cylinder, respectively install the two cylinders of the strong opening cylinder and the strong closing cylinder and connect the pneumatic Component decompression filter, solenoid valve, quick exhaust valve, manual test valve (see Figure 6);

(7)安装活塞杆锁紧螺母、圆螺母并调节位置:在R侧与强开传动柄接触,在L侧与强关传动柄接触,阀体旋入中法兰螺柱,安装缠绕垫片、阀盖,加中法兰防松垫片和中法兰平垫圈,拧紧中法兰螺母。 (7) Install the piston rod lock nut and round nut and adjust the position: contact with the forced opening drive handle on the R side, contact with the forced close drive handle on the L side, screw the valve body into the middle flange stud, and install the wound gasket , Bonnet, add the anti-loosening gasket of the middle flange and the flat washer of the middle flange, and tighten the nut of the middle flange.

本发明具有的有益效果是: The beneficial effects that the present invention has are:

1.阀体采用成型铸造,均匀壁厚,在使用过程中阀门抗受力性能好,重量轻,管道负荷小; 1. The valve body adopts molding casting with uniform wall thickness. The valve has good force resistance, light weight and small pipeline load during use;

2.轴销由强开轴和强关轴组成,强开轴和摇臂之间用键连接,强关轴与摇臂之间采用空行程离合连接,执行器只起辅助快速关闭和阀门开启作用; 2. The shaft pin is composed of a strong opening shaft and a strong closing shaft. The strong opening shaft and the rocker arm are connected by a key, and the strong closing shaft and the rocker arm are connected by an idle travel clutch. The actuator only assists in quick closing and valve opening effect;

3.阀门具有强开功能,当流量小于规定流量时,让强开气缸动作,活塞杆上行推动传动柄旋转,带动强开轴旋转并使阀瓣开启。这就防止在启动初期由于气流的不稳定引起阀瓣振荡而损坏密封面; 3. The valve has a forced opening function. When the flow rate is less than the specified flow rate, the forced opening cylinder is activated, and the piston rod moves upward to push the transmission handle to rotate, driving the forced opening shaft to rotate and open the valve disc. This prevents the sealing surface from being damaged due to the oscillation of the disc caused by the instability of the air flow at the initial stage of start-up;

4.具有随动关闭和强制关闭两套独立的保护系统。当强开气缸关闭、强关气缸开启时,阀瓣处于自由状态,气体流向决定阀门启闭。此时该阀相当于一般的旋启式止回阀,阀瓣随介质顺流开启,逆流关闭。当接到关闭信号时,使强关气缸压缩空气经快排阀迅速排气,同时压缩弹簧力瞬间释放,会强制阀门迅速关闭,关闭时间小于0.5秒; 4. It has two independent protection systems of follow-up closing and forced closing. When the forced opening cylinder is closed and the forced closing cylinder is opened, the valve disc is in a free state, and the gas flow direction determines the opening and closing of the valve. At this time, the valve is equivalent to a general swing check valve, the disc opens with the medium flowing downstream and closes upstream. When the closing signal is received, the compressed air of the forced closing cylinder is quickly exhausted through the quick discharge valve, and at the same time the compressed spring force is released instantly, which will force the valve to close quickly, and the closing time is less than 0.5 seconds;

5.气动装置采用双气缸动作结构,利用下腔进气活塞上行同时压缩弹簧蓄能,一个气缸辅助阀门开启,另一个气缸辅助阀门关闭; 5. The pneumatic device adopts a double-cylinder action structure, and uses the lower cavity intake piston to go up and compress the spring to store energy at the same time. One cylinder assists the valve to open, and the other cylinder assists the valve to close;

6.在强开轴处位置安装三个行程开关,可以随时了解阀门的开启关闭位置及中间位置。 6. Install three travel switches at the position of the forced opening shaft, so that you can know the opening and closing position and the middle position of the valve at any time.

鉴于本发明高排逆止阀,具有可自动开启,遇紧急情况强关气缸能在小于0.5秒内迅速自动关闭阀门的优点,可进行广泛应用,是一种具有推广价值的新技术。 In view of the advantages of the high-row check valve of the present invention, which can be opened automatically, and the cylinder can be closed automatically within less than 0.5 seconds in case of emergency, it can be widely used and is a new technology with popularization value.

附图说明 Description of drawings

下面结合附图和具体实施方式对本发明作进一步详细说明。 The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.

图1是高排逆止阀结构示意图; Figure 1 is a schematic diagram of the structure of the high row check valve;

图2是高排逆止阀轴销部分安装示意图; Figure 2 is a schematic diagram of the installation of the shaft pin part of the high row check valve;

图3是气动装置结构示意图; Fig. 3 is a schematic diagram of the structure of the pneumatic device;

图4是气动装置中强关气缸示意图; Fig. 4 is a schematic diagram of a strong closing cylinder in a pneumatic device;

图5是气动装置中强开气缸示意图; Fig. 5 is a schematic diagram of the forced opening cylinder in the pneumatic device;

图6是强开气缸、强关气缸气动原理示意图; Fig. 6 is a schematic diagram of the pneumatic principle of forced opening and closing of the cylinder;

图7是阀门打开时强开气缸、强关气缸调节位置示意图; Fig. 7 is a schematic diagram of the adjustment position of the forced opening cylinder and the forced closing cylinder when the valve is opened;

图8是阀门关闭打开时强开气缸、强关气缸调节位置示意图; Fig. 8 is a schematic diagram of the adjustment position of the forced opening cylinder and the forced closing cylinder when the valve is closed and opened;

图1~图8中所示的附图标记如下:1、阀体,2、阀座,3、阀瓣,4、摇臂,5、阀瓣螺母垫圈,6、阀瓣螺母,7、开口销,8、防转销,9、缠绕垫片,10、阀盖,11、中法兰平垫圈,12、中法兰防松垫片,13、中法兰螺母,14、中法兰螺柱,15、吊环螺钉,16、强开气缸,17、强关气缸,18、强开传动柄,19、导向套,20、轴承压盖,21、轴承,22、强开轴,23、左轴套,24、键,25、强关轴,26、右支架防松垫片,27、右支架螺母,28、右支架螺柱,29、填料,30、左填料压板,31、右填料压板,32、油杯,33、锁紧螺母,34、强关传动柄,35、右支架,36、右填料压板螺柱,37、右填料压板螺母,38、缠绕垫片,39、右轴套,40、左支架平垫圈,41、左支架,42、压板螺柱,43、压板螺母,44、填料压套,45、左支架防松垫片,46、左支架螺柱,47、左支架螺母,48、强开活塞,49、强开缸螺柱,50、强开缸螺母,51、强开弹簧缸,52、强开缸活塞杆O形圈,53、强开活塞杆,54、气缸后盖,55、强开缸后盖O形圈,56气缸体,57、强开活塞O形圈,58、缓冲螺母,59、强开活塞杆O形圈,60、强开弹簧,61、弹簧垫圈,62、内六角圆柱头螺钉,63、强关气缸支撑板,64、活塞杆锁紧螺母,65、圆螺母,66、行程开关,67、紧钉螺钉,68、内开关固定板,69、上开槽盘头螺钉,70、开关压板,71、外开关固定板,72、强开气缸支撑板,73、强关活塞杆,74、强关弹簧缸,75、强关活塞,76、强关弹簧,77、下开槽盘头螺钉,78、减压过滤器,79、电磁阀,80、快速排气阀,81、手动试验阀。 The reference signs shown in Figures 1 to 8 are as follows: 1. valve body, 2. valve seat, 3. disc, 4. rocker arm, 5. disc nut washer, 6. disc nut, 7. opening Pin, 8, anti-rotation pin, 9, wound gasket, 10, bonnet, 11, middle flange flat washer, 12, middle flange anti-loosening gasket, 13, middle flange nut, 14, middle flange screw Column, 15, ring screw, 16, forced opening cylinder, 17, forced closing cylinder, 18, forced opening drive handle, 19, guide sleeve, 20, bearing gland, 21, bearing, 22, forced opening shaft, 23, left Shaft sleeve, 24, key, 25, strong off shaft, 26, right bracket lock washer, 27, right bracket nut, 28, right bracket stud, 29, stuffing, 30, left stuffing plate, 31, right stuffing plate , 32, oil cup, 33, lock nut, 34, strong off drive handle, 35, right bracket, 36, right packing platen stud, 37, right packing platen nut, 38, wound gasket, 39, right shaft sleeve , 40, left bracket flat washer, 41, left bracket, 42, pressure plate stud, 43, pressure plate nut, 44, packing gland, 45, left bracket anti-loosening washer, 46, left bracket stud, 47, left bracket Nut, 48, strong open piston, 49, strong open cylinder stud, 50, strong open cylinder nut, 51, strong open spring cylinder, 52, strong open cylinder piston rod O-ring, 53, strong open piston rod, 54, Cylinder rear cover, 55, forced opening cylinder rear cover O-ring, 56 cylinder block, 57, forced opening piston O-ring, 58, buffer nut, 59, forced opening piston rod O-ring, 60, forced opening spring, 61 , spring washer, 62, hexagon socket head cap screw, 63, strong closing cylinder support plate, 64, piston rod lock nut, 65, round nut, 66, travel switch, 67, tightening screw, 68, inner switch fixing plate , 69, upper slotted pan head screw, 70, switch pressure plate, 71, outer switch fixing plate, 72, forced opening cylinder support plate, 73, forced closing piston rod, 74, forced closing spring cylinder, 75, forced closing piston, 76, strong closing spring, 77, lower slotted pan head screw, 78, decompression filter, 79, solenoid valve, 80, quick exhaust valve, 81, manual test valve.

具体实施方式 Detailed ways

结合图1~图8,对本发明高排逆止阀结构进行进一步说明: With reference to Figures 1 to 8, the structure of the high row check valve of the present invention is further described:

(1)摇臂4、阀瓣3、开口销7、阀瓣螺母6、阀瓣螺母垫圈5、防转销8组装成组件置于阀体1内,阀座2焊接在阀体1上; (1) The rocker arm 4, the disc 3, the cotter pin 7, the disc nut 6, the disc nut washer 5, and the anti-rotation pin 8 are assembled into components and placed in the valve body 1, and the valve seat 2 is welded on the valve body 1;

(2)强开轴22左轴套23键24安装于阀体1左侧轴销孔内(见图2),与摇臂4组件连接。在阀体1轴销孔右侧插入强关轴25、右轴套39; (2) The forced opening shaft 22 left bushing 23 key 24 is installed in the shaft pin hole on the left side of the valve body 1 (see Figure 2), and is connected with the rocker arm 4 assembly. Insert the strong closing shaft 25 and the right bushing 39 on the right side of the shaft pin hole of the valve body 1;

(3)阀体1两侧轴销孔内装填料29,阀体1两侧拧入右支架螺柱28、左支架螺柱46。右支架35上旋入右填料压板螺柱36,装右填料压板31、填料29、压套右填料压板螺母37、导向套19、轴承21、轴承压盖20、油杯32、缠绕垫片38一同套入强关轴25,与阀体1配紧,放上右支架防松垫片26,拧紧右支架螺母27; (3) Filling 29 is installed in the pin holes on both sides of the valve body 1, and the right bracket stud 28 and the left bracket stud 46 are screwed into both sides of the valve body 1. Screw in the right packing plate stud 36 on the right bracket 35, install the right packing plate 31, packing 29, press sleeve right packing plate nut 37, guide sleeve 19, bearing 21, bearing gland 20, oil cup 32, spiral gasket 38 Insert the strong closing shaft 25 together, and tighten it with the valve body 1, put the right bracket anti-loosening washer 26, and tighten the right bracket nut 27;

(4)左侧强开轴22处压入填料29、填料压套44,拧入压板螺柱42,放入左填料压板30,拧上压板螺母43。左支架41、轴承21、轴承压盖20、导向套19组装后和开关压板70同时插入强开轴22,加左支架防松垫片45,拧紧左支架螺母47 ;两侧安装强开传动柄18、强关传动柄34,锁紧螺母33及左支架平垫圈40;拧上紧钉螺钉67。安装上开槽盘头螺钉69、下开槽盘头螺钉77、内开关固定板68、外开关固定板71、行程开关66; (4) Press the packing 29 and the packing gland 44 into the left forced opening shaft 22, screw in the pressure plate stud 42, put in the left packing pressure plate 30, and screw on the pressure plate nut 43. After the left bracket 41, bearing 21, bearing gland 20, guide sleeve 19 are assembled, insert the forced opening shaft 22 with the switch plate 70 at the same time, add the left bracket anti-loosening gasket 45, and tighten the left bracket nut 47; install the forced opening drive handle on both sides 18. Forcibly close the driving handle 34, the locking nut 33 and the left bracket flat washer 40; screw on the tightening screw 67. Install the upper slotted pan head screw 69, the lower slotted pan head screw 77, the inner switch fixing plate 68, the outer switch fixing plate 71, and the travel switch 66;

(5)安装强开气缸16、强关气缸17(见图4、5),强开弹簧缸51、强关弹簧缸74镶入强开缸活塞杆O形圈52、强开缸后盖O形圈55,安装气缸体56。强开活塞杆53、强关活塞杆73镶入强开活塞杆O形圈59,分别安装强开活塞48、强关活塞75,镶入强开活塞O形圈57,拧紧缓冲螺母58,分别套入强开弹簧60、强关弹簧76后安装气缸体56内,然后安装气缸后盖54、强开缸后盖O形圈55,拧紧强开缸螺母50、强开缸螺柱49、弹簧垫圈61; (5) Install forced opening cylinder 16, forced closing cylinder 17 (see Figure 4, 5), forced opening spring cylinder 51, forced closing spring cylinder 74 to insert forced opening cylinder piston rod O-ring 52, forced opening cylinder rear cover O Shaped ring 55, cylinder block 56 is installed. Forced opening piston rod 53, strong closing piston rod 73 are inserted into strong opening piston rod O-ring 59, respectively install strong opening piston 48, strong closing piston 75, insert strong opening piston O-ring 57, tighten buffer nut 58, respectively Put the strong opening spring 60 and the strong closing spring 76 into the cylinder block 56, then install the cylinder rear cover 54, the strong opening cylinder rear cover O-ring 55, tighten the strong opening cylinder nut 50, the strong opening cylinder stud 49, the spring washer 61;

(6)气缸组合后,分别安装阀体1两侧,用强关气缸支撑板63、强开气缸支撑板72的内六角圆柱头螺钉62固定,分别安装强开气缸16、强关气缸17这两个气缸并连接气动元件减压过滤器78、电磁阀79、快速排气阀80、手动试验阀81(见图6); (6) After the cylinders are combined, install the two sides of the valve body 1 respectively, and fix them with the hexagon socket head screws 62 of the strong closing cylinder support plate 63 and the strong opening cylinder support plate 72, respectively install the strong opening cylinder 16 and the strong closing cylinder 17 The two cylinders are connected to the pneumatic element decompression filter 78, solenoid valve 79, quick exhaust valve 80, and manual test valve 81 (see Figure 6);

(7)安装活塞杆锁紧螺母64、圆螺母65并调节位置:在R侧与强开传动柄18接触,在L侧与强关传动柄34接触,阀体1旋入中法兰螺柱14,安装缠绕垫片9、阀盖10,加中法兰防松垫片12和中法兰平垫圈11,拧紧中法兰螺母13。  (7) Install the piston rod lock nut 64 and round nut 65 and adjust the position: contact with the strong opening drive handle 18 on the R side, contact with the strong close drive handle 34 on the L side, and screw the valve body 1 into the middle flange stud 14. Install the wound gasket 9, the valve cover 10, add the anti-loosening gasket 12 of the middle flange and the flat washer 11 of the middle flange, and tighten the nut 13 of the middle flange. the

Claims (1)

1. critical, supercritical thermal power unit valve height is arranged check valve, it is characterized in that:
(1) rocking arm, flap, cotter pin, flap nut, flap nut collar, stop pin are assembled into assembly and are placed in valve body, and valve seat is welded on valve body;
(2) open by force axle left axle sleeve key and be installed in valve body left-hand axis pin-and-hole, be connected with rocker arm assembly, on valve body pivot hole right side, insert strong off-axis, right axle sleeve;
(3) the in-built filler of valve body both sides pivot hole, valve body both sides are screwed into right support double-screw bolt, left socle double-screw bolt, on right support, screw in right hold-down grid double-screw bolt, fill right hold-down grid, filler, the right hold-down grid nut of gland, guide sleeve, bearing, bearing gland, lubricating cup, spirotallic gasket and be together inserted in strong off-axis, join tightly with valve body, put right support check washer, tighten right support nut;
(4) left side is opened by force axle place and is pressed into filler, filler pressing sleeve, is screwed into pressing plate double-screw bolt, puts into left hold-down grid, the panel nut of screwing on, after left socle, bearing, bearing gland, guide sleeve assembling and switch press plate insert simultaneously and open by force axle, add left socle check washer, tighten left socle nut; Both sides are installed and to be opened by force transmission handle, close transmission handle, locking nut and left socle plain washer by force; Screw on and mark closely screw; Install slotted pan head screw, lower slotted pan head screw, interior switch fixing casing, external switch fixed plate, position limit switch;
(5) install and open by force cylinder, the strong cylinder that closes, open by force spring cylinder, strong pass spring cylinder is bumped into and opens by force cylinder piston rod O shape circle, open by force cylinder bonnet O shape circle, cylinder block is installed, open by force piston rod, strong pass piston rod is bumped into and opens by force piston rod O shape circle, install and open by force piston respectively, the strong piston that closes, be bumped into and open by force piston O shape circle, tighten buffering nut, be inserted in respectively and open by force spring, after the spring of strong pass, install in cylinder block, then cylinder back cover is installed, open by force cylinder bonnet O shape circle, tighten and open by force cylinder nut, open by force cylinder double-screw bolt, spring washer, strong pass cylinder back cover and cylinder body pass through nut, bolt is tightened,
(6) after cylinder combination, valve body both sides are installed respectively, with strong pass cylinder supports plate, the hexagon socket cap head screw of opening by force cylinder supports plate, fix, install respectively and open by force cylinder, close these two cylinders of cylinder and connect pneumatic element vacuum filter, solenoid valve, rapid escape valve, manual pet valve by force;
(7) piston rod locking nut, round nut adjusted position are installed: R side with open by force transmission handle and contact, in L side, contact with the strong transmission handle that closes, flange stud during valve body screws in, installs spirotallic gasket, valve gap, add middle flange check washer and middle flange plain washer, tighten middle flange nut.
CN201210292893.2A 2012-08-17 2012-08-17 High exhaust check valve of critical and supercritical thermal power generating set valve Active CN102808977B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210292893.2A CN102808977B (en) 2012-08-17 2012-08-17 High exhaust check valve of critical and supercritical thermal power generating set valve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210292893.2A CN102808977B (en) 2012-08-17 2012-08-17 High exhaust check valve of critical and supercritical thermal power generating set valve

Publications (2)

Publication Number Publication Date
CN102808977A CN102808977A (en) 2012-12-05
CN102808977B true CN102808977B (en) 2014-03-19

Family

ID=47232780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210292893.2A Active CN102808977B (en) 2012-08-17 2012-08-17 High exhaust check valve of critical and supercritical thermal power generating set valve

Country Status (1)

Country Link
CN (1) CN102808977B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103438250A (en) * 2013-05-03 2013-12-11 无锡富盛阀业有限公司 Swing check valve
CN104089055A (en) * 2014-07-02 2014-10-08 南通国电电站阀门有限公司 Supercritical large-caliber two-direction buffer control type check valve
CN105042123A (en) * 2015-07-03 2015-11-11 南通国电电站阀门有限公司 Supercritical Y-shaped internally-hung hard self-sealing flap-turning check valve
CN115163868B (en) * 2022-09-07 2022-12-02 烟台海悦能源科技有限公司 Intelligent balance valve of remote control

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4188973A (en) * 1977-12-06 1980-02-19 Anderson, Greenwood & Co. Check valve
CN2104361U (en) * 1991-05-13 1992-05-13 山东龙口发电厂 Hydraulically steam-pumping check valve
US5261449A (en) * 1992-05-15 1993-11-16 Val-Matic Valve And Manufacturing Corp. Quick change coupling for tilted disc check valve with top mounted dashpot
CN2436740Y (en) * 2000-08-08 2001-06-27 黄作兴 Check valve for vapour pumping
CN200955611Y (en) * 2006-10-08 2007-10-03 兰州高压阀门有限公司 Pneumatic air-extraction non-return valve
CN201416674Y (en) * 2009-06-03 2010-03-03 环球阀门集团有限公司 Steam bleeding check valve
CN201513610U (en) * 2009-09-18 2010-06-23 鞍钢集团矿业公司 A new type of non-return valve
CN201963963U (en) * 2010-12-13 2011-09-07 南方阀门制造有限公司 Extraction check valve

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4188973A (en) * 1977-12-06 1980-02-19 Anderson, Greenwood & Co. Check valve
CN2104361U (en) * 1991-05-13 1992-05-13 山东龙口发电厂 Hydraulically steam-pumping check valve
US5261449A (en) * 1992-05-15 1993-11-16 Val-Matic Valve And Manufacturing Corp. Quick change coupling for tilted disc check valve with top mounted dashpot
CN2436740Y (en) * 2000-08-08 2001-06-27 黄作兴 Check valve for vapour pumping
CN200955611Y (en) * 2006-10-08 2007-10-03 兰州高压阀门有限公司 Pneumatic air-extraction non-return valve
CN201416674Y (en) * 2009-06-03 2010-03-03 环球阀门集团有限公司 Steam bleeding check valve
CN201513610U (en) * 2009-09-18 2010-06-23 鞍钢集团矿业公司 A new type of non-return valve
CN201963963U (en) * 2010-12-13 2011-09-07 南方阀门制造有限公司 Extraction check valve

Also Published As

Publication number Publication date
CN102808977A (en) 2012-12-05

Similar Documents

Publication Publication Date Title
CN102808977A (en) High exhaust check valve of critical and supercritical thermal power generating set valve
CN206723461U (en) Without pressure difference multifunction valve
CN103672011A (en) Cryogenic top entry type fireproof ball valve with composite heat dissipation disc valve cover
CN219432527U (en) Slowly-closed check valve and slowly-closed oil cylinder thereof
CN201599415U (en) Positive-pressure internal balance stop valve
CN105257893B (en) A kind of high-temperature molten salt segment ball valve
CN101725583B (en) Combined valve
CN208381452U (en) A kind of cylinder valve pneumatic actuator component
CN112361037A (en) Quick-closing type air-extracting check valve
CN207161751U (en) A kind of multi-sealed adjustable plug valve
CN108036086A (en) Swing check valve with operation device
CN206280527U (en) A valve with the function of adjusting and stopping leakage
CN212297796U (en) Balance buffer cavity for resetting safety valve with pressure grade of more than 35Mpa
CN202165656U (en) Butterfly slow-shut type check valve
CN212480263U (en) Reset safety valve
CN207278923U (en) A kind of double adapters of band lengthen welds buried fuel gas ball valve entirely
CN201836435U (en) Top entry type two-way eccentric metal hard sealing ball valve
CN207906523U (en) A kind of swing check valve with operating device
CN204942727U (en) A kind of torque overload Control protection manual operating device
CN220646974U (en) A sealing structure of a lever type safety valve
CN204141040U (en) A kind of overcritical valve
CN107806522B (en) Steam extraction type quick-closing check valve and working method thereof
CN209604556U (en) A kind of automatic compensation fire prevention cryogenic globe valve
CN224214738U (en) Soft seal ball valve
CN207554842U (en) A kind of high platform integral heat preservation ball valve

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: High discharge check valve for critical and supercritical thermal power unit valves

Effective date of registration: 20230927

Granted publication date: 20140319

Pledgee: Dalian Branch of Shanghai Pudong Development Bank Co.,Ltd.

Pledgor: DALIAN DV VALVE Co.,Ltd.

Registration number: Y2023980059639

PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20140319

Pledgee: Dalian Branch of Shanghai Pudong Development Bank Co.,Ltd.

Pledgor: DALIAN DV VALVE Co.,Ltd.

Registration number: Y2023980059639

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Valve high discharge check valve for critical and supercritical thermal power units

Granted publication date: 20140319

Pledgee: Dalian Branch of Shanghai Pudong Development Bank Co.,Ltd.

Pledgor: DALIAN DV VALVE Co.,Ltd.

Registration number: Y2024980045328

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20140319

Pledgee: Dalian Branch of Shanghai Pudong Development Bank Co.,Ltd.

Pledgor: DALIAN DV VALVE Co.,Ltd.

Registration number: Y2024980045328