CN102745524B - Silo cluster storage and coal transfer method for large-sized coal logistics base - Google Patents

Silo cluster storage and coal transfer method for large-sized coal logistics base Download PDF

Info

Publication number
CN102745524B
CN102745524B CN201210208133.9A CN201210208133A CN102745524B CN 102745524 B CN102745524 B CN 102745524B CN 201210208133 A CN201210208133 A CN 201210208133A CN 102745524 B CN102745524 B CN 102745524B
Authority
CN
China
Prior art keywords
coal
silo
belt conveyer
storehouse
sun
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210208133.9A
Other languages
Chinese (zh)
Other versions
CN102745524A (en
Inventor
翟胜
乔朝起
胡艳
王鑫
张文生
刘协伟
周合亭
黄健仓
陈祖武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Installation Engineering Co Ltd
Original Assignee
CCCC First Harbor Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Installation Engineering Co Ltd filed Critical CCCC First Harbor Installation Engineering Co Ltd
Priority to CN201210208133.9A priority Critical patent/CN102745524B/en
Publication of CN102745524A publication Critical patent/CN102745524A/en
Application granted granted Critical
Publication of CN102745524B publication Critical patent/CN102745524B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)

Abstract

The invention discloses a silo cluster storage and coal transfer method for a large-sized coal logistics base. The method comprises the following steps of: (a) feeding coal raw materials into a silo; (2) discharging and proportioning the coal raw materials; (c) directly conveying coal to a shipment relay belt conveyor through a silo bottom belt conveyor, or when the silo is required to be reversed, unloading coal to a storage yard by the silo bottom belt conveyor through a silo reversing belt conveyor. The method has the advantages of effectively meeting the requirements of high-altitude maintenance of silo equipment and overhauling of daily equipment, emergently treating high temperature or spontaneous combustion coal in the silo and ensuring accuracy and uniformity of silo mixed coal by combination of an activating feeder and a belt weigher. Mixed coal operation can be implemented in the same operation line, and can also be implemented between any two operation lines.

Description

For silo group storage and the transfer coal method of Large-scale Coal Logistic Base
Technical field
The present invention relates to harbour coal saving, transfer technique, relate in particular to silo group storage and transfer coal method for Large-scale Coal Logistic Base.
Background technology
The outdoor Coal Yard of tradition Coal Ports stockyard arrangement form, the coal that stockyard adopts stacker-reclaimer, reclaimer work pattern to carry out stockyard is marched into the arena and appears on the scene.Under this form, the dustproof key area of coal jetty is the airborne dust of controlling stockyard.What China's harbour open storage was generally carried out is the mode of watering dust suppression, and carries out dust suppression in conjunction with wind-proof dust-suppression net around stockyard.
Watering dust suppression is subject to the impact of the natural conditions such as temperature, strong wind, and use is subject to certain restrictions, and also exists the actual coverage rate of stockyard sprinkler system cannot reach 100% simultaneously, must repeat at regular intervals watering, and produces the disadvantages such as secondary pollution.
Anti-wind net dust suppression can suppress coal dust by large-area reduction wind speed, and the northern ports of growing for water shortage, ice period has practicality.But anti-wind net dust suppression also exists following problem to need to solve: one, because being subject to that strong wind weather easily blows down etc., assurance factor limits, anti-wind net establish net height and covering power is very restricted, for the larger open storage of area, the coverage of anti-wind net cannot reach 100%.Two, the existence such as the operation circuit of the setting of anti-wind net and stockyard stacker-reclaimer and vehicle delivery conduit conflicts, and cannot accomplish that stockyard surrounding all lays, and has windproof blind area.
Summary of the invention
The object of the invention is to overcome the defect of prior art, a kind of generation that greatly reduces coal dust is provided, avoided the storage of the silo group for Large-scale Coal Logistic Base and the transfer coal method of environmental pollution.
Silo group for Large-scale Coal Logistic Base storage of the present invention and transfer coal method, it comprises the following steps:
(a) coal feedstock warehouse entry: coal feedstock enters dump car by top, the storehouse belt conveyer being arranged in a strip-type conveyer gallery 3 of same row's silo Cang Ding, dump car is sent into each silo by dump car funnel through the inlet point that is positioned at belt conveyer both sides, every silo top by coal, described belt conveyer gallery line of centers and silo disalignment 0.9-1.1 rice;
(b) coal feedstock delivers from godown and prepares burden: coal is by opening the import of a corresponding activating feeder of arranging below the discharging opening at the bottom of every silo cylinder enters each discharging opening, then by activating feeder to belt conveyer feed at the bottom of storehouse, by being arranged at the bottom of described storehouse the belt conveyer locational pair of roller belt conveyer scale that deliver from godown, the flow of the raw material that delivers from godown is measured according to predetermined proportion scale discharging simultaneously, described two roller belt conveyer scales pass to controller by metering signal, controller compares setting signal and metering signal then to export the motor of control signal to described activating feeder, reach the effect of controlling flow,
(c) at the bottom of storehouse, belt conveyer is directly delivered to shipment relay belt conveyer or when needs silo is taken grain out of a granary to sun it, at the bottom of storehouse, belt conveyer unloads coal to stockyard by coal by the belt conveyer of taking grain out of a granary to sun it by coal.
The major advantage of the inventive method is:
1. belt conveyer gallery line of centers and silo disalignment 0.9-1.1 rice, the larger side in vestibule space, top, storehouse can be used as plant maintenance region, in this region, can carry out maintenance of equipment transport channel and the maintenance activity points such as dump car, belt feeder, also can set up standby redundancy storage area, actv. has solved the needs of silo equipment high-altitude maintenance and everyday devices maintenance simultaneously.
2. the method for taking grain out of a granary to sun it is high temperature or spontaneous combustion coal in emergency handling silo, due to uncertain factor, makes the interior coal period of storage of silo long, especially hot summer, silo tans by the sun for a long time under the sun, and coal temperature is easy to raise, and coal need to be poured out while reaching the situation of dangerous values; The 2nd, coal of the same race closes storehouse.When silo is changed coal, in silo, part clout is poured out.
3. silo coal blending can guarantee accuracy, the homogeneity of mixture coal by activating feeder and belt conveyer scale combination.
4. the operation of mixture coal both can realize in same lines, also can between two lines, realize arbitrarily.
5. the coal of sealing silo is stored up form, actv. solved the environmental protection of Large-scale Coal harbour, energy-conservation, account for Land less.
Accompanying drawing explanation
Fig. 1 is the technology arrangement figure of the storage of the silo group for Large-scale Coal Logistic Base of the present invention and transfer coal method;
Fig. 2 is the lateral plan of the technology arrangement figure shown in Fig. 1;
Fig. 3 is for the silo group storage of Large-scale Coal Logistic Base and top, the silo storehouse technology arrangement figure of transfer coal method;
Fig. 4 is for the silo group storage of Large-scale Coal Logistic Base and the silo storehouse bottom technique arrangement plan of transfer coal method;
Fig. 5 is the 2-2 cutaway view of the silo storehouse bottom technique arrangement plan shown in Fig. 4;
Fig. 6 is the flow scheme of taking grain out of a granary to sun it of the storage of the silo group for Large-scale Coal Logistic Base of the present invention and transfer coal method.
The specific embodiment
Below in conjunction with the specific embodiment and embodiment, the invention will be further described.
Silo group for Large-scale Coal Logistic Base storage of the present invention and transfer coal method, it comprises the following steps: (a) coal feedstock warehouse entry: coal feedstock enters dump car 4 by top, the storehouse belt conveyer 5 being arranged in a strip-type conveyer gallery 3 of same row's silo 1 Cang Ding, dump car 4 is sent into each silo by dump car funnel through the inlet point 6 that is positioned at every silo top, belt conveyer 5 both sides by coal, described belt conveyer gallery 3 line of centerss and same row's silo 1 disalignment 0.9-1.1 rice, (b) coal feedstock delivers from godown and prepares burden: coal is by opening the import of a corresponding activating feeder 9 of arranging below the discharging opening 2 at the bottom of every silo cylinder enters each discharging opening, then by activating feeder to belt conveyer 8 feed at the bottom of storehouse, by being arranged at the bottom of described storehouse the belt conveyer 8 locational pair of roller belt conveyer scale 11 that deliver from godown, the flow of the raw material that delivers from godown is measured with the proportion scale discharging according to predetermined simultaneously, described two roller belt conveyer scales 11 pass to controller by metering signal, controller compares setting signal and metering signal then to export the motor of control signal to described activating feeder, (c) coal material is had bad luck and is taken grain out of a granary to sun it: at the bottom of storehouse, belt conveyer 8 is delivered to shipment relay belt conveyer or when needs silo is taken grain out of a granary to sun it, in the silo that at the bottom of storehouse, belt conveyer 8 is taken grain out of a granary to sun it need, coal unloads coal to stockyard 12 by the belt conveyer 13 of taking grain out of a granary to sun it by coal.
Preferred in described step (c), the working process that at the bottom of storehouse, belt conveyer 8 is delivered to shipment relay belt conveyer by coal is: in each silo bottom, be arranged symmetrically with 6 discharging openings, activating feeder of each discharging opening arranged beneath, by activating feeder to belt conveyer feed at the bottom of storehouse, belt conveyer at the bottom of the corresponding storehouse of every 3 discharging openings, when requiring ship-loading operation without batching, raw material is by a silo discharging, and at the bottom of two storehouses, belt conveyer is worked simultaneously and supplied with a shipment relay belt conveyer; When having batching to require ship-loading operation, two silos of batching are when same row, article two, at the bottom of storehouse, belt conveyer is worked simultaneously, and the material of two silos is realized batching according to arbitrary proportion on belt conveyer at the bottom of Liang Tiaocang or at the shipment relay belt conveyer in downstream; When two silos of needs batchings are not during a row, if 1:1 batching, start respectively under two row's silos belt conveyer feed at the bottom of a storehouse separately, on downstream shipment relay belt conveyer, realize batching; If not 1:1, prepare burden, belt conveyer feed at the bottom of two storehouses of startup, silo bottom that proportion scale is high, the silo bottom that proportion scale is low starts belt conveyer feed at the bottom of any storehouse, by three deliver from godown line simultaneously downstream the mode of a shipment relay belt conveyer feed realize the batching of arbitrary proportion.
As preferred embodiment; for the operation of taking grain out of a granary to sun it in spontaneous combustionof coal situation; for belt at the bottom of avoiding high temperature coal to storehouse causes damage; in described step (c); when needing silo to take grain out of a granary to sun it, first start the activating feeder of the silo bottom of the operation that do not need to take grain out of a granary to sun it; first by the belt bottom layer overlay coal of belt conveyer at the bottom of storehouse with protection belt, and then in the silo that need are taken grain out of a granary to sun it, coal unloads coal to stockyard by the belt conveyer of taking grain out of a granary to sun it.
As preferred embodiment, for preventing producing dust pollution when the operation, on the sun deck of silo top, roof scrubber 7 is installed.
For prevent occurring that hardening appears in solid accumulation and the situation of arch camber in the future, at silo discharging opening and discharging opening and bulkhead junction installation air bubble 10.
Embodiment 1
(a) coal feedstock warehouse entry: coal feedstock enters dump car 4 by top, the storehouse belt conveyer 5 being arranged in a strip-type conveyer gallery 3 of same row's silo 1 Cang Ding, dump car 4 is sent into each silo by dump car funnel through the inlet point 6 that is positioned at every silo top, belt conveyer 5 both sides by coal, 0.9 meter of described belt conveyer gallery 3 line of centerss and same row's silo 1 disalignment, on the sun deck of silo top, roof scrubber 7 is installed, the dust at inlet point place is processed, (b) coal feedstock delivers from godown and prepares burden: coal is by opening the import of a corresponding activating feeder 9 of arranging below the discharging opening 2 at the bottom of every silo cylinder enters each discharging opening, then by activating feeder to belt conveyer 8 feed at the bottom of storehouse, by being arranged at the bottom of described storehouse the belt conveyer 8 locational pair of roller belt conveyer scale 11 that deliver from godown, the flow of the raw material that delivers from godown is measured with the proportion scale discharging according to predetermined simultaneously, described two roller belt conveyer scales 11 pass to controller by metering signal, controller compares setting signal and metering signal then to export the motor of control signal to described activating feeder, (c) coal material is had bad luck and is taken grain out of a granary to sun it: the working process that at the bottom of storehouse, belt conveyer 8 is delivered to shipment relay belt conveyer by coal is: in each silo bottom, be arranged symmetrically with 6 discharging openings, activating feeder of each discharging opening arranged beneath, by activating feeder to belt conveyer feed at the bottom of storehouse, belt conveyer at the bottom of the corresponding storehouse of every 3 discharging openings, when requiring ship-loading operation without batching, raw material is by a silo discharging, and at the bottom of two storehouses, belt conveyer is worked simultaneously and supplied with a shipment relay belt conveyer, when having batching to require ship-loading operation, two silos of batching are when same row, article two, at the bottom of storehouse, belt conveyer is worked simultaneously, and the material of two silos is realized batching according to arbitrary proportion on belt conveyer at the bottom of Liang Tiaocang or at the shipment relay belt conveyer in downstream, when two silos of needs batchings are not during a row, if 1:1 batching, start respectively under two row's silos belt conveyer feed at the bottom of a storehouse separately, on downstream shipment relay belt conveyer, realize batching, if not 1:1, prepare burden, belt conveyer feed at the bottom of two storehouses of startup, silo bottom that proportion scale is high, the silo bottom that proportion scale is low starts belt conveyer feed at the bottom of any storehouse, by three deliver from godown line simultaneously downstream the mode of a shipment relay belt conveyer feed realize the batching of arbitrary proportion.When needing silo to take grain out of a granary to sun it, first start the activating feeder of the silo bottom of the operation that do not need to take grain out of a granary to sun it; first by the belt bottom layer overlay coal of belt conveyer at the bottom of storehouse with protection belt, and then in the silo that need are taken grain out of a granary to sun it, coal unloads coal to stockyard by the belt conveyer of taking grain out of a granary to sun it.
Through scene, use: above technology arrangement and flow arrangement are obtained good practicality, environmental protection and economic effects in actual use.The method is used dump car and activating feeder combination process to replace heap, reclaimer to realize coal is entered to the heap of storing up region and is unloaded, gets and pretend industry.In discharging process, by belt feeder, activating feeder and belt conveyer scale at the bottom of storehouse, cooperatively interact and flow process is switched and can be met the various coal blending demands of all types of user, and proportioning is comparatively accurate.By top, storehouse dusting equipment actv., solve the secondary that material enters after silo and played dirt.Air and activating feeder that silo surrounding is arranged cooperatively interact, and actv. solves the generation of the situations such as putty, arch camber.0.9 meter of top, storehouse gallery and same row's silo disalignment, mark off maintenance channel actv. and solved the narrow problem of silo top service clearance.This invention has solved Large-scale Coal harbour effectively in environmental protection, energy-conservation, the many-sided problem of land occupation resource, increase the accuracy of stockyard storage safe and coal blending process simultaneously, to bulk cargo terminals technology arrangement, provide a new thinking and new implementation.
Embodiment 2
(a) coal feedstock warehouse entry: coal feedstock enters dump car 4 by top, the storehouse belt conveyer 5 being arranged in a strip-type conveyer gallery 3 of same row's silo 1 Cang Ding, dump car 4 is sent into each silo by dump car funnel through the inlet point 6 that is positioned at every silo top, belt conveyer 5 both sides by coal, 1.1 meters of described belt conveyer gallery 3 line of centerss and same row's silo 1 disalignments, (b) coal feedstock delivers from godown and prepares burden: coal is by opening the import of a corresponding activating feeder 9 of arranging below the discharging opening 2 at the bottom of every silo cylinder enters each discharging opening, then by activating feeder to belt conveyer 8 feed at the bottom of storehouse, by being arranged at the bottom of described storehouse the belt conveyer 8 locational pair of roller belt conveyer scale 11 that deliver from godown, the flow of the raw material that delivers from godown is measured with the proportion scale discharging according to predetermined simultaneously, described two roller belt conveyer scales 11 pass to controller by metering signal, controller compares setting signal and metering signal then to export the motor of control signal to described activating feeder, (c) coal material is had bad luck and is taken grain out of a granary to sun it: the working process that at the bottom of storehouse, belt conveyer 8 is delivered to shipment relay belt conveyer by coal is: in each silo bottom, be arranged symmetrically with 6 discharging openings, activating feeder of each discharging opening arranged beneath, by activating feeder to belt conveyer feed at the bottom of storehouse, belt conveyer at the bottom of the corresponding storehouse of every 3 discharging openings, when requiring ship-loading operation without batching, raw material is by a silo discharging, and at the bottom of two storehouses, belt conveyer is worked simultaneously and supplied with a shipment relay belt conveyer, when having batching to require ship-loading operation, two silos of batching are when same row, article two, at the bottom of storehouse, belt conveyer is worked simultaneously, and the material of two silos is realized batching according to arbitrary proportion on belt conveyer at the bottom of Liang Tiaocang or at the shipment relay belt conveyer in downstream, when two silos of needs batchings are not during a row, if 1:1 batching, start respectively under two row's silos belt conveyer feed at the bottom of a storehouse separately, on downstream shipment relay belt conveyer, realize batching, if not 1:1, prepare burden, belt conveyer feed at the bottom of two storehouses of startup, silo bottom that proportion scale is high, the silo bottom that proportion scale is low starts belt conveyer feed at the bottom of any storehouse, by three deliver from godown line simultaneously downstream the mode of a shipment relay belt conveyer feed realize the batching of arbitrary proportion.When needing silo to take grain out of a granary to sun it, first start the activating feeder of the silo bottom of the operation that do not need to take grain out of a granary to sun it; first by the belt bottom layer overlay coal of belt conveyer at the bottom of storehouse with protection belt, and then in the silo that need are taken grain out of a granary to sun it, coal unloads coal to stockyard by the belt conveyer of taking grain out of a granary to sun it.
Through scene, use: above technology arrangement and flow arrangement are obtained good practicality, environmental protection and economic effects in actual use.The method is used dump car and activating feeder combination process to replace heap, reclaimer to realize coal is entered to the heap of storing up region and is unloaded, gets and pretend industry.In discharging process, by belt feeder, activating feeder and belt conveyer scale at the bottom of storehouse, cooperatively interact and flow process is switched and can be met the various coal blending demands of all types of user, and proportioning is comparatively accurate.By top, storehouse dusting equipment actv., solve the secondary that material enters after silo and played dirt.Air and activating feeder that silo surrounding is arranged cooperatively interact, and actv. solves the generation of the situations such as putty, arch camber.1.0 meters of top, storehouse gallery and same row's silo disalignments, mark off maintenance channel actv. and solved the narrow problem of silo top service clearance.This invention has solved Large-scale Coal harbour effectively in environmental protection, energy-conservation, the many-sided problem of land occupation resource, increase the accuracy of stockyard storage safe and coal blending process simultaneously, to bulk cargo terminals technology arrangement, provide a new thinking and new implementation.
Embodiment 3
(a) coal feedstock warehouse entry: coal feedstock enters dump car 4 by top, the storehouse belt conveyer 5 being arranged in a strip-type conveyer gallery 3 of same row's silo 1 Cang Ding, dump car 4 is sent into each silo by dump car funnel through the inlet point 6 that is positioned at every silo top, belt conveyer 5 both sides by coal, 1 meter of described belt conveyer gallery 3 line of centerss and same row's silo 1 disalignment, on the sun deck of silo top, roof scrubber 7 is installed, the dust at inlet point place is processed, (b) coal feedstock delivers from godown and prepares burden: coal is by opening the import of a corresponding activating feeder 9 of arranging below the discharging opening 2 at the bottom of every silo cylinder enters each discharging opening, then by activating feeder to belt conveyer 8 feed at the bottom of storehouse, by being arranged at the bottom of described storehouse the belt conveyer 8 locational pair of roller belt conveyer scale 11 that deliver from godown, the flow of the raw material that delivers from godown is measured with the proportion scale discharging according to predetermined simultaneously, described two roller belt conveyer scales 11 pass to controller by metering signal, controller compares setting signal and metering signal then to export the motor of control signal to described activating feeder, (c) coal material is had bad luck and is taken grain out of a granary to sun it: the working process that at the bottom of storehouse, belt conveyer 8 is delivered to shipment relay belt conveyer by coal is: in each silo bottom, be arranged symmetrically with 6 discharging openings, activating feeder of each discharging opening arranged beneath, by activating feeder to belt conveyer feed at the bottom of storehouse, belt conveyer at the bottom of the corresponding storehouse of every 3 discharging openings, when requiring ship-loading operation without batching, raw material is by a silo discharging, and at the bottom of two storehouses, belt conveyer is worked simultaneously and supplied with a shipment relay belt conveyer, when having batching to require ship-loading operation, two silos of batching are when same row, article two, at the bottom of storehouse, belt conveyer is worked simultaneously, and the material of two silos is realized batching according to arbitrary proportion on belt conveyer at the bottom of Liang Tiaocang or at the shipment relay belt conveyer in downstream, when two silos of needs batchings are not during a row, if 1:1 batching, start respectively under two row's silos belt conveyer feed at the bottom of a storehouse separately, on downstream shipment relay belt conveyer, realize batching, if not 1:1, prepare burden, belt conveyer feed at the bottom of two storehouses of startup, silo bottom that proportion scale is high, the silo bottom that proportion scale is low starts belt conveyer feed at the bottom of any storehouse, by three deliver from godown line simultaneously downstream the mode of a shipment relay belt conveyer feed realize the batching of arbitrary proportion.When needing silo to take grain out of a granary to sun it, first start the activating feeder of the silo bottom of the operation that do not need to take grain out of a granary to sun it; first by the belt bottom layer overlay coal of belt conveyer at the bottom of storehouse with protection belt, and then in the silo that need are taken grain out of a granary to sun it, coal unloads coal to stockyard by the belt conveyer of taking grain out of a granary to sun it.
Through scene, use: above technology arrangement and flow arrangement are obtained good practicality, environmental protection and economic effects in actual use.The method is used dump car and activating feeder combination process to replace heap, reclaimer to realize coal is entered to the heap of storing up region and is unloaded, gets and pretend industry.In discharging process, by belt feeder, activating feeder and belt conveyer scale at the bottom of storehouse, cooperatively interact and flow process is switched and can be met the various coal blending demands of all types of user, and proportioning is comparatively accurate.By top, storehouse dusting equipment actv., solve the secondary that material enters after silo and played dirt.Air and activating feeder that silo surrounding is arranged cooperatively interact, and actv. solves the generation of the situations such as putty, arch camber.1.1 meters of top, storehouse gallery and same row's silo disalignments, mark off maintenance channel actv. and solved the narrow problem of silo top service clearance.This invention has solved Large-scale Coal harbour effectively in environmental protection, energy-conservation, the many-sided problem of land occupation resource, increase the accuracy of stockyard storage safe and coal blending process simultaneously, to bulk cargo terminals technology arrangement, provide a new thinking and new implementation.

Claims (4)

1. for silo group storage and the transfer coal method of Large-scale Coal Logistic Base, it is characterized in that it comprises the following steps:
(a) coal feedstock warehouse entry: coal feedstock enters dump car by top, the storehouse belt conveyer being arranged in a strip-type conveyer gallery of same row's silo Cang Ding, dump car is sent into each silo by dump car funnel through the inlet point that is positioned at belt conveyer both sides, every silo top by coal, described belt conveyer gallery line of centers and silo disalignment 0.9-1.1 rice;
(b) coal feedstock delivers from godown and prepares burden: coal is by opening the import of a corresponding activating feeder of arranging below the discharging opening at the bottom of every silo cylinder enters each discharging opening, then by activating feeder to belt conveyer feed at the bottom of storehouse, by being arranged at the bottom of described storehouse the belt conveyer locational pair of roller belt conveyer scale that deliver from godown, the flow of the raw material that delivers from godown is measured simultaneously, according to predetermined proportion scale discharging, described two roller belt conveyer scales pass to controller by metering signal, controller compares setting signal and metering signal then to export the motor of control signal to described activating feeder, reach the effect of controlling flow,
(c) at the bottom of storehouse, belt conveyer is directly delivered to shipment relay belt conveyer or when needs silo is taken grain out of a granary to sun it, at the bottom of storehouse, belt conveyer unloads coal to stockyard by coal by the belt conveyer of taking grain out of a granary to sun it by coal.
2. the storage of the silo group for Large-scale Coal Logistic Base according to claim 1 and transfer coal method, it is characterized in that: in described step (c), the working process that at the bottom of storehouse, belt conveyer is delivered to shipment relay belt conveyer by coal is: in each silo bottom, be arranged symmetrically with 6 discharging openings, activating feeder of each discharging opening arranged beneath, by activating feeder to belt conveyer feed at the bottom of storehouse, belt conveyer at the bottom of the corresponding storehouse of every 3 discharging openings, when requiring ship-loading operation without batching, raw material is by a silo discharging, article two, at the bottom of storehouse, belt conveyer is worked simultaneously and is supplied with a shipment relay belt conveyer, when having batching to require ship-loading operation, two silos of batching are when same row, article two, at the bottom of storehouse, belt conveyer is worked simultaneously, and the material of two silos is realized batching according to arbitrary proportion on belt conveyer at the bottom of Liang Tiaocang or at the shipment relay belt conveyer in downstream, when two silos of needs batchings are not during a row, if 1:1 batching, start respectively under two row's silos belt conveyer feed at the bottom of a storehouse separately, on downstream shipment relay belt conveyer, realize batching, if not 1:1, prepare burden, belt conveyer feed at the bottom of two storehouses of startup, silo bottom that proportion scale is high, the silo bottom that proportion scale is low starts belt conveyer feed at the bottom of any storehouse, by three deliver from godown line simultaneously downstream the mode of a shipment relay belt conveyer feed realize the batching of arbitrary proportion.
3. the storage of the silo group for Large-scale Coal Logistic Base according to claim 1 and 2 and transfer coal method; it is characterized in that: in described step (c); when needing silo to take grain out of a granary to sun it, first start the activating feeder of the silo bottom of the operation that do not need to take grain out of a granary to sun it; first by the belt bottom layer overlay coal of belt conveyer at the bottom of storehouse with protection belt, and then in the silo that need are taken grain out of a granary to sun it, coal unloads coal to stockyard by the belt conveyer of taking grain out of a granary to sun it.
4. the storage of the silo group for Large-scale Coal Logistic Base according to claim 3 and transfer coal method, is characterized in that: on the sun deck of silo top, roof scrubber is installed.
CN201210208133.9A 2012-06-21 2012-06-21 Silo cluster storage and coal transfer method for large-sized coal logistics base Active CN102745524B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210208133.9A CN102745524B (en) 2012-06-21 2012-06-21 Silo cluster storage and coal transfer method for large-sized coal logistics base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210208133.9A CN102745524B (en) 2012-06-21 2012-06-21 Silo cluster storage and coal transfer method for large-sized coal logistics base

Publications (2)

Publication Number Publication Date
CN102745524A CN102745524A (en) 2012-10-24
CN102745524B true CN102745524B (en) 2014-05-07

Family

ID=47026114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210208133.9A Active CN102745524B (en) 2012-06-21 2012-06-21 Silo cluster storage and coal transfer method for large-sized coal logistics base

Country Status (1)

Country Link
CN (1) CN102745524B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103771152B (en) * 2014-01-10 2016-03-02 新兴能源装备股份有限公司 A kind of lime rotary kiln raw material underground discharging trench system
CN104986580A (en) * 2015-06-12 2015-10-21 中交一航局安装工程有限公司 Whole integration and comprehensive debugging method of port bulk cargo wharf integrated system
CN106628683A (en) * 2016-12-02 2017-05-10 中冶京诚工程技术有限公司 Group of silos and single silo of square steel structure
CN106869507A (en) * 2017-01-09 2017-06-20 中交航局安装工程有限公司 A kind of mounting process across spherical storehouse super large truss
CN106904418A (en) * 2017-01-09 2017-06-30 中交航局安装工程有限公司 A kind of activating feeder feed control system and control method
CN109095022B (en) * 2018-10-16 2023-11-03 山西众创达科技有限公司 Totally-enclosed horizontal coal storage tank system
CN110525992A (en) * 2019-08-19 2019-12-03 包头钢铁(集团)有限责任公司 The blanking of big volume silo is let slip a remark and coal blending operating method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101863363A (en) * 2010-06-12 2010-10-20 中冶赛迪工程技术股份有限公司 Closed storage place
CN102381569A (en) * 2010-09-03 2012-03-21 中国石油化工股份有限公司 Fixed-point quantitative automatic loading method of bulk sulfur
CN102390631A (en) * 2011-07-26 2012-03-28 中国神华能源股份有限公司 Discharging hopper of silo and silo

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08143162A (en) * 1994-11-18 1996-06-04 Mitsubishi Heavy Ind Ltd Coal storage equipment
JPH1045259A (en) * 1996-08-07 1998-02-17 Lion Corp Dust preventing device for powder product conveying device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101863363A (en) * 2010-06-12 2010-10-20 中冶赛迪工程技术股份有限公司 Closed storage place
CN102381569A (en) * 2010-09-03 2012-03-21 中国石油化工股份有限公司 Fixed-point quantitative automatic loading method of bulk sulfur
CN102390631A (en) * 2011-07-26 2012-03-28 中国神华能源股份有限公司 Discharging hopper of silo and silo

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JP特开平10-45259A 1998.02.17
JP特开平8-143162A 1996.06.04

Also Published As

Publication number Publication date
CN102745524A (en) 2012-10-24

Similar Documents

Publication Publication Date Title
CN102745524B (en) Silo cluster storage and coal transfer method for large-sized coal logistics base
CN209456335U (en) Organic materials pocket type fermentation system
WO2015085738A1 (en) Material storage device of material storage plant, and enclosed material storage plant
CN103010768B (en) Closed bulk cargo warehouse
CN205240475U (en) Semi -underground formula is arranged storehouse and is stored structure with combination of wall storehouse
CN101177978A (en) Spherical coalyard
CN101792835B (en) Feeding system for blast furnace ore and coke channel system
CN106429487B (en) A kind of optimal path transport system and its raw material store production technology in parallel with mixing
CN106628683A (en) Group of silos and single silo of square steel structure
CN207432499U (en) A kind of concrete agitation station sand material stores transportation system
CN203430122U (en) Coal bunker
CN209259067U (en) A kind of material shunting device
CN101941598A (en) Method for weighing and loading granular goods
CN105540079B (en) Circle storage is with integrated feed bin
CN206751002U (en) The arm-type ship loader of circular arc
CN109095022B (en) Totally-enclosed horizontal coal storage tank system
CN205932562U (en) Powder ore bin storehouse top dust pelletizing system
CN210504514U (en) Fuel storage and conveying system for biomass direct combustion
CN206691730U (en) A kind of square steel construction storing group storehouse and storing list storehouse
CN113754330A (en) Processing technology for producing high-strength gypsum powder by using phosphogypsum and desulfurized gypsum product
CN108176489B (en) Matte powder preparation and conveying equipment and factory building integrated configuration system
CN215983404U (en) Aggregate temperature control equipment for low-heat cement concrete dam
CN103171885B (en) To turn back buffer slide chute and installation method thereof
CN212333791U (en) Safe calcium carbide conveying and caching system for super-high structure
CN208288197U (en) A kind of preparation of matte powder and conveying equipment and workshop unified collocation system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant