CN102734897B - For the method for the step price adjust automatically air-conditioner set special duration of runs - Google Patents

For the method for the step price adjust automatically air-conditioner set special duration of runs Download PDF

Info

Publication number
CN102734897B
CN102734897B CN201210241781.4A CN201210241781A CN102734897B CN 102734897 B CN102734897 B CN 102734897B CN 201210241781 A CN201210241781 A CN 201210241781A CN 102734897 B CN102734897 B CN 102734897B
Authority
CN
China
Prior art keywords
time
air
peak
less
conditioner set
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210241781.4A
Other languages
Chinese (zh)
Other versions
CN102734897A (en
Inventor
徐艳丽
时斌
由秀玲
纪彩艳
宿平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haier Group Corp
Qingdao Haier Air Conditioning Electric Co Ltd
Original Assignee
Haier Group Corp
Qingdao Haier Air Conditioning Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haier Group Corp, Qingdao Haier Air Conditioning Electric Co Ltd filed Critical Haier Group Corp
Priority to CN201210241781.4A priority Critical patent/CN102734897B/en
Publication of CN102734897A publication Critical patent/CN102734897A/en
Application granted granted Critical
Publication of CN102734897B publication Critical patent/CN102734897B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of method for the step price adjust automatically air-conditioner set special duration of runs, comprise the following steps:MCU processing modules obtain peak valley flat period and current time;Judge current time whether in peak time section;When current time is in peak time section, judge whether current time was less than for first scheduled time with flat period or the time difference of paddy time section;And when the time difference being less than for first scheduled time, make special operating delayed, until reaching flat period or paddy time section.By technical scheme, avoid carry out special operating in peak times of power consumption in both cases, so as to save the electricity charge.

Description

For the method for the step price adjust automatically air-conditioner set special duration of runs
Technical field
It is special for step price adjust automatically air-conditioner set more particularly, to one kind the present invention relates to field of air conditioning The method of the duration of runs.
Background technology
Today of energy-saving and emission-reduction is being advocated, step price is trend of the times.Step price mainly has two kinds, and one kind is user Total electricity consumption come stepping confirm electricity consumption unit price;Another is concentrated with supplying electricity to the shadow that power network is caused aiming at peak of power consumption Ring, advocate shunting electricity consumption, the policy of the different unit prices of different time sections, using different periods electricity price " peak-to-valley-flat " processing.
Air-conditioner set, in order to protect unit, will also be transported while the basic functions such as user's refrigerating/heating/dehumidifying are realized Row oil return, defrosting, equal oil etc. are operated.The operating such as defrosting, oil return, equal oil usually requires unit and is operated in a high frequency and need configuration System outdoor unit all start, power consumption is larger.
However, there is presently no the solution for the special operating that air-conditioner set is adjusted for step price.
The content of the invention
The present invention automatically adjusts to the special duration of runs of air-conditioner set, reached for second of step price scheme To peak times of power consumption are avoided, in the case where not influenceing unit to run well, it is to avoid carry out air conditioner in electricity Unit Price high-stage The special operating of group, reaches the purpose for saving the electricity charge.
Embodiments in accordance with the present invention are directed to the step price adjust automatically air-conditioner set special duration of runs there is provided one kind Method, comprise the following steps:MCU processing modules obtain peak valley flat period and current time;Judge whether current time is located In in peak time section;When current time is in peak time section, judge current time and flat period or paddy time section when Between difference whether be less than first scheduled time;And when the time difference be less than first scheduled time when, make it is special operating it is delayed, until to Up to flat period or paddy time section.
Preferably, this method also includes:When current time is not in peak time section, judge within second scheduled time Whether special operating can be occurred;When occurring special operating within second scheduled time, judge that the time difference with peak time section is It is no to be less than for second scheduled time;And when being less than for second scheduled time with the time difference of peak time section, shift to an earlier date special operating.
Preferably, first scheduled time and second scheduled time are identical or different.
Preferably, judging current time with flat period or the time difference of paddy time section whether less than first scheduled time Before, this method also includes:Judge currently with the presence or absence of special operating mark;When there is special operating mark, judge current Whether the time was less than for first scheduled time with flat period or the time difference of paddy time section.
Preferably, when judging to exist special operating mark, this method also includes:Judging the output ratio of air-conditioner set is It is no to be less than predetermined percentage;When the output of air-conditioner set is compared less than predetermined percentage, judge current time and flat period or Whether the time difference of paddy time section was less than for first scheduled time;And when the output of air-conditioner set is compared more than predetermined percentage, Carry out special operating.
Preferably, MCU processing modules obtain the peak valley flat period from the memory cell of the outdoor computer board of air-conditioner set.
Preferably, when installing air-conditioner set, the environment modification used according to air-conditioner set is stored in the memory unit Give tacit consent to the peak valley flat period.
Preferably, MCU processing modules are obtained currently from the time block on the outdoor computer board for being arranged on air-conditioner set Time.
Preferably, time block has independent power supply not influenceed by air-conditioner set power down.
Preferably, it is special to operate the oil return for including air-conditioner set, defrosting and the one or more in oil operation.
The present invention, can be in the case where closing on peak time section by making special operating delayed under specific circumstances or in advance Carry out in advance it is special operating and make in the case where closing on flat period or paddy time section it is special operating it is delayed so that this two Avoided in the case of kind and carry out special operating in peak times of power consumption, so as to save the electricity charge;In addition, being normally in peak time When section, flat period and paddy time section, special operating is not adjusted, from without influenceing the normal operation of unit.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to institute in embodiment The accompanying drawing needed to use is briefly described, it should be apparent that, drawings in the following description are only some implementations of the present invention Example, for those of ordinary skill in the art, on the premise of not paying creative work, can also be obtained according to these accompanying drawings Obtain other accompanying drawings.
Fig. 1 is the method for the step price adjust automatically air-conditioner set special duration of runs according to embodiments of the present invention Flow chart;
Fig. 2 is that MCU module according to embodiments of the present invention obtains current time and the schematic diagram of peak valley flat period;And
Fig. 3 is the flow chart of the detail of the method for the adjustment special duration of runs according to embodiments of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belongs to what the present invention was protected Scope.
Hereinafter, embodiments of the invention are described referring to figs. 1 to Fig. 3.
Reference picture 1, it is according to embodiments of the present invention for the step price adjust automatically air-conditioner set special duration of runs Method includes:S102, MCU processing module obtain peak valley flat period and current time;S104, MCU processing module judge current Whether the time is in peak time section;S106 judges current time and flat period when current time is in peak time section Or whether the time difference of paddy time section is less than first scheduled time (being 30 minutes in Fig. 3);And S108, it is less than the when the time difference During one scheduled time, make special operating delayed, until reaching flat period or paddy time section.
Hereinafter, the processing between reference picture 2 describes MCU processing modules acquisition current time and peak valley usually.
Reference picture 2, between MCU processing modules obtain peak valley usually from the memory cell of the outdoor computer board of air-conditioner set Section.In the figure, memory cell is eeprom, and there is default value " peak-to-valley-flat " period, when installing air-conditioner set installation, such as Really " peak-to-valley-flat " period changes or each provinces and cities, every country " peak-to-valley-flat " period of outlet are variant, can To realize the change of " peak-to-valley-flat " period by changing parameter in eeprom.
A timing mould is added in method in order to realize the present invention, the hardware on the outdoor computer board of air-conditioner set Block is to obtain current time.The time block has independent power supply not influenceed by air-conditioner set power down.For example, tool The battery that the oriented time block is powered, and the battery is replaceable.
Value that MCU processing modules are stored by calling in memory cell and by obtaining current time from time block, Realized using certain processing special operating in advance with it is delayed.
Referring to Fig. 3, it is described in detail how to realize the in advance and delayed of special operating.
Reference picture 3, when current time is not in peak time section, judges whether can occur spy within second scheduled time Different operating;When occurring special operating within second scheduled time, it is pre- whether the time difference judged with peak time section is less than second Fix time;And when being less than for second scheduled time with the time difference of peak time section, shift to an earlier date special operating.
In figure 3, first scheduled time and second scheduled time are 30 minutes, it is to be understood that the two can be different. The two scheduled times are determined according to factors such as the interval times of various operations of special operating, however it is not limited to shown in figure 30 minutes, such as can also be 25 minutes, 35 minutes.
From figure 3, it can be seen that whether being less than the in the time difference for judging current time and flat period or paddy time section Before one scheduled time, this method can also include:Judge currently with the presence or absence of special operating mark.There is special operating mark In the case of will, continue subsequent treatment.
In addition, when judging to exist special operating mark, this method can also include:Judge the output ratio of air-conditioner set Whether predetermined percentage is less than;When the output of air-conditioner set is compared less than predetermined percentage, the follow-up of delayed special operating is carried out Operation;And when the output of air-conditioner set is compared more than predetermined percentage, carry out special operating.
Here, predetermined percentage is 75%, certainly, and the predetermined percentage can also be other values.More than predetermined percentage Than in the case of, no longer delayed special operating, because now the outdoor unit of air-conditioner set all starts, power consumption sheet Body state at a high value, delayed special operating is without too big meaning.
Generally speaking, method of the invention is specially:If current electricity prices are in " peak ", it is necessary to carry out special operating, away from It is less than a scheduled time (such as 30 minutes) from " paddy " or " flat " time, unit operating output retains special than being less than 75%, then Different operating mark, when electricity price is in " paddy " or " flat ", this special operating mark is effective;If current electricity prices be in " paddy " or Person's " flat ", is less than or equal to a scheduled time (such as 30 minutes) apart from special operating, is less than or equal to apart from electricity price " peak " time pre- Fix time, then carry out special operating in advance.
Note, special one kind or many operated in the oil return for including air-conditioner set, defrosting and oily operation mentioned here Kind.Certainly, the method for the present invention can also be applied to other similar situations by those skilled in the art.
The present invention, can be in the case where closing on peak time section by making special operating delayed under specific circumstances or in advance Carry out in advance it is special operating and make in the case where closing on flat period or paddy time section it is special operating it is delayed so that this two Avoided in the case of kind and carry out special operating in peak times of power consumption, so as to save the electricity charge;In addition, being normally in peak time When section, flat period and paddy time section, special operating is not adjusted, from without influenceing the normal operation of unit.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention God is with principle, and any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.

Claims (9)

1. a kind of method for the step price adjust automatically air-conditioner set special duration of runs, it is characterised in that methods described Comprise the following steps:
MCU processing modules obtain peak valley flat period and current time;
Judge the current time whether in peak time section;
When the current time is in the peak time section, judge the current time and flat period or paddy time section Whether the time difference was less than for first scheduled time;And
When the time difference being less than first scheduled time, make special operating delayed, until reach flat period or The paddy time section;
Wherein, whether be less than in the time difference for judging the current time and flat period or paddy time section first scheduled time it Before, methods described also includes:
Judge currently with the presence or absence of special operating mark;
When there is the special operating mark, judge the current time and flat period or paddy time section time difference whether Less than first scheduled time;
Wherein, when judging to exist the special operating mark,
Judge the output of the air-conditioner set than whether being less than predetermined percentage;
When the output of the air-conditioner set is than more than the predetermined percentage, special operating is carried out.
2. according to the method described in claim 1, it is characterised in that methods described also includes:
When the current time is not in the peak time section, judge whether can occur special fortune within second scheduled time Turn;
When judging to occur special operating within second scheduled time, whether the time difference of judgement and the peak time section Less than second scheduled time;And
When being less than second scheduled time with the time difference of the peak time section, shift to an earlier date special operating.
3. method according to claim 2, it is characterised in that first scheduled time and second scheduled time phase It is same or different.
4. according to the method described in claim 1, it is characterised in that methods described also includes:
When the output of the air-conditioner set is than less than the predetermined percentage, the current time and flat period or paddy are judged Whether the time difference of period was less than for first scheduled time.
5. method according to any one of claim 1 to 4, it is characterised in that the MCU processing modules are from the air-conditioning The peak valley flat period is obtained in the memory cell of the outdoor computer board of unit.
6. method according to claim 5, it is characterised in that when installing the air-conditioner set, according to the air conditioner The environment modification that group is used is stored in the acquiescence peak valley flat period in the memory cell.
7. method according to any one of claim 1 to 4, it is characterised in that the MCU processing modules are from being arranged on State and the current time is obtained in the time block on the outdoor computer board of air-conditioner set.
8. method according to claim 7, it is characterised in that the time block have independent power supply with not by The influence of the air-conditioner set power down.
9. method according to any one of claim 1 to 4, it is characterised in that the special operating includes the air-conditioning Oil return, defrosting and the one or more in oil operation of unit.
CN201210241781.4A 2012-07-12 2012-07-12 For the method for the step price adjust automatically air-conditioner set special duration of runs Active CN102734897B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210241781.4A CN102734897B (en) 2012-07-12 2012-07-12 For the method for the step price adjust automatically air-conditioner set special duration of runs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210241781.4A CN102734897B (en) 2012-07-12 2012-07-12 For the method for the step price adjust automatically air-conditioner set special duration of runs

Publications (2)

Publication Number Publication Date
CN102734897A CN102734897A (en) 2012-10-17
CN102734897B true CN102734897B (en) 2017-08-22

Family

ID=46990870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210241781.4A Active CN102734897B (en) 2012-07-12 2012-07-12 For the method for the step price adjust automatically air-conditioner set special duration of runs

Country Status (1)

Country Link
CN (1) CN102734897B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104019524B (en) * 2014-06-23 2017-02-01 珠海格力电器股份有限公司 Regulating and controlling method and device for air conditioner
CN108917132B (en) * 2018-07-27 2020-11-27 奥克斯空调股份有限公司 Air conditioner operation control method and device and air conditioner
CN112669064A (en) * 2020-12-24 2021-04-16 新疆友通电子科技有限公司 Electric power marketing service management system based on internet of things technology

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6694753B1 (en) * 2001-07-17 2004-02-24 Robertshaw Controls Company Defrost delay module
CN101105321A (en) * 2007-08-03 2008-01-16 华南理工大学 Central air conditioner end environmental temperature and cold source load remote control and regulation method and system
CN101922845A (en) * 2010-05-07 2010-12-22 海信容声(广东)冰箱有限公司 Timesharing control intelligent refrigerator and control method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2337282C2 (en) * 2003-12-15 2008-10-27 Арчелык Аноним Ширкети Refrigerating facility and method of its control

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6694753B1 (en) * 2001-07-17 2004-02-24 Robertshaw Controls Company Defrost delay module
CN101105321A (en) * 2007-08-03 2008-01-16 华南理工大学 Central air conditioner end environmental temperature and cold source load remote control and regulation method and system
CN101922845A (en) * 2010-05-07 2010-12-22 海信容声(广东)冰箱有限公司 Timesharing control intelligent refrigerator and control method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
美国全速驶向"宽带时代";王晓丹等;《上海信息化》;20101031(第10期);全文 *
适应智能电网的家用电器;黄逊青;《电器》;20110831(第8期);全文 *

Also Published As

Publication number Publication date
CN102734897A (en) 2012-10-17

Similar Documents

Publication Publication Date Title
TWI364518B (en) Power saving managing method and system using the same
CN103344028B (en) Air conditioner energy saving control method and air-conditioning
US20170191694A1 (en) Solar air conditioner and control method and control device thereof
CN104344496B (en) A kind of air conditioner and its energy-saving control method
CN104089378B (en) The control method of PV air-conditioner system, control device and PV air-conditioner system
CN104315672A (en) Air conditioning unit and power consumption control system thereof
WO2007030470A3 (en) Local power consumption load control
CN107062558B (en) Electric quantity control method for air conditioner
CN103836762A (en) Variable frequency air conditioner and method and device for controlling variable frequency air conditioning system
CN102734897B (en) For the method for the step price adjust automatically air-conditioner set special duration of runs
CN111076370B (en) Standby control device, air conditioner and stand-by control method thereof
CN105588255A (en) Control method for energy-saving type air conditioner
CN107101344A (en) A kind of power peak regulation control method, device and air-conditioning equipment
CN105180360A (en) Information display method, information display device and air conditioner
CN103629080B (en) The controlling method of oil heater and device and air conditioner
CN101645602B (en) Power load energy-saving management and control method and system
CN102998981B (en) Electrical equipment and standby controlling method, device and control system
CN107917503A (en) Solar air conditioner control method and solar air conditioner
CN105783210A (en) Multi-split air conditioner system applied to subway station and control method of multi-split air conditioner system
CN103900196A (en) Air conditioner working mode adjusting method and air conditioner
Park et al. An energy efficient smart LED lighting system for building energy management
CN104729005A (en) Air-conditioner energy saving control method and device
CN101231020A (en) Demand control system and method for multi-type air conditioner
JP2001153423A (en) Environment/energy-saving control system
CN103298179B (en) LED light device and light decay control method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant