CN102720508B - Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation - Google Patents

Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation Download PDF

Info

Publication number
CN102720508B
CN102720508B CN201210131594.0A CN201210131594A CN102720508B CN 102720508 B CN102720508 B CN 102720508B CN 201210131594 A CN201210131594 A CN 201210131594A CN 102720508 B CN102720508 B CN 102720508B
Authority
CN
China
Prior art keywords
shield
soil
ring
water
foaming agent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210131594.0A
Other languages
Chinese (zh)
Other versions
CN102720508A (en
Inventor
陈强
段绍和
陈卓
盛亮
邱秀松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
Original Assignee
China Railway Erju Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CN201210131594.0A priority Critical patent/CN102720508B/en
Publication of CN102720508A publication Critical patent/CN102720508A/en
Application granted granted Critical
Publication of CN102720508B publication Critical patent/CN102720508B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a shield construction method which uses a shield machine to continuously under-pass dense buildings in a silty-soil and silty-sand formation. The method comprises the following steps: (1) soil improvement, (2) shield tunnel, (3) segment assembly, and (4) synchronized grout injection. The method in the invention overcomes the problem that the prior shield construction methods can not satisfy requirements for ground settlement in shield constructions of water-rich silty-soil and silty-sand formations. Through the soil improvement, the shield in the construction process can maintain tunneling with stable tunneling speeds and cutterhead torques. With construction parameters strictly controlled, single ground settlement can be controlled within 3mm while accumulative ground settlement and building settlement can be controlled within 10mm. Thus, roads over the tunnel can be ensured to be unblocked, and buildings to be safe and normally used. The shield in the construction process can maintain tunneling with stable tunnel speeds and cutterhead torques, thereby increasing working efficiency and reducing construction cost.

Description

Intensive building shield construction method is worn under silt sandy silt soil stratum is continuous
Technical field
The present invention relates to a kind of shield construction method, particularly a kind of silt sandy silt soil stratum shield machine continuously under wear the construction method of intensive building.
Background technology
" shield construction " is a kind of set of tunneling construction method that mechanization and automaticity are higher, and from the sixties in 20th century, this technology is applied to city underground and the construction of large size city outlet tunnel by western developed country in a large number.Along with developing rapidly of field of urban rail, metro shield working skill is used widely.Shield construction take shield machine as tunneling equipment, does supporting with the shield shell of shield machine, with the front end knife cutting soil body, advanced, do lining cutting with prefabricated section of jurisdiction assembled in excavation face by jack pushing tow shield machine, thus form the construction method in tunnel.Shield Method Tunnel for Metro is used for municipal construction, because the excavation driving of shield machine causes loosening and depression of surrounding soil more greatly to tunnel surrounding soil disturbance, namely causes the sedimentation on earth's surface; There is structure void between excavation face and lining segment and also have certain influence to surrounding soil, therefore, certain sedimentation can be there is in shield-tunneling construction earth's surface along the line, affect by it, building around tunnel will deform, sedimentation or displacement etc., if do not take measures, ground settlement is controlled, once occur to show sedimentation significantly, serious consequence may be produced.
In shield machine tunneling process, construction parameter (as support pressure, shield driving speed, shield structure unearthed amount, simultaneous grouting slurry match ratio etc.) is larger on the impact of ground settlement.In existing shield-tunneling construction, by strictly controlling construction parameter, earth's surface cumulative settling can be controlled at-30mm ~+10mm.Such sedimentation degree, for general area, can meet construction requirement.But in Surface Buildings thickly district, then need cumulative settling to control, within ± 10mm, just effectively to avoid the impact on surface buildings caused because ground settlement is excessive.Existing shield construction method still can not reach this requirement.Further, be rich pigment soil flour sand area in construction environment, slightly control accidentally, namely the dangerous situations such as earth's surface house crack may occur because ground settlement is excessive.Therefore, need more strictly to control ground settlement.But in rich pigment soil flour sand area, because this environment has high osmosis, poor stability, shield-tunneling construction is comparatively large on its impact, and the ground settlement controlling this area exists larger difficulty.
Summary of the invention
The object of the invention is to overcome existing shield construction method cumulative settling larger, the deficiency within ± 10mm can not be controlled, wear intensive building shield construction method under providing a kind of silt powder stratum continuously, earth's surface cumulative settling can control within ± 10mm by the method.
In order to realize foregoing invention object, the invention provides following technical scheme:
Wear intensive building shield-tunneling construction construction method under silt sandy silt soil stratum shield machine is continuous, comprise the following steps:
(1) soil improvement:
Use shield-tunneling construction soil improvement foaming agent to soil improvement before shield driving, described soil improvement foaming agent mixes obtained with water by HHZ-01 foaming agent stoste, and in soil improvement foaming agent, the volume ratio of foam dope and water is 3%: 97%;
(2) shield driving:
Carry out shield driving after soil improvement, the parameter of shield driving is: shield machine thrust is 1500 ~ 1900T, and cutter head torque is 1.5 ~ 2.2MNm; Support pressure is 1.8 ~ 2.2bar, fluctuates as ± 0.2bar;
(3) pipe sheet assembling:
When shield machine thrust oil cylinder overhang reaches 1.2m, close conveying worm gate, shield machine stops advancing after continuing to push ahead 2 ~ 3cm, carries out pipe sheet assembling work; After every ring pipe sheet assembling completes, carry out next ring shield driving;
(4) synchronous grouting:
When shield structure pushes ahead the formation of shield tail space, carry out synchronous grouting by the built-in Grouting Pipe of synchronous grouting system and shield tail, the grouting pressure of synchronous grouting is 4 ~ 5.5bar, and synchronous grouting amount is 250% ~ 300%.
In above-mentioned shield construction method, by using HHZ-01 foaming agent to improve the soil body, make the soil body more soft, there is better workability, experimental data shows, under aforementioned proportion and consumption, to the disturbance of the soil body when contributing to alleviating shield driving, thus contribute to controlling ground settlement; On the other hand, soil improvement makes the soil body pliability of whole construction line consistent, contributes to keeping stable fltting speed and cutter head torque to advance in shield driving; Above-mentioned construction method is optimized construction parameter, under the condition of above-mentioned construction method, effectively can control earth's surface cumulative settling within ± 10mm.
In order to improve the soil body further, preferably, in above-mentioned shield construction method, in step (1), the consumption of soil improvement foaming agent is 0.21 ‰ of the amount of being unearthed.
In order to make shield driving stablize propelling, preferably, in above-mentioned shield construction method, in step (2), driving speed is 2.5 ~ 3cm/min.
In order to control ground settlement further, keep excavated volume be unearthed measure balanced, in above-mentioned shield construction method, in shield tunneling process control excavate soil layer be lost within 5 ‰.
In order to control ground settlement further, prevent line clogging, preferably, in above-mentioned shield construction method, in step (4), the match ratio of the slurries that synchronous grouting adopts is: in every cubic metre of slurries, each material usage is: fineness modulus is the fine sand 750 ~ 930kg of 1.6 ~ 2.2, gray scale is the flyash 390 ~ 455kg of II level, sodium bentonite 40 ~ 65kg, water 550 ~ 650kg.The proportioning of above-mentioned slurries is more preferably: in every cubic metre of slurries, each material usage is: modulus is the fine sand 820 ~ 900kg of 1.6 ~ 2.2, II level flyash 400 ~ 450kg, sodium bentonite 40 ~ 60kg, water 550 ~ 600kg.
In order to control ground settlement further, preferably, carry out the monitoring of ground settlement when shield driving, monitoring frequency is: the front 10m of cutterhead to rear 20m, and monitoring in every 4 hours once; Otch front 20 ring, to rear 30 ring scope, monitors 3 every day; After pressure surface in 30 ring to 100 rings, monitor 1 time weekly; 100 ring to 200 ring sections after pressure surface, monthly monitor 1 time;
When every day ground settlement or accumulative ground settlement exceed 70 ~ 80% of controlling value time, carry out secondary grouting, first adopt during secondary grouting single liquid starch carry out interstitial diffusion, then adopt dual slurry fill, until surface settlement control is within the scope of controlling value.
Preferably, in above-mentioned shield construction method, single slurries that described secondary grouting adopts consist of cement, water: the weight proportion of single slurries is: cement: water is 1: 0.8; Two slurries consist of cement, water glass, water, the weight proportion of two slurries is: cement: water glass: water is 1: 0.06: 0.8.
In above-mentioned shield construction method, every day, surface settlement control was in ± 3mm, and accumulative surface settlement control is in+3 ~ ± 10mm.
When tunneling to prevent shield machine, underground water and simultaneous grouting slurry scurry into tunnel from shield tail; protect shield ventral brush simultaneously; reach the sealing function of shield structure, also comprise filling shield tail grease step in above-mentioned shield construction method: when shield driving, the uniform shield tail grease of brush is brushed to shield tail steel plate.
Compared with prior art, beneficial effect of the present invention:
1, shield construction method of the present invention, use foam solution the soil body is improved, make the soil body more soft, there is better workability, the disturbance of shield structure to the soil body can be alleviated during driving, so reduce ground settlement; On the other hand, soil improvement makes the soil body pliability of whole construction line consistent, and then makes shield structure that stable fltting speed and cutter head torque can be kept to advance, and improves operating efficiency, reduces construction cost.
2, shield construction method of the present invention is adopted, within the single sedimentation of building can be controlled in 3mm, in the settlement monitoring point of earth's surface and building, the monitoring point settlement Control of 97.3%, within 10mm, ensure that the safety of unimpeded, the building of tunnel upper road and normally uses.
Detailed description of the invention
Below in conjunction with test example and detailed description of the invention, the present invention is described in further detail.But this should be interpreted as that the scope of the above-mentioned theme of the present invention is only limitted to following embodiment, all technology realized based on content of the present invention all belong to scope of the present invention.
Embodiment
For certain silt sandy silt soil stratum shield-tunneling construction, this project two-wire total length 2238.442m, amounts to section of jurisdiction 1866 ring, wherein left line length 1116.447m (931 ring), right line length 1121.995m (935 ring).Two-wire total length 2238.442m, amounts to section of jurisdiction 1866 ring, wherein left line length 1116.447m (931 ring), right line length 1121.995m (935 ring).Interval plane least radius 450m, longitudinal minimum grade is 2 ‰, and maximum gradient is 25.567 ‰.Center, tunnel the minimum depth is 12.635m, and maximum buried depth is 20.35m.Left line is advanced into 21 rings, right line 22 ring tunnel starts to wear intensive house continuously, to left line advance 695 rings, right line 701 ring completes passing through of residential block, wear raw water tubes under starting, paste Shahe; Paste passing through of Shahe start undercrossing tunnel trestle when left tunnel line advances to complete when 715 rings, right line 721 ring.After having worn the construction of Railway Trestle Bridge under shield machine, just arrive with station, station, city after undercrossing tunnel station track, discarded stake, walkway, overhead waiting hall and Zhejiang Railway Hotel successively and receive.The mainly silt sandy silt soil stratum that interval is passed through is: 3 layers of sandy silt, 5 layers of sandy silt folder flour sand, 7 layers of sandy silt, 8 layers of sandy silt folder flour sand, 1 layer of very soft sill clay, 1 farinose argillic horizon, 2 layers of silty clay.Interval silt, silty sand ground are all in saturation state, permeability slightly well, belong to aquitard, for main phreatic aquifer, its mechanical property has obvious thixotropy and mobility, under hydrodynamic condition effect, easily produces piping, quicksand and thixotropy phenomenon, thus reduce soil layer construction intensity, affect construction safety.
This silt powder stratum shield construction method comprises the following steps:
(1) soil improvement:
Use shield-tunneling construction soil improvement foaming agent to soil improvement before shield driving, described soil improvement foaming agent mixes obtained with water by domestic clear and bright HHZ-01 foaming agent stoste, in soil improvement foaming agent, the volume ratio of foam dope and water is 3%: 97%, the consumption of foaming agent is: often tunnel a ring and need foam dope 1.1L, water 35.6L;
(2) shield driving:
Carry out shield driving after soil improvement, the parameter of shield driving is: shield machine thrust is 1500 ~ 1900T, and cutter head torque is 1.5 ~ 2.2MNm; Support pressure is 1.8 ~ 2.2bar, fluctuates as ± 0.2bar; Driving speed is 2.5 ~ 3cm/min; The loss of excavation soil layer will control within 5 ‰, strict controls the amount of being unearthed, accomplish excavated volume with unearthed measure balanced.This tunnel excavation diameter 6.2m, consider the soil layer loss that shield attitude change or other reasons cause and the soil layer coefficient of volumetric expansion, every ring 1.2m is unearthed and measures about 38.4m 3.
(3) pipe sheet assembling:
When shield machine thrust oil cylinder overhang reaches 1.2m, close conveying worm gate, shield machine stops advancing after continuing to push ahead 2 ~ 3cm, carries out pipe sheet assembling work; After every ring pipe sheet assembling completes, carry out next ring shield driving;
(4) synchronous grouting:
When shield structure pushes ahead the formation of shield tail space, synchronous grouting is carried out by the built-in Grouting Pipe of synchronous grouting system and shield tail, the grouting pressure of synchronous grouting is 4 ~ 5.5bar, synchronous grouting amount is 6.8-7.5 side, the match ratio of the slurries that synchronous grouting adopts is: in every cubic metre of slurries, each material usage is: modulus be 1.6 ~ 2.2 fine sand be about 900kg, II level flyash is about 450kg, sodium bentonite 40 ~ 60kg, water 550 ~ 600kg, slurry consistency is 120mm.Simultaneous grouting slurry obtains by the following method: (1) adds sodium bentonite and water in slurry mixing tank, and the consumption of water is 1/3 of sodium bentonite consumption, mixing 30min; (2) drop in slurry mixing tank fineness modulus be 1.6 ~ 2.2 fine sand, ash for gray scale be that the flyash of II level and water carry out mixing, mixing 20min.
In above-mentioned shield construction method, by using HHZ-01 foaming agent, the soil body is improved, make the soil body more soft, there is better workability, experimental data shows, adopts the foaming agent of said method preparation gained, can reach 15 times in the pressure lower frothing multiplying power of 0.03MPa, maximum injection rate in sandy soil layer can reach 50%, under aforementioned proportion and consumption, to the disturbance of the soil body when contributing to alleviating shield driving, thus contribute to controlling ground settlement; On the other hand, soil improvement makes the soil body pliability of whole construction line consistent, contributes to keeping stable fltting speed and cutter head torque to advance in shield driving; Above-mentioned construction method is optimized construction parameter, under the condition of above-mentioned construction method, effectively can control earth's surface cumulative settling within ± 10mm.
Carry out the monitoring of ground settlement when shield driving, monitoring frequency is: the front 10m of cutterhead to rear 20m, and monitoring in every 4 hours once; Otch front 20 ring, to rear 30 ring scope, monitors 3 every day; After pressure surface in 30 ring to 100 rings, monitor 1 time weekly; 100 ring to 200 ring sections after pressure surface, monthly monitor 1 time;
When every day ground settlement exceed ± 2mm or accumulative ground settlement more than 7mm time, carry out secondary grouting, first use single liquid to starch and carry out interstitial diffusion, then adopt dual slurry to fill, until surface settlement control is within the scope of controlling value.Described single slurries consist of cement, water: the weight proportion of single slurries is: cement: water is 1: 0.8; Two slurries consist of cement, water glass, water, the weight proportion of two slurries is: cement: water glass: water is 1: 0.06: 0.8.
When tunneling to prevent shield machine, underground water and simultaneous grouting slurry scurry into tunnel from shield tail; protect shield ventral brush simultaneously; reach the sealing function of shield structure; filling shield tail grease step is also comprised: when shield driving in above-mentioned shield construction method; the uniform shield tail grease of brush is brushed to shield tail steel plate, every ring filling shield tail grease amount 35 ~ 45kg.
Adopt the simultaneous grouting slurry of above-mentioned cooperation when preparation method's preparation, there is good workability and pumpability, the disturbance of construction to the soil body can be alleviated, decrease slurries segregation, blocking Grouting Pipe phenomenon simultaneously, accelerate construction speed.
By adopting above-mentioned silt sandy silt soil stratum shield construction method, this project overcomes existing shield construction method can not meet rich pigment soil sandy silt soil stratum shield-tunneling construction to the requirement of ground settlement, make the single settlement Control of building within 3mm, in the settlement monitoring point of earth's surface and building, the monitoring point settlement Control of 97.3% is within 10mm, ensure that the safety of unimpeded, the building of tunnel upper road and normally use, the life of resident is not had any impact, maintain the favorable image in city, environmental benefit is good.
The Selection experiment of test example soil improvement foaming agent
Soil improvement test is carried out at the test section in location similar to embodiment, soil improvement foaming agent is selected, be beneficial to effectively control ground settlement, use respectively in process of the test import Condar special and domestic clear and bright respectively according to 3%, 5% proportioning and do not use foaming agent to carry out field trial, its shield driving parameter is respectively as shown shown in 1-table 4.
Table 1 sandy silt soil stratum does not add the boring parameter of foam
Table 1 result shows, when using foaming agent to improve the soil body, the situation of the excessive autostop of cutter head torque is repeatedly there is in tunneling process, and shield driving is slow, only 2mm/min can be maintained, mechanical load strengthens, temperatures as high more than 50 ° in tunnel, and the material consumptions such as shield tail grease, cutterhead grease are huge; Furthermore do not have drilling depth shield structure to be unearthed and show as water and soil released state, had a strong impact on the civilized construction in tunnel.Advance because shield structure is positioned at rich pigment soil sandy silt soil stratum, earth's surface is again the situation that intensive old house does not possess the inspection of personnel's warehouse entry, and Given this situation, has to carry out sediment improvement.To think by analysis in shield driving process 3. 6,3. 8 layers of " iron plate sand " stratum be commonly called as Hangzhou, original propelling is just more difficult, and shield structure thrusts always in addition, to the continuous dehydration of the sandy soil in card, to such an extent as to be deposited on cutterhead face and support arm top, affect the propelling of shield structure.
Table 2 adds the boring parameter record sheet of the special foaming agent of 5% import Condar
Table 3 adds the boring parameter record sheet of the special foaming agent of 3% import Condar
The driving keeping identical support pressure to carry out shield structure, from table 2-3 result, after the import foam to excavation face injection Different adding amount, shield driving parameter has had obvious improvement.
Wherein, after adding import foaming agent according to 5% proportioning, make the average driving speed in driving the 20th ring ~ the 24th ring process reach 28.8mm/min, and jack gross thrust reduces about 44.3%, cutter head torque reduces about 31.0%; The phenomenon but earth's surface generation foam is emerged.
After adding import foaming agent according to 3% proportioning, make the average driving speed in driving the 30th ring ~ the 34th ring process reach 19.6mm/min, and jack gross thrust reduces about 31.7%, cutter head torque reduces about 21.5%.
Therefore domestic clear and bright foaming agent test directly adopts 3% to carry out, and test is as table 4.
Table 4 sandy silt soil stratum adds the boring parameter record sheet of 3% domestic clear and bright foaming agent
After adding domestic foaming agent according to 3% proportioning, make the average driving speed in driving the 41st ring ~ the 45th ring process reach 22.7mm/min, and jack gross thrust reduces about 31.3%, cutter head torque reduces about 26.7%.
In comprehensive scene examination tunneling process, the boring parameter fruit of shield structure, finally determines to select domestic clear and bright foaming agent.In shield-tunneling construction, carry out preparation foam solution according to the volume ratio 3%: 97% of foam dope and water, reach 15 times according to this foam liquid of test in the pressure lower frothing multiplying power of 0.03MPa, the maximum injection rate in grittiness stone soil layer reaches 50%.Be that 52m3 (loose measure) calculates and knownly needs foam dope 1.1L according to the soil discharge quantity of often tunneling a ring, need water 35.6L.

Claims (1)

1. silt sandy silt soil stratum shield machine continuously under wear intensive building shield construction method, it is characterized in that, comprise the following steps:
(1) soil improvement:
Use shield-tunneling construction soil improvement foaming agent to soil improvement before shield driving, described soil improvement foaming agent mixes obtained with water by HHZ-01 foaming agent stoste, in soil improvement foaming agent, the volume ratio of foaming agent stoste and water is 3%:97%, the consumption of soil improvement foaming agent is: often tunnel a ring and need foaming agent stoste 1.1L, water 35.6L;
(2) shield driving:
Carry out shield driving after soil improvement, the parameter of shield driving is: shield machine thrust is 1500 ~ 1900T, and cutter head torque is 1.5 ~ 2.2MNm; Support pressure is 1.8 ~ 2.2bar, fluctuates as ± 0.2bar; Driving speed is 2.5 ~ 3cm/min, controls excavation soil layer and be lost within 5 ‰ in shield tunneling process;
(3) pipe sheet assembling:
When shield machine thrust oil cylinder overhang reaches 1.2m, close conveying worm gate, shield machine stops advancing after continuing to push ahead 2 ~ 3cm, carries out pipe sheet assembling work; After every ring pipe sheet assembling completes, carry out next ring shield driving;
(4) synchronous grouting:
When shield structure pushes ahead the formation of shield tail space, synchronous grouting is carried out by the built-in Grouting Pipe of synchronous grouting system and shield tail, the grouting pressure of synchronous grouting is 4 ~ 5.5bar, synchronous grouting amount is 250% ~ 300%, the match ratio of the slurries that synchronous grouting adopts is: in every cubic metre of slurries, each material usage is: modulus is the fine sand 820 ~ 900kg of 1.6 ~ 2.2, II level flyash 400 ~ 450kg, sodium bentonite 40 ~ 60kg, water 550 ~ 600kg, slurry consistency is 120mm;
Carry out the monitoring of ground settlement when shield driving, monitoring frequency is: the front 10m of cutterhead to rear 20m, and monitoring in every 4 hours once; Otch front 20 ring, to rear 30 ring scope, monitors 3 every day; After pressure surface in 30 ring to 100 rings, monitor 1 time weekly; 100 ring to 200 ring sections after pressure surface, monthly monitor 1 time;
When every day ground settlement or accumulative ground settlement exceed 70 ~ 80% of controlling value time, carry out secondary grouting, during secondary grouting, first adopt single slurries to carry out interstitial diffusion, then adopt two slurries to fill, until surface settlement control is within the scope of controlling value; Single slurries that described secondary grouting adopts consist of cement, water, the weight proportion of single slurries is: cement: water is 1:0.8; Two slurries consist of cement, water glass, water, the weight proportion of two slurries is: cement: water glass: water is 1:0.06:0.8;
When shield driving, the uniform shield tail grease of brush is brushed to shield tail steel plate, every ring filling shield tail grease amount 35 ~ 45kg.
CN201210131594.0A 2012-04-28 2012-04-28 Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation Active CN102720508B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210131594.0A CN102720508B (en) 2012-04-28 2012-04-28 Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210131594.0A CN102720508B (en) 2012-04-28 2012-04-28 Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation

Publications (2)

Publication Number Publication Date
CN102720508A CN102720508A (en) 2012-10-10
CN102720508B true CN102720508B (en) 2015-03-04

Family

ID=46946356

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210131594.0A Active CN102720508B (en) 2012-04-28 2012-04-28 Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation

Country Status (1)

Country Link
CN (1) CN102720508B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121662A (en) * 2016-05-06 2016-11-16 同济大学 Backbreak region synchronous grouting dynamic compensation of shield digging local fills control method

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244132A (en) * 2013-04-28 2013-08-14 上海市机械施工有限公司 Construction method for crossing houses by aid of shield tunneling machine in sandy soil and slurry injecting system
CN103527209A (en) * 2013-10-22 2014-01-22 北京交通大学 Micro disturbance tunneling method used for shield machine to tunnel under building on rich water weak formation
CN105626086B (en) * 2014-11-20 2018-09-04 宏润建设集团股份有限公司 A method of the Shield Construction Method Used in boulder bed
CN105885867A (en) * 2016-05-25 2016-08-24 重庆科技学院 Residue soil improver for waterless gravel backfilled stratum shield driving construction
CN106285715B (en) * 2016-10-26 2018-06-08 中铁十一局集团城市轨道工程有限公司 Closely the construction method of first branch bored tunnel is worn in side to balancing earth-pressure shielding machine
CN106499399A (en) * 2016-12-30 2017-03-15 中铁二局集团有限公司 A kind of Shield Construction Method Used method of overlapping tunnel in rich water powder land floor
CN106958448B (en) * 2017-05-16 2019-04-12 宁波市交通建设工程试验检测中心有限公司 A kind of shallow tunnel construction method and system
CN107129221A (en) * 2017-06-26 2017-09-05 中铁四局集团第工程有限公司 A kind of slurries suitable for low strength stratum shield duct piece grouting behind shaft or drift lining
CN108049878B (en) * 2017-11-13 2019-06-25 浙江大学城市学院 A kind of powder land floor shield cuts the construction method that stake is crossed the river
CN108533277B (en) * 2018-04-12 2020-07-24 中启胶建集团有限公司 Sedimentation control construction method for long-distance penetration of large-diameter slurry shield through shed area under non-reinforced condition
CN108868781A (en) * 2018-05-28 2018-11-23 中铁五局集团有限公司 A kind of shield construction method for shale sandy silt soil stratum
CN108999218B (en) * 2018-08-14 2020-11-24 中铁十二局集团有限公司 Construction method for shield interval construction to penetrate through anti-seepage plate wall
CN109538216B (en) * 2018-12-21 2020-11-03 中铁二十五局集团第五工程有限公司 Tunnel construction process for crossing mining and subsidence areas
CN109869158B (en) * 2019-03-20 2020-10-30 南通勘察设计有限公司 Construction process for subway shield in sandy soil
CN110939451A (en) * 2019-12-24 2020-03-31 中铁隧道集团三处有限公司 Construction method for preventing shield construction from penetrating through building to prevent settlement
CN111156010B (en) * 2020-01-10 2021-06-08 中铁隧道局集团有限公司 Construction method for shield of expansion soil layer to penetrate through existing train station house
CN111411971B (en) * 2020-03-25 2021-12-14 中铁三局集团有限公司 Settlement control construction method for water-rich silt stratum shield underpass building group
CN112554913A (en) * 2020-12-11 2021-03-26 中铁二十局集团第四工程有限公司 Reinforcing method for underground crossing channel under shield
CN113494313A (en) * 2021-06-25 2021-10-12 中铁一局集团有限公司 Contact passage portal breaking construction method for main tunnel segment
CN114278311B (en) * 2021-12-07 2023-11-24 北京工业大学 Device and method for coupling control of shield tunneling speed
CN114278323A (en) * 2021-12-31 2022-04-05 中铁五局集团有限公司 Shield construction method for underground through construction structure
CN114293998A (en) * 2021-12-31 2022-04-08 中铁五局集团有限公司 Subway underpass highway shield construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1854462A (en) * 2005-04-28 2006-11-01 上海市基础工程公司 Shiedling construction without influence on top layer of earth
CN100543270C (en) * 2008-08-04 2009-09-23 中铁十一局集团城市轨道工程有限公司 The job practices of composite soil pressure balance tunnel shielding machine for traversing shallow-buried water-rich sand layer
CN101571044B (en) * 2009-06-16 2011-04-20 中铁一局集团有限公司 Subway shield gas tunnel construction method
CN101749025B (en) * 2009-12-24 2012-11-28 上海隧道工程股份有限公司 Improved construction method of soil mass of extra-large-diameter soil pressure balancing shield on soft soil stratum
CN101967978B (en) * 2010-02-04 2012-10-03 上海隧道工程股份有限公司 Construction method for improving shield soil in composite sand gravel stratum

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121662A (en) * 2016-05-06 2016-11-16 同济大学 Backbreak region synchronous grouting dynamic compensation of shield digging local fills control method
CN106121662B (en) * 2016-05-06 2018-07-06 同济大学 Shield digging is locally backbreak, and dynamically control method is filled in compensation to region synchronous grouting

Also Published As

Publication number Publication date
CN102720508A (en) 2012-10-10

Similar Documents

Publication Publication Date Title
CN102720508B (en) Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation
Chen et al. Long rectangular box jacking project: a case study
Xu et al. Geological and hydrogeological environment in Shanghai with geohazards to construction and maintenance of infrastructures
CN101967978B (en) Construction method for improving shield soil in composite sand gravel stratum
CN102352757B (en) Method for controlling upward floating of pipe piece during shield machine air pushing through mining tunnel
CN110924967B (en) Fine control construction method for shield proximity sensitive building in water-rich sandy gravel stratum
CN104265307A (en) Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method
CN107842374B (en) The novel inert slurry of shield and combination grouting process for upper soft lower hard water rich strata
CN203961994U (en) Under balancing earth-pressure shielding machine, wear the concealed tunneling structure of having runed shield tunnel
CN102926759A (en) Long-distance tunneling construction method for big-diameter slurry shield underwater shallow earthing
CN109681236A (en) Big cross section water-rich sand layer shield driving synchronous grouting method
CN104533432A (en) Construction method for shield to penetrate through buildings in old town of downtown in complex stratums
CN110259449A (en) A kind of super high seam strip-type filling mining method for relying on telescoping steel form
CN108868796A (en) For wearing skyscraper group construction method under the shield sharp radius curve and heavy grade under water-rich sand layer
RU2529197C1 (en) Drilling wastes underground burial
ZHANG et al. Technology of groundwater reservoir construction in goafs of shallow coalfields
Song et al. Adaptability study of EPB shield machine in clay stratum in Xuzhou
CN102718441A (en) Slurry used in shield construction synchronous grouting and method for preparing same
KR100764590B1 (en) The methods of earth grouting for dam up a groundwater used by the technics of plasma glassification
CN108222954A (en) The construction method of shield crossing sand material back filled region
Chen et al. Shield construction techniques in tunneling
CN114198124A (en) Construction method for grouting and water plugging of roof fall area of inclined shaft of coal mine
CN102966353A (en) Arch-type full-mining method for three-unders coal in thick coal seam
CN113818889B (en) Construction method for crossing underground shield tunnel through civil air defense roadway
Huang et al. The coal mining mode of paste-like fill and its application prospects

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160104

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: 610041, No. nine, No. 156, building B, high building, Xing Xing Road, Chengdu hi tech Zone, Sichuan

Patentee before: China Railway Erju Co., Ltd.

CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee after: China Railway No. 2 Engineering Group Co., Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

CP01 Change in the name or title of a patent holder