CN102710357A - Smart power grid distribution type measurement and control synchronizing method - Google Patents
Smart power grid distribution type measurement and control synchronizing method Download PDFInfo
- Publication number
- CN102710357A CN102710357A CN2012101780139A CN201210178013A CN102710357A CN 102710357 A CN102710357 A CN 102710357A CN 2012101780139 A CN2012101780139 A CN 2012101780139A CN 201210178013 A CN201210178013 A CN 201210178013A CN 102710357 A CN102710357 A CN 102710357A
- Authority
- CN
- China
- Prior art keywords
- terminal
- synchronous
- control
- program
- test
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000005259 measurement Methods 0.000 title abstract description 6
- 230000001360 synchronised effect Effects 0.000 claims abstract description 38
- 238000012360 testing method Methods 0.000 claims abstract description 24
- 238000012545 processing Methods 0.000 claims abstract description 16
- 230000006855 networking Effects 0.000 claims abstract description 3
- 238000001514 detection method Methods 0.000 claims description 4
- 238000003860 storage Methods 0.000 claims description 3
- 238000000151 deposition Methods 0.000 claims description 2
- 230000002452 interceptive effect Effects 0.000 claims description 2
- 230000009466 transformation Effects 0.000 claims description 2
- 238000012544 monitoring process Methods 0.000 abstract description 6
- 230000006854 communication Effects 0.000 description 4
- 238000004891 communication Methods 0.000 description 3
- 238000006243 chemical reaction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 101100350613 Arabidopsis thaliana PLL1 gene Proteins 0.000 description 1
- 101100082028 Arabidopsis thaliana PLL2 gene Proteins 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 238000013507 mapping Methods 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
Images
Landscapes
- Small-Scale Networks (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210178013.9A CN102710357B (en) | 2012-06-01 | 2012-06-01 | Smart power grid distribution type measurement and control synchronizing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210178013.9A CN102710357B (en) | 2012-06-01 | 2012-06-01 | Smart power grid distribution type measurement and control synchronizing method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102710357A true CN102710357A (en) | 2012-10-03 |
CN102710357B CN102710357B (en) | 2014-09-10 |
Family
ID=46902937
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210178013.9A Active CN102710357B (en) | 2012-06-01 | 2012-06-01 | Smart power grid distribution type measurement and control synchronizing method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102710357B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103326802A (en) * | 2013-05-31 | 2013-09-25 | 燕山大学 | Wireless network system for achieving synchronous acquisition, synchronous acquisition device and method |
CN105425662A (en) * | 2015-11-06 | 2016-03-23 | 北京广利核系统工程有限公司 | Main processor in DCS (distributed control system) based on FPGA, and control method of main processor |
CN105515706A (en) * | 2015-10-13 | 2016-04-20 | 福州开发区慧聚通信技术有限公司 | Method and system for employing pulse mapping domain for achieving synchronization |
CN105577839A (en) * | 2016-02-29 | 2016-05-11 | 武汉大学 | Distributed data collection system and method of three-dimensional partial quadrat network |
CN108089468A (en) * | 2018-01-11 | 2018-05-29 | 尚健静 | A kind of medical examination equipment control sequential visualized generation method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201226521Y (en) * | 2008-02-28 | 2009-04-22 | 江苏电力调度通信中心 | System for monitoring time synchronization |
CN101789624A (en) * | 2009-12-09 | 2010-07-28 | 中国电力科学研究院 | Centralized digital transformer substation system |
CN101873005A (en) * | 2010-06-17 | 2010-10-27 | 深圳市科陆电子科技股份有限公司 | Method for realizing balanced acquisition of electric energy |
US20120082048A1 (en) * | 2010-10-05 | 2012-04-05 | Cisco Technology, Inc. | System and method for providing smart grid communications and management |
CN102437641A (en) * | 2011-09-20 | 2012-05-02 | 淮阴工学院 | 3G-based remote power quality monitoring method |
-
2012
- 2012-06-01 CN CN201210178013.9A patent/CN102710357B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201226521Y (en) * | 2008-02-28 | 2009-04-22 | 江苏电力调度通信中心 | System for monitoring time synchronization |
CN101789624A (en) * | 2009-12-09 | 2010-07-28 | 中国电力科学研究院 | Centralized digital transformer substation system |
CN101873005A (en) * | 2010-06-17 | 2010-10-27 | 深圳市科陆电子科技股份有限公司 | Method for realizing balanced acquisition of electric energy |
US20120082048A1 (en) * | 2010-10-05 | 2012-04-05 | Cisco Technology, Inc. | System and method for providing smart grid communications and management |
CN102437641A (en) * | 2011-09-20 | 2012-05-02 | 淮阴工学院 | 3G-based remote power quality monitoring method |
Non-Patent Citations (2)
Title |
---|
朱超等: "基于FPGA与ARM的智能合并单元", 《电网技术》 * |
游雪峰等: "以太网分布式数据采集同步和实时传输研究", 《仪器仪表学报》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103326802A (en) * | 2013-05-31 | 2013-09-25 | 燕山大学 | Wireless network system for achieving synchronous acquisition, synchronous acquisition device and method |
CN105515706A (en) * | 2015-10-13 | 2016-04-20 | 福州开发区慧聚通信技术有限公司 | Method and system for employing pulse mapping domain for achieving synchronization |
CN105425662A (en) * | 2015-11-06 | 2016-03-23 | 北京广利核系统工程有限公司 | Main processor in DCS (distributed control system) based on FPGA, and control method of main processor |
CN105425662B (en) * | 2015-11-06 | 2019-04-09 | 北京广利核系统工程有限公司 | Primary processor and its control method in Distributed Control System based on FPGA |
CN105577839A (en) * | 2016-02-29 | 2016-05-11 | 武汉大学 | Distributed data collection system and method of three-dimensional partial quadrat network |
CN105577839B (en) * | 2016-02-29 | 2018-10-26 | 武汉大学 | A kind of distributed data acquisition system and method for three-dimensional local sample prescription networking |
CN108089468A (en) * | 2018-01-11 | 2018-05-29 | 尚健静 | A kind of medical examination equipment control sequential visualized generation method |
Also Published As
Publication number | Publication date |
---|---|
CN102710357B (en) | 2014-09-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102055544B (en) | System and method for synchronously monitoring secondary equipment time of power supply system | |
CN102710357B (en) | Smart power grid distribution type measurement and control synchronizing method | |
RU112441U1 (en) | ELECTRIC ENERGY QUALITY MONITORING SYSTEM BASED ON SYNCHRONOUS MEASUREMENTS OF ELECTRIC ENERGY QUALITY INDICATORS | |
CN107819537A (en) | It is a kind of based on synchronous closed loop monitoring electric substation automation system pair when method of calibration | |
CN104217127A (en) | PMU (Power Management Unit) dynamic data simulation generating method | |
CN110798276B (en) | Time synchronization method and system for SDN (software defined network) of intelligent substation | |
CN104751280A (en) | Petrochemical enterprise electric energy consumption monitoring system and data management method thereof | |
CN104601652A (en) | Beidou satellite communication system based electric communication system and method | |
CN107276709B (en) | A kind of method for synchronizing time and system | |
CN101692106A (en) | Time frequency tester | |
KR101082522B1 (en) | Multi-Functional Gataway System for Providing Power Information | |
CN109472476A (en) | A kind of power failure identifying and analyzing method and system | |
CN106712880B (en) | A kind of communication management system | |
CN103576014B (en) | The clock monitor device of transformer station and monitoring method | |
CN106771599B (en) | The test device of intelligent substation synchronous phasor measuring device | |
CN105471540A (en) | Beidou GPS clock synchronization system based on wind power converter | |
KR101048496B1 (en) | Remote Power Control System Using Distributed Network Protocol | |
Clarizia et al. | Smart meter systems for smart grid management | |
CN108282384A (en) | A kind of Auto-Test System of the MMS server-side communication stabilities based on IEC61850 | |
CN105471572B (en) | A kind of time synchronized measurement method based on GOOSE message | |
CN204291048U (en) | Based on the power communication system of Beidou satellite communication system | |
CN106788839A (en) | A kind of digital transformer substation time synchronized performance detection method and its device | |
CN110224882A (en) | A kind of energy-accumulating power station remote control time delay measuring method and device | |
CN205232242U (en) | Big dipper GPS clock synchronization system based on wind power converter | |
CN117135662A (en) | Fault detection method and device for equipment and storage medium |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent of invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Zhao Jianyang Inventor after: Ding Weihong Inventor after: Li Haining Inventor before: Zhao Jianyang Inventor before: Ding Weihong Inventor before: Li Haining Inventor before: Chen Xiaogang Inventor before: Wu Hongtao |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: ZHAO JIANYANG DING WEIHONG LI HAINING CHEN XIAOGANG WU HONGTAO TO: ZHAO JIANYANG DING WEIHONG LI HAINING |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP02 | Change in the address of a patent holder | ||
CP02 | Change in the address of a patent holder |
Address after: 223200 Jiangsu province Huaian Huaian District bamboo Lane Street Huaiyin Institute of Technology Xiao Hu Campus Patentee after: Huaijin Polytechnical College Address before: 223001 Beijing North Road, Qinghe District, Huaian, Jiangsu, 89 Patentee before: Huaijin Polytechnical College |
|
CP02 | Change in the address of a patent holder | ||
CP02 | Change in the address of a patent holder |
Address after: 223400 8th floor, Anton building, 10 Haian Road, Lianshui County, Jiangsu. Patentee after: Huaijin Polytechnical College Address before: 223200 Jiangsu province Huaian Huaian District bamboo Lane Street Huaiyin Institute of Technology Xiao Hu Campus Patentee before: Huaijin Polytechnical College |