CN102701093B - Mechanically-driven double-gear winch for casing drilling machine - Google Patents

Mechanically-driven double-gear winch for casing drilling machine Download PDF

Info

Publication number
CN102701093B
CN102701093B CN201210190229.7A CN201210190229A CN102701093B CN 102701093 B CN102701093 B CN 102701093B CN 201210190229 A CN201210190229 A CN 201210190229A CN 102701093 B CN102701093 B CN 102701093B
Authority
CN
China
Prior art keywords
winch
drive shaft
speed reduction
reduction gearing
air tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210190229.7A
Other languages
Chinese (zh)
Other versions
CN102701093A (en
Inventor
屈晓妮
危峰
王凌寒
余长柏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Oilfield Equipment Corp
Research Institute of Sinopec Oilfield Equipment Co Ltd
Original Assignee
Sinopec Petroleum Engineering Machinery Co Ltd
Research Institute of Sinopec Petroleum Engineering Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Petroleum Engineering Machinery Co Ltd, Research Institute of Sinopec Petroleum Engineering Machinery Co Ltd filed Critical Sinopec Petroleum Engineering Machinery Co Ltd
Priority to CN201210190229.7A priority Critical patent/CN102701093B/en
Publication of CN102701093A publication Critical patent/CN102701093A/en
Application granted granted Critical
Publication of CN102701093B publication Critical patent/CN102701093B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a mechanically-driven double-gear winch for a casing drilling machine. The double-gear winch comprises a winch input shaft and a speed reducing shifting mechanism, wherein the speed reducing shifting mechanism comprises a high-gear speed reducing mechanism and a low-gear speed reducing mechanism. The double-gear winch is characterized in that the winch input shaft is respectively connected with input ends of the high-gear speed reducing mechanism and the low-gear speed reducing mechanism; both the high-gear speed reducing mechanism and the low-gear speed reducing mechanism are chain wheel and chain driven mechanisms; the output end of the low-gear speed reducing mechanism is connected with a driving shaft at one end of a roller through a first air tube clutch; the output end of the high-gear speed reducing mechanism is connected with a driving shaft at other end of the roller through a second air tube clutch; and a third air tube clutch is arranged on the drive shaft on the high-gear speed reducing mechanism. By adoption of the double-gear winch, gears are reduced, the structure is simplified, the shortcoming that the gears are required to be frequently shifted during tripping of the conventional winch is overcome, the structure of a winch control part can be simultaneously simplified, and the double-gear winch is simply operated, the driving efficiency of the winch is effectively improved; and therefore, the working efficiency is improved, and the energy consumption is reduced.

Description

A kind of mechanical drive two spotting hoist being applied to casing drilling rig
Technical field
The present invention relates to well drilling hoist field, especially one is applied to mechanical drive two spotting hoist of casing drilling rig (less than 4000 meters well depths).
Background technology
Well drilling hoist is one of core component of borer system, is also the main lift device boring equipment of repairing.Winch not only for the effect of drilling and lower pipe box, also controls the effect of the pressure of the drill, serves as speed-changing mechanism and the intermediate transmission mechanism of rotating disk in addition for drilling process, and the integral lifting of derrick.
At present in China, the mechanical drawworks for oil-well rig is mainly many spotting hoists of multiaxis chain gear, is characterized in: adopt Integral box structure, multiaxis chain gear, by clutch gear-shift, is generally 4 ~ 6 mechanical gears.This winch capacity is comparatively strong, and maximum lift speed is comparatively large, but complex structure, volume is large, and driving efficiency is low, needs shift hunting when winch makes a trip, and is difficult to the requirement effectively meeting casing drilling technique.The fundamental point of casing drilling rig technique directly adopts sleeve pipe (replacing traditional drilling rod) to transmit mechanical energy and hydraulic energy to down-hole, DHA is connected on below casing string, creep into while case in, the sleeve pipe doing drill string after finishing drilling is stayed in well and is used as completion.Casing drilling drilling rig technique is merged into an operation process by creeping into case in, and no longer need conventional round trip, and its supporting winch is mainly used in casing drilling, controls the pressure of the drill, derrick telescoping etc., and two promote gear and both can realize operating mode operation.
Summary of the invention
The object of the invention is to propose for the technical matters existed in above-mentioned prior art that a kind of gear reduces, structure is simple, improve mechanical drive two spotting hoist being applied to casing drilling rig of driving efficiency.
The present invention for the adopted technical scheme that solves the problem is: a kind of mechanical drive two spotting hoist being applied to casing drilling rig, comprise winch input shaft, Downshift mechanism, described Downshift mechanism comprises high-grade speed reduction gearing, low-grade speed reduction gearing, it is characterized in that described winch input shaft is connected with the input end of high-grade speed reduction gearing, low-grade speed reduction gearing respectively; Described high-grade speed reduction gearing, low-grade speed reduction gearing are sprocket chain strip transmission mechanism, the mouth of low-grade speed reduction gearing is connected with the axle drive shaft of cylinder one end by the first air tube clutch, the mouth of high-grade speed reduction gearing is connected with the axle drive shaft of the cylinder other end by the second air tube clutch, and the 3rd air tube clutch is installed on high-grade speed reduction gearing.
By technique scheme, described low-grade speed reduction gearing comprises the first tween drive shaft, winch input shaft is by the motion of sprocket wheel chain-driving first tween drive shaft, first tween drive shaft drives the axle drive shaft motion of cylinder one end through the first air tube clutch by sprocket wheel, described high-grade speed reduction gearing comprises the second tween drive shaft, winch input shaft drives the second tween drive shaft motion by sprocket wheel chain through the 3rd air tube clutch, and the second tween drive shaft drives the axle drive shaft motion of the cylinder other end through the second air tube clutch by sprocket wheel.
By technique scheme, the two ends, left and right of described cylinder are respectively equipped with hydraulic disc type brake device.
By technique scheme, also comprise assist brake, described assist brake adopts water cooled electromagnetic eddy current brake, and assist brake is connected by the axle drive shaft of tooth clutch with the cylinder other end.
By technique scheme, also comprise emergency mechanism, described emergency mechanism comprises emergent motor, retarder and emergent tooth clutch, and emergency mechanism is installed in one end of winch input shaft by emergent tooth clutch.
In casing drilling operation, when needs high tap position works, throw off the first air tube clutch, winch power by and winch Power output beam warp versatile spindle on car transmission gearbox drives winch input shaft to move, hang conjunction second air tube clutch, the 3rd air tube clutch, the high tap position of winch can be obtained; When needs low-grade location works, throw off the second air tube clutch on high-grade speed reduction gearing, the 3rd air tube clutch, winch input shaft drives the input end of low-grade speed reduction gearing to move, and hangs conjunction first air tube clutch, can obtain the low-grade location of winch.
Technique effect acquired by the present invention is compared with prior art: 1, gear of the present invention reduces, and designs simplification, overcomes the shortcoming needing buty shifting when existing machinery winch makes a trip, make operation simpler, effectively improve winch driving efficiency, and then improve operating efficiency, reduce energy consumption.2, owing to being single casing drilling when casing drilling rig creeps into, do not need to promote thribble, derrick height reduces, and the master rotor of supporting winch holds rope amount to be reduced, when diameter of cylinder and wirerope diameter constant, the corresponding reduction of length of cylinder.The reduction of drum length is conducive to cylinder row rope on the one hand, not easily occurs stinging rope, disorder cable situation; On the other hand winch volume is reduced, designs simplification, oad reduces, and weight is corresponding to be alleviated, and reduces floor area, cost-saving.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
Detailed description of the invention
Below in conjunction with accompanying drawing, the invention will be further described.
As shown in Figure 1 ,the present invention includes winch input shaft, Downshift mechanism, braking mechanism and emergency mechanism four part.And the band winch axle in car transmission gearbox drives winch input shaft 13 to move by versatile spindle, described Downshift mechanism comprises low-grade speed reduction gearing, high-grade speed reduction gearing, and the input shaft 13 of winch is connected with the input end of low-grade speed reduction gearing, high-grade speed reduction gearing respectively by sprocket wheel chain; Low-grade speed reduction gearing is made up of tween drive shaft 17, air tube clutch 1, sprocket wheel 14, sprocket wheel 16, sprocket wheel 18, sprocket wheel 2 and chain, and low-range reduction mechanism is connected with the axle drive shaft of cylinder 3 one end by air tube clutch 1; High-grade speed reduction gearing is made up of tween drive shaft 19, air tube clutch 9, air tube clutch 6, sprocket wheel 11, sprocket wheel 10, sprocket wheel 12, sprocket wheel 20, sprocket wheel 8 and chain, and high-grade reduction gear is connected with the axle drive shaft of cylinder 3 other end through air tube clutch 9, air tube clutch 6; Winch brake mechanism comprises major-minor brake, main brake adopts two groups of hydraulic disc brakes 4,5, two groups of hydraulic disc brakes 4,5 are separately positioned on the two ends of winch drum 3, assist brake adopts water cooled electromagnetic eddy current brake 7, adopts tooth clutch to connect between assist brake 7 and the axle drive shaft of the cylinder other end.For the object of safe operation, in input shaft one end, emergency facility 15 is set, emergency facility 15 comprises emergent motor, retarder and emergent tooth clutch, when mair motor break down or cisco unity malfunction time, start emergency facility 15, drive Downshift mechanism by emergent tooth clutch, reach the object promoting maximum drill string weight, ensure downhole safety and operator safety, and the emergent operation such as derrick telescoping, movable drilling tool can be realized.
During casing drilling operation, winch power by and car transmission gearbox on band winch beam warp versatile spindle be input to winch input shaft 13, sprocket wheel 11 on winch input shaft, sprocket wheel 14 drives the sprocket wheel 16 on the sprocket wheel 10 of tween drive shaft 19 and tween drive shaft 17 to rotate respectively, throw off the air tube clutch 9 on tween drive shaft 19, now sprocket wheel 10 dallies, power transmits on sprocket wheel 16 by sprocket wheel 14 through chain, sprocket wheel 16 drives tween drive shaft 17 to move, tween drive shaft 17 is with movable sprocket 18 to rotate, power is delivered on sprocket wheel 2 through chain by sprocket wheel 18, now, hang and close air tube clutch 1, sprocket wheel 2 drives the axle drive shaft of cylinder 3 one end to move, low-grade location work can be realized.When needs high tap position works, throw off air tube clutch 1, sprocket wheel 2 dallies, and power is delivered on sprocket wheel 10 by sprocket wheel 11 through chain, hangs the air tube clutch 9 closed on tween drive shaft 19, sprocket wheel 10 drives tween drive shaft 19 to move, sprocket wheel 12 on tween drive shaft 19 rotates through chain-driving sprocket wheel 20, and hang and close air tube clutch 6, power is delivered on sprocket wheel 8 by sprocket wheel 20 through chain, sprocket wheel 8 drives the axle drive shaft of cylinder 3 other end to move, and can realize high tap position work.Sprocket wheel 16 now on tween drive shaft 17, sprocket wheel 18 are in idling conditions.
Matching used two spotting hoists of casing drilling rig are mainly used in casing drilling, control the pressure of the drill, derrick telescoping etc., two promote gear and both can realize operating mode operation, overcome the shortcoming needing buty shifting when existing machinery winch makes a trip, make operation simpler, effectively improve winch driving efficiency, and then raising operating efficiency, reduce energy consumption.Meanwhile, owing to being single casing drilling when casing drilling rig creeps into, do not need to promote thribble, derrick height reduces, and the master rotor of supporting winch holds rope amount and can greatly reduce.

Claims (1)

1. one kind is applied to mechanical drive two spotting hoist of casing drilling rig, comprise winch input shaft, Downshift mechanism, emergency mechanism, described winch input shaft propulsion source comes from diesel machine, described Downshift mechanism comprises high-grade speed reduction gearing, low-grade speed reduction gearing, and described winch input shaft is connected with the input end of high-grade speed reduction gearing, low-grade speed reduction gearing respectively, described high-grade speed reduction gearing, low-grade speed reduction gearing is sprocket chain strip transmission mechanism, the mouth of low-grade speed reduction gearing is connected with the axle drive shaft of cylinder one end by the first air tube clutch, the mouth of high-grade speed reduction gearing is connected with the axle drive shaft of the cylinder other end by the second air tube clutch, 3rd air tube clutch is installed on the second tween drive shaft of high-grade speed reduction gearing, it is characterized in that described low-grade speed reduction gearing comprises winch input shaft, first tween drive shaft and drum shaft, winch input shaft is by the motion of sprocket wheel chain-driving first tween drive shaft, first tween drive shaft drives the axle drive shaft motion of cylinder low speed end through the first air tube clutch by sprocket wheel, described high-grade speed reduction gearing comprises winch input shaft, the second tween drive shaft and drum shaft, winch input shaft drives the second tween drive shaft motion by sprocket wheel chain through the 3rd air tube clutch, second tween drive shaft drives the axle drive shaft motion of cylinder speed end through the second air tube clutch by sprocket wheel, described emergency mechanism comprises emergent motor, retarder and emergent tooth clutch, and emergency mechanism is installed in one end of winch input shaft by emergent tooth clutch, the two ends, left and right of described cylinder are respectively equipped with hydraulic disc type brake device, also comprise assist brake, described assist brake adopts water cooled electromagnetic eddy current brake, and assist brake is connected by the axle drive shaft of tooth clutch with the cylinder other end.
CN201210190229.7A 2012-06-11 2012-06-11 Mechanically-driven double-gear winch for casing drilling machine Active CN102701093B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210190229.7A CN102701093B (en) 2012-06-11 2012-06-11 Mechanically-driven double-gear winch for casing drilling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210190229.7A CN102701093B (en) 2012-06-11 2012-06-11 Mechanically-driven double-gear winch for casing drilling machine

Publications (2)

Publication Number Publication Date
CN102701093A CN102701093A (en) 2012-10-03
CN102701093B true CN102701093B (en) 2015-07-08

Family

ID=46894236

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210190229.7A Active CN102701093B (en) 2012-06-11 2012-06-11 Mechanically-driven double-gear winch for casing drilling machine

Country Status (1)

Country Link
CN (1) CN102701093B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105035988A (en) * 2015-06-29 2015-11-11 南阳二机石油装备(集团)有限公司 Integral four-shaft chain transmission direct current boring winch
CN105540470B (en) * 2016-02-17 2017-11-24 宁波新宏液压有限公司 Double clutch Winch Wire Rope Ranging Devices and its application

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2350371Y (en) * 1998-11-12 1999-11-24 兰州石油化工机器总厂 Transmission of shift winch for pneumatic tyre clutch
CN2705440Y (en) * 2004-05-14 2005-06-22 胡德祥 Electric winch for petroleum drilling machine
CN2815995Y (en) * 2004-12-27 2006-09-13 中国石油集团科学技术研究院江汉机械研究所 Driller winch
CN201052952Y (en) * 2007-05-31 2008-04-30 四川宏华石油设备有限公司 Alternating current frequency conversion two-shift winch

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020171072A1 (en) * 2001-05-18 2002-11-21 Lin Tso-Kuo Two speed windlass

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2350371Y (en) * 1998-11-12 1999-11-24 兰州石油化工机器总厂 Transmission of shift winch for pneumatic tyre clutch
CN2705440Y (en) * 2004-05-14 2005-06-22 胡德祥 Electric winch for petroleum drilling machine
CN2815995Y (en) * 2004-12-27 2006-09-13 中国石油集团科学技术研究院江汉机械研究所 Driller winch
CN201052952Y (en) * 2007-05-31 2008-04-30 四川宏华石油设备有限公司 Alternating current frequency conversion two-shift winch

Also Published As

Publication number Publication date
CN102701093A (en) 2012-10-03

Similar Documents

Publication Publication Date Title
CN204571836U (en) Double power vehicle-mounted workover rig
CN103130133A (en) Winch rolling spiral rope arranging method
CN203655147U (en) Power head for deep-hole core drilling machine
CN105035988A (en) Integral four-shaft chain transmission direct current boring winch
CN102701093B (en) Mechanically-driven double-gear winch for casing drilling machine
CN202107466U (en) Hydraulic winch control device for workover rig
CN203284122U (en) Integrated type four-shaft chain transmission direct current boring winch
CN103130121A (en) Hydraulic rope guiding system applicable to drill well winch and hydraulic rope guiding method applicable to drill well winch
CN201212362Y (en) Seven-kilometer triaxial DC electric drilling winch
CN202467646U (en) Spiral piling machine
CN202296943U (en) Oil workover rig power-driven winch assembly
CN106429921B (en) Five shaft gear drive petroleum rig winches
CN201052952Y (en) Alternating current frequency conversion two-shift winch
CN201810200U (en) Hydraulic independent driven turntable device for petroleum drilling machine
CN202897891U (en) Novel chain transmission heavy load boring winch
CN102493765A (en) Spiral hammer
CN203285333U (en) Full hydraulic rotation lifting type vehicle-mounted drilling and workover rig
CN206273768U (en) Five shaft gear drive petroleum rig winches
CN201560078U (en) Novel power-driven single shaft winch of large or medium oil rig
CN105019830A (en) Novel efficient drilling machine convenient to use
CN205973568U (en) But transfer double drum winch
CN106895118B (en) Reduction gearbox and boring winch
CN203715140U (en) High and low speed gear transmission well repairing winch
CN203701947U (en) Novel rotary drilling rig auxiliary winching driving device
CN205100909U (en) Rig is with sending brill device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: SINOPEC PETROLEUM ENGINEERING MACHINERY CO., LTD.

Free format text: FORMER OWNER: SINOPEC GROUP

Effective date: 20141126

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 430223, Hubei, East Lake province Wuhan New Technology Development Zone 77 Optics Valley Avenue, Optics Valley finance port, block A2, 12

Applicant after: Sinopec Petroleum Engineering Machinery Co.,Ltd.

Applicant after: PERTOLEUM MACHINERY RESEARCH INSTITUTE OF SINOPEC OILFIELD EQUIPMENT Corp.

Address before: 430223, Hubei, East Lake province Wuhan New Technology Development Zone 77 Optics Valley Avenue, Optics Valley finance port, block A2, 12

Applicant before: Sinopec Petroleum Engineering Machinery Co.,Ltd.

Applicant before: PETROLEUM MACHINERY RESEARCH INSTITUTE OF JIANGHAN PETROLEUM ADMINISTRATION BUREAU, CHINA PETROCHEMICAL Corp.

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 100728 CHAOYANG, BEIJING TO: 430223 WUHAN, HUBEI PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20141126

Address after: 430223, Hubei, East Lake province Wuhan New Technology Development Zone 77 Optics Valley Avenue, Optics Valley finance port, block A2, 12

Applicant after: Sinopec Petroleum Engineering Machinery Co.,Ltd.

Applicant after: PETROLEUM MACHINERY RESEARCH INSTITUTE OF JIANGHAN PETROLEUM ADMINISTRATION BUREAU, CHINA PETROCHEMICAL Corp.

Address before: 100728 Beijing, Chaoyangmen, North Street, No. 22, No.

Applicant before: CHINA PETROLEUM & CHEMICAL Corp.

Applicant before: PETROLEUM MACHINERY RESEARCH INSTITUTE OF JIANGHAN PETROLEUM ADMINISTRATION BUREAU, CHINA PETROCHEMICAL Corp.

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171103

Address after: 430223, No. 5, Chinese workers' garden, Temple Hill community, East Lake New Technology Development Zone, Wuhan, Hubei

Co-patentee after: SINOPEC OILFIELD EQUIPMENT CORPORATION INSTITUTE

Patentee after: SINOPEC OILFIELD EQUIPMENT Corp.

Address before: 430223, Hubei, East Lake province Wuhan New Technology Development Zone 77 Optics Valley Avenue, Optics Valley finance port, block A2, 12

Co-patentee before: PERTOLEUM MACHINERY RESEARCH INSTITUTE OF SINOPEC OILFIELD EQUIPMENT Corp.

Patentee before: Sinopec Petroleum Engineering Machinery Co.,Ltd.