CN102619196B - 沿海宽河谷地区混凝土坝和土坝的接头 - Google Patents

沿海宽河谷地区混凝土坝和土坝的接头 Download PDF

Info

Publication number
CN102619196B
CN102619196B CN201210114161.4A CN201210114161A CN102619196B CN 102619196 B CN102619196 B CN 102619196B CN 201210114161 A CN201210114161 A CN 201210114161A CN 102619196 B CN102619196 B CN 102619196B
Authority
CN
China
Prior art keywords
dam
earth
connector
concrete
coastal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210114161.4A
Other languages
English (en)
Other versions
CN102619196A (zh
Inventor
曾雪艳
王庆祥
赵红敏
夏建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Zhongnan Engineering Corp Ltd
Original Assignee
PowerChina Zhongnan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Zhongnan Engineering Corp Ltd filed Critical PowerChina Zhongnan Engineering Corp Ltd
Priority to CN201210114161.4A priority Critical patent/CN102619196B/zh
Publication of CN102619196A publication Critical patent/CN102619196A/zh
Application granted granted Critical
Publication of CN102619196B publication Critical patent/CN102619196B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

本发明公开了一种沿海宽河谷地区混凝土坝和土坝的接头,属于混凝土坝和土坝接头领域,为了解决现有插入式接头的上游侧裹头受高风速影响导致护坡破坏的问题,一种沿海宽河谷地区混凝土坝和土坝的接头,所述混凝土坝和土坝的接头为插入式接头,该插入式接头具有上游侧裹头,该上游侧裹头的外轮廓线与坝轴线水平投影线的交角β为大于120°的钝角。本发明大大缓解了波能集中,避免了土坝上游变坡失稳甚至跨坝的威胁,尤其适用于高风速的宽河谷地区。

Description

沿海宽河谷地区混凝土坝和土坝的接头
技术领域
本发明主要适用于沿海宽河谷地区土坝和混凝土坝连接处的插入式接头上游外包土坝部位(简称上游裹头),尤其适用于高风速的宽河谷地区。
背景技术
在人类抵抗大自然洪涝、干旱灾害过程中,筑坝历史悠久。最早采用的坝型为土坝。土坝适应地基条件良好、抗震能力也较强,但不利于布置坝身泄水建筑物。
随着筑坝技术的发展和新型筑坝材料的发明,有利于布置坝身泄水建筑物的混凝土坝成为首选坝型。但宽河谷地区大坝轴线较长,河床覆盖层较深,采用混凝土坝一般经济性较差,故一般在主河床采用混凝土坝泄洪,两侧河床采用土坝挡水以节约投资,混凝土坝和土坝的连接成为大坝设计的关键。
土坝同混凝土坝连接,一般可采取翼墙式和插入式。自70年代末广西西津水库成功采用工程量相对节省的插入式接头以来,插入式接头成为土坝和混凝土坝连接的首推型式。
该种型式具体结构是:将变截面的混凝土坝插入土坝一段距离,用土坝包裹截面变小的混凝土坝,接头处土坝上、下游坝坡保持不变,以90°圆锥将混凝土半插入段包裹住(该部分土坝简称裹头)。这种结构在低风速的内地峡谷地区运用情况良好。但对于沿海宽河谷地区,在台风季节,高风速极易在上游裹头侧引起波能集中,产生很大的波浪压力,破坏该部位土坝的护坡,从而直接淘刷土坝坝体,存在导致土坝上游变坡失稳甚至跨坝的安全隐患。
例如海南大广坝水电站其河床为碾压混凝土重力坝,左、右两岸为均质土坝,混凝土坝和土坝采用插入式接头,结构由土坝包裹混凝土坝段。土坝裹头上游为90°圆锥裹头。
2005年,海南达维台风在大广坝坝址处产生最大风速达39.3 m/s。本次台风对接头的混凝土插入式坝段基本无损害,但对高程132.0m以上的均质土坝裹头毁坏严重,90°圆锥裹头表层抛石、碎石护坡失稳全部滑入库区,下部土工织物全部被冲走,均质土坝坝壳被冲毁,靠近混凝土坝面接触区的防渗层(粘土)被冲走。
水毁原因分析认为:造成该次过头破坏的主要原因为接头裹头部位的结构型式不适合沿海宽河谷地区。
大广坝枢纽土坝和混凝土坝接头部位需承受沿河道和沿坝轴线两个方向的风力。在内陆地区,因河谷狭窄,两岸山体陡竣,其沿坝轴线方向吹程较短,风力较小,几乎可以忽略。故原土坝设计规范未对接头部位的波浪压力计算做特殊规定,仅参考土坝计算波浪压力。
大广坝枢纽地势十分开阔,坝顶坝轴线长度将近6km,为亚洲最长坝。其沿坝轴线方向吹程接近河道吹程,沿坝轴线波浪压力几乎等同于河道方向产生的波浪压力,在90°圆锥裹头部位易造成波能集中,波浪压力大于土坝其它部位的浪压力。本次台风是建库以来的最大风速,库区水位也是建库以来最高,各种不利因素组合,造成裹头高程132.0m以上抛石部位的护坡失稳破坏。护坡破坏后,裹头土坝极易被波浪淘刷,此时坝前波浪受防浪墙阻碍破碎后大股水流顺混凝土插入式接头上游面流下,直接冲击裹头和混凝土面间的防渗体(粘土),使得防渗体破坏更为严重。
发明内容
本发明要解决的技术问题是:针对现有沿海宽河谷地区混凝土坝和土坝插入式接头的上游侧裹头受高风速影响导致护坡破坏的问题,本发明旨在提供一种沿海宽河谷地区混凝土坝和土坝的接头,该接头能大大缓解波能集中,避免护坡破坏,有效地延长了土坝坝体寿命。
为实现上述目的,本发明采用的技术方案是:一种沿海宽河谷地区混凝土坝和土坝的接头,所述混凝土坝和土坝的接头为插入式接头,该插入式接头具有上游侧裹头,其结构特点是,该上游侧裹头的外轮廓线与坝轴线水平投影线的交角β为大于120°的钝角。
作为优选方案,所述β为150°,缓解波能集中效果更好。
藉由上述结构,将混凝土坝和土坝插入式接头的常规上游侧裹头的外轮廓线与坝轴线水平投影线的交角β由90°圆锥改变为大于120°的钝角,类似于椭圆锥,大大缓解了波能集中。
与现有技术相比,本发明的有益效果是:本发明大大缓解了波能集中,避免了土坝上游变坡失稳甚至跨坝的威胁,尤其适用于高风速的宽河谷地区。
以下结合附图和实施例对发明作进一步阐述。
附图说明
图1是本发明一种实施例的俯视图;
图2是图1的剖面图;
图3是图1的立面视图;
在图中:
1-上游裹头各级坡底线; 2-上游裹头各级变坡线;
4-坝轴线水平投影线;  5-上游裹头;6-土坝同混凝土坝间粘土部分;
7-混凝土坝半插入段或全插入段;
β-上游裹头外轮廓线同坝轴线水平投影线的交角。
具体实施方式
一种沿海宽河谷地区混凝土坝和土坝的接头,如图1~3所示,所述混凝土坝和土坝接头的上游裹头为插入式接头的上游侧裹头5,该上游侧裹头的外轮廓线1与坝轴线水平投影线4的β为大于120°的钝角,优选为150°,缓解波能集中效果更好。
本发明应用于海南大广坝水电站达维台风裹头修复时,接头上游土坝填筑土体、粘土和排水砂带同原设计结构,创新的关键是接头上游裹头。从接头土坝起始端利用抛石的不同厚度,变裹头外轮廓线同坝轴线水平投影线4的交角β由原设计90°为150°钝角,消除了波能集中现象。
修复至今,历经多次大台风考验,接头处土坝坝体稳定,未见破坏现象。
上述实施例阐明的内容应当理解为这些实施例仅用于更清楚地说明本发明,而不用于限制本发明的范围,在阅读了本发明之后,本领域技术人员对本发明的各种等价形式的修改均落于本申请所附权利要求所限定的范围。

Claims (2)

1.一种沿海宽河谷地区混凝土坝和土坝的接头,所述混凝土坝和土坝的接头为插入式接头,该插入式接头具有上游侧裹头,其特征在于,该上游侧裹头的外轮廓线(1)与坝轴线水平投影线(4)的交角β为大于120°的钝角。
2.根据权利要求1所述的沿海宽河谷地区混凝土坝和土坝的接头,其特征在于,所述β为150°。
CN201210114161.4A 2012-04-18 2012-04-18 沿海宽河谷地区混凝土坝和土坝的接头 Active CN102619196B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210114161.4A CN102619196B (zh) 2012-04-18 2012-04-18 沿海宽河谷地区混凝土坝和土坝的接头

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210114161.4A CN102619196B (zh) 2012-04-18 2012-04-18 沿海宽河谷地区混凝土坝和土坝的接头

Publications (2)

Publication Number Publication Date
CN102619196A CN102619196A (zh) 2012-08-01
CN102619196B true CN102619196B (zh) 2015-05-06

Family

ID=46559380

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210114161.4A Active CN102619196B (zh) 2012-04-18 2012-04-18 沿海宽河谷地区混凝土坝和土坝的接头

Country Status (1)

Country Link
CN (1) CN102619196B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102966079A (zh) * 2012-11-09 2013-03-13 广东省水利水电科学研究院 阶梯型纵向围堰上游裹头
CN105040724B (zh) * 2015-07-02 2017-03-01 中国电建集团华东勘测设计研究院有限公司 一种混凝土坝接头不良基础的处理方法
CN111256754B (zh) * 2020-01-19 2021-08-10 河海大学 一种混凝土坝长期运行安全预警方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1493719A1 (ru) * 1987-04-09 1989-07-15 Всесоюзный научно-исследовательский институт гидротехники им.Б.Е.Веденеева Способ возведени грунтовой плотины с асфальтобетонной противофильтрационной диафрагмой
CN200978430Y (zh) * 2006-12-07 2007-11-21 中国水电顾问集团华东勘测设计研究院 混凝土坝接头结构
RU2374387C1 (ru) * 2008-07-21 2009-11-27 Василий Петрович Ягин Гидроузел на многолетнемерзлых грунтах
CN101718086A (zh) * 2009-11-05 2010-06-02 河海大学 一种混凝土-堆石混合坝及其施工方法
CN101974894A (zh) * 2010-08-23 2011-02-16 清华大学 一种组合坝
CN202543864U (zh) * 2012-04-18 2012-11-21 中国水电顾问集团中南勘测设计研究院 沿海宽河谷地区混凝土坝和土坝的接头

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1493719A1 (ru) * 1987-04-09 1989-07-15 Всесоюзный научно-исследовательский институт гидротехники им.Б.Е.Веденеева Способ возведени грунтовой плотины с асфальтобетонной противофильтрационной диафрагмой
CN200978430Y (zh) * 2006-12-07 2007-11-21 中国水电顾问集团华东勘测设计研究院 混凝土坝接头结构
RU2374387C1 (ru) * 2008-07-21 2009-11-27 Василий Петрович Ягин Гидроузел на многолетнемерзлых грунтах
CN101718086A (zh) * 2009-11-05 2010-06-02 河海大学 一种混凝土-堆石混合坝及其施工方法
CN101974894A (zh) * 2010-08-23 2011-02-16 清华大学 一种组合坝
CN202543864U (zh) * 2012-04-18 2012-11-21 中国水电顾问集团中南勘测设计研究院 沿海宽河谷地区混凝土坝和土坝的接头

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
南水北调中线与安阳河交叉工程裹头体型优化;王勤香等;《长江科学院院报》;20090831(第8期);第32-35页 *
土坝与混凝土泄水建筑物连接的渗流稳定;林昭;《水利水电技术》;19840531(第05期);第6-8、13页 *
大广坝水利水电工程的布置与设计优化;王兴隆;《水力发电》;19940212(第2期);第6页第1段-第8页第2章第2.2.4节第1段及附图 *
王快水库溢洪道水力学试验研究;戴梅;《河北水利水电技术》;20040630(第3期);第42页第1章第1-3段、第43页第4章第4.3节第1段-第44页最后1段及图3-6 *
等角螺线型土坝裹头设计;刘锐等;《黑龙江水利科技》;20100430(第2期);第67页 *

Also Published As

Publication number Publication date
CN102619196A (zh) 2012-08-01

Similar Documents

Publication Publication Date Title
CN103498452B (zh) 高陡狭窄河谷泄水建筑物的窄缝挑坎结构
CN204282308U (zh) 一种适应深厚覆盖层的格宾石笼复合材料坝
CN103510493A (zh) 过水低坝洞库式水电站
CN102619196B (zh) 沿海宽河谷地区混凝土坝和土坝的接头
CN203429606U (zh) 一种临时围堰改建而成的拦沙坎
CN204282292U (zh) 一种降低波浪爬高的防浪墙结构
CN207244572U (zh) 堤坝防渗装置
CN204728261U (zh) 用于沟水处理及泥石流防护的拦挡组合结构
CN203514275U (zh) 高陡狭窄河谷泄水建筑物的窄缝挑坎结构
CN202543864U (zh) 沿海宽河谷地区混凝土坝和土坝的接头
CN206015619U (zh) 一种降低面板应力应变水平的面板堆石坝
CN101768941B (zh) 河道设有上游围堰的导流明渠截流进占戗堤
CN207484405U (zh) 一种混凝土防渗墙
CN206752427U (zh) 一种水电站地面厂房尾水出口结构及其水电站
CN210395268U (zh) 一种用于高流速无压隧洞的泄洪消能结构
CN104612101B (zh) 一种透水管沙滩养滩方法及专用透水管
CN114293582A (zh) 一种多地震区域混凝土重力坝的减震结构
CN203878534U (zh) 一种用于围海造地的促淤堤坝
CN209603094U (zh) 一种低速流体消能流道构造
CN205975474U (zh) 一种在河弯上设置高堆石坝的枢纽布置结构
CN207211212U (zh) 水电站大坝坝基排水孔改造结构
CN101798804A (zh) 河道上游围堰拆除的导流明渠截流进占戗堤
CN201627176U (zh) 土石过水围堰堰脚防冲结构
CN207419407U (zh) 一种消能预制件结构
CN207143879U (zh) 缺口分流式二道坝结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 410014, 16 camphor Road, Yuhua District, Hunan, Changsha

Applicant after: POWERCHINA ZHONGNAN ENGINEERING Corp.,Ltd.

Address before: 410014, 16 camphor Road, Yuhua District, Hunan, Changsha

Applicant before: HYDROCHINA ZHONGNAN ENGINEERING Corp.

Address after: 410014, 16 camphor Road, Yuhua District, Hunan, Changsha

Applicant after: HYDROCHINA ZHONGNAN ENGINEERING Corp.

Address before: 410014, 9 camphor Road, Yuhua District, Hunan, Changsha

Applicant before: Mid-South Hydroelectric Investigation & Design Institute of China Hydropower Engineering Consulting Group

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: ZHONGNAN PROSPECTING DESIGN INST. CHINA HYDRAUELECTRIC CONSULTANT GROUP TO: HYDROCHINA ZHONGNAN ENGINEERING CORPORATION

Free format text: CORRECT: APPLICANT; FROM: HYDROCHINA ZHONGNAN ENGINEERING CORPORATION TO: CHINA POWER GROUP ZHONGNAN INVESTIGATION DESIGN + RESEARCH INSTITUTE CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant