CN102591296A - Self-adaptive coordination control system for cement clinker production and cogeneration - Google Patents

Self-adaptive coordination control system for cement clinker production and cogeneration Download PDF

Info

Publication number
CN102591296A
CN102591296A CN2012100495787A CN201210049578A CN102591296A CN 102591296 A CN102591296 A CN 102591296A CN 2012100495787 A CN2012100495787 A CN 2012100495787A CN 201210049578 A CN201210049578 A CN 201210049578A CN 102591296 A CN102591296 A CN 102591296A
Authority
CN
China
Prior art keywords
cogeneration
self
clinker
control system
coordination control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100495787A
Other languages
Chinese (zh)
Inventor
叶金辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LOUKABEN NEW ENERGY SCIENCE AND TECHNOLOGY DEVELOPMENT(SHANGHAI)CO LTD
Original Assignee
LOUKABEN NEW ENERGY SCIENCE AND TECHNOLOGY DEVELOPMENT(SHANGHAI)CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LOUKABEN NEW ENERGY SCIENCE AND TECHNOLOGY DEVELOPMENT(SHANGHAI)CO LTD filed Critical LOUKABEN NEW ENERGY SCIENCE AND TECHNOLOGY DEVELOPMENT(SHANGHAI)CO LTD
Priority to CN2012100495787A priority Critical patent/CN102591296A/en
Publication of CN102591296A publication Critical patent/CN102591296A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Testing And Monitoring For Control Systems (AREA)

Abstract

The invention relates to a self-adaptive coordination control system for cement clinker production and cogeneration, which comprises a clinker production line DCS (Distributed Control System) system, a cogeneration DCS system, a blind spot indicating system, and a clinker process quality analysis system. All the systems access a same industrial Ethernet, and all the system can carry out effective communication of partial data points by the same industrial Ethernet. The operation of process staffs are guided in a forecasting way by the blind spot indicating system and the clinker process quality analysis system, and meanwhile, the partial control is automatically coordinated. On the premise of meeting clinker craft and not enhancing coal consumption, the self-adaptive coordination control system adjusts cogeneration parameters, and realizes the maximization of generated energy. When the abnormal condition of cogeneration equipment appears, the self-adaptive coordination control system ensures the output maximization on the premise that dried raw materials are qualified is maximum.

Description

Cement clinker is produced and cogeneration self-adaptation coordinated control system
Technical field
The invention belongs to automation control area, is a kind of self-adaptation coordinated control system that relates to cement industry clinker production line and cogeneration.
Background technology
At present; The cogeneration of cement line is important measures of cement production enterprise energy-conserving and environment-protective; Be the technology that the low temperature exhaust heat (account for cement clinker and burn till total heat consumption more than 30%) that utilizes primary heater and cooler carries out cogeneration, can reduce the grog power consumption in theory more than 60%.And it is as an auxiliary workshop section of cement clinker line, can not be as traditional power station independent operating, can bring influence to original technological process, production status, quality condition inevitably; On the other hand, clinker cement production abnormal conditions, the form of raw material mill, coal mill, position of the sum of series conditioning Tower of primary heater or the like also can have influence on generated energy.Because cogeneration and grog line belong to two different industries; And in design, construction, also be independently; Be that clinker cement territory DCS and cogeneration territory DCS are two independently systems, present two domain operators understand the other side's production data situation through oral or phone, command separately through operator's self experience and produce; Such mode of production not only labour intensity is big; And be difficult in the maximization of pursuing generated energy under the situation that does not influence clinker quality, output, in case waste heat power generation equipment occurs unusually, also be difficult to the quality and the output of control raw material stoving.Pursue the maximization of generated energy in addition simply, bring negative effect for probably whole factory benefit.
Summary of the invention
In order to adapt to interacting between cogeneration and the grog production; Reduce operator's labour intensity to a certain extent; Improve generated energy not influencing under clinker quality, the output, the present invention provides the local auto-adaptive coordinated control system of a kind of cement industry clinker production line and cogeneration, and grog line DCS and cogeneration DCS are carried out partial data communication interlocking; Automatically regulate technological parameter through related data analysis and blind spot indication, accomplish the end in view.
Technical scheme
The technical solution adopted for the present invention to solve the technical problems is: total system comprises clinker production line DCS system, cogeneration DCS system, blind spot indication mechanism, grog processing quality analytic system, and each system inserts same EPA.Through same EPA, each system can carry out partial data point effective communication, and multiple domain is coordinated control; The blind spot infosystem through transferring to active station after the process data analytic system analyzing and processing, is used for the ruuning situation and the parameter of the local blind spot equipment of collection site to instruct and produces; The process data analytic system writes down real-time technological parameter; Division technique section and equipment group generate grog Wiring technology curve and generating curve, are the basis through the operational factor model of setting up a perfect condition, constantly upgrade the technology controlling and process rule automatically according to historical data; Through fine setting and forecast analysis; Carry out early warning in advance, and change the Passive Control parameter of regulating local control, on the basis of monitoring grog lineman condition, do not change the coal amount of feeding according to the active adjustment parameter; Automatically regulate the passive adjusting parameter in cogeneration territory, make cogeneration not improve the basic generated energy maximization of grog cost.
Beneficial effect
Control more comprehensively, more coherent, improved whole robotization intensity,, do not increase under the situation of production cost, make the generated energy maximization, alleviated labor intensity of operating personnel to a certain extent, make factory's overall efficiency maximization not influencing clinker quality, output.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the utility model is further specified.
Fig. 1 cement clinker is produced with cogeneration self-adaptation coordinated control system and is formed structural drawing;
Fig. 2 data acquisition and conveying flow.
Embodiment
The utility model is made up of clinker production line DCS system, cogeneration DCS system, blind spot indication mechanism, grog processing quality analytic system, and each system inserts same EPA.Through same EPA, each system can carry out partial data point effective communication, and multiple domain is coordinated control.Clinker cement " territory " by raw material control station, calcining kiln tail control station, burn till the kiln hood control station, the cement control station is formed; Cogeneration " territory " is made up of boiler control station, turbodynamo control station, utility appliance control station.
Field control station PS (Process Control Station) mainly is made up of the PLC of uniform brand and corresponding I/O module, Ethernet interface, EBI, coupling mechanism etc.; Through hardwire and bus mode monitoring field apparatus and intelligence instrument, data are passed to data transfer to active station and process data analytic system through Ethernet.
The engineer station is the basis with process section and OS site configuration; Conveying, grinding, storage, calcining and other processes according to actual materials flow are refined as a plurality of equipment start-stop groups; The warning of every equipment of configuration, fault, self is chain and equipment room is chain; During according to the characterizing definition group running status of field apparatus each equipment time-delay along open, along the chain condition and the time-delay that stop, be downloaded to field controller.When parameter reaches preset value, output alarm or fault-signal, the chain relevant device of delaying time jump stop, operation such as deceleration, valve closing.In the light of actual conditions, it is chain that the linkage relationship of field apparatus is divided into the startup that is used for opening device protection usefulness, the safety interlocking that self-protection is used in the equipment operation, in the equipment running process mutually between the operation of protection usefulness chain.
Operating personnel go up at active station OS (Operate Station) whole process flow are kept watch on, and in this process, divide territory, branchs authority to control the start-stop of field apparatus and the modification of technological parameter according to on-the-spot actual demand, and instruction issuing is handled to PS;
At general cement production enterprise; Some simple signals that oil station, Hydraulic Station, homogenization system, stacker-reclaimer, local control station, steam turbine DEH, the relevant control of ETS just simply will influence equipment operation offer host computer; The ruuning situation of these equipment is difficult to detect and control through host computer; And the operation of these equipment is directly chain to a lot of main process equipments, causes the monitoring blind spot.The blind spot indication mechanism is through the communication of PROFIBUS-DP bus mode; Through engineer station's configuration; Directly keep watch on its internal operation situation and correlation parameter; But do not participate in control directly, it directly transfers to the process data analytic system with relevant information, through the process data analytic system blind spot facility information is carried out pre-service after; Equipment failure, alerting signal, pre-alarm signal and reason thereof are transferred to the associative operation station with the mode of message queue, be beneficial to find out more rapidly the equipment breakdown reason and in time handle.
The production data analytic system comprises information acquisition unit, data storage cell, data analysis unit, and its execution in step is following:
Information acquisition unit through Ethernet from the below PS website gather grog line and cogeneration production technology related data, behind the production data that the blind spot indication mechanism is transmitted, divide workshop section, the subset group is stored to data storage cell;
Data analysis unit is at first produced real-time history curve with the data of data storage cell automatically, feeds back to active station and is used for inquiry; Simultaneously; Relevant device and parameter value during production data analytic system record typical fault state, according to the periodicity that detects cycle data variable quantity, equipment failure generation, the parameter information that expection is reached fault, alarm set point feeds back in active station; Be used for the operator is pointed out; So that carry out the technological parameter adjustment in advance, avoid causing accidents such as equipment failure, shutdown, putty, thereby have influence on the production capacity of whole factory;
Grog process monitoring unit has carried out initialization design according to cement production enterprise grog line and power generation process with waste heat system; Processing parameter requirement and technological parameter relevance to set customized parameter, perfect condition are the basis; Each parameter according to whole technology when stable changes to be analyzed; Infer repeated related parameter, calculate corresponding technological parameters cycle variation law and storage and renewal automatically.As customized parameter again refinement be divided into active adjustment parameter and passive adjusting parameter, active adjustment parameter such as kiln feeding, grinding machine feeding capacity; Be parameter concerning output, manual adjustments only, and passive adjusting parameter is as feeding coal amount, valve; The water pump feedwater; Motor speeds etc. all are for after realizing changing the active adjustment parameter, keep the technological parameter of perfect condition and serve.Production of grog line and cogeneration all are to be based upon on the basis of the heat energy distribution of coal combustion generation; When ature of coal changes; All process sections all can be affected; So at first system can change according to the parameter of production technology and comes on the basis of the desirable technological parameter of keeping each process section of grog line that to feed the coal amount be main to regulate, it is auxilliary regulating local adjustable parameter, seeks an equilibrium point automatically; And when certain local initiatively parameter (like grinding machine, kiln feeding capacity) when manually changing; Guaranteeing under the constant situation of other local process environments; System can come forecast analysis and calculate other process parameter value that reach the required change of desirable technological parameter according to the rule that historical data analysis obtains; Through active station with instruction issuing to control station, recomputate according to actual change curve and prediction, meet the requirements of the technological parameter environment so repeatedly;
Behind grog line active adjustment parameter change; The cogeneration regulon can be through cogeneration field parameters such as automatic fine tuning waste gas valve, turbine speed, steam water-levels; Changes in process parameters that real-time monitoring grog burns till with guarantee process environments that grog is produced scope in, make the generated energy maximization.

Claims (1)

1. cement clinker production and cogeneration self-adaptation coordinated control system comprise clinker production line DCS system, cogeneration DCS system, blind spot indication mechanism, grog processing quality analytic system, it is characterized in that each system inserts same EPA.
CN2012100495787A 2012-02-29 2012-02-29 Self-adaptive coordination control system for cement clinker production and cogeneration Pending CN102591296A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100495787A CN102591296A (en) 2012-02-29 2012-02-29 Self-adaptive coordination control system for cement clinker production and cogeneration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100495787A CN102591296A (en) 2012-02-29 2012-02-29 Self-adaptive coordination control system for cement clinker production and cogeneration

Publications (1)

Publication Number Publication Date
CN102591296A true CN102591296A (en) 2012-07-18

Family

ID=46480123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100495787A Pending CN102591296A (en) 2012-02-29 2012-02-29 Self-adaptive coordination control system for cement clinker production and cogeneration

Country Status (1)

Country Link
CN (1) CN102591296A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104199414A (en) * 2014-09-02 2014-12-10 叶金辉 Integrated self-adaptive coordinated control system for magnetic suspension ORC waste heat power generation
CN104536404A (en) * 2014-12-17 2015-04-22 马钢(集团)控股有限公司 Automatic load regulation system and method for dry quenching waste heat power generation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104199414A (en) * 2014-09-02 2014-12-10 叶金辉 Integrated self-adaptive coordinated control system for magnetic suspension ORC waste heat power generation
CN104536404A (en) * 2014-12-17 2015-04-22 马钢(集团)控股有限公司 Automatic load regulation system and method for dry quenching waste heat power generation
CN104536404B (en) * 2014-12-17 2017-03-08 马钢(集团)控股有限公司 Dry coke quenching cogeneration load automatic regulating system and method

Similar Documents

Publication Publication Date Title
CN202453708U (en) Brick tile entire plant DCS central distributed control system
CN103322547B (en) Boiler control and combustion optimization method
CN201040260Y (en) Coal mill self-adaptive control system
CN102721288B (en) High-efficiency intelligentized heating furnace control method
RU131083U1 (en) MAIN FAN INSTALLATION AUTOMATION SYSTEM
CN202315985U (en) Automatic control system of hydraulic cone crusher
CN104766138A (en) Thermal power plant equipment property evaluation and early warning method and system based on industrial internet
CN202018027U (en) Automatic control system for full-automatic coal burning boiler
CN201926899U (en) Self-adaption coordinated control system for cement clinker production and waste heat power generation
CN102591296A (en) Self-adaptive coordination control system for cement clinker production and cogeneration
CN103411234A (en) Quantitative air distribution economic combustion energy saving control system
CN102541034A (en) Biogas power generation control system
CN202187896U (en) Energy-saving device of synchronous control type cooling circulating water pump
JP2016537729A (en) Method, system, and computer program product for analyzing generation processes and / or process engineering processes and / or process steps in a plant
CN104632416A (en) Control method for rotating speed of gas turbine
CN109882883B (en) Method and device for optimizing boiler coal burning efficiency based on artificial intelligence
CN203768420U (en) Control system for water-mist-air quantitative cooling of vertical quenching machine tool
CN102023595A (en) Automatic control and energy-saving system of boiler
CN201909989U (en) Automatically-controlled energy-saving system of boiler
CN202267226U (en) Automatic control system of coal burning boiler
CN202993251U (en) Automatic control system for air distribution optimization of boiler
CN104949092A (en) Multi-boiler system capable of automatic control and control method thereof
CN202415640U (en) DCS (Distributed Control System) for vertical continuous quenching and tempering thermal treatment furnace of anchor chain
CN203658829U (en) Mining machinery intelligent control device
CN202494906U (en) Biogas power generation control system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120718