CN102570352A CN2011103933651A CN201110393365A CN102570352A CN 102570352 A CN102570352 A CN 102570352A CN 2011103933651 A CN2011103933651 A CN 2011103933651A CN 201110393365 A CN201110393365 A CN 201110393365A CN 102570352 A CN102570352 A CN 102570352A
Authority
CN
China
Prior art keywords
power cable
base plate
support
column
bedplate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103933651A
Other languages
Chinese (zh)
Inventor
刘岭
袁宪彬
侯文�
宋畅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taian Power Supply Co of State Grid Shandong Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
Taian Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taian Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical Taian Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN2011103933651A priority Critical patent/CN102570352A/en
Publication of CN102570352A publication Critical patent/CN102570352A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Installation Of Indoor Wiring (AREA)

Abstract

The invention discloses a power cable laying bracket, which comprises two vertical columns and a first base plate, wherein the first base plate is connected with a second base plate; the two vertical columns are vertically connected to the first base plate; a supporting rod is arranged between the two vertical columns; two ends of the supporting rod are connected with the vertical columns respectively; the outer side of each of the vertical columns is connected with one end of each large inclined support; the other end of each large inclined support is connected with the first base plate; one end of each small inclined support is connected with the second base plate; and the other end of each inclined support is connected with each vertical column. The power cable laying bracket has a firm structure, can easily turn a cable disk, and is adjusted flexibly, convenient to transport and low in cost.

Description

电力线缆展放支架Power cable deployment bracket

技术领域 technical field

本发明涉及一种用于线缆展放的支架,尤其涉及一种电力线缆展放支架。 The invention relates to a bracket for deploying cables, in particular to a bracket for deploying power cables.

背景技术 Background technique

伴随着电缆线路的广泛应用,电缆线路施工量日益增多。而粗重的电缆牵引展放的过程中往往直接把线盘置于地面,或者用简单的支架支起线盘,但这种支架在线盘转动过程中极不稳定,给工作带来了极大的不便,降低效率。为解决这一普遍存在的难题,我们研制出“电力线缆展放支架”,结合工作实际,注重细节,把关质量,使得该项目真正解决了电缆展放过程中的各种难题。 With the wide application of cable lines, the amount of cable line construction is increasing day by day. In the process of traction and deployment of thick and heavy cables, the wire reel is often placed on the ground directly, or the wire reel is supported by a simple bracket, but this bracket is extremely unstable during the rotation of the wire reel, which brings great difficulties to the work. Inconvenient and reduce efficiency. In order to solve this ubiquitous problem, we developed the "power cable display bracket", combined with the actual work, paying attention to details, and checking the quality, so that this project truly solved various problems in the process of cable display.

发明内容 Contents of the invention

本发明的目的是提供一种结构稳固、能够轻松转动线盘、灵活调节、运输方便、造价低廉的电力线缆展放支架。 The purpose of the present invention is to provide a stable structure, easy to rotate the reel, flexible adjustment, convenient transportation, and low cost power cable display bracket.

为实现上述目的,本发明采用的技术方案为: To achieve the above object, the technical solution adopted in the present invention is:

一种电力线缆展放支架,包括立柱、第一底座板,其特征是:第一底座板与第二底座板相连接,两个立柱垂直连接在第一底座板上,两个立柱之间设置支撑杆,支撑杆的两端分别连接立柱。 A power cable deployment bracket, including a column and a first base plate, characterized in that: the first base plate is connected to the second base plate, the two columns are vertically connected to the first base plate, and the space between the two columns is A support rod is provided, and the two ends of the support rod are respectively connected to the column.

根据所述的电力线缆展放支架,其特征在于:所述立柱的外侧连接大斜撑的一端,大斜撑的另一端连接第一底座板;小斜撑的一端连接第二底座板,小斜撑的另一端连接立柱。 According to the power cable deployment support, it is characterized in that: the outer side of the column is connected to one end of the large diagonal brace, the other end of the large diagonal brace is connected to the first base plate; one end of the small diagonal brace is connected to the second base plate, The other end of the small diagonal brace is connected to the column.

    根据所述的电力线缆展放支架,其特征在于:所述立柱上设有多个调节孔,支撑杆上设有相对应的孔;支撑杆的两端通过销连接立柱。 According to the power cable deployment bracket, it is characterized in that: the column is provided with a plurality of adjustment holes, and the support rod is provided with corresponding holes; the two ends of the support rod are connected to the column through pins.

根据所述的电力线缆展放支架,其特征在于:所述支撑杆上设有两组相对应的轴承支架,所述的轴承支架上安装轴承。 According to the power cable deployment support, it is characterized in that: the support rod is provided with two sets of corresponding bearing brackets, and bearings are installed on the bearing brackets.

根据所述的电力线缆展放支架,其特征在于:所述第一底座板、第二底座板上设有固定孔。 According to the power cable deploying support, it is characterized in that: the first base plate and the second base plate are provided with fixing holes.

    根据所述的电力线缆展放支架,其特征在于:立柱为角钢双面焊接;小斜撑、大斜撑、第一底座板、第二底座板、支撑杆都为槽型钢;中空轴安装在所述轴承上,中空轴为中空的管状圆钢。 According to the power cable deployment bracket, it is characterized in that: the upright column is welded on both sides of the angle steel; the small diagonal brace, the large diagonal brace, the first base plate, the second base plate, and the support rod are all channel steel; On the bearing, the hollow shaft is a hollow tubular round steel.

本发明的优点效果在于:我们研制的这种电力线缆展放支架造价低廉且结实耐用,造价可比市场上销售的支架便宜一倍以上的价格。根据线盘的大小可灵活调节,最大可支撑直径为两米半、重达8吨的电缆线盘,达到“一架多用”的效果。 The advantages and effects of the present invention are: the power cable display bracket developed by us is cheap and durable, and the cost can be more than twice as cheap as the brackets sold in the market. It can be flexibly adjusted according to the size of the reel, and can support a cable reel with a maximum diameter of two and a half meters and a weight of 8 tons, achieving the effect of "one rack with multiple uses".

该支架既可应用于现场施工也可应用于仓库管理中电缆的分区摆放,在线缆使用量不大的工作情况下,方便直接到仓库快速截取。因此我们研制的电力线缆展放支架可推广使用于各种电缆施工现场,应用前景十分可观。 The bracket can be applied not only to on-site construction but also to the partition placement of cables in warehouse management. It is convenient to go directly to the warehouse for quick interception when the cable usage is not large. Therefore, the power cable display bracket developed by us can be popularized and used in various cable construction sites, and the application prospect is very promising.

附图说明 Description of drawings

图1为本发明的主视图。 Fig. 1 is the front view of the present invention.

图2为图1的左视图。 Fig. 2 is a left side view of Fig. 1 .

图3为图1中8的主视图。 Fig. 3 is a front view of 8 in Fig. 1 .

图4为图3的俯视图。 FIG. 4 is a top view of FIG. 3 .

附图中:1、立柱; 2、小斜撑; 3、大斜撑;4、第一底座板;5、第二底座板; 6、固定孔;7、调节孔;8、支撑杆;9、销;10、轴承支架;11、轴承;12、线盘;13、中空轴。 In the attached drawings: 1. Upright column; 2. Small diagonal brace; 3. Large diagonal brace; 4. First base plate; 5. Second base plate; 6. Fixing hole; 7. Adjusting hole; 8. Support rod; 9 , pin; 10, bearing bracket; 11, bearing; 12, reel; 13, hollow shaft.

具体实施方式 Detailed ways

下面结合附图和具体实施例对本发明作进一步说明: The present invention will be further described below in conjunction with accompanying drawing and specific embodiment:

本发明的结构如图1、3所示,一种电力线缆展放支架,包括立柱1、第一底座板4,其特征是:第一底座板4与第二底座板5相连接,两个立柱1垂直连接在第一底座板4上,两个立柱1之间设置支撑杆8,支撑杆8的两端分别连接立柱1。根据所述的电力线缆展放支架,其特征在于:所述立柱1的外侧连接大斜撑3的一端,大斜撑3的另一端连接第一底座板4;小斜撑2的一端连接第二底座板5,小斜撑2的另一端连接立柱1。根据所述的电力线缆展放支架,其特征在于:所述立柱1上设有多个调节孔7,支撑杆8上设有相对应的孔;支撑杆8的两端通过销9连接立柱1。根据所述的电力线缆展放支架,其特征在于:所述支撑杆8上设有两组相对应的轴承支架10,所述的轴承支架10上安装轴承11。根据所述的电力线缆展放支架,其特征在于:所述第一底座板4、第二底座板5上设有固定孔6。根据所述的电力线缆展放支架,其特征在于:立柱1为角钢双面焊接;小斜撑2、大斜撑3、第一底座板4、第二底座板5、支撑杆8都为槽型钢;中空轴13安装在所述轴承11上,中空轴13为中空的管状圆钢。 The structure of the present invention is shown in Figures 1 and 3. A power cable deployment bracket includes a column 1 and a first base plate 4. It is characterized in that: the first base plate 4 is connected to the second base plate 5, and the two A column 1 is vertically connected to the first base plate 4, a support rod 8 is arranged between the two columns 1, and two ends of the support rod 8 are respectively connected to the column 1. According to the power cable deployment support, it is characterized in that: the outer side of the column 1 is connected to one end of the large diagonal brace 3, and the other end of the large diagonal brace 3 is connected to the first base plate 4; one end of the small diagonal brace 2 is connected to The other end of the second base plate 5 and the small diagonal brace 2 is connected to the column 1 . According to the power cable deployment support, it is characterized in that: the column 1 is provided with a plurality of adjustment holes 7, and the support rod 8 is provided with corresponding holes; the two ends of the support rod 8 are connected to the column through pins 9 1. According to the power cable deployment support, it is characterized in that two sets of corresponding bearing brackets 10 are provided on the support rod 8, and bearings 11 are installed on the bearing brackets 10. According to the power cable deploying support, it is characterized in that: the first base plate 4 and the second base plate 5 are provided with fixing holes 6 . According to the power cable deployment support, it is characterized in that: the upright column 1 is double-sided welding of angle steel; the small diagonal brace 2, the large diagonal brace 3, the first base plate 4, the second base plate 5, and the support rod 8 are Channel steel; the hollow shaft 13 is installed on the bearing 11, and the hollow shaft 13 is a hollow tubular round steel.

支架结构说明 Description of the bracket structure

以角钢制作立柱,下端用槽钢从正面及侧面加固底座,均形成三角形稳定结构,以圆钢制作中空轴13,两侧各用两对轴承11支撑中空轴13,承托轴承11的钢材通过支架打孔、螺栓螺帽加固。中空轴13高低可调,通过立柱1上调节孔7的高度来灵活调节中空轴13的高度。 The column is made of angle steel, and the lower end is reinforced with channel steel from the front and side to form a triangular stable structure. The hollow shaft 13 is made of round steel, and two pairs of bearings 11 are used to support the hollow shaft 13 on both sides. The steel supporting the bearing 11 passes through The bracket is punched, and the bolts and nuts are reinforced. The height of the hollow shaft 13 is adjustable, and the height of the hollow shaft 13 can be flexibly adjusted through the height of the adjustment hole 7 on the column 1 .

一、     注重细节,不断完善 1. Pay attention to details and keep improving

1、          钢材部件间实现双面焊接,使支架整体更加牢固。 1. Double-sided welding is realized between steel parts, which makes the whole bracket stronger.

2、          通过实践发现实心圆钢做转轴,经过长时间的重压,造成不易恢复的弯曲变形,直接影响电缆线盘的转动展放。当把圆钢制作成空心后,实践证明,可承重八吨左右的电缆重量,并且不发生任何变形,足够满足目前电缆的重量。以空心圆钢作转轴既节省了材料又大大减轻了设备的重量。 2. Through practice, it is found that the solid round steel is used as the rotating shaft. After a long period of heavy pressure, it will cause bending deformation that is not easy to recover, which directly affects the rotation and deployment of the cable reel. When the round steel is made hollow, practice has proved that it can bear about eight tons of cable weight without any deformation, which is enough to meet the weight of the current cable. Using hollow round steel as the rotating shaft not only saves materials but also greatly reduces the weight of the equipment.

3、          中空轴13的每一端各用两对轴承11,从侧面看,三者正好组成三角形,极具稳定性;承托轴承11的钢材用螺纹销子及螺帽通过打好的孔固定,十分结实。轴承11以黄油为润滑油,使线盘12的转动十分省力,一个人即可轻松拉动线缆。 3. Two pairs of bearings 11 are used at each end of the hollow shaft 13. Viewed from the side, the three just form a triangle, which is very stable; Very strong. Bearing 11 uses butter as lubricating oil, so that the rotation of wire reel 12 is very labor-saving, and one person can easily pull the cable.

4、          支架的第一底座板4、第二底座板5上设有固定孔6,现场使用时可方便将支架打桩固定,更有利于电力线缆的拉动。 4. The first base plate 4 and the second base plate 5 of the bracket are provided with fixing holes 6, which can facilitate the piling and fixing of the bracket during on-site use, and are more conducive to the pulling of power cables.

5、          整个支架涂上银白色油漆,不仅美观大方,而且有效防止长期使用造成的支架生锈,使支架更加耐用。 5. The whole bracket is painted with silver white paint, which is not only beautiful and elegant, but also effectively prevents the bracket from rusting caused by long-term use, making the bracket more durable.

三、经济效益及应用前景 3. Economic benefits and application prospects

    面对目前电缆施工依赖于购买支架,且这种支架往往不能灵活调节应用于多种线盘,运输不便,造成成本浪费。而我们研制的这种电力线缆展放支架造价低廉且结实耐用,造价可比市场上销售的支架便宜一倍以上的价格。根据线盘的大小可灵活调节,最大可支撑直径为两米半、重达8吨的电缆线盘,达到“一架多用”的效果。 In the face of the current cable construction depends on the purchase of brackets, and this bracket is often not flexible to adjust for a variety of wire reels, transportation is inconvenient, resulting in waste of cost. The power cable display bracket we developed is cheap and durable, and the cost can be more than twice as cheap as the brackets sold on the market. It can be flexibly adjusted according to the size of the reel, and can support a cable reel with a maximum diameter of two and a half meters and a weight of 8 tons, achieving the effect of "one rack with multiple uses".

该支架既可应用于现场施工也可应用于仓库管理中电缆的分区摆放,在线缆使用量不大的工作情况下,方便直接到仓库快速截取。因此我们研制的电力线缆展放支架可推广使用于各种电缆施工现场,应用前景十分可观。 The bracket can be applied not only to on-site construction but also to the partition placement of cables in warehouse management. It is convenient to go directly to the warehouse for quick interception when the cable usage is not large. Therefore, the power cable display bracket developed by us can be popularized and used in various cable construction sites, and the application prospect is very promising.

上面所述的实施例仅仅是对本发明的优选实施方式进行描述,并非对本发明的构思和保护范围进行限定,在不脱离本发明设计构思的前提下,本领域中普通工程技术人员对本发明的技术方案作出的各种变型和改进,均应落入本发明的保护范围。  The above-described embodiments are only described to the preferred implementation of the present invention, and are not intended to limit the concept and protection scope of the present invention. Various modifications and improvements made in the scheme should fall within the protection scope of the present invention. the

Claims (6)

1. support is put in an electric power cable exhibition; Comprise column (1), first bedplate (4); It is characterized in that: first bedplate (4) is connected with second bedplate (5); Two columns (1) are vertically connected on first bedplate (4), and support bar (8) is set between two columns (1), and the two ends of support bar (8) connect column (1) respectively.
2. support is put in electric power cable exhibition according to claim 1, and it is characterized in that: the outside of said column (1) connects an end of big diagonal brace (3), and the other end of big diagonal brace (3) connects first bedplate (4); One end of little diagonal brace (2) connects second bedplate (5), and the other end of little diagonal brace (2) connects column (1).
3. support is put in electric power cable exhibition according to claim 1, and it is characterized in that: said column (1) is provided with a plurality of adjustment holes (7), and support bar (8) is provided with corresponding hole; The two ends of support bar (8) connect column (1) through pin (9).
4. support is put in electric power cable exhibition according to claim 1, and it is characterized in that: said support bar (8) is provided with two groups of corresponding supports of bearing (10), and the described support of bearing (10) is gone up bearing (11) is installed.
5. support is put in electric power cable exhibition according to claim 1, and it is characterized in that: said first bedplate (4), second bedplate (5) are provided with fixing hole (6).
6. support is put in electric power cable exhibition according to claim 1, it is characterized in that: column (1) is the two-sided welding of angle steel; Little diagonal brace (2), big diagonal brace (3), first bedplate (4), second bedplate (5), support bar (8) all are U-steel; Quill shaft (13) is installed on the said bearing (11), and quill shaft (13) is the tubulose round steel of hollow.
CN2011103933651A 2011-12-02 2011-12-02 Power cable laying bracket Pending CN102570352A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103933651A CN102570352A (en) 2011-12-02 2011-12-02 Power cable laying bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103933651A CN102570352A (en) 2011-12-02 2011-12-02 Power cable laying bracket

Publications (1)

Publication Number Publication Date
CN102570352A true CN102570352A (en) 2012-07-11

Family

ID=46415097

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103933651A Pending CN102570352A (en) 2011-12-02 2011-12-02 Power cable laying bracket

Country Status (1)

Country Link
CN (1) CN102570352A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103326274A (en) * 2013-06-29 2013-09-25 国家电网公司 Insulating holding pole erecting tool
CN104714117A (en) * 2013-12-13 2015-06-17 珠海格力电器股份有限公司 Radiation emission test tool
CN105790199A (en) * 2014-06-28 2016-07-20 国家电网公司 Pulley mechanism of power cable unwinding for power construction

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201282300Y (en) * 2008-09-28 2009-07-29 中煤第九十二工程处 Hydraulic type cable unfolding stent
CN201402957Y (en) * 2009-03-02 2010-02-10 于韶红 Automatic aligning type double-vertical-frame payoff rack
CN201466641U (en) * 2009-05-07 2010-05-12 中冶天工上海十三冶建设有限公司 Cable pay-off rack for cable coil
CN202333630U (en) * 2011-12-02 2012-07-11 山东电力集团公司枣庄供电公司 Electric power cable pay-off support

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201282300Y (en) * 2008-09-28 2009-07-29 中煤第九十二工程处 Hydraulic type cable unfolding stent
CN201402957Y (en) * 2009-03-02 2010-02-10 于韶红 Automatic aligning type double-vertical-frame payoff rack
CN201466641U (en) * 2009-05-07 2010-05-12 中冶天工上海十三冶建设有限公司 Cable pay-off rack for cable coil
CN202333630U (en) * 2011-12-02 2012-07-11 山东电力集团公司枣庄供电公司 Electric power cable pay-off support

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103326274A (en) * 2013-06-29 2013-09-25 国家电网公司 Insulating holding pole erecting tool
CN103326274B (en) * 2013-06-29 2016-03-23 国家电网公司 A kind of insulated mast assembly stands up instrument
CN104714117A (en) * 2013-12-13 2015-06-17 珠海格力电器股份有限公司 Radiation emission test tool
CN105790199A (en) * 2014-06-28 2016-07-20 国家电网公司 Pulley mechanism of power cable unwinding for power construction
CN105790199B (en) * 2014-06-28 2017-07-04 国家电网公司 The power construction pulley mechanism of electric power cable unwrapping wire

Similar Documents

Publication Publication Date Title
CN102570352A (en) Power cable laying bracket
CN202333630U (en) Electric power cable pay-off support
CN201634281U (en) Vertical anti-twist cable display device
CN102386582A (en) Portable type adjustable cable pay-off rack
CN203660426U (en) Transverse-type optical cable laying plate
CN204528942U (en) Portable grounding wire winding device
CN204277336U (en) The vertical bracing frame of herringbone bar group
CN103342265A (en) Cable winding devices
CN111661703B (en) Cable bearing frame for power construction and operation method
CN207010098U (en) A kind of electric wire payout stand
CN210480416U (en) Cable paying-off device for power transmission line
CN201785098U (en) Wire coil bracket
CN206665839U (en) Novel heavy duty pay off rack
CN204383529U (en) A kind of civil engineering pipe fitting rack
CN105692321A (en) Novel control cable pay-off frame
CN204528875U (en) A kind of screw type coil spring unit unfolding frame
CN206395580U (en) A kind of cable unreeling rack
CN207553654U (en) A kind of vertical supporting device of assembled architecture
CN111049062B (en) Reel support that power cable laid for electromechanical engineering construction
CN205772357U (en) A kind of modular cable apparatus for displaying
CN202912486U (en) Cable reel unwinding support
CN103343646B (en) A kind of movable communication tower
CN204847572U (en) Support frame that cable laying used
CN103588050A (en) Coil containing rack for coiled steel wire rope
CN203938227U (en) A kind of anti-tarnish paper exhibition bin

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130722

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130722

Address after: 277000 the Yellow River Road, Xuecheng District, Shandong, No. 999, No.

Applicant after: Tai'an Power Supply Co., Ltd. of Shandong Electric Power Corporation

Applicant after: State Grid Corporation of China

Address before: 277000 Guangming Middle Road, Zaozhuang, Shandong, China, No. 60

Applicant before: Tai'an Power Supply Co., Ltd. of Shandong Electric Power Corporation

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120711