CN102565617A - 零起升流检验主变套管电流回路的方法 - Google Patents
零起升流检验主变套管电流回路的方法 Download PDFInfo
- Publication number
- CN102565617A CN102565617A CN2012100213282A CN201210021328A CN102565617A CN 102565617 A CN102565617 A CN 102565617A CN 2012100213282 A CN2012100213282 A CN 2012100213282A CN 201210021328 A CN201210021328 A CN 201210021328A CN 102565617 A CN102565617 A CN 102565617A
- Authority
- CN
- China
- Prior art keywords
- phase
- loop
- current
- main transformer
- transformer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)
Abstract
零起升流检验主变套管电流回路的方法,在220kV变电站带电投产前,用试验线把三相调压器输出的A相回路、B相回路和C相回路,分别对应连接到主变110kV侧一次三相的A相回路、B相回路和C相回路;随后在地端子箱及控制室屏柜以一次A相回路的电压UA为参考向量,检测110kV侧套管电流互感器二次电流幅值和相位角及中性线的电流;最后在地端子箱及控制室屏柜,以一次A相回路电压UA为参考向量,检测220kV侧套管二次电流幅值和相位角,及中性线的电流,通过对数据进行分析判断,判断回路正确与否。本发明可用零起升流对主变套管交流电流回路的极性、变比以及接线情况进行检验,发现漏、错连接的二次回路接线。
Description
技术领域
本发明属于电工技术领域,特别用于变电站在投产前,对主变一次进行零起升流试验,检测套管电流回路的交流电流幅值及相位角,通过数据判断回路是否正确,保证回路接线正确性的方法。
背景技术
电力已成为人们不可或缺的生活必须品,变电站是电力输送的重要环节,其主变套管交流电流回路的正确性,将会影响到电网的安全稳定,影响电力的正常提供和人们的正常生活。
在变电站带电投产前,现今采用的零起升流检验电流回路的方法有两种,方法一是采用行灯变在电流互感器进行一次升流,但是由于套管电流互感器一端已经密封在主变器身内,连接了一次绕组,主变的阻抗较大,采用行灯变电压低升不起电流。方法二是在发电厂主变高压侧短路,发电机带主变,缓慢增加发电机励磁电流,使主变套管及从零电流开始升至目标电流值,进行升流试验检查电流回路正确性。由于变电站缺少发电机电源,不能采用此法检验电流回路。
发明内容
为克服上述现有技术存在的缺陷和不足,本发明提供一种零起升流对主变套管交流电流回路的极性、变比以及接线情况进行检验,发现漏、错连接的二次回路接线,有较高实用性的检验方法。
本发明的技术方案如下。
零起升流检验主变套管电流回路的方法,是在220kV变电站带电投产前,按照下列步骤执行:
本发明的有益效果是:
(一)可对变电站的主变套管电流互感器实现零起逐步升流。解决了变电站缺少升流发电机组的问题,在发现问题后可立即处理,避免突然加压带来的意外冲击。
(二)可实现对套管电流互感器的检查,解决了采用大电流发生器不能对主变套管电流互感器电流回路进行升流的问题。
(三)通过检测主变套管电流回路的电流幅值和相位角,进行数据的分析判断,可确保套管电流回路的正确性。
(四)以统一固定的电压为参考向量,进行套管电流回路的检测,为套管电流相位角的比较统一了基准,对电流回路二次判断极性配合的判断提供了依据。
(五)本方法所用设备材料,简单方便,减少了工作量和试验时间。
下面结合附图及具体实施方式对本发明做进一步说明。
附图说明
图1为主变套管零起升流试验一次接线示意图;
图2为110kV侧套管电流回路二次接线示意图;
图3为220kV侧套管电流回路二次接线示意图。
具体实施方式
零起升流检验主变套管电流回路的方法,本发明特征在于:在220kV变电站带电投产前,按照下列步骤执行:步骤一,按照电缆接线一一对应的顺序,把三相调压器输出用试验线的A相回路、B相回路和C相回路,分别对应连接到主变110kV侧一次三相的A相回路、B相回路和C相回路;在主变220kV侧设置三相接地短路点;步骤二,合上试验空气开关,用钳形表监视试验电流,用钳形相位表监视二次回路电流;调节三相调压器从零开始缓慢升高一次三相试验电流,使二次电流达到钳形相位仪表可进行测量相位的数值;步骤三,在就地端子箱及控制室屏柜,以一次A相回路的电压UA为参考向量,检测110kV侧套管电流互感器二次电流幅值和相位角及中性线的电流;步骤四,在就地端子箱及控制室屏柜,以一次A相回路电压UA为参考向量,检测220kV侧套管二次电流幅值和相位角,及中性线的电流;通过对检测数据进行分析判断,得出判断回路正确与否的结果。
实施方式以三种电压等级的220kV某变电站为示例,阐述具体的实施过程。
1. 该变电站的情况
220kV#1号主变是三相共体式变压器,额定容量为180/180
/90MVA,额定电压为220/115/35kV,阻抗电压及负载损耗见表1。---
表1 阻抗电压及负载损耗测量
220kV侧套管电流互感器变比为800/1, 110kV侧套管电流互感器变比为1600/1。
2. 检验步骤
步骤一,参考图1,实线部分为主变一次接线,虚线部分的试验试验接线。三相调压器电源出线,按照A、B、C的一一对应的顺序连接至主变110kV侧一次。断开2016、1016、3014隔离开关,在220kV位置1合上20167隔离开关设置三相接地短路点。
步骤二,一次零起升电流:合上试验空气开关,用钳形表监视试验电流,钳形相位表监视二次回路电流,调节三相调压器从零开始逐步升高三相电流,由于大多数钳形相位表只能对10mA以上的电流进行相位检测,所以升流至二次电流达到10mA以上。为确保能测量到电流相位角,加到二次电流为13mA。测量所加一次电试验压为UA=223.5V,UB=222.7V,UC=223.6V,一次试验电流为IA=21.2A,IB=21.1A,IC=21.3A。试验电流流过主变110kV套管电流互感器;流过主变110kV线圈;在主变220kV侧感应产生电流;电流流过主变220kV套管电流互感器;流到位置1通过20167接地刀闸短路接地。
步骤三,检测主变110kV套管电流回路电流幅值和相位角:参考图2,主变110kV套管电流互感器二次绕组产生电流;二次绕组产生的电流,流过二次线圈接线柱1,流过电缆接线1,流过就地端子箱接线端子,流过电缆接线2,流过屏柜电流端子,流入屏柜的元器件,流到中性线N。
在控制室屏柜端子,采用钳形相位表,以试验电源UA为参考向量,对主变110kV侧套管电流回路进行测量, 测量所得数据情况如下:
表2 主变110kV侧套管第一组电流回路电流测量数据
Ia | Ib | Ic | IN | |
幅值(mA) | 13.2 | 13.2 | 13.1 | 0.0 |
相位角(度) | 86.8 | 207.8 | 327.1 | -- |
步骤四,检测主变220kV套管电流回路电流幅值和相位角:参考图3,在就地端子箱、控制室屏柜端子,采用钳形相位表,以UA为参考向量,对主变220kV侧套管电流回路进行测量,测量数据情况如下:
表3 主变220kV侧套管第一组电流回路电流测量数据
Ia’ | Ib’ | Ic’ | IN’ | |
幅值mA | 14.8 | 14.8 | 14.8 | 0.0 |
相位角 | 267.0 | 27.2 | 147.0 | -- |
对数据进行分析判断,根据检测的数据,主变110kV侧套管电流回路Ia滞后参考向量UA相位角为86.8度,符合主变110kV短路电抗角度,Ia、Ib、Ic幅值相同,Ib相位角滞后Ia相位角120度角,Ic相位角滞后Ib1相位角120度角,中性线N电流IN=0,可判断电流回路接线符合设计要求,接线正确。按相同的方法,通过测量得到的电流幅值及相位角,可判断主变220kV侧套管电流回路接线正确性与否。
Claims (1)
1. 零起升流检验主变套管电流回路的方法,其特征在于:在220kV变电站带电投产前,按照下列步骤执行:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100213282A CN102565617A (zh) | 2012-01-31 | 2012-01-31 | 零起升流检验主变套管电流回路的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100213282A CN102565617A (zh) | 2012-01-31 | 2012-01-31 | 零起升流检验主变套管电流回路的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102565617A true CN102565617A (zh) | 2012-07-11 |
Family
ID=46411531
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100213282A Pending CN102565617A (zh) | 2012-01-31 | 2012-01-31 | 零起升流检验主变套管电流回路的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102565617A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103207344A (zh) * | 2013-03-07 | 2013-07-17 | 云南电力试验研究院(集团)有限公司电力研究院 | 一种基于主变短路试验检查变电站二次电流回路的方法 |
CN103743994A (zh) * | 2014-01-27 | 2014-04-23 | 广州供电局有限公司 | 低压带负荷测试方法及装置 |
CN104125693A (zh) * | 2014-08-12 | 2014-10-29 | 国网重庆市电力公司 | 变电站灯光控制系统及其控制方法 |
CN107064711A (zh) * | 2017-02-17 | 2017-08-18 | 云南电网有限责任公司 | 厂站普通高抗一次及二次电流回路检验方法 |
CN114114127A (zh) * | 2021-12-02 | 2022-03-01 | 广西电网有限责任公司梧州供电局 | 主变套管ct及主变间隔零序、间隙ct的升流试验方法 |
CN117388575A (zh) * | 2023-12-11 | 2024-01-12 | 广东威恒输变电工程有限公司 | 一种供配电系统电流互感器数据向量测试方法及系统 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101726687A (zh) * | 2009-12-10 | 2010-06-09 | 贵州电力试验研究院 | 变电站及电厂电压互感器二次中性点一点接地监测方法 |
-
2012
- 2012-01-31 CN CN2012100213282A patent/CN102565617A/zh active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101726687A (zh) * | 2009-12-10 | 2010-06-09 | 贵州电力试验研究院 | 变电站及电厂电压互感器二次中性点一点接地监测方法 |
Non-Patent Citations (3)
Title |
---|
印永华等: "750kV输变电示范工程系统调试概况", 《电网技术》 * |
吴建辉等: "变压器套管电流互感器试验方法探讨", 《变压器》 * |
瞿纲举: "一种换流变套管TA极性校验的新方法", 《湖南电力》 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103207344A (zh) * | 2013-03-07 | 2013-07-17 | 云南电力试验研究院(集团)有限公司电力研究院 | 一种基于主变短路试验检查变电站二次电流回路的方法 |
CN103743994A (zh) * | 2014-01-27 | 2014-04-23 | 广州供电局有限公司 | 低压带负荷测试方法及装置 |
CN103743994B (zh) * | 2014-01-27 | 2017-02-01 | 广州供电局有限公司 | 低压带负荷测试方法及装置 |
CN104125693A (zh) * | 2014-08-12 | 2014-10-29 | 国网重庆市电力公司 | 变电站灯光控制系统及其控制方法 |
CN104125693B (zh) * | 2014-08-12 | 2016-04-06 | 国网重庆市电力公司 | 变电站灯光控制系统的控制方法 |
CN107064711A (zh) * | 2017-02-17 | 2017-08-18 | 云南电网有限责任公司 | 厂站普通高抗一次及二次电流回路检验方法 |
CN114114127A (zh) * | 2021-12-02 | 2022-03-01 | 广西电网有限责任公司梧州供电局 | 主变套管ct及主变间隔零序、间隙ct的升流试验方法 |
CN117388575A (zh) * | 2023-12-11 | 2024-01-12 | 广东威恒输变电工程有限公司 | 一种供配电系统电流互感器数据向量测试方法及系统 |
CN117388575B (zh) * | 2023-12-11 | 2024-03-19 | 广东威恒输变电工程有限公司 | 一种供配电系统电流互感器数据向量测试方法及系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205080251U (zh) | 一种电流互感器二次回路通流校验系统 | |
CN102565617A (zh) | 零起升流检验主变套管电流回路的方法 | |
CN102540001B (zh) | 500kV变电站模拟穿越式三相短路检验交流电流回路的方法 | |
CN102608485B (zh) | 变电站零序电流回路检验方法 | |
CN102565618A (zh) | 变电站零序电压回路检验方法 | |
CN202548258U (zh) | 交流电流电压回路检验装置 | |
CN201319064Y (zh) | 一种高压电流互感器现场准确度检测试验线路 | |
CN102540128A (zh) | 组合式三相电流互感器误差自动检定方法 | |
CN203894379U (zh) | 一种用于检测矿用低压馈电开关性能的综合试验台 | |
CN201681138U (zh) | 轻便型发电机工频交流耐压试验器 | |
CN207798935U (zh) | 一体化gis管道内电流互感器校验装置 | |
CN203204109U (zh) | 变压器差动保护现场校验装置 | |
CN105467239A (zh) | 一种电压互感器励磁特性试验系统 | |
CN201281729Y (zh) | 一种接地电阻测试仪 | |
CN109283421B (zh) | 一种铁路牵引变电所低电压通电检测试验方法及装置 | |
CN208580172U (zh) | 一种用于电力系统设备接地状况快速检测装置 | |
CN204740329U (zh) | 高低压交流电机试验系统 | |
CN103743994B (zh) | 低压带负荷测试方法及装置 | |
CN105319478A (zh) | 变压器套管不解体极性和变比测试的方法 | |
CN107153135A (zh) | 柱上配变接地网接地阻抗的测试方法 | |
CN104111438B (zh) | 一种电流互感器误差测试试验中一次大电流回路监控方法 | |
CN201697974U (zh) | 有线、无线一体化核相仪 | |
CN205450243U (zh) | 一种故障指示器线圈测试仪 | |
CN102565614A (zh) | 交流电压回路检验方法 | |
CN205229335U (zh) | 一种电压互感器励磁特性试验装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120711 |