CN102556926A - Uninterrupted gasoline feeding system for automobile production line - Google Patents

Uninterrupted gasoline feeding system for automobile production line Download PDF

Info

Publication number
CN102556926A
CN102556926A CN2010105779447A CN201010577944A CN102556926A CN 102556926 A CN102556926 A CN 102556926A CN 2010105779447 A CN2010105779447 A CN 2010105779447A CN 201010577944 A CN201010577944 A CN 201010577944A CN 102556926 A CN102556926 A CN 102556926A
Authority
CN
China
Prior art keywords
pump
gasoline
production line
uninterrupted
feeding system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105779447A
Other languages
Chinese (zh)
Inventor
鲁仲平
施春晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN2010105779447A priority Critical patent/CN102556926A/en
Publication of CN102556926A publication Critical patent/CN102556926A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Loading And Unloading Of Fuel Tanks Or Ships (AREA)

Abstract

The invention relates to automobile production lines, in particular to an uninterrupted gasoline feeding system for an automobile production line, which comprises an emergency pump parallelly connected with an original pump. A pressure transmitter is arranged on a head pipeline of the original pump and the emergency pump, is used for detecting and transmitting oil pressure of the pipeline and is in communicated connection with a controller, the controller is in control connection with two electromagnetic valves and an acousto-optic alarm, and the two electromagnetic valves are used for controlling the original pump and the emergency pump respectively. By the aid of the uninterrupted gasoline feeding system, the emergency pump can be automatically started within five minutes once an air diaphragm pump for delivering gasoline fails, so that the gasoline is guaranteed to be uninterruptedly supplied to downstream gasoline use points.

Description

A kind of auto production line gasoline of uninterrupted feed flow adds liquid systems
Technical field
The present invention relates to auto production line, relate in particular to a kind of auto production line gasoline and add liquid systems.
Background technology
The fuel-feed system of auto production line is the automobile centralized oil supply to the car production conveyor line, and wherein gasoline refuels a car after delivering to fuel charger by one in 2 two pneumatic diaphragm pumps again.Present present situation be in the fuel feeding process because of membrane pump holddown termination of pumping phenomenon can occur during at transformation point when coming and going stroke, this is the intrinsic mechanical specialities of pump.Wait to find that like a termination of pumping back leans on rapidly manual switching to another pump operation fuel feeding, because not prompting, the time of often delaying all will be more than half an hour.If the beat of auto production line is 40JPH, promptly productive temp is that per hour 40 cars roll off the production line when busy, whenever stops line and just produces a car less in 1.5 minutes, will produce vehicle less more than at least 45 with this.And all be that class Three produced in 24 hours at present, the production vehicle of loss is not free to be refilled.Suppose the value 150,000 of each car, will bring economic loss 6,750,000.What taken place stops line because of termination of pumping influences, at every turn all more than 40 minutes.
Existing need to solve, thereby reduce the time of off-production, simultaneously also will be under the prerequisite that guarantees a pump normal fuel injection the instant maintenance recovery of fault pump be in normal standby status because of fault holddown termination of pumping wherein influences the key issue of off-production.
Present situation from the U.S. and domestic each automobile manufacturing enterprise consulting and understanding; Refueling industry at car production does not also solve because of termination of pumping and launches the technical barrier that is equipped with the uninterrupted fuel feeding that pump guarantees rapidly automatically; Be to lean on personal monitoring and manual switchover enforcement fully, influence the economic loss that off-production causes therefrom and also do not cause enough attention.
Summary of the invention
The present invention is intended to address the aforementioned drawbacks, and provides a kind of auto production line gasoline of uninterrupted feed flow to add liquid systems.In case the present invention can start stand by pump automatically to guarantee that gasoline uses point that supply continuously is provided downstream within 5 seconds behind the air diaphragms pump et out of order of gasoline feed.
The present invention is achieved in that a kind of auto production line gasoline of uninterrupted feed flow adds liquid systems; It comprises a stand by pump with former parallel connection of pumps; The main pipe rail of said former pump and stand by pump be provided with one be used for surveying, the pressure transformer of transfer canal oil pressure; Said pressure transformer communication is connected with a controller, two electromagnetic valves of this controller control linkage and a combined aural and visual alarm, described two former pumps of each Self Control of electromagnetic valve and stand by pump.
The auto production line gasoline of described a kind of uninterrupted feed flow adds liquid systems, and the ball valve that said two electromagnetic valves have through two ends is connected in the pipeline of respective pump.
The present invention can solve because of fault holddown termination of pumping wherein influences the key issue of off-production, thereby reduces the time of off-production, and the value 150,000 of average holddown 3 times, each 40 minutes, each car is calculated with every year, and can reduce economic loss 6,750,000 every year.Also guarantee simultaneously under the prerequisite of a pump normal fuel injection instant maintenance with the fault pump to recover and be in normal standby status.
Description of drawings
Below, further specify the specific embodiment of the present invention in conjunction with accompanying drawing:
Fig. 1 is a structural representation of the present invention.
The specific embodiment
As shown in Figure 1, in case gasoline liquid-feeding tube system reform purpose is within 5 seconds, to start stand by pump behind the air diaphragms pump et out of order of gasoline feed automatically to guarantee that gasoline uses point that supply continuously is provided downstream.
In order to reach above-mentioned transformation purpose, on the basis that gasoline liquid-feeding tube system has used, undergo technological transformation, from minute instrument automatic guidance and process pipe the present invention is described below:
1, instrument automatic guidance major remake explanation
Native system is made up of intelligent pressure transmitter 1, intelligent digital controller 2,8 annunciators, change-over switch, reset switch and equipment such as electromagnetic valve 4 and 24VDC power supply; Electromagnetic valve 4 is selected import flame-proof type product for use, and intelligent digital controller 2 is selected universal digital controller for use.Pressure transformer 1 is installed in the scene with electromagnetic valve 4, and controller, annunciator and conversion and reset switch and 24VDC power supply are installed in the indoor gauge control case.
Explain:
1# pump, 2# pump electromagnetic valve can be chosen one of which place auto state at ordinary times wantonly, and another is a manual state, and by the manual turn on pump of staff, the auto state pump then starts as interlocking behind the pressure alarm, but after starting still this working barrel still go manual unlocking by operating personal.After oil pressure is normal, pressing the reset switch cancellation by operating personal reports to the police.Operating personal is opened and must cooresponding change-over swith be placed behind the on-site manual valve manually, and the change-over swith of an other pump is placed automatic transmission.The cooresponding change-over swith of working barrel is in manual, and at this moment electromagnetic valve is not worked, and opens the on-site manual valve by operating personal.Electromagnetic valve carries out self-locking through relay, does not have from reset function.When warning was sent, the operating personal fibrous root was opened the on-site manual valve according to warning, then corresponding change-over swith on the control box was transferred to manually.After change-over swith transfers to manually, the sound and light alarm signal at stop.Reset switch is by back relay cancellation self-locking.
2, process pipe major remake explanation
A, the pressurized air of supplying with two air diaphragms pump sources of the gas through when increasing the automatically controlled electromagnetic valve respectively behind the filter at the other parallelly connected manual ball valve of this electromagnetic valve, and increase ball valve before and after the electromagnetic valve, be convenient to mode of operation under dismounting and keep in repair electromagnetic valve.
B, on the oil circuit house steward of two air diaphragms pump discharges, increase a pressure transformer that carries out related teletransmission with electromagnetic valve.In case the pressure that this pressure transformer measures is opened the auto state electromagnetic valve of stand by pump source of the gas by digital display controller sender in the control instrument case after less than setting value automatically, sends sound and light alarm on the gauge control panel in operator's compartment simultaneously.
C, pipeline modification content:
1) increase the ball valve of 304 materials of 1/2 " negative thread behind the compressed-air cleaner of two air diaphragms pump sources of the gas respectively, the material of this pipeline is zinc-plated carbon steel pipe, and standard is GB/T3091.
2) behind the metallic hose of two air diaphragms pump discharges, increase boiler check valve, material 304.
3) explanation of pressure pipeline: the pipeline nominal diameter of this transformation is≤DN25, so the pipeline of this transformation do not belong to pressure pipeline, promptly need not go extra enforcement testing by the specific (special) requirements of special equipment.

Claims (2)

1. the auto production line gasoline of a uninterrupted feed flow adds liquid systems; It comprises a stand by pump with former parallel connection of pumps; It is characterized in that, the main pipe rail of said former pump and stand by pump be provided with one be used for surveying, the pressure transformer of transfer canal oil pressure, said pressure transformer communication is connected with a controller; Two electromagnetic valves of this controller control linkage and a combined aural and visual alarm, described two former pumps of each Self Control of electromagnetic valve and stand by pump.
2. the auto production line gasoline of a kind of uninterrupted feed flow according to claim 1 adds liquid systems, it is characterized in that, the ball valve that said two electromagnetic valves have through two ends is connected in the pipeline of respective pump.
CN2010105779447A 2010-12-08 2010-12-08 Uninterrupted gasoline feeding system for automobile production line Pending CN102556926A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105779447A CN102556926A (en) 2010-12-08 2010-12-08 Uninterrupted gasoline feeding system for automobile production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105779447A CN102556926A (en) 2010-12-08 2010-12-08 Uninterrupted gasoline feeding system for automobile production line

Publications (1)

Publication Number Publication Date
CN102556926A true CN102556926A (en) 2012-07-11

Family

ID=46403769

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105779447A Pending CN102556926A (en) 2010-12-08 2010-12-08 Uninterrupted gasoline feeding system for automobile production line

Country Status (1)

Country Link
CN (1) CN102556926A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106402658A (en) * 2016-11-09 2017-02-15 安徽启东热能科技有限公司 Double-channel automatic oil inlet device driven by compressed air and control method thereof

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1995011193A1 (en) * 1993-10-19 1995-04-27 Dong Nam Co., Ltd. Oil supply apparatus for oil tank trucks
CN2336153Y (en) * 1998-06-01 1999-09-01 北京阀门四厂 Straight oil sealed ball valve
CN2395100Y (en) * 1999-05-30 2000-09-06 姚一博 Speciali switch control valve
CN2625596Y (en) * 2003-06-20 2004-07-14 三一重工股份有限公司 Diesel cold starting preheating device for engineering machinery
CN2634149Y (en) * 2003-06-26 2004-08-18 中国石油天然气股份有限公司辽河石化分公司 High speed pump automatic startor for propylene raw material
CN2659982Y (en) * 2003-11-19 2004-12-01 张明亮 Self-suction water feeder
CN2759876Y (en) * 2004-12-24 2006-02-22 武汉理工大学 Automatic dispensing apparatus for locomotive fuel oil
CN2773657Y (en) * 2004-08-18 2006-04-19 长安汽车(集团)有限责任公司 Fuel-oil centralized supply system for thermal experiment
CN101192353A (en) * 2006-11-23 2008-06-04 辽宁石油化工大学 Pipeline oil transportation simulator
CN201292248Y (en) * 2008-10-22 2009-08-19 韩芝宁 Mobile automatic oiler
CN201314061Y (en) * 2008-08-21 2009-09-23 张伟林 Microcomputer-controlled fire-fighting water supply system
CN101654179A (en) * 2009-09-02 2010-02-24 上海华篷防爆科技有限公司 Dirt removing device of anti-explosion storage tank and method for circularly removing dirt by storage media in tank
CN101788322A (en) * 2010-01-29 2010-07-28 重庆长安汽车股份有限公司 Automobile fuel automatic pumping and injecting test device
CN201662597U (en) * 2010-04-02 2010-12-01 中国海洋石油总公司 Fluid pipeline electrostatic measuring device

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1995011193A1 (en) * 1993-10-19 1995-04-27 Dong Nam Co., Ltd. Oil supply apparatus for oil tank trucks
CN2336153Y (en) * 1998-06-01 1999-09-01 北京阀门四厂 Straight oil sealed ball valve
CN2395100Y (en) * 1999-05-30 2000-09-06 姚一博 Speciali switch control valve
CN2625596Y (en) * 2003-06-20 2004-07-14 三一重工股份有限公司 Diesel cold starting preheating device for engineering machinery
CN2634149Y (en) * 2003-06-26 2004-08-18 中国石油天然气股份有限公司辽河石化分公司 High speed pump automatic startor for propylene raw material
CN2659982Y (en) * 2003-11-19 2004-12-01 张明亮 Self-suction water feeder
CN2773657Y (en) * 2004-08-18 2006-04-19 长安汽车(集团)有限责任公司 Fuel-oil centralized supply system for thermal experiment
CN2759876Y (en) * 2004-12-24 2006-02-22 武汉理工大学 Automatic dispensing apparatus for locomotive fuel oil
CN101192353A (en) * 2006-11-23 2008-06-04 辽宁石油化工大学 Pipeline oil transportation simulator
CN201314061Y (en) * 2008-08-21 2009-09-23 张伟林 Microcomputer-controlled fire-fighting water supply system
CN201292248Y (en) * 2008-10-22 2009-08-19 韩芝宁 Mobile automatic oiler
CN101654179A (en) * 2009-09-02 2010-02-24 上海华篷防爆科技有限公司 Dirt removing device of anti-explosion storage tank and method for circularly removing dirt by storage media in tank
CN101788322A (en) * 2010-01-29 2010-07-28 重庆长安汽车股份有限公司 Automobile fuel automatic pumping and injecting test device
CN201662597U (en) * 2010-04-02 2010-12-01 中国海洋石油总公司 Fluid pipeline electrostatic measuring device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106402658A (en) * 2016-11-09 2017-02-15 安徽启东热能科技有限公司 Double-channel automatic oil inlet device driven by compressed air and control method thereof

Similar Documents

Publication Publication Date Title
CN203036254U (en) Online hydrogen supply system of emergency dynamo van based on fuel cell
CN101603602A (en) A kind of intelligent disconnecting valve and method of work thereof
CN103738872B (en) Flame-proof type hydraulic power unit and SQ-1200 endless rope series tractor collection control integration unit
CN109340549A (en) A kind of control method that lubricating system oil pump fault judges automatically and switches
CN105422430A (en) Diesel engine water pump control system and method
CN102556926A (en) Uninterrupted gasoline feeding system for automobile production line
CN201715217U (en) Full automatic intelligent integrated lubricating system
CN101737627A (en) Automatic switching cylinder manifold device
CN203489008U (en) ESD system for LNG and LCNG site sub station skid-mounted full integration
CN2875508Y (en) Low pressure carbon dioxide fire-extinguishing system with self-pressure increasing function
CN101327782A (en) CNG air entraining substation system and air entraining method thereof
CN110848179A (en) Intelligent gas pressurization system and use method thereof
CN102620145A (en) Automatic low-pressure protection system for coke oven gas pipeline
CN205002156U (en) Domestic gas formula boiler monitoring system
CN202284671U (en) System special for isolating valve and system special for isolating one or more valves
CN208204557U (en) A kind of more gas source feed systems
CN212062589U (en) Integrated hydrogen supply control panel system for fuel cell
CN201293205Y (en) Automatic switchover busbar apparatus
CN109811829B (en) Standardized pump room and remote control system for controlling same
CN203146269U (en) Gas supplying device for dry gas sealing of compressor
CN103982223B (en) Compressed-air supply system
CN202156435U (en) Emergency shutdown device for railway vehicle
CN218209013U (en) Medium-pressure nitrogen system for caprolactam production
CN218544021U (en) Compressor air supply system
CN101285554A (en) Multipath oxygen filling system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120711