CN102535510A - 海上风机导管架基础安装方法及一体化导管架装置 - Google Patents

海上风机导管架基础安装方法及一体化导管架装置 Download PDF

Info

Publication number
CN102535510A
CN102535510A CN201210045137XA CN201210045137A CN102535510A CN 102535510 A CN102535510 A CN 102535510A CN 201210045137X A CN201210045137X A CN 201210045137XA CN 201210045137 A CN201210045137 A CN 201210045137A CN 102535510 A CN102535510 A CN 102535510A
Authority
CN
China
Prior art keywords
jacket
pile tube
platform
leg
sea bed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210045137XA
Other languages
English (en)
Inventor
朱荣华
傅强
崔靓亮
张康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Mingyang Wind Power Group Co Ltd
Original Assignee
Guangdong Mingyang Wind Power Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Mingyang Wind Power Group Co Ltd filed Critical Guangdong Mingyang Wind Power Group Co Ltd
Priority to CN201210045137XA priority Critical patent/CN102535510A/zh
Publication of CN102535510A publication Critical patent/CN102535510A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)
  • Revetment (AREA)
  • Wind Motors (AREA)

Abstract

本发明公开了一体化导管架装置,包括有水平设置在海床面上的导管架体,该导管架体包括有多根导管架腿,在各根导管架腿中插入有固定在海床面上的管桩,导管架体的顶部设置有可安装风机榙筒的导管架平台,该导管架平台与导管架体连为一体。另外公开了海上风机导管架基础安装方法,包括如下步骤:A、安装导管架平台,在导管架体上端设置导管架平台,使导管架平台与导管架体连为一体。B、安放导管架体,将导管架体放置到海床上,使导管架体水平放置在海床上。C、打桩,将管桩从各根导管架腿中插入,利用打桩机将管桩牢固地置于海床中。D、灌浆,打好管桩后,从管桩与导管架腿之间的间隙之间灌入水泥砂浆。

Description

海上风机导管架基础安装方法及一体化导管架装置
【技术领域】
本发明涉及一种海上风机导管架基础安装方法及一体化导管架安装置。
【背景技术】
由于陆上风资源有限、且陆上风机日趋饱和,海洋已成为风力发电的新场地。国内外传统的海上风机导管架基础,一般将管桩通过打桩机打到海床面上,然后放置导管架,最后在导管架桩腿和钢管桩之间灌浆固定。
传统的这种导管架结构施工在操作上比较困难,譬如水下打桩,管桩定位,管桩内部的杂质清除,水下灌浆以及风机榙筒基座调平等诸多问题。
本发明就是在此种情况下作出的。
【发明内容】
本发明目的是克服了现有技术中的不足而提供一种使用效果好、定位容易的海上风机安装装置。
本发明的另一目的是提供一种使用效果好、定位容易、操作简单的海上风机导管架基础安装方法。
为了解决上述存在的技术问题,本发明采用下列技术方案:
一体化导管架装置,其特征在于包括有水平设置在海床面3上的导管架体1,该导管架体1包括有多根导管架腿2,在各根导管架腿2中插入有固定在海床面3上的管桩4,导管架体1的顶部设置有可安装风机榙筒的导管架平台5,该导管架平台5与导管架体1连为一体。
如上所述的一体化导管架装置,其特征在于在导管架腿2与管桩4之间的间隙灌有砂浆。
如上所述的一体化导管架装置,其特征在于在各根导管架腿2底部设有挡泥板7。
一种海上风机导管架基础安装方法,其特征在于包括有如下步骤:
A、安装导管架平台,在具有多根导管架腿2和横杆8连接起来形成的导管架体1的上端设置有导管架平台5,并使导管架平台5与导管架体1连为一体;
B、安放导管架体,将导管架体1放置到海床上,并调整导管架体1,使导管架体1水平放置在海床上;
C、打桩,将管桩4相应地从各根导管架腿2中插入,并使管桩4下端伸出导管架腿2,从而进入海床,之后利用打桩机将管桩4打入海床中并使管桩4牢固地置于海床中,而管桩4上端则露出导管架腿2一部分;
D、灌浆,打好管桩后,管桩与导管架腿2之间会留有间隙,从间隙之间灌入水泥砂浆,并使水泥砂浆流入到导管架腿2的底部并固定在海床上,而管桩与导管架腿2之间的间隙也会充满。
如上所述的海上风机导管架基础安装方法,其特征在于在各根导管架腿2底部设有挡泥板7。
本发明与现有技术相比有如下优点:
本发明的装置利用一个导管架体,先将其放置到海床上,之后再将管桩插入导管架腿中并从导管架腿底部伸出并进入到海床中,之后利用打桩机将管桩打到海床中实现固定。
由于有导管架腿的定位,所以管桩的定位十分准确,同时导管架平台可以借助打入的钢桩调平。
而本发明的方法,利用了导管架装置,从而使该海上风机导管架基础安装方法具有使用效果好、定位容易、操作简单、安装高效、成本低等优点。
【附图说明】
图1是实施例一的立体图。
图2是实施例二的立体图。
图3是实施例二的立体图。
【具体实施方式】
下面结合附图对本发明进行详细描述:
如图所示,一体化导管架装置,包括有水平设置在海床面3上的导管架体1。该导管架体1包括有多根导管架腿2。在各根导管架腿2中插入有固定在海床面3上的管桩4。其安装方式为:先将管桩4插入导管架腿2中并从导管架腿底部伸出并进入到海床中,之后利用打桩机将管桩打到海床中实现固定。有导管架腿的定位,所以管桩的定位十分准确。而导管架体1一部分浸泡在海水6中,另一部分则置于海平面上方。
导管架体1的顶部设置有可安装风机榙筒的导管架平台5。设置的导管架平台5有两种实施方式。
其中一种方式是:所述导管架平台5与导管架体1连为一体。即在将导管架体1放置到海床之前,导管架平台5就设置好在导管架体1上。本实施例就是采用此种方式。
另一种方式是:所述各根管桩4上端平齐切断后并通过焊接方式与导管架平台5连接在一起。即,先将导管架体1放置到海床上,并将管桩打好在海床上之后,将管桩上部露出导管架腿的部分进行平齐切断后,再通过焊接方式与导管架平台5连接在一起。
作为本实施例的优选方式,在导管架腿2与管桩4之间的间隙灌有粘合料。所述的粘合料为砂浆。即,打好管桩之后,就需要灌浆,完成导管架体1的固定安装。
作为本实施例的优选方式,所述管桩4为钢桩。
作为本实施例的优选方式,所述导管架腿2的个数有四根,各个导管架腿2之间通过横杆8连接。
作为本实施例的优选方式,在各根导管架腿2底部设有挡泥板7,挡泥板7的作用主要是防止导管架沉入淤泥。
一种海上风机导管架基础安装方法,包括有如下步骤:
A、安装导管架平台,在具有多根导管架腿2和横杆8连接起来形成的导管架体1的上端设置有导管架平台5,并使导管架平台5与导管架体1连为一体。导管架体1安装过程中,导管架平台5可以通过焊接或其它方便连接固定到导管架腿上。
B、安放导管架体,将导管架体1放置到海床上,并调整导管架体1,使导管架体1水平放置在海床上。
C、打桩,将管桩4相应地从各根导管架腿2中插入,并使管桩4下端伸出导管架腿2,从而进入海床,之后利用打桩机将管桩4打入海床中并使管桩4牢固地置于海床中,而管桩4上端则露出导管架腿2一部分。
D、灌浆,打好管桩后,管桩与导管架腿2之间会留有间隙,从间隙之间灌入水泥砂浆,并使水泥砂浆流入到导管架腿2的底部并固定在海床上,而管桩与导管架腿2之间的间隙也会充满。此外,在各根导管架腿2底部设有挡泥板7,该挡泥板7的作用主要是防止导管架沉入淤泥。

Claims (5)

1.一体化导管架装置,其特征在于包括有水平设置在海床面(3)上的导管架体(1),该导管架体(1)包括有多根导管架腿(2),在各根导管架腿(2)中插入有固定在海床面(3)上的管桩(4),导管架体(1)的顶部设置有可安装风机榙筒的导管架平台(5),该导管架平台(5)与导管架体(1)连为一体。
2.根据权利要求1所述的一体化导管架装置,其特征在于在导管架腿(2)与管桩(4)之间的间隙灌有砂浆。
3.根据权利要求1或2所述的一体化导管架装置,其特征在于在各根导管架腿(2)底部设有挡泥板(7)。
4.一种海上风机导管架基础安装方法,其特征在于包括有如下步骤:
A、安装导管架平台,在具有多根导管架腿(2)和横杆(8)连接起来形成的导管架体(1)的上端设置有导管架平台(5),并使导管架平台(5)与导管架体(1)连为一体;
B、安放导管架体,将导管架体(1)放置到海床上,并调整导管架体(1),使导管架体(1)水平放置在海床上;
C、打桩,将管桩(4)相应地从各根导管架腿(2)中插入,并使管桩(4)下端伸出导管架腿(2),从而进入海床,之后利用打桩机将管桩(4)打入海床中并使管桩(4)牢固地置于海床中;
D、灌浆,打好管桩后,管桩与导管架腿(2)之间会留有间隙,从间隙之间灌入水泥砂浆,并使水泥砂浆流入到导管架腿(2)的底部并固定在海床上,而管桩与导管架腿(2)之间的间隙也会充满。
5.根据权利要求4所述的海上风机导管架基础安装方法,其特征在于在各根导管架腿(2)底部设有挡泥板(7)。
CN201210045137XA 2012-02-27 2012-02-27 海上风机导管架基础安装方法及一体化导管架装置 Pending CN102535510A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210045137XA CN102535510A (zh) 2012-02-27 2012-02-27 海上风机导管架基础安装方法及一体化导管架装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210045137XA CN102535510A (zh) 2012-02-27 2012-02-27 海上风机导管架基础安装方法及一体化导管架装置

Publications (1)

Publication Number Publication Date
CN102535510A true CN102535510A (zh) 2012-07-04

Family

ID=46343415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210045137XA Pending CN102535510A (zh) 2012-02-27 2012-02-27 海上风机导管架基础安装方法及一体化导管架装置

Country Status (1)

Country Link
CN (1) CN102535510A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852154A (zh) * 2012-08-01 2013-01-02 天津大学 一种复合桩基
CN102852155A (zh) * 2012-08-01 2013-01-02 天津大学 一种复合桩基础
CN104099917A (zh) * 2014-08-07 2014-10-15 熊翱 一种多层多脚架结构及其施工方法
CN104564545A (zh) * 2015-01-07 2015-04-29 广东明阳风电产业集团有限公司 一种海上风电导管架基础过渡段结构
CN105971000A (zh) * 2016-06-16 2016-09-28 江苏海上龙源风力发电有限公司 一种海上风机嵌岩单桩基础临时施工平台
CN107218179A (zh) * 2017-07-26 2017-09-29 中交第三航务工程局有限公司宁波分公司 海上风力发电机分体安装的施工方法
WO2021141490A1 (en) * 2020-01-10 2021-07-15 Van Oord Offshore Wind B.V. Method of Installing a Support for Supporting a Load Structure, such as a Wind Turbine, on, for instance, a Sea Bed

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10109040C1 (de) * 2001-02-24 2002-07-11 Conrad Hansen Gründung für eine Windkraftanlage
CN200978412Y (zh) * 2006-12-13 2007-11-21 中国水利水电科学研究院 防沉陷易调平易拆除的大型海上风电基础承台
CN201513303U (zh) * 2009-09-25 2010-06-23 中国水电顾问集团华东勘测设计研究院 多桩钢构架海上风电机组基础结构
CN201599157U (zh) * 2009-09-29 2010-10-06 中国水电顾问集团华东勘测设计研究院 无周边连接管的多桩钢构架海上风电机组基础结构
CN201649118U (zh) * 2010-04-07 2010-11-24 中国水电顾问集团华东勘测设计研究院 导管架式海上风电机组基础结构
CN102312435A (zh) * 2010-07-02 2012-01-11 Ihc荷兰Ie有限公司 在水下地层中安装多个基础构件的模板和方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10109040C1 (de) * 2001-02-24 2002-07-11 Conrad Hansen Gründung für eine Windkraftanlage
CN200978412Y (zh) * 2006-12-13 2007-11-21 中国水利水电科学研究院 防沉陷易调平易拆除的大型海上风电基础承台
CN201513303U (zh) * 2009-09-25 2010-06-23 中国水电顾问集团华东勘测设计研究院 多桩钢构架海上风电机组基础结构
CN201599157U (zh) * 2009-09-29 2010-10-06 中国水电顾问集团华东勘测设计研究院 无周边连接管的多桩钢构架海上风电机组基础结构
CN201649118U (zh) * 2010-04-07 2010-11-24 中国水电顾问集团华东勘测设计研究院 导管架式海上风电机组基础结构
CN102312435A (zh) * 2010-07-02 2012-01-11 Ihc荷兰Ie有限公司 在水下地层中安装多个基础构件的模板和方法

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852154A (zh) * 2012-08-01 2013-01-02 天津大学 一种复合桩基
CN102852155A (zh) * 2012-08-01 2013-01-02 天津大学 一种复合桩基础
CN104099917A (zh) * 2014-08-07 2014-10-15 熊翱 一种多层多脚架结构及其施工方法
CN104564545A (zh) * 2015-01-07 2015-04-29 广东明阳风电产业集团有限公司 一种海上风电导管架基础过渡段结构
CN105971000A (zh) * 2016-06-16 2016-09-28 江苏海上龙源风力发电有限公司 一种海上风机嵌岩单桩基础临时施工平台
CN107218179A (zh) * 2017-07-26 2017-09-29 中交第三航务工程局有限公司宁波分公司 海上风力发电机分体安装的施工方法
CN107795438A (zh) * 2017-07-26 2018-03-13 中交第三航务工程局有限公司宁波分公司 一种辅助平台的施工方法
CN107795438B (zh) * 2017-07-26 2019-06-14 中交第三航务工程局有限公司宁波分公司 一种辅助平台的施工方法
CN107218179B (zh) * 2017-07-26 2019-07-16 中交第三航务工程局有限公司宁波分公司 海上风力发电机分体安装的施工方法
WO2021141490A1 (en) * 2020-01-10 2021-07-15 Van Oord Offshore Wind B.V. Method of Installing a Support for Supporting a Load Structure, such as a Wind Turbine, on, for instance, a Sea Bed
EP4286592A2 (en) 2020-01-10 2023-12-06 Van Oord Offshore Wind B.V. Method of installing a support for supporting a load structure, such as a wind turbine, on, for instance, a sea bed
TWI826763B (zh) * 2020-01-10 2023-12-21 荷蘭商凡諾德離岸風電工程有限公司 用於提供負載結構的方法、支撐負載結構的支撐件及其安裝方法及安裝方法使用的樁及護套、以及安裝支撐件的樁引導框架

Similar Documents

Publication Publication Date Title
CN102587405A (zh) 海上风机导管架基础安装方法及分离式导管架装置
CN102535510A (zh) 海上风机导管架基础安装方法及一体化导管架装置
AU2007202274B2 (en) Method and apparatus for wind power foundation
CN206034408U (zh) 用于海上升压站的后插桩式导管架结构
CN103233481B (zh) 一种可灌浆连接的导管架支撑结构
CN102777333A (zh) 桁架式风力发电机组结构
CN202732247U (zh) 桁架式海上风力发电机组基础结构
JP3764643B2 (ja) 洋上風力発電装置の基礎構造
CN104631338A (zh) 一种钢吊箱及定位施工方法
CN202440828U (zh) 分离式导管架装置
CN204824319U (zh) 一种便于固定和安装的水体曝气装置
CN202466618U (zh) 一体化导管架装置
CN202543954U (zh) 一种海上风电风机多角架基础
CN206052761U (zh) 一种海上风电场单桩基础
CN103088801A (zh) 海上风力发电机及桩基一次整体安装平台
CN106013213B (zh) 一种可增加单机容量的海上风电桩基础及其使用方法
KR101383159B1 (ko) 암반 설치용 중력식 해상풍력 기초 슬래브
CN105256760B (zh) 堤坝渗透性试验模拟器动水装置
CN103410677A (zh) 带吸力式沉箱的单桩固定式垂直轴风电机
CN204803907U (zh) 一种海上风电钢构重力式风机基础
CN104476055B (zh) 一种米字型撑管的桩腿制作方法
CN205224074U (zh) 水上发电设备及其安装基础
CN105672317A (zh) 水下导管架打桩内插式定位装置
CN103277262A (zh) 一种海上风力发电机组基础结构
CN213420117U (zh) 一种用于水利水电埋管的固定装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120704