CN102535349B - 双层围挡断流水下修筑系梁承力梁建桥方法 - Google Patents

双层围挡断流水下修筑系梁承力梁建桥方法 Download PDF

Info

Publication number
CN102535349B
CN102535349B CN201210071412.5A CN201210071412A CN102535349B CN 102535349 B CN102535349 B CN 102535349B CN 201210071412 A CN201210071412 A CN 201210071412A CN 102535349 B CN102535349 B CN 102535349B
Authority
CN
China
Prior art keywords
enclosing
bearing beam
binder
double
enclosing barrier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210071412.5A
Other languages
English (en)
Other versions
CN102535349A (zh
Inventor
李晓明
于景武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chifeng Acer building (Group) Co. Ltd.
Original Assignee
Chifeng Acer Building (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chifeng Acer Building (group) Co Ltd filed Critical Chifeng Acer Building (group) Co Ltd
Priority to CN201210071412.5A priority Critical patent/CN102535349B/zh
Publication of CN102535349A publication Critical patent/CN102535349A/zh
Application granted granted Critical
Publication of CN102535349B publication Critical patent/CN102535349B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明的双层围挡断流水下修筑系梁承力梁建桥方法,属于桥梁建造,其包括桥墩、系梁、承力梁、内围挡、外围挡、围挡板、围挡固定桩、稳定支撑、斜拉索和拉索固定桩锚。其特征是在双层围挡断流的平静水面环境下水下修筑系梁和承力梁。本发明与现有技术相比,搭建围挡技术含量低,搭建和清除,简单、快捷、较少动用土方,工期短、成本低,对河床形态和河道生态环境影响小,双层围挡断流而不断水,围挡内、中、外水面持平,压力相等,挖掘沟槽不会滑坡及坍塌,施工安全,应用技术成熟,因此,本发明的双层围挡断流水下修筑系梁承力梁建桥方法具有很好的推广应用价值。

Description

双层围挡断流水下修筑系梁承力梁建桥方法
一、技术领域:
本发明涉及桥梁建造,具体的说是一种双层围挡断流水下修筑系梁承力梁建桥方法。
二、背景技术:
现有技术下桥梁的系梁、承力梁修筑,通常采用筑坝断流,抽水挖槽,搭模灌注,清理河床程序实现,这种程序修筑系梁,承力梁,施工现场清理彻底,在直视无障碍情况下作业,方便施工和保证施工质量,但是也存在许多问题和不足。第一,筑坝断流和完工后清理河床,需搬动大量土方完成,工期长,成本高。第二,水中河床上填土筑坝,牢固度差,坝壁易滑坡坍塌,不但常为施工增添障碍和麻烦,也凭添许多安全隐患。第三,流中水筑坝填土,土方流失多,完工后清理河床麻烦且不易彻底,散落土方抬高河床,对河道原有状态和生态影响大。
三、发明内容:
本发明的目的是针对以上不足和风险,提供一种工期短、成本低、环保安全、能够保证施工要求的双层围挡断流水下修筑系梁承力梁建桥方法。
本发明的技术任务是通过以下技术方案实现的:
一种双层围挡断流水下修筑系梁承力梁建桥方法,其包括桥墩、系梁、承力梁、内围挡、外围挡、围挡板、围挡固定桩、稳定支撑、斜拉索和拉索固定桩锚,其特征是由围挡固定桩、稳定支撑、斜拉索、拉索固定桩锚和围挡板组成的内围挡和外围挡阻隔,使围挡内形成相对静止的死水区,由内围挡阻隔在内围挡内挖掘系梁、承力梁坑槽后,在平静的水下搭模修筑系梁、承力梁。
所述的双层围挡断流水下修筑系梁承力梁建桥方法,其特征是内围挡兼作系梁、承力梁模板,清挖后在内围挡内构筑系梁、承力梁砼体。
所述的双层围挡断流水下修筑系梁承力梁建桥方法,其特征是在内围挡与外围挡之间填土断水,内围挡内抽水,挖掘系梁、承力梁沟槽,直视下搭模灌注,构筑系梁和承力梁砼体。
本发明的双层围挡断流水下修筑系梁承力建桥方法与现有技术相比,具有以下显著优点:
1、双层围挡断流而不断水,围挡内、中、外水面持平,压力相等,挖掘的系梁、承力梁沟槽不会滑坡及坍塌。水下灌注为现有成熟技术,能够满足系梁、承力梁的施工技术要求。
2、搭建围挡技术含量低,搭建和清除简单快捷,较少动用土方,工期短,成本低,对河床形态和河道生态环境影响小。
3、在内围挡与外围挡内填土代坝,抽水挖槽,直视下搭模灌注,可兼收并蓄现有技术和创新技术的优点。
因而,本发明有很好的推广使用价值。
四、附图说明
图1为双层围挡断流水下修筑系梁承力梁建桥方法的侧视断面示意图。
图2为双层围挡断流水下修筑系梁承力梁建桥方法的俯视平面示意图。
图中:1水面、2河床、3桥墩、4系梁、5承力梁、6内围挡、7外围挡、8围挡板、9围挡固定桩、10稳定支撑、11拉索固定桩锚、12斜拉索
五、具体实施例:
结合说明书附图对本发明的双层围挡断流水下修筑系梁承力梁建桥方法作以下详细说明:
如图1所示,本发明的双层围挡断流水下修筑系梁承力梁建桥方法包括桥墩3、系梁4、承力梁5、内围档6、外围挡7、围档板8、围档固定桩9、稳定支撑10、拉索固定桩锚11和斜拉索12。首先在环绕两个桥墩需建系梁4和承力梁5外围设置围挡固定桩9,围挡固定桩的上端应露出水面1、内围挡6的围挡固定桩9的深度超越所筑系梁4和承力梁5下底深度、外围挡7的围挡固定桩9的深度以使其稳固于河床2为准,在围挡固定桩9内侧设置围挡板8、内围挡6和外围挡7之间设置稳定支撑10、在外围挡7外侧设置抗拉力和抗拔力均佳的拉索固定桩锚11,并以斜拉索12连接外围挡7的围挡固定桩9、在内围挡6内挖掘河床2至所需深度、荡平后搭模筑砼。
除说明书所述的技术特征外,均为本专业技术人员的已知技术。

Claims (3)

1.一种双层围挡断流水下修筑系梁承力梁建桥方法,其包括桥墩、系梁、承力梁、内围挡、外围挡、围挡板、围挡固定桩、稳定支撑、斜拉索和拉索固定桩锚,其特征是由围挡固定桩、稳定支撑、斜拉索、拉索固定桩锚和围挡板组成的内围挡和外围挡阻隔,使围挡内形成相对静止的死水区,由内围挡阻隔,在内围挡内挖掘系梁、承力梁坑槽后,在平静的水下修筑系梁、承力梁。
2.根据权利要求1所述的双层围挡断流水下修筑系梁承力梁建桥方法,其特征是内围挡兼作系梁、承力梁模板,清挖后在内围挡内构筑系梁、承力梁砼体。
3.根据权利要求1所述的双层围挡断流水下修筑系梁承力梁建桥方法,其特征是在内围挡与外围挡之间填土断水,内围挡内抽水,挖掘系梁、承力梁沟槽,直视下搭模灌注,构筑系梁和承力梁砼体。
CN201210071412.5A 2012-03-19 2012-03-19 双层围挡断流水下修筑系梁承力梁建桥方法 Active CN102535349B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210071412.5A CN102535349B (zh) 2012-03-19 2012-03-19 双层围挡断流水下修筑系梁承力梁建桥方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210071412.5A CN102535349B (zh) 2012-03-19 2012-03-19 双层围挡断流水下修筑系梁承力梁建桥方法

Publications (2)

Publication Number Publication Date
CN102535349A CN102535349A (zh) 2012-07-04
CN102535349B true CN102535349B (zh) 2014-03-05

Family

ID=46343255

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210071412.5A Active CN102535349B (zh) 2012-03-19 2012-03-19 双层围挡断流水下修筑系梁承力梁建桥方法

Country Status (1)

Country Link
CN (1) CN102535349B (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB208620A (en) * 1922-10-28 1923-12-27 Francis Gascoigne Lynde Improvements in and relating to caissons, coffer dams, platforms and the like
FR1316341A (fr) * 1962-02-28 1963-01-25 Procédé destiné à la construction des fondations d'ouvrages au-dessous du niveau de la nappe liquide dans une fouille asséchée
CN101074561A (zh) * 2006-05-19 2007-11-21 中船第九设计研究院 一种水中大直径圆形钢板桩围堰及其施工方法
CN101205720A (zh) * 2007-12-05 2008-06-25 中铁大桥局股份有限公司 一种超大型钢围堰下放、着床、下沉控制技术
CN201254727Y (zh) * 2008-09-09 2009-06-10 武汉武大巨成加固实业有限公司 桥梁桩柱水下维修施工围堰
CN201883444U (zh) * 2010-11-11 2011-06-29 中铁十三局集团有限公司 水中低桩承台双壁钢围堰

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB208620A (en) * 1922-10-28 1923-12-27 Francis Gascoigne Lynde Improvements in and relating to caissons, coffer dams, platforms and the like
FR1316341A (fr) * 1962-02-28 1963-01-25 Procédé destiné à la construction des fondations d'ouvrages au-dessous du niveau de la nappe liquide dans une fouille asséchée
CN101074561A (zh) * 2006-05-19 2007-11-21 中船第九设计研究院 一种水中大直径圆形钢板桩围堰及其施工方法
CN101205720A (zh) * 2007-12-05 2008-06-25 中铁大桥局股份有限公司 一种超大型钢围堰下放、着床、下沉控制技术
CN201254727Y (zh) * 2008-09-09 2009-06-10 武汉武大巨成加固实业有限公司 桥梁桩柱水下维修施工围堰
CN201883444U (zh) * 2010-11-11 2011-06-29 中铁十三局集团有限公司 水中低桩承台双壁钢围堰

Also Published As

Publication number Publication date
CN102535349A (zh) 2012-07-04

Similar Documents

Publication Publication Date Title
CN104695380B (zh) 一种塑钢板桩与混凝土组合的护岸结构
CN102677592B (zh) 在浅海裸露基岩上搭设深水钢栈桥及平台的方法
CN103422510B (zh) 钢管框架式围堰结构及施工方法
CN205314116U (zh) 一种复合式连续型钻孔抗滑结构
CN202220341U (zh) 一种淤泥中基坑的支护结构
CN104404949A (zh) 一种树根形灌注桩
CN101824825A (zh) 一种深基坑明挖施工方法
CN202969370U (zh) 一种新型钢管桩
CN102535349B (zh) 双层围挡断流水下修筑系梁承力梁建桥方法
CN204645058U (zh) 一种设有加芯旋喷桩的h型双排桩结构
CN204212161U (zh) 基坑支护斜钢顶撑体系
CN217517602U (zh) 近江堤基坑支护结构
CN203741852U (zh) 一种管式地下水排渗盲沟
CN202430742U (zh) 预制板组装挡土墙
CN103967033A (zh) 一种水电站厂房地基处理方法
CN210887256U (zh) 挡水围堰平直组合板桩地连墙式框架
CN103866787A (zh) 一种敞挖逆筑法混凝土防渗墙建造施工工艺
CN103938585A (zh) 土坝+重力坝混合坝型的布置结构
CN203924005U (zh) 水域泥炭质土层中的填土筑坝结构
CN203603162U (zh) 一种位于基坑边的施工电梯荷载基础系统
CN102704489B (zh) 基坑支护结构及其建造方法
CN203741782U (zh) 一种高面板堆石坝多段面板结构
CN202705883U (zh) 在浅海裸露基岩上搭设的深水钢栈桥及平台
CN204875665U (zh) 用于中等厚度砂砾石基础上的电站尾水渠挡墙
CN202530450U (zh) 一种柔性桩与刚性桩上下同体组合桩

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHIFENG HONGJI BUILDING (GROUP) CO., LTD.

Free format text: FORMER OWNER: DONG LANTIAN

Effective date: 20140117

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Li Xiaoming

Inventor after: Yu Jingwu

Inventor before: Wang Weikai

Inventor before: Li Lei

Inventor before: Dong Na

Inventor before: Dong Tingting

Inventor before: Dong Lantian

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: WANG WEIKAI LI LEI DONG NA DONG TINGTING DONG LANTIAN TO: LI XIAOMING YU JINGWU

Free format text: CORRECT: ADDRESS; FROM: 250013 JINAN, SHANDONG PROVINCE TO: 024005 CHIFENG, INNER MONGOLIA AUTONOMOUS REGION

TA01 Transfer of patent application right

Effective date of registration: 20140117

Address after: The northern section of Songshan District, Chifeng city the Inner Mongolia Autonomous Region road 024005 English

Applicant after: Chifeng Acer building (Group) Co. Ltd.

Address before: 250013 Shandong Province, Lixia District of Ji'nan City Luo River District 8 Building 4 unit 301 room

Applicant before: Dong Lantian

GR01 Patent grant
GR01 Patent grant