CN102494421B - Guide rail installation frame - Google Patents
Guide rail installation frame Download PDFInfo
- Publication number
- CN102494421B CN102494421B CN2011103920187A CN201110392018A CN102494421B CN 102494421 B CN102494421 B CN 102494421B CN 2011103920187 A CN2011103920187 A CN 2011103920187A CN 201110392018 A CN201110392018 A CN 201110392018A CN 102494421 B CN102494421 B CN 102494421B
- Authority
- CN
- China
- Prior art keywords
- hole
- installation frame
- guide rail
- rail installation
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24S—SOLAR HEAT COLLECTORS; SOLAR HEAT SYSTEMS
- F24S25/00—Arrangement of stationary mountings or supports for solar heat collector modules
- F24S25/10—Arrangement of stationary mountings or supports for solar heat collector modules extending in directions away from a supporting surface
- F24S25/12—Arrangement of stationary mountings or supports for solar heat collector modules extending in directions away from a supporting surface using posts in combination with upper profiles
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24S—SOLAR HEAT COLLECTORS; SOLAR HEAT SYSTEMS
- F24S25/00—Arrangement of stationary mountings or supports for solar heat collector modules
- F24S25/60—Fixation means, e.g. fasteners, specially adapted for supporting solar heat collector modules
- F24S25/65—Fixation means, e.g. fasteners, specially adapted for supporting solar heat collector modules for coupling adjacent supporting elements, e.g. for connecting profiles together
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/40—Solar thermal energy, e.g. solar towers
- Y02E10/47—Mountings or tracking
Abstract
The invention relates to a guide rail installation frame, which comprises a transverse beam, a bracket and a connecting piece for connecting the transverse beam with the bracket, wherein support frames are symmetrically arranged on both sides of the transverse beam; the bracket consists of a first bent pipe, a second bent pipe and a support post; and the lower parts of the first bent pipe and the second bent pipe are placed into the support post respectively, and are detachably connected with the support post. The guide rail installation frame has a simple structure and high practicability; the load bearing area of the transverse beam on the installation frame is increased, the bearing capacity of the installation frame is increased, the stability of the installation frame is ensured, and the service life of the installation frame is prolonged; meanwhile, the support post on the installation frame is vertical, so that a floor area is small when the guide rail installation frame is in use, the combination stability between the bent pipe and the support post is high, an overall structure is enhanced, and materials are saved; and the support angle of the installation frame can be changed, so that energy is collected by using a solar panel on a guide rail to the maximum extent.
Description
Technical field
The present invention relates to a kind of installing rack for support rails.
Background technology
Installing rack, as a kind of support member, is widely used in every field, such as being used for the carrying solar panels.Existing installing rack can not support normally under the environment of motion or shake, and lifting surface area is little, and total holding capacity is large, and easily distortion causes discontinuity and the danger that comes off is arranged.In addition, existing installing rack is generally stationary structure, can not carry out the adjusting of angle and height, in order better to utilize solar energy, first fixed guide on installing rack, afterwards solar panels are fixed on guide rail, because installing rack can not carry out the adjusting of angle, solar panels are unadjustable with respect to the angle on ground, and the energy collecting effect is restricted, the utilization rate of solar energy is low, can not give full play to the effect of solar panels.
Summary of the invention
The present invention has overcome the deficiencies in the prior art, and a kind of guide rail installation frame simple in structure is provided.
For achieving the above object, the technical solution used in the present invention is: a kind of guide rail installation frame, the connector that comprises crossbeam, support and connecting cross beam and support, the bilateral symmetry of described crossbeam is equipped with bracing frame, described support is comprised of the first bend pipe, the second bend pipe, pillar, and the bottom of described the first bend pipe, the second bend pipe is inserted respectively in described pillar and with described pillar, removably connected.
In a preferred embodiment of the present invention, guide rail installation frame comprises that further described crossbeam is the hollow structure that cross section is square, and comprises upper supporting plate, lower carrier plate and biside plate along its length.
In a preferred embodiment of the present invention, guide rail installation frame further comprises on described upper supporting plate the first through hole that has kidney-shaped, corresponding the second through hole that has kidney-shaped on described lower carrier plate, the symmetrical third through-hole that has kidney-shaped respectively on described biside plate.
In a preferred embodiment of the present invention, guide rail installation frame further comprises the width of the width of described the first through hole greater than described the second through hole.
In a preferred embodiment of the present invention, guide rail installation frame comprises that further the quantity of described the first through hole, the second through hole is two, and the quantity of described third through-hole is four.
In a preferred embodiment of the present invention, guide rail installation frame comprises that further the quantity of support frame as described above is four, vertically disposed transverse plate and vertical plate, consists of, and has the fourth hole of kidney-shaped on described transverse plate, has square through hole on described vertical plate.
In a preferred embodiment of the present invention, guide rail installation frame comprises that further described column section is I-shaped, comprises two parallel long shaped plates and perpendicular to the intermediate plate of described long shaped plate, described long shaped plate and described intermediate plate surround the longitudinal fluting of two symmetries.
In a preferred embodiment of the present invention, guide rail installation frame further comprises on described two long shaped plates fifth hole and the 6th through hole that is respectively equipped with the evenly distributed kidney-shaped of two row.
In a preferred embodiment of the present invention, guide rail installation frame further comprises the 7th through hole that top, the bottom of described the first bend pipe have the first pin-and-hole, with described fifth hole, match, the 8th through hole that the top of described the second bend pipe, bottom have the second pin-and-hole, with described the 6th through hole, match.
In a preferred embodiment of the present invention, guide rail installation frame comprises that further described connector is a shape, comprises two parallel risers and the substrate that connects two risers, has the 3rd pin-and-hole on described two risers, has manhole on described substrate.
The invention solves the defect that exists in background technology, the present invention is simple in structure, practical, increased the load-bearing area of installing rack entablature, improved the bearing capacity of installing rack, guaranteed the stability of installing rack, improved the service life of installing rack, pillar on installing rack is vertical simultaneously, during use, floor space is little, the combinative stability of bend pipe and pillar is good, has strengthened overall structure, has saved material, can the support angle of installing rack be changed, realized the energy collecting to greatest extent of the solar panels on the guide rail.
Description of drawings
The present invention is further described below in conjunction with drawings and Examples.
Fig. 1 is the structural representation of the preferred embodiments of the present invention;
Fig. 2 is the decomposition texture schematic diagram of Fig. 1;
Fig. 3 is the syndeton schematic diagram of crossbeam and bracing frame;
Fig. 4 is the top view of crossbeam;
Fig. 5 is the structural representation of support;
Fig. 6 is the enlarged diagram of B in Fig. 5;
Fig. 7 is the structural representation of connector;
in figure: 1, crossbeam, 2, support, 3, connector, 4, bracing frame, 5, the first bend pipe, 6, the second bend pipe, 7, pillar, 8, upper supporting plate, 9, lower carrier plate, 10, side plate, 11, the first through hole, 12, the second through hole, 13, third through-hole, 14, transverse plate, 15, vertical plate, 16, fourth hole, 17, square through hole, 18, elongated hole, 19, intermediate plate, 20, longitudinal fluting, 21, longitudinal fluting, 22, fifth hole, 23, the 6th through hole, 24, the 7th through hole, 25, the 8th through hole, 26, riser, 27, substrate, 28, the first pin-and-hole, 29, the second pin-and-hole, 30, the 3rd pin-and-hole, 31, manhole, 32, square neck bolt.
The specific embodiment
The present invention is further detailed explanation in conjunction with the accompanying drawings and embodiments now, and these accompanying drawings are the schematic diagram of simplification, basic structure of the present invention only is described in a schematic way, so it only shows the formation relevant with the present invention.
as Fig. 1, Fig. 2, shown in Figure 3, a kind of guide rail installation frame, comprise crossbeam 1, the connector 3 of support 2 and connecting cross beam 1 and support 2, the bilateral symmetry of described crossbeam 1 is equipped with bracing frame 4, described support 2 is by the first bend pipe 5, the second bend pipe 6, pillar 7 forms, described the first bend pipe 5, the bottom of the second bend pipe 6 is inserted respectively in described pillar 7 and with described pillar 7, is removably connected, but be not limited to this kind mode, can also make the first bend pipe 5 be fixed into integrative-structure with pillar 7, the second bend pipe 6 removably connects with this integrative-structure or makes the second bend pipe 6 be fixed into integrative-structure with pillar 7, the first bend pipe 5 removably connects with this integrative-structure.
As shown in Figure 3, described crossbeam 1 is the hollow structure that cross section is square, and comprises upper supporting plate 8, lower carrier plate 9 and biside plate along its length 10.Wherein, have the first through hole 11 of two kidney-shapeds on upper supporting plate 8, corresponding the second through hole 12 that has two kidney-shapeds on described lower carrier plate 9, the symmetrical third through-hole 13 that has four kidney-shapeds respectively on described biside plate 10, be convenient to install bracing frame 4 and connector 3, can carry out locational trickle adjustment simultaneously.
As shown in Figure 4, the width of described the first through hole 11 is greater than the width of described the second through hole 12.When screwdriver was screwed into the second through hole 12 with screw from the first through hole 11, screw can be inserted in the first through hole 11 fully, makes the length of screw reduce, and has reduced production cost and installer's labour intensity, has improved operating efficiency.
In order to increase the load-bearing area of crossbeam 1, improve the bearing capacity of crossbeam 1, the quantity of support frame as described above 4 is four, vertically disposed transverse plate 14 and vertical plate 15, consists of, have the fourth hole 16 of kidney-shaped on described transverse plate 14, have square through hole 17 on described vertical plate 15.Can pass square through hole 17 by a square neck bolt 32, third through-hole 13 is fixed on bracing frame 4 on side plate 10, reduce erecting tools, improved installation effectiveness, guide rail can be fixed on bracing frame 4 by fourth hole 16, avoid the high-low side that causes due to installation dimension, further guaranteed availability and stability.
As shown in Figure 5, Figure 6, described pillar 7 cross sections are I-shaped, comprise two parallel long shaped plates 18 and perpendicular to the intermediate plate 19 of described long shaped plate 18, and described long shaped plate 18 and described intermediate plate 19 surround the longitudinal fluting 20,21 of two symmetries.Simultaneously, be respectively equipped with fifth hole 22 and the 6th through hole 23 of the evenly distributed kidney-shaped of two row on two long shaped plates 18, the 8th through hole 25 that the 7th through hole 24 that the top of described the first bend pipe 5, bottom have the first pin-and-hole 28, with described fifth hole 22, match, the top of described the second bend pipe 6, bottom have the second pin-and-hole 29, with described the 6th through hole 23, match.when being fixed, with the first bend pipe 5, longitudinal fluting 20 is inserted respectively in the bottom of the second bend pipe 6, in 21, can pass fifth hole 22 by a plurality of screws, the 7th through hole 24 and the 6th through hole 23, the 8th through hole 25 is with the first bend pipe 5, the second bend pipe 6 is fixed on pillar 7 and makes the three connect into an integral body, if this moment, loosening screw can be regulated the first bend pipe 5 or the height of the second bend pipe 6 in pillar 7, angle A between crossbeam 1 and the first bend pipe 5 is also along with change, realize the adjusting of the solar panels angle on the guide rail of placing on crossbeam 1, reach energy collecting to greatest extent.
As shown in Figure 7, described connector 3 is a shape, comprises two parallel risers 26 and the substrate 27 that connects two risers 26, has the 3rd pin-and-hole 30 on described two risers 26, has manhole 31 on described substrate 27.Can pass the first through hole 11, the second through hole 12, manhole 31 by screw is fixed on connector 3 on crossbeam 1, simultaneously the top of the top of the first bend pipe 5, the second bend pipe 6 is inserted in connector 3, passed the 3rd pin-and-hole 30, the first pin-and-hole 28 and the 3rd pin-and-hole 30, the second pin-and-hole 29 by bearing pin crossbeam 1 and support 2 are coupled together.
Above foundation desirable embodiment of the present invention is enlightenment, and by above-mentioned description, the related personnel can in the scope that does not depart from this invention technological thought, carry out various change and modification fully.The technical scope of this invention is not limited to the content on specification, must determine technical scope according to the claim scope.
Claims (10)
1. guide rail installation frame, it is characterized in that: the connector that comprises crossbeam, support and connecting cross beam and support, the bilateral symmetry of described crossbeam is equipped with bracing frame, described support is comprised of the first bend pipe, the second bend pipe, pillar, and the bottom of described the first bend pipe, the second bend pipe is inserted respectively in described pillar and with described pillar, removably connected.
2. guide rail installation frame according to claim 1, it is characterized in that: described crossbeam is the hollow structure that cross section is square, and comprises upper supporting plate, lower carrier plate and biside plate along its length.
3. guide rail installation frame according to claim 2 is characterized in that: have the first through hole of kidney-shaped on described upper supporting plate, corresponding the second through hole that has kidney-shaped on described lower carrier plate, the symmetrical third through-hole that has kidney-shaped respectively on described biside plate.
4. guide rail installation frame according to claim 3, it is characterized in that: the width of described the first through hole is greater than the width of described the second through hole.
5. guide rail installation frame according to claim 3, it is characterized in that: the quantity of described the first through hole, the second through hole is two, and the quantity of described third through-hole is four.
6. guide rail installation frame according to claim 1, it is characterized in that: the quantity of support frame as described above is four, vertically disposed transverse plate and vertical plate, consists of, and has the fourth hole of kidney-shaped on described transverse plate, has square through hole on described vertical plate.
7. guide rail installation frame according to claim 1, it is characterized in that: described column section is I-shaped, comprise two parallel long shaped plates and perpendicular to the intermediate plate of described long shaped plate, described long shaped plate and described intermediate plate surround the longitudinal fluting of two symmetries.
8. guide rail installation frame according to claim 7, is characterized in that: the fifth hole and the 6th through hole that are respectively equipped with the evenly distributed kidney-shaped of two row on described two long shaped plates.
9. guide rail installation frame according to claim 8, it is characterized in that: the 8th through hole that the 7th through hole that the top of described the first bend pipe, bottom have the first pin-and-hole, with described fifth hole, match, the top of described the second bend pipe, bottom have the second pin-and-hole, with described the 6th through hole, match.
10. guide rail installation frame according to claim 1, it is characterized in that: described connector is a shape, comprises two parallel risers and the substrate that connects two risers, has the 3rd pin-and-hole on described two risers, has manhole on described substrate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103920187A CN102494421B (en) | 2011-12-01 | 2011-12-01 | Guide rail installation frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103920187A CN102494421B (en) | 2011-12-01 | 2011-12-01 | Guide rail installation frame |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102494421A CN102494421A (en) | 2012-06-13 |
CN102494421B true CN102494421B (en) | 2013-11-13 |
Family
ID=46186265
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011103920187A Active CN102494421B (en) | 2011-12-01 | 2011-12-01 | Guide rail installation frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102494421B (en) |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4300530A (en) * | 1980-03-24 | 1981-11-17 | Tetirick Jack E | Solar heat control apparatus for a body of water |
CN201820766U (en) * | 2010-06-21 | 2011-05-04 | 鸿富锦精密工业(深圳)有限公司 | Solar photovoltaic panel mounting bracket |
CN201837130U (en) * | 2010-10-08 | 2011-05-18 | 盛林君 | Installation bracket of split solar energy thermal collector |
CN202049974U (en) * | 2011-06-09 | 2011-11-23 | 浙江力源光伏科技有限公司 | Solar panel support feet and track connecting structure |
CN202393059U (en) * | 2011-12-01 | 2012-08-22 | 苏州瑞得恩光能科技有限公司 | Guide rail installation rack |
-
2011
- 2011-12-01 CN CN2011103920187A patent/CN102494421B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN102494421A (en) | 2012-06-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207260360U (en) | A kind of Anti-seismic building structure | |
CN102800722A (en) | All-aluminium solar stand | |
CN202268359U (en) | Support for fixedly installing solar photovoltaic assemblies on flat roof | |
CN101949187B (en) | Force bearing device three-dimensionally adjusted and positioned by unitized curtain wall | |
CN202393059U (en) | Guide rail installation rack | |
CN102494421B (en) | Guide rail installation frame | |
CN203509580U (en) | Mounting structure for tool changer of vertical machining centre | |
CN206873724U (en) | A kind of freely adjustable support component | |
CN102832277B (en) | Support and support group of solar cell panel | |
CN202259336U (en) | Guide-rail sectional material | |
CN202839638U (en) | All-aluminum solar support | |
CN209488489U (en) | Flexible photovoltaic bracket | |
CN203428765U (en) | Hoist trolley and crane using same | |
CN208088657U (en) | A kind of truss structure | |
CN203810679U (en) | Screw rod parallel unit frame and screw rod parallel unit with same | |
CN202393058U (en) | Angle-adjustable Y-shaped rack | |
CN204847705U (en) | Sedan -chair frame structure of no entablature | |
CN202839657U (en) | Support of solar cell panel and support set of solar cell panel | |
CN202392366U (en) | Support crossbeam | |
CN219068122U (en) | Photovoltaic bracket for communication tower base station | |
CN216866087U (en) | House reinforcing structure | |
CN202658421U (en) | Gantry frame of embroidery machine | |
CN209134332U (en) | A kind of photovoltaic module support frame | |
CN202706223U (en) | Z-shaped keel floor hanging component | |
CN203103763U (en) | Power distributing cabinet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |