CN102479188A - Electric energy quality data acquisition method - Google Patents

Electric energy quality data acquisition method Download PDF

Info

Publication number
CN102479188A
CN102479188A CN2010105554922A CN201010555492A CN102479188A CN 102479188 A CN102479188 A CN 102479188A CN 2010105554922 A CN2010105554922 A CN 2010105554922A CN 201010555492 A CN201010555492 A CN 201010555492A CN 102479188 A CN102479188 A CN 102479188A
Authority
CN
China
Prior art keywords
data
database
quality
pqview
power supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010105554922A
Other languages
Chinese (zh)
Other versions
CN102479188B (en
Inventor
王庆
何维国
奚永巍
董瑞安
曹文
刘隽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ELECTRIC POWER COMMUNICATION CO Ltd
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Original Assignee
Shanghai Jiulong Electric Power Technology Co Ltd
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiulong Electric Power Technology Co Ltd, Shanghai Municipal Electric Power Co filed Critical Shanghai Jiulong Electric Power Technology Co Ltd
Priority to CN201010555492.2A priority Critical patent/CN102479188B/en
Publication of CN102479188A publication Critical patent/CN102479188A/en
Application granted granted Critical
Publication of CN102479188B publication Critical patent/CN102479188B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses an electric energy quality data acquisition method. The method comprises the following steps of: acquiring data from a database based on PQView and importing the data to an electric energy quality intelligent information system, wherein the database based on PQView comprises event data and stable data stored in different tables. In the invention, the event data and the stable data are imported by adopting different tasks, data for one day is imported every time, the data importing time is delayed by 1-2 days than the ending time of the event data in the table and the ending time of the stable data, and importing ways include an automatic way and a manual way. By using the electric energy quality data acquisition method, data in the database based on PQView can be well acquired, and a basis for analyzing electric energy quality is provided.

Description

A kind of collecting method that is used for the quality of power supply
Technical field
The present invention relates to quality of power supply field, relate in particular to a kind of collecting method that is used for the quality of power supply.
Background technology
Along with the application of exact instrument and complex electronic equipment, the user more and more requires the supply of electrical energy of high-quality and high reliability.In recent years, along with the introduction of external sophisticated equipment and the development of application and electron trade, by power quality problem cause increasing unusually.
The quality of power supply (Power Quality) is said from universal significance to be meant quality supply, comprises quality of voltage, electric current quality, power supply quality and uses electricity quality.It can be defined as: cause the deviation of voltage, electric current or the frequency of consumer fault or cisco unity malfunction, its content comprises frequency departure, voltage deviation, voltage fluctuation and flicker, three-phase imbalance, temporary transient or transient overvoltage, wave form distortion (harmonic wave), voltage dip, interruption, rises and power supply continuity etc. temporarily.
In recent years along with rapid development of economy; Electric load increases swift and violent; Increasingly sophisticatedization of power load and variation, increasing non-linear, impact, the application apparatus that uneven harmonic is abundant insert electrical network in succession, all can have influence on the quality of power supply of power supply grid to some extent.Monitoring means imperfection and operation, extraneous interference and various failure and other reasons in addition, power quality problem becomes increasingly conspicuous.
At present; The database that all is based on PQView that a lot of Utilities Electric Co.s electric energy quality monitoring system adopts; PQView is the power quality analysis software of U.S.'s DianKeYuan development; How the many electric energy quality monitoring data of storage gather the data from this database in this database, are that the present inventor is devoted to the problem studying and solve.
Summary of the invention
The objective of the invention is to overcome the defective of prior art and a kind of collecting method that is used for the quality of power supply is provided, it can be good at collecting the data based in the database of PQView, and coming provides foundation for the analysis of the quality of power supply.
The technical scheme that realizes above-mentioned purpose is: a kind of collecting method that is used for the quality of power supply; This method be from based on image data the database of PQView and with this data importing in a quality of power supply intelligent information system; The event data and the steady state data that should comprise the table storage that branch is different based on the database of PQView wherein, adopt various tasks to import event data and steady state data; Each data that import a day; Event data concluding time and steady state data concluding time keep one to two day delay in the time of importing data and the table, and the mode of importing comprises automated manner and manual mode, wherein:
Described automated manner adopts the form of windows service, and service is carried out data acquisition and calculating according to configuration file automatically;
When gathering, having only the part monitoring point that data are arranged, the data of a part of check point are to join afterwards based in the database of PQView, at this moment, adopt manual mode to gather this part data again, and repeat computational data;
When using manual mode to carry out data acquisition and calculate, the date of system prompt source data and calculated date, the from date that user's input is recomputated, Close Date, and select to participate in again the monitoring point of calculating.
The above-mentioned collecting method that is used for the quality of power supply, wherein, in the described automated manner, the content of institute's configuration file comprises two parts, wherein:
The time range that database IP address, database-name, the service of part definition quality of power supply intelligent information system starts, the collection period and the double counting fate of harmonic data;
Another part configuration information is to based on the table of the database of PQView, confirm the table under the image data through the configuration of this part information, and the content that defines comprises the database table that will import.
The above-mentioned collecting method that is used for the quality of power supply wherein, when using manual mode to carry out data acquisition and calculate, when selecting to participate in the monitoring point of calculating again, can be selected several monitoring points simultaneously.
The invention has the beneficial effects as follows: the present invention periodically will be based on the data importing in the database of PQView in a quality of power supply intelligent information system; Through automatically and the mode that manually combines collected this based on the data in the database of PQView, for people provide the scientific decision foundation to the improvement of the quality of power supply.
Embodiment
To be described further the present invention below.
A kind of collecting method that is used for the quality of power supply; This method be from based on image data the database of PQView and with this data importing in a quality of power supply intelligent information system; The event data and the steady state data that should comprise the table storage that branch is different based on the database of PQView; The present invention adopts various tasks to import event data and steady state data, imports one day data at every turn, and event data concluding time and steady state data concluding time keep one to two day delay in the time of importing data and the table; The mode that imports comprises automated manner and manual mode, wherein:
Automated manner adopts the form of windows service; Service is carried out data acquisition and calculating according to configuration file automatically; In the automated manner; The content of institute's configuration file comprises two parts, wherein: the time range that database I P address, database-name, the service of part definition quality of power supply intelligent information system starts, the collection period and the double counting fate of harmonic data; Another part configuration information is to based on the table of the database of PQView, confirm the table under the image data through the configuration of this part information, and the content that defines comprises the database table that will import;
Automatically gathering with calculating is according to gathering based on the time in the database of PQView; The content time of gathering moves after gradually; When gathering, having only the part monitoring point that data are arranged, the data of a part of check point are to join afterwards based in the database of PQView, at this moment; Adopt manual mode to gather this part data again, and repeat computational data;
When using manual mode to carry out data acquisition and calculate; The date of system prompt source data and calculated date; The from date that user input is recomputated, Close Date, and select to participate in again the monitoring point of calculating; When selecting to participate in the monitoring point of calculating again, can select several monitoring points simultaneously.
Data acquisition should be unit with the sky, and method of the present invention is simple, and can effectively avoid repeated acquisition, generally has one to two day than the database based on PQView or more the delay.
More than combine embodiment that the present invention is specified, those skilled in the art can make the many variations example to the present invention according to above-mentioned explanation.Thereby some details among the embodiment should not constitute qualification of the present invention, and the scope that the present invention will define with appended claims is as protection scope of the present invention.

Claims (3)

1. collecting method that is used for the quality of power supply; This method be from based on image data the database of PQView and with this data importing in a quality of power supply intelligent information system; Should comprise the event data and the steady state data of the table storage that branch is different based on the database of PQView, it is characterized in that, and adopt various tasks to import event data and steady state data; Each data that import a day; Event data concluding time and steady state data concluding time keep one to two day delay in the time of importing data and the table, and the mode of importing comprises automated manner and manual mode, wherein:
Described automated manner adopts the form of windows service, and service is carried out data acquisition and calculating according to configuration file automatically;
When gathering, having only the part monitoring point that data are arranged, the data of a part of check point are to join afterwards based in the database of PQView, at this moment, adopt manual mode to gather this part data again, and repeat computational data;
When using manual mode to carry out data acquisition and calculate, the date of system prompt source data and calculated date, the from date that user's input is recomputated, Close Date, and select to participate in again the monitoring point of calculating.
2. the collecting method that is used for the quality of power supply according to claim 1 is characterized in that, in the described automated manner, the content of institute's configuration file comprises two parts, wherein:
The time range that database IP address, database-name, the service of part definition quality of power supply intelligent information system starts, the collection period and the double counting fate of harmonic data;
Another part configuration information is to based on the table of the database of PQView, confirm the table under the image data through the configuration of this part information, and the content that defines comprises the database table that will import.
3. the collecting method that is used for the quality of power supply according to claim 1 is characterized in that, when using manual mode to carry out data acquisition and calculate, when selecting to participate in the monitoring point of calculating again, can select several monitoring points simultaneously.
CN201010555492.2A 2010-11-23 2010-11-23 Electric energy quality data acquisition method Active CN102479188B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010555492.2A CN102479188B (en) 2010-11-23 2010-11-23 Electric energy quality data acquisition method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010555492.2A CN102479188B (en) 2010-11-23 2010-11-23 Electric energy quality data acquisition method

Publications (2)

Publication Number Publication Date
CN102479188A true CN102479188A (en) 2012-05-30
CN102479188B CN102479188B (en) 2014-04-09

Family

ID=46091838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010555492.2A Active CN102479188B (en) 2010-11-23 2010-11-23 Electric energy quality data acquisition method

Country Status (1)

Country Link
CN (1) CN102479188B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102938130A (en) * 2012-11-09 2013-02-20 内蒙古东部电力有限公司电力科学研究院 Comprehensive assessment method for performance indexes of power quality based on PQView
CN108596686A (en) * 2018-05-09 2018-09-28 珠海横琴盛达兆业科技投资有限公司 A method of realizing that chain partner drugstore management system and Foshan food medicine prison system data are integrated
CN108647362A (en) * 2018-05-21 2018-10-12 珠海横琴盛达兆业科技投资有限公司 A method of realizing that Mono-drugstore management system and Foshan food medicine prison system data are integrated

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201576059U (en) * 2009-11-13 2010-09-08 上海市电力公司 Access system of power-quality monitoring and analysis system

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201576059U (en) * 2009-11-13 2010-09-08 上海市电力公司 Access system of power-quality monitoring and analysis system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘小舟 等: "PQDIF在电能质量检测系统中的应用", 《华北电力技术》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102938130A (en) * 2012-11-09 2013-02-20 内蒙古东部电力有限公司电力科学研究院 Comprehensive assessment method for performance indexes of power quality based on PQView
CN108596686A (en) * 2018-05-09 2018-09-28 珠海横琴盛达兆业科技投资有限公司 A method of realizing that chain partner drugstore management system and Foshan food medicine prison system data are integrated
CN108647362A (en) * 2018-05-21 2018-10-12 珠海横琴盛达兆业科技投资有限公司 A method of realizing that Mono-drugstore management system and Foshan food medicine prison system data are integrated

Also Published As

Publication number Publication date
CN102479188B (en) 2014-04-09

Similar Documents

Publication Publication Date Title
Bracale et al. Site and system indices for power-quality characterization of distribution networks with distributed generation
Kairies et al. Scientific measuring and evaluation program for photovoltaic battery systems (WMEP PV-Speicher)
CN201789341U (en) Monitoring system of intelligent micro-grid
CN103746404B (en) A kind of honourable fiery bundling direct current delivery system method for estimating stability
CN204203354U (en) Line loss monitoring device
CN102938130A (en) Comprehensive assessment method for performance indexes of power quality based on PQView
CN102479284A (en) Calculation method of single sag characteristic quantity for power quality
CN101286635A (en) Synthetic monitoring method and device in medium-voltage power supply system
CN102467556B (en) Power quality intelligent information system and method
CN102479188B (en) Electric energy quality data acquisition method
CN201639302U (en) Programmable harmonic wave generating device
CN102467567A (en) Data acquiring and computing system for power quality
CN114140266A (en) Intelligent low-voltage power grid fault studying and judging algorithm
CN101707372A (en) Method for calculating and releasing rate of qualified power quality and voltage indexes
CN106849154B (en) Photovoltaic power station node harmonic voltage and harmonic source sensitivity relation analysis method
CN102467614A (en) Data collecting and calculating method for power quality
CN208782501U (en) A kind of double-fed wind power generator group
CN102005759A (en) System and method for acquiring electric power quality data from intelligent electric meter management system
CN105529740A (en) Method and system for evaluating flickering of wind power plant and wind power plant grid-connected part
CN201892971U (en) System for obtaining electric energy quality data from intelligent electric meter management system
CN102479285B (en) Calculation method for sag characteristic quantity of power quality
CN101718809B (en) System and method for acquiring power quality data
CN205544313U (en) High -pressure reactive power compensator of intelligence remote monitoring control
CN108667000B (en) Ferromagnetic resonance detection and suppression device for large photovoltaic power station
Luo et al. Pollution of renewable energies to the grid: Measured data and statistical analysis via large-scale urban power quality monitoring system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: SHANGHAI ELECTRIC POWER COMMUNICATION CO., LTD.

Free format text: FORMER OWNER: SHANGHAI JIULONG ELECTRIC SCIENCE + TECHNOLOGY CO., LTD.

Effective date: 20120625

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20120625

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant after: Shanghai Electric Power Corporation

Co-applicant after: Shanghai Electric Power Communication Co., Ltd.

Address before: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant before: Shanghai Electric Power Corporation

Co-applicant before: Shanghai Jiulong Electric Power Co., Ltd.

ASS Succession or assignment of patent right

Owner name: SHANGHAI ELECTRIC COMMUNICATION CO., LTD. STATE EL

Free format text: FORMER OWNER: SHANGHAI ELECTRIC COMMUNICATION CO., LTD.

Effective date: 20120911

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20120911

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant after: Shanghai Electric Power Corporation

Applicant after: Shanghai Electric Power Communication Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant before: Shanghai Electric Power Corporation

Applicant before: Shanghai Electric Power Communication Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant