CN102434227A - 一种发电机组超速保护系统 - Google Patents

一种发电机组超速保护系统 Download PDF

Info

Publication number
CN102434227A
CN102434227A CN2011104554972A CN201110455497A CN102434227A CN 102434227 A CN102434227 A CN 102434227A CN 2011104554972 A CN2011104554972 A CN 2011104554972A CN 201110455497 A CN201110455497 A CN 201110455497A CN 102434227 A CN102434227 A CN 102434227A
Authority
CN
China
Prior art keywords
generator set
air valve
rotating speed
generator
regulated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104554972A
Other languages
English (en)
Inventor
侯凯元
安宁
邵广惠
施浩波
徐兴伟
夏天
夏德明
徐希望
王钢
赵敏
贾伟
訾鹏
岳涵
吴远志
张健男
周莹
马新
李泽宇
刘家庆
马志民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NORTHEAST GRID CO Ltd
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
NORTHEAST GRID CO Ltd
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NORTHEAST GRID CO Ltd, China Electric Power Research Institute Co Ltd CEPRI filed Critical NORTHEAST GRID CO Ltd
Priority to CN2011104554972A priority Critical patent/CN102434227A/zh
Publication of CN102434227A publication Critical patent/CN102434227A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Control Of Eletrric Generators (AREA)
  • Control Of Turbines (AREA)

Abstract

本发明提供了一种发电机组超速保护系统,控制输出信号作用于发电机组调速器系统,控制发电机的中压调节汽阀、高压调节汽阀以及主气阀,所述保护系统设置逻辑控制单元。本发明提供的发电机组超速保护系统,根据发电机组超速保护系统的动作特性,对发电机组超速保护系统进行建模仿真有利于促进机网协调控制,进一步提高电网安全稳定运行水平。

Description

一种发电机组超速保护系统
技术领域
本发明属于电力系统安全稳定控制领域,具体涉及一种发电机组超速保护系统。
背景技术
电厂和电网是电力系统重要的构成部分,两者密不可分。电厂调速系统动作直接影响到发电机的出力,从而影响到系统的有功、频率等,进而影响到整个系统的运行状态。现有的发电机组超速保护系统(Over Speed Protect Controller,简称OPC)是一种抑制发电机组超速的保护控制系统,其作用是在发电机转速超过一定限制,或者功率不平衡率超过一定限制,抢断调节系统的控制权,强行将调节气阀短时关闭,经过一定的延时,转速控制交给调节系统,以避免转速过高。但是,在发电机组并网运行时,如果发电机组超速保护系统控制策略选择不当,不仅无法实现对发电机本身的超速保护,而且会使气阀频繁开关,产生“乓乓”现象,给机组轴系和热力系统造成频繁冲击,严重影响机组安全,甚至可能使电网大规模地甩负荷,发生频率振荡或频率失稳事故,最终造成整个电网崩溃。
发明内容
为克服上述缺陷,本发明提供了一种发电机组超速保护系统,根据发电机组超速保护系统的动作特性,对发电机组超速保护系统进行建模仿真有利于促进机网协调控制,进一步提高电网安全稳定运行水平。
为实现上述目的,本发明提供一种发电机组超速保护系统,控制输出信号作用于发电机组调速器系统,控制发电机的中压调节汽阀、高压调节汽阀以及主气阀;其改进之处在于,所述保护系统设置逻辑控制单元。
本发明提供的优选技术方案中,所述逻辑控制单元包括依次设置的中压调节气阀关闭模块、中高压调节气阀延迟关闭模块、中高压调节气阀快速关闭模块、气阀快速关闭模块和正常调节恢复模块。
本发明提供的第二优选技术方案中,所述中压调节气阀关闭模块,当发电机组转速达到发电机超速保护系统启动定值时快速关闭中压调节汽阀。
本发明提供的第三优选技术方案中,所述中高压调节气阀延迟关闭模块,根据判断条件,快速关闭中压调节汽阀并延迟Δt1关闭高压调节汽阀;其中,Δt1为关闭高压调节汽阀所需的延迟时间。
本发明提供的第四优选技术方案中,所述判断条件为以下两种:(1).在发电机组转速大于发电机超速保护系统启动定值小于107%n0,且功率不平衡率大于设定的功率不平衡率;(2).发电机组转速大于发电机超速保护系统启动定值小于107%n0,且转速增长速率超过设定的转速增长速率。
本发明提供的第五优选技术方案中,所述中高压调节气阀快速关闭模块,当发电机组转速处于107%n0<n<110%n0时,且功率不平衡率大于设定的功率不平衡率时或转速增长速率超过设定的转速增长速率时,快速关闭中压调节汽阀并快速关闭高压调节汽阀。
本发明提供的第六优选技术方案中,所述气阀快速关闭模块,当发电机组转速大于110%n0时,快速关闭调节气阀和主气阀。
本发明提供的第七优选技术方案中,所述正常调节恢复模块,在发电机组超速保护系统动作后,发电机组转速低于重开气阀定值时,延时Δt2使电磁阀复位,中高压调节气阀恢复至正常调节位;其中,Δt2为电磁阀复位所需的延迟时间。
本发明提供的第八优选技术方案中,n0为发电机组额定转速。
与现有技术比,本发明提供的一种发电机组超速保护系统,在电力系统机电暂态分析计算中建立了考虑发电机组中、高压调节气阀动作的发电机超速保护系统模型;该发电机超速保护系统的输出信号可以独立的控制发电机组的中压调节汽阀和高压调节汽阀,在紧急状态下快速控制主气阀,并可以根据机组实际情况设置合理的延时,这样可以在保证机组和电网安全的前提下有效的减少气阀的开闭,避免产生“乓乓”现象;该系统能够较为准确的反映发电机超速保护系统动作行为,扩展了机电暂态研究中对发电机超速保护系统的仿真分析,能够提升电力系统机电暂态仿真分析的准确性,为制定科学合理的电网安全稳定控制策略奠定了基础。
附图说明
图1为考虑发电机超速保护系统的发电机组功率控制示意图。
图2为发电机超速保护系统的逻辑控制环节示意图。
图3为发电机超速保护系统的设置界面。
图4为PMU实测发电机组转速与PSASP仿真对比曲线。
图5为PMU实测发电机组有功功率与PSASP仿真对比曲线。
具体实施方式
图1为考虑发电机超速保护系统的发电机组功率控制示意图,发电机超速保护系统的输出信号可以独立的控制发电机组的中压调节汽阀和高压调节汽阀,并在紧急状态下快速控制主气阀,输入信息包括发电机组转速、转速增长速率、功率不平衡率。
图2为发电机超速保护系统的逻辑控制环节示意图,包含6个逻辑控制规则:
规则1.发电机组转速达到发电机超速保护系统启动定值时快速关闭中压调节汽阀;
规则2.发电机组转速大于发电机超速保护系统启动定值小于107%n0,且功率不平衡率大于设定的功率不平衡率时,快速关闭中压调节汽阀并延迟Δt1关闭高压调节汽阀;
规则3.发电机组转速大于发电机超速保护系统启动定值小于107%n0,且转速增长速率超过设定的转速增长速率时,快速关闭中压调节汽阀并延迟Δt1关闭高压调节汽阀;
规则4.发电机组转速处于107%n0<n<110%n0,且功率不平衡率大于设定的功率不平衡率时或转速增长速率超过设定的转速增长速率时时,快速关闭中压调节汽阀并快速关闭高压调节汽阀;
规则5.发电机组转速大于110%n0,快速关闭调节气阀和主气阀;
规则6.发电机组超速保护系统动作后,发电机组转速低于重开气阀定值时,延时Δt2使电磁阀复位,中高压调节气阀恢复至正常调节位;
其中,假设n为发电机组转速,n0为机组额定转速,103%n0为发电机超速保护系统启动定值和重开气阀定值。
图3为电力系统分析综合程序(PSASP)的发电机超速保护系统的设置界面,该界面中可以设置发电机超速保护系统的的名称和编号、发电机超速保护系统启动定值和延时、重开气阀定值和延时、功率不平衡率以及转速增长速率,对应界面中继电器名称和继电器编号、OPC启动定值和延时、重开气阀定值和延时、功率不平衡率以及转速增长速率设置。
设置发电机超速保护系统启动定值为103%并延时Δt10.06s,重开气阀定值为103%并延时Δt20.06s;功率不平衡率为30%;转速增长速率为57.5r/min。
在东北电网数据基础上对霍林河1#机组装设超速保护,PMU实测发电机转速与基于电力系统分析综合程序(PSASP)仿真的发电机转速对比曲线如图4所示,横坐标为时间,图5为PMU实测发电机组有功功率与PSASP仿真对比曲线,横坐标为时间。从对比曲线可以看出,基于电力系统分析综合程序(PSASP)的仿真结果基本和PMU实测结果一致。
需要声明的是,本发明内容及具体实施方式意在证明本发明所提供技术方案的实际应用,不应解释为对本发明保护范围的限定。本领域技术人员在本发明的精神和原理启发下,可作各种修改、等同替换、或改进。但这些变更或修改均在申请待批的保护范围内。

Claims (9)

1.一种发电机组超速保护系统,控制输出信号作用于发电机组调速器系统,控制发电机的中压调节汽阀、高压调节汽阀以及主气阀;其特征在于,所述保护系统设置逻辑控制单元。
2.根据权利要求1所述的保护系统,其特征在于,所述逻辑控制单元包括依次设置的中压调节气阀关闭模块、中高压调节气阀延迟关闭模块、中高压调节气阀快速关闭模块、气阀快速关闭模块和正常调节恢复模块。
3.根据权利要求2所述的保护系统,其特征在于,所述中压调节气阀关闭模块,当发电机组转速达到发电机超速保护系统启动定值时快速关闭中压调节汽阀。
4.根据权利要求2所述的保护系统,其特征在于,所述中高压调节气阀延迟关闭模块,根据判断条件,快速关闭中压调节汽阀并延迟Δt1关闭高压调节汽阀;其中,Δt1为关闭高压调节汽阀所需的延迟时间。
5.根据权利要求4所述的保护系统,其特征在于,所述判断条件为以下两种:(1).在发电机组转速大于发电机超速保护系统启动定值小于107%n0,且功率不平衡率大于设定的功率不平衡率;(2).发电机组转速大于发电机超速保护系统启动定值小于107%n0,且转速增长速率超过设定的转速增长速率。
6.根据权利要求2所述的保护系统,其特征在于,所述中高压调节气阀快速关闭模块,当发电机组转速处于107%n0<n<110%n0时,且功率不平衡率大于设定的功率不平衡率时或转速增长速率超过设定的转速增长速率时,快速关闭中压调节汽阀并快速关闭高压调节汽阀。
7.根据权利要求2所述的保护系统,其特征在于,所述气阀快速关闭模块,当发电机组转速大于110%n0时,快速关闭调节气阀和主气阀。
8.根据权利要求2所述的保护系统,其特征在于,所述正常调节恢复模块,在发电机组超速保护系统动作后,发电机组转速低于重开气阀定值时,延时Δt2使电磁阀复位,中高压调节气阀恢复至正常调节位;其中,Δt2为电磁阀复位所需的延迟时间。
9.根据权利要求5、6、7所述的保护系统,其特征在于,n0为发电机组额定转速。
CN2011104554972A 2011-12-30 2011-12-30 一种发电机组超速保护系统 Pending CN102434227A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104554972A CN102434227A (zh) 2011-12-30 2011-12-30 一种发电机组超速保护系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104554972A CN102434227A (zh) 2011-12-30 2011-12-30 一种发电机组超速保护系统

Publications (1)

Publication Number Publication Date
CN102434227A true CN102434227A (zh) 2012-05-02

Family

ID=45982545

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104554972A Pending CN102434227A (zh) 2011-12-30 2011-12-30 一种发电机组超速保护系统

Country Status (1)

Country Link
CN (1) CN102434227A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103075206A (zh) * 2013-01-24 2013-05-01 广东电网公司电力调度控制中心 一种基于安全自动装置控制的火电机组超速保护方法
CN106194290A (zh) * 2016-07-08 2016-12-07 国网河南省电力公司电力科学研究院 一种适用于孤网/微网的火电机组opc策略优化方法
CN111175536A (zh) * 2020-03-03 2020-05-19 贵州电网有限责任公司 一种发电机组甩负荷测试系统及测试方法
CN112290587A (zh) * 2020-10-12 2021-01-29 辽宁红沿河核电有限公司 一种柴油发电机组的运行控制方法和调速控制器

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011019374A (ja) * 2009-07-10 2011-01-27 Toyo Electric Mfg Co Ltd 風力発電装置における過回転防止装置
CN102071978A (zh) * 2010-12-08 2011-05-25 广东电网公司电力科学研究院 一种汽轮机甩负荷工况下超速保护的方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011019374A (ja) * 2009-07-10 2011-01-27 Toyo Electric Mfg Co Ltd 風力発電装置における過回転防止装置
CN102071978A (zh) * 2010-12-08 2011-05-25 广东电网公司电力科学研究院 一种汽轮机甩负荷工况下超速保护的方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吴跃明: "汽轮发电机组在不同工况下控制能力分析", 《全国火电大机组竞赛第34届年会论文集》 *
吴锋: "茂名热电厂110kV系统小网运行分析及应对措施", 《广东电力》 *
徐衍会等: "调速系统超速保护控制对电力系统稳定的影响", 《现代电力》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103075206A (zh) * 2013-01-24 2013-05-01 广东电网公司电力调度控制中心 一种基于安全自动装置控制的火电机组超速保护方法
CN106194290A (zh) * 2016-07-08 2016-12-07 国网河南省电力公司电力科学研究院 一种适用于孤网/微网的火电机组opc策略优化方法
CN106194290B (zh) * 2016-07-08 2018-07-10 国网河南省电力公司电力科学研究院 一种适用于孤网/微网的火电机组opc策略优化方法
CN111175536A (zh) * 2020-03-03 2020-05-19 贵州电网有限责任公司 一种发电机组甩负荷测试系统及测试方法
CN112290587A (zh) * 2020-10-12 2021-01-29 辽宁红沿河核电有限公司 一种柴油发电机组的运行控制方法和调速控制器
CN112290587B (zh) * 2020-10-12 2022-08-12 辽宁红沿河核电有限公司 一种柴油发电机组的运行控制方法和调速控制器

Similar Documents

Publication Publication Date Title
Li et al. Wind power impact on system frequency deviation and an ESS based power filtering algorithm solution
CN102434227A (zh) 一种发电机组超速保护系统
CN102095582B (zh) 汽轮发电机组用测功法甩负荷试验累积做功时间测取方法
Xie et al. Long-term frequency stability assessment based on extended frequency response model
Jiang et al. An improved under frequency load shedding scheme based on rate of change of frequency
Wang et al. Control Method for Additional Damper in Hydro-turbine Speed Governor of Hydro-dominant Power Systems
CN208669360U (zh) 一种利用天然气压力能的发电装置
Fang et al. Modeling and simulation of hydraulic transients for hydropower plants
Wu et al. Simulation and optimization of load shedding scheme for islanded power system
Murat et al. Validation of hydroelectric power plant model for speed governor development studies
Papangelis et al. Design principles of wind turbine inertia emulators for autonomous systems
CN106451526B (zh) 孤网运行时汽轮机opc保护设置方法
Da-hai et al. Modeling and parameter measurement research pressurized water reactor nuclear power generator's prime mover and governor
Zhao et al. A comprehensive on-line voltage stability assessment method based on continuation power flow
Rogers Control for stability in interconnected power systems
Huang et al. Research on HVDC frequency limit control to improve frequency restoration in muti-HVDC asynchronous system
Yanhui et al. The resonance mechanism low frequency oscillations induced by nonlinear governor system
Yan et al. Research on governor parameter optimization to suppress ultra-low frequency oscillation of power system caused by hydropower unit
Yang et al. Research on Temporary Overvoltage in PMSG-based Wind Power Transmission System in case of Load Rejection
Fan et al. Frequency Emergency Control Strategy Considering the Operation Speed of Frequency Regulation resources
Lu et al. Research on frequency simulation model and control strategy of hydropower islands
Liu et al. Dynamic frequency simulation and study on turbine-generator including the effect of boiler and fuel system
Chen et al. Research on Unit Removal Method Under Islanding Operation of Small Hydropower Microgrid
Libin Analysis and Modeling Simulation of Power Oscillation in Thermal Power Plant
Guo et al. The analysis of the primary frequency regulation in electric power system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120502