CN102393022A - Temperature-adjusting baffle for boiler flue - Google Patents
Temperature-adjusting baffle for boiler flue Download PDFInfo
- Publication number
- CN102393022A CN102393022A CN2010106030765A CN201010603076A CN102393022A CN 102393022 A CN102393022 A CN 102393022A CN 2010106030765 A CN2010106030765 A CN 2010106030765A CN 201010603076 A CN201010603076 A CN 201010603076A CN 102393022 A CN102393022 A CN 102393022A
- Authority
- CN
- China
- Prior art keywords
- baffle
- backboard
- front apron
- temperature adjustment
- baffle plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Control Of Steam Boilers And Waste-Gas Boilers (AREA)
Abstract
The invention relates to a temperature-adjusting baffle for a boiler flue. The temperature-adjusting baffle comprises a front baffle and a rear baffle, wherein the front baffle is arranged in a front flue, the rear baffle is arranged in a rear flue, the front baffle and the rear baffle are respectively arranged in parallel to a left wall and a right wall, the front baffle and the rear baffle are coaxially coupled, the positions of the front baffle and the rear baffle are mutually vertical and fixed, and operations of the front baffle and the rear baffle can be controlled by a couple axle from a front wall or a rear wall. The temperature-adjusting baffle for the boiler flue provided by the invention has the advantages of simple for coupling, convenient for manufacture and installation, flexible for adjustment, better adaptability and good temperature-adjusting effect.
Description
Technical field
The present invention relates to a kind of boiler flue temperature adjustment baffle plate.
Background technology
Boiler technology constantly develops at present, and the capacity of domestic station boiler constantly enlarges, and in boiler operatiopn, is different from superheater system, and for the adjusting of reheater steam temperature, the method for most of now employing back-end ductwork temperature adjustment baffle plate is regulated.
Because present boiler (coal-powder boiler and recirculating fluidized bed CFB) the continuous cause of increased of capacity; The cross section of boiler back end ductwork also constantly increases, and more and more wideer, the smoke distribution non-uniform phenomenon is serious all the more; In actual moving process, we find that reheater local overheating phenomenon happens occasionally; In addition, present temperature adjustment shutter configuration is the temperature control panel that laterally arranges with front-back wall, because the flue width between the front-back wall is bigger; Generally therefrom separate, the wall control from the left and right sides is simultaneously outside flue; There is interlock that the backboard of the front apron of reheater side and superheater side is coupled together operation simultaneously, like this, increased technology manufacturing and field erected difficulty on the one hand; On the other hand, because the structure of original reheater temperature adjustment baffle plate causes in field operator's operating process often because carelessness; Ignorance causes thermoregulation effect can not reach design effect reheater and chain the hanging up of superheater temperature adjustment baffle plate.
Summary of the invention
A kind of boiler flue temperature adjustment baffle plate provided by the invention, interlock is simple, makes easy for installation, regulate flexible, better adaptability, thermoregulation effect is good.
In order to achieve the above object, the present invention provides a kind of boiler flue temperature adjustment baffle plate, and this temperature adjustment baffle plate comprises front apron and backboard, and in the flue, backboard was arranged in the rear pass before described front apron was arranged on;
Described front apron and backboard are parallel to Zuo Qiang and right wall setting;
Described front apron and backboard are set to coaxial interlock, and the position of front apron and backboard is vertical each other, immobilizes.
Pass through the operation that universal driving shaft is controlled front apron and backboard from front wall or back wall.
The length of described front apron and backboard and width respectively with the degree of depth of preceding flue and rear pass and width coupling.
The present invention has the following advantages:
1, makes reheater, superheater temperature adjustment interlock become simple, the only situation of a moving side can not take place again, reduced operations staff's burden.
2, the arrangement of temperature adjustment baffle plate is changed into be parallel to left and right sides wall, the length of temperature adjustment baffle plate reduces greatly, is more prone to making in the processing.
3, the arrangement of temperature adjustment baffle plate is changed into be parallel to left and right sides wall, make that reheater steam temperature bias adjustment is more simple on width, increased a kind of method of controlling the reheater local overheating.
Description of drawings
Fig. 1 is the front view that the position is set that the present invention provides a kind of boiler flue temperature adjustment baffle plate.
Fig. 2 is the vertical view that the position is set that the present invention provides a kind of boiler flue temperature adjustment baffle plate.
Fig. 3 is the structural representation that the present invention provides a kind of boiler flue temperature adjustment baffle plate.
The specific embodiment
Following according to Fig. 1 and Fig. 2, specify preferred embodiment of the present invention:
As depicted in figs. 1 and 2; A kind of boiler flue temperature adjustment baffle plate provided by the invention comprises front apron 1, and (front apron is a reheater temperature adjustment baffle plate with backboard 2; Backboard is a superheater temperature adjustment baffle plate), among the flue F, backboard 2 was arranged among the rear pass B before described front apron 1 was arranged on.
Described front apron 1 is parallel to left wall 33 with backboard 2 and is provided with right wall 44.
As shown in Figure 3, described front apron 1 is set to coaxial interlock with backboard 2, and the position of front apron 1 and backboard 2 is vertical each other, immobilizes.
Pass through the operation that universal driving shaft is controlled front apron 1 and backboard 2 from front wall 11 or back wall 22.
The length L of described front apron 1 and backboard 2 and width D are mated with the degree of depth and the width of preceding flue F and rear pass B respectively.
Although content of the present invention has been done detailed introduction through above-mentioned preferred embodiment, will be appreciated that above-mentioned description should not be considered to limitation of the present invention.After those skilled in the art have read foregoing, for multiple modification of the present invention with to substitute all will be conspicuous.Therefore, protection scope of the present invention should be limited appended claim.
Claims (3)
1. a boiler flue temperature adjustment baffle plate is characterized in that, this temperature adjustment baffle plate comprises front apron (1) and backboard (2), and described front apron (1) is arranged in the preceding flue (F), and backboard (2) is arranged in the rear pass (B);
Described front apron (1) and backboard (2) are parallel to left wall (33) He Youqiang (44) and are provided with;
Described front apron (1) and backboard (2) are set to coaxial interlock, and front apron (1) is vertical each other with the position of backboard (2), immobilizes.
2. boiler flue temperature adjustment baffle plate as claimed in claim 1 is characterized in that, from the operation through universal driving shaft control front apron (1) and backboard (2) of front wall (11) or back wall (22).
3. boiler flue temperature adjustment baffle plate as claimed in claim 1 is characterized in that, the length (L) of described front apron (1) and backboard (2) and width (D) respectively with the degree of depth of preceding flue (F) and rear pass (B) and width coupling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010106030765A CN102393022A (en) | 2010-12-24 | 2010-12-24 | Temperature-adjusting baffle for boiler flue |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010106030765A CN102393022A (en) | 2010-12-24 | 2010-12-24 | Temperature-adjusting baffle for boiler flue |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102393022A true CN102393022A (en) | 2012-03-28 |
Family
ID=45860381
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010106030765A Pending CN102393022A (en) | 2010-12-24 | 2010-12-24 | Temperature-adjusting baffle for boiler flue |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102393022A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102777896A (en) * | 2012-07-05 | 2012-11-14 | 哈尔滨锅炉厂有限责任公司 | Device for fixing temperature-adjusting baffle of tail portion flue of circulating fluid bed (CFB) boiler and temperature-adjusting method |
CN103017153A (en) * | 2012-12-26 | 2013-04-03 | 哈尔滨锅炉厂有限责任公司 | 300MW subcritical circulating fluidized bed boiler and working method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD214913A1 (en) * | 1983-05-04 | 1984-10-24 | Luebbenau Vetschau Kraftwerke | DEVICE FOR REDUCING MECHANICAL WEAR OF BURN CARBON STEAM-FIRED STEAM GENERATORS |
JPS61250405A (en) * | 1985-04-26 | 1986-11-07 | 三菱重工業株式会社 | Steam-generating boiler |
DE19730227A1 (en) * | 1997-07-15 | 1999-01-21 | Abb Patent Gmbh | Promoting greater uniformity of gases liberated from untreated waste |
JP3485798B2 (en) * | 1998-05-14 | 2004-01-13 | 株式会社クボタ | Flue structure |
CN201187784Y (en) * | 2008-04-15 | 2009-01-28 | 重庆市疾病预防控制中心 | Controllable defluorination double-smoke canal for fire coal cooking stove |
-
2010
- 2010-12-24 CN CN2010106030765A patent/CN102393022A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD214913A1 (en) * | 1983-05-04 | 1984-10-24 | Luebbenau Vetschau Kraftwerke | DEVICE FOR REDUCING MECHANICAL WEAR OF BURN CARBON STEAM-FIRED STEAM GENERATORS |
DD214913B1 (en) * | 1983-05-04 | 1987-02-04 | Luebbenau Vetschau Kraftwerke | DEVICE FOR REDUCING MECHANICAL WEAR OF BURN CARBON STEAM-FIRED STEAM GENERATORS |
JPS61250405A (en) * | 1985-04-26 | 1986-11-07 | 三菱重工業株式会社 | Steam-generating boiler |
DE19730227A1 (en) * | 1997-07-15 | 1999-01-21 | Abb Patent Gmbh | Promoting greater uniformity of gases liberated from untreated waste |
JP3485798B2 (en) * | 1998-05-14 | 2004-01-13 | 株式会社クボタ | Flue structure |
CN201187784Y (en) * | 2008-04-15 | 2009-01-28 | 重庆市疾病预防控制中心 | Controllable defluorination double-smoke canal for fire coal cooking stove |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102777896A (en) * | 2012-07-05 | 2012-11-14 | 哈尔滨锅炉厂有限责任公司 | Device for fixing temperature-adjusting baffle of tail portion flue of circulating fluid bed (CFB) boiler and temperature-adjusting method |
CN102777896B (en) * | 2012-07-05 | 2017-01-04 | 哈尔滨锅炉厂有限责任公司 | Fixing device and temperature adjusting method for CFB boiler tail flue temperature adjusting baffle |
CN103017153A (en) * | 2012-12-26 | 2013-04-03 | 哈尔滨锅炉厂有限责任公司 | 300MW subcritical circulating fluidized bed boiler and working method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206380554U (en) | A kind of automatic tunnel stove baking system of biscuit | |
CN102393022A (en) | Temperature-adjusting baffle for boiler flue | |
CN111207390B (en) | Opposed firing boiler and temperature deviation adjusting method thereof | |
CN103875746A (en) | Tunnel type hot air circulation tunnel furnace | |
CN203549790U (en) | Biomass burning device | |
CN102353043B (en) | Adjustable external heat exchanger for circulating fluidized bed boiler | |
US10712013B2 (en) | Biomass pellet stove | |
CN202253607U (en) | Adjustable external heat exchanger of circulating fluidized bed boiler | |
CN206380544U (en) | A kind of continuous tunnel furnace for biscuit baking system to the effective control of humidity | |
CN205505639U (en) | Special dry production line of iron oxide pigment | |
CN106152116A (en) | A kind of Novel anti-abrasion burning in circulating fluid bed boiler room water-cooling wall | |
CN205448625U (en) | But hot -blast distributor | |
CN108240621A (en) | Circulating fluid bed boiler secondary air system | |
CN205535772U (en) | Circulating fluidized bed boiler external heat exchanger | |
CN102261642B (en) | 350MW supercritical boiler combustor nozzle tube panel device and method | |
CN102393007B (en) | Multi-passage casting and forging linkage structure used for connecting boiler piping | |
CN201344543Y (en) | Chain grate for air scoop type uniform air distribution in intermediate air chamber of large air bin | |
CN201357109Y (en) | Coal mill separator baffle asynchronous adjusting device | |
CN212133198U (en) | Drying device is used in bellows production | |
CN204665659U (en) | A kind of duct insert heater U-shaped pipe | |
CN205066485U (en) | Big flue waste heat recovery of external sintering machine utilizes system | |
CN205143468U (en) | Formula hot air circulating system goes into under following current of hot -blast moist leaf machine | |
CN204629452U (en) | For the particle burning machine of roller fixation machine | |
CN206034181U (en) | A cooling turns to platform for papermaking | |
CN202984029U (en) | Novel curing barn |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20120328 |