CN102385037A - 一种用于发电机组的电气试验方法和电气试验系统 - Google Patents
一种用于发电机组的电气试验方法和电气试验系统 Download PDFInfo
- Publication number
- CN102385037A CN102385037A CN2011102387918A CN201110238791A CN102385037A CN 102385037 A CN102385037 A CN 102385037A CN 2011102387918 A CN2011102387918 A CN 2011102387918A CN 201110238791 A CN201110238791 A CN 201110238791A CN 102385037 A CN102385037 A CN 102385037A
- Authority
- CN
- China
- Prior art keywords
- genset
- electrical test
- test
- switch
- generator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Control Of Eletrric Generators (AREA)
Abstract
本发明针对现有发电机组电气试验方法的周期长、费用高的缺陷,提供一种用于发电机组的电气试验方法和电气试验系统,能够减小电气试验的周期和费用。本发明提供一种用于发电机组的电气试验方法,该方法包括:将第一发电机组的发电机作为对第二发电机组进行电气试验所需的电源;对所述第二发电机组进行电气试验。
Description
技术领域
本发明涉及电网领域,尤其涉及一种用于发电机组的电气试验方法和电气试验系统。
背景技术
在新建火力发电机组投产并网前,需要进行相关电气试验,试验完成后发电机组及设备才能在电网内运行。目前,在进行电气试验时,都是用备用变压器来提供电气试验所需的电源,但是由于备用电压器的容量较小,所以不能同时为多台发电机组提供电气试验所需的电源,使得电气试验的效率低、周期长;但是若使发电机组的主变和高厂变尽快带电来提供电气试验所需的电源,则会由于目前某一发电机组中的发电机只能为本发电机组内的设备供电而导致电气试验的费用增加。
发明内容
本发明针对现有发电机组电气试验方法的周期长、费用高的缺陷,提供一种用于发电机组的电气试验方法和电气试验系统,能够减小电气试验的周期和费用。
本发明提供一种用于发电机组的电气试验方法,该方法包括:
将第一发电机组的发电机作为对第二发电机组进行电气试验所需的电源;
对所述第二发电机组进行电气试验。
本发明还提供一种用于发电机组的电气试验系统,该系统包括多个发电机组,各个所述发电机组之间通过连接在各个所述发电机组的负载节点之间的开关连接在一起。
由于根据本发明的电气试验方法和电气试验系统能够用第一发电机组的发电机来对供应对第二发电机组进行电气试验所需的电源,所以不仅能够降低试验周期还能够降低试验费用。
附图说明
图1是根据本发明的用于发电机组的电气试验方法的流程图;
图2是根据本发明的用于发电机组的短路试验;
图3是根据本发明的用于发电机组的升压试验;
图4是根据本发明的用于发电机组的电气试验系统。
具体实施方式
下面结合附图来详细描述根据本发明的用于发电机组的电气试验方法和电气试验系统。
如图1所示,根据本发明的用于发电机组的电气试验方法包括:
S11、将第一发电机组的发电机作为对第二发电机组进行电气试验所需的电源;
S12、对所述第二发电机组进行电气试验。
通常,发电机组的电气试验一般包括短路试验和升压试验。
下面结合图2和图3的示意图来对根据本发明的用于发电机组的电气试验方法进行具体说明。
图2示出了两个发电机组,即第一发电机组A和第二发电机组B,并且第一发电机组A通过第一开关205联络到第二发电机组B。其中,第一发电机组A中的第一发电机213以及该第一发电机组A中的各个设备(包括第一厂变203、第一主变215、第二开关200、第三开关204)以及将第一发电机组A和第二发电机组B相连接的第一开关205都已经建设完成,并且等待进行电气试验。同时,第二发电机组B中的第二主变216、第二厂变212、第四开关211和第五开关207也已经建设完成,但是第二发电机组B中的第二发电机214尚未建设完成(这是因为,发电机组的建设情况一般是第一台机组建设快些,第二台机组建设慢些,原因在于发电机系统建设完成之后,还需要其庞大的辅助系统也要建设完成,所以第二台发电机组建设要慢些)。
由于第二发电机组B的第二发电机214尚未建设完成,所以根据本发明的用于发电机组的电气试验由第一发电机组A中的第一发电机213来供应第二发电机组B电气试验所需的电源,即第一发电机213沿着第二开关200、第一主变215、第三开关204和第一开关205的路径来供应第二发电机组B电气试验所需的电源。由于每启动一次发电机组,其费用是相当高的(例如,发电机组启动48小时,费用大约为200万元左右),所以通过启动第一发电机组A,既能够为第一发电机组A的电气试验供应电源,又能够为第二发电机组B的电气试验进行供电,所以节省了费用,并降低了试验时间。另外,图2中的201、202、209、210表示要检测的短路点。应当理解的是,图2中的开关数量仅是示例性,并实用新型并不局限于此。
图3和图2类似,区别在于图2示出的是短路试验,图3示出的是升压试验。其中,在短路试验中,利用第一发电机213的供电来对第二发电机组B中除了第二发电机214之外的短路点进行电气试验,检验各个短路点是否满足要求,即短路试验包括以下步骤:通过调节所述第一发电机组A的第一发电机213的励磁来设置电流;检测需要进行短路试验的回路中的设备和节点的运行参数是否满足要求;而在升压试验中,利用第一发电机213的供电来对第二发电机组B中除了第二发电机214之外的设备进行升压试验,检验它们是否满足运行参数要求以及各个节点(例如,节点206和208)的电压是否满足要求,即升压试验包括以下步骤:设置第一发电机组A的第一发电机213的电压;检测需要进行升压试验的回路中的设备和节点的运行参数是否满足要求。
由于本领域技术人员能够通过现有技术中的短路试验和升压试验来很容易地得到发电机励磁的调节、各个GIS(气体绝缘开关设备)闸刀的开关顺序以及各个GIS开关的开关顺序,所以此次不再赘述。
本发明还提供了一种用于发电机组的电气试验系统,如图4所示,根据本发明的用于发电机组的电气试验系统包括多个发电机组101,各个所述发电机组之间通过连接在各个所述发电机组的负载节点之间的开关102连接在一起。
其中,所述开关102可以为电控开关或手动开关。其中,所述电控开关可以为断路器。
根据本发明的电气试验系统可以采用前面描述的电气试验方法来实现对发电机组的电气试验(例如,短路试验、升压试验),所以此处不再赘述。
以上仅结合优选实施方式对本发明进行了详细描述,但是本领域技术人员应当理解,在不背离本发明精神和范围的情况下,可以对本发明进行各种变形和修改。
Claims (7)
1.一种用于发电机组的电气试验方法,该方法包括:
将第一发电机组的发电机作为对第二发电机组进行电气试验所需的电源;
对所述第二发电机组进行电气试验。
2.根据权利要求1所述的方法,其中,所述电气试验包括短路试验和升压试验。
3.根据权利要求2所述的方法,其中,所述短路试验包括:
通过调节所述第一发电机组的发电机的励磁来设置电流;
检测需要进行短路试验的回路中的设备和节点的运行参数是否满足要求。
4.根据权利要求2所述的方法,其中,所述升压试验包括:
设置所述第一发电机组的发电机的电压;
检测需要进行升压试验的回路中的设备和节点的运行参数是否满足要求。
5.一种用于发电机组的电气试验系统,其中,该系统包括多个发电机组,各个所述发电机组之间通过连接在各个所述发电机组的负载节点之间的开关连接在一起。
6.根据权利要求5所述的系统,其特征在于,所述开关为电控开关或手动开关。
7.根据权利要求6所述的系统,其特征在于,所述电控开关为断路器。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102387918A CN102385037A (zh) | 2011-08-19 | 2011-08-19 | 一种用于发电机组的电气试验方法和电气试验系统 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102387918A CN102385037A (zh) | 2011-08-19 | 2011-08-19 | 一种用于发电机组的电气试验方法和电气试验系统 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102385037A true CN102385037A (zh) | 2012-03-21 |
Family
ID=45824654
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102387918A Pending CN102385037A (zh) | 2011-08-19 | 2011-08-19 | 一种用于发电机组的电气试验方法和电气试验系统 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102385037A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5949247A (en) * | 1996-05-23 | 1999-09-07 | Fremont/Dynamics Coporation Of America | Method and apparatus for automatically testing and evaluating electric generator sets |
DE10200733A1 (de) * | 2002-01-11 | 2003-07-24 | Bosch Gmbh Robert | Generatormodell zur Bestimmung von Generatortemperatur,-Strom und-Drehmoment |
EP2146264A1 (en) * | 2007-04-11 | 2010-01-20 | Fundación CIRCE - Centro de Investigación de Recursos y Consumos Energéticos | Voltage sag generating equipment |
CN102037534A (zh) * | 2007-08-18 | 2011-04-27 | 洛根·纳普 | 具有高速机械连锁性接地开关的断路开关装置 |
-
2011
- 2011-08-19 CN CN2011102387918A patent/CN102385037A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5949247A (en) * | 1996-05-23 | 1999-09-07 | Fremont/Dynamics Coporation Of America | Method and apparatus for automatically testing and evaluating electric generator sets |
DE10200733A1 (de) * | 2002-01-11 | 2003-07-24 | Bosch Gmbh Robert | Generatormodell zur Bestimmung von Generatortemperatur,-Strom und-Drehmoment |
EP2146264A1 (en) * | 2007-04-11 | 2010-01-20 | Fundación CIRCE - Centro de Investigación de Recursos y Consumos Energéticos | Voltage sag generating equipment |
CN102037534A (zh) * | 2007-08-18 | 2011-04-27 | 洛根·纳普 | 具有高速机械连锁性接地开关的断路开关装置 |
Non-Patent Citations (1)
Title |
---|
杨文超: "大型发电机组启动电气试验中的问题探讨", 《电力建设》, no. 08, 31 August 2007 (2007-08-31) * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10283965B2 (en) | Method for incorporating non-operating station into operating system in multi-terminal flexible DC transmission system | |
CN103633623A (zh) | 高压直流变压器及其控制方法 | |
EP3264550B1 (en) | Access control method for parallel direct current power supplies and device thereof | |
CN204948018U (zh) | 一种多机并联系统预防电池板pid效应的电路 | |
CN104040666B (zh) | 直流断路器和包括这样的直流断路器的电力系统 | |
CN104184138A (zh) | 一种多端柔性直流输电系统单端退出运行系统的方法 | |
CN103746553B (zh) | 高压dc-dc变换器及控制方法 | |
CN102593941A (zh) | 用于通讯基站的储能系统及储能方法 | |
CN104426236A (zh) | 电源供应转换系统及其控制方法 | |
CN109274182A (zh) | 直流电源远程一体化监测平台 | |
CN102629776A (zh) | 一种电力变换器的辅助供电系统及方法 | |
CN104578386A (zh) | 变压器低压侧分段路器备自投电路及其自投方法 | |
CN103269155A (zh) | 一种级联拓扑的功率单元的放电控制方法和系统 | |
CN104916856A (zh) | 一种提高液流电池运行可靠性的储能系统及其方法 | |
CN206584019U (zh) | 一种双电源自动转换开关试验电路与一种电气系统 | |
CN202749184U (zh) | 大功率风电整机试验台变压器预充磁装置 | |
CN202906774U (zh) | 一种辅助电源电路可自动断电的大功率光伏逆变器 | |
CN202495535U (zh) | 一种动力电池包和一种动力电池系统 | |
CN103490408A (zh) | 一种基于电网多回直流协同调制的方法 | |
CN202204915U (zh) | 一种用于发电机组的电气试验系统 | |
CN103138384B (zh) | 交流与柔性直流混合供电区域备自投配置系统及方法 | |
CN104838577A (zh) | 电力电子设备模块中用于改进的故障模式处理的无源电路 | |
CN202586103U (zh) | 智能化低压电容柜 | |
CN102385037A (zh) | 一种用于发电机组的电气试验方法和电气试验系统 | |
CN201935987U (zh) | 一种用于直流开关试验的合成试验回路 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120321 |
|
WD01 | Invention patent application deemed withdrawn after publication |