CN102346883A - Total life cycle management method for relay protection products - Google Patents
Total life cycle management method for relay protection products Download PDFInfo
- Publication number
- CN102346883A CN102346883A CN2011102755229A CN201110275522A CN102346883A CN 102346883 A CN102346883 A CN 102346883A CN 2011102755229 A CN2011102755229 A CN 2011102755229A CN 201110275522 A CN201110275522 A CN 201110275522A CN 102346883 A CN102346883 A CN 102346883A
- Authority
- CN
- China
- Prior art keywords
- relay protection
- protection product
- life cycle
- management method
- products
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention discloses a total life cycle management method for relay protection products, which comprises the following steps of: analyzing and evaluating the producing, processing, debugging, storing, transporting, running and maintaining processes of the relay protection products; setting different weights according to the time point and the running state of each process; classifying the relay protection products according to the type of the relay protection products; and calculating an expected set value of each relay protection product in a station level and a system level by synthesizing the information of the above steps, and establishing a relay protection product station-level management database and a relay protection product system-level management database. In the method, the producing, processing, debugging and maintaining processes, and the like of the products are watched and analyzed, and the total life cycle of the relay protection products is managed; moreover, the running state of the products is evaluated so as to ensure that the products can run reliably.
Description
Technical field
The present invention relates to a kind of method that the relay protection of power system product life cycle is managed, belong to the electrical equipment technical field.
Background technology
Relay protection is the important secondary device of electric system, must be reliably, rapidly, selectively fault element is excised from electric system, and make fault element avoid continuing to be destroyed, guarantee that other non-fault parts recover normal operation rapidly.The develop rapidly of the widespread usage of high-performance processor and large scale integrated circuit technology has greatly promoted the development of digital protective relay technology.Because the equipment of serving engineering site receives the influence of electromagnetic interference (EMI), high temperature wet environment easily; The hardware performance of the digital protective relay product of high volume applications exists the product life cycle rule, therefore must carry out the hardware longevity management to the relay protection product.
Hardware is intact to be an essential condition that guarantees the good operation of relay protection device.Hardware longevity management at present is a weak link, guarantee that the relay protection safe and reliable operation just must be to protecting the device hardware life-span manage.This managerial demand extends to the final user from manufacturer, and it is retired to extend to product from production.
Summary of the invention
The objective of the invention is the relay protection products-hardware is carried out lifecycle management, guarantee the product reliability service, can assess, analyze the product operation conditions simultaneously, for product provides the planning foundation in process links such as production, processing, debugging, maintenances.
In order to realize above-mentioned functions, the present invention provides following technical scheme:
The present technique scheme is to pay close attention to each main time point, and the relay protection products-hardware is carried out lifecycle management.
A kind of full life cycle management method that is used for the relay protection product is characterized in that, comprises following steps:
Step 1: relay protection production, processing, debugging, stock, transportation, operation, maintenance process are carried out analysis and evaluation;
Step 2: time point and operation conditions according to each process are provided with different weights;
Step 3: the type according to the relay protection product is classified it;
Step 4: the information of comprehensive above-mentioned steps, the life cycle calculations value of computer installation level, system-level interior each relay protection product is set up relay protection product station level, system-level management database.
The life cycle calculations value is calculated by following arithmetic expression:
A
kThe expression weight is used for indicating various process to the products-hardware effect on service life, is provided with according to being operating experience, can adjust according to actual conditions;
T
kRepresenting operation time, is unit with actual fate.
Through to the arithmetic expression accumulating operation, a life cycle calculations value and an expection setting value are compared, when the calculated value of certain relay protection product reaches the expection setting value, notify the user that the relay protection product is upgraded, safeguarded or changes.
Also comprise the retired time of relay protection product, reprocess the step that maintenance time is planned in advance.
Form prior notice user with report output.
Type according to the relay protection product is divided into conventional plug-in unit, rapid wear plug-in unit or alternative plug-in unit with it.
Principle of work of the present invention is following:
According to buying device time, the time of making the product, debug time, putting into operation the time, as node, different weights are set with each time point according to operation condition in site, the products-hardware life-span is managed.When certain device calculated value reached expection setting boundary, prior notice user changed or handles.
The beneficial effect that the present invention reached:
Products-hardware is carried out lifecycle management;
Prior notice, planning in advance;
Form product database, classification is safeguarded;
Guarantee the reliable and secure operation of relay protection product.
Description of drawings
The hardware longevity management block diagram of Fig. 1 relay protection product.
Embodiment
Below in conjunction with accompanying drawing the present invention is further described.Following examples only are used for technical scheme of the present invention more clearly is described, and can not limit protection scope of the present invention with this.
As shown in Figure 1, the relay protection products-hardware is carried out equipment control, retired from device buying, production processing beginning until product, every device of every block of plug-in unit, plug-in unit is carried out life cycle management.According to the difference of each time point, the difference of service condition, carry out different weight computings.
Life cycle calculations value arithmetic expression:
Wherein: 0≤A
k≤1;
A
kThe expression weight is used for indicating various process to the products-hardware effect on service life, and it is operating experience that foundation is set, as the system weight parameter of setting up departments is following, can adjust according to actual conditions:
Production, processing link A
k=0.5;
Debugging A
k=0.2;
Stock A
k=0.05;
Transportation A
k=0.1;
Actual motion A
k=1.0;
Safeguard A
k=0.8;
T
kRepresenting operation time, is unit with actual fate.
Through accumulating operation, a calculated value and an expection setting value are compared, system can point out and alarm.
Full station or total system relay protection products-hardware life-span are managed, conventional plug-in unit, rapid wear plug-in unit, alternative plug-in unit are classified, form station level, Complex Structural System management database.The relay protection products-hardware is upgraded and safeguard with report output form prior notice user.
The above only is a preferred implementation of the present invention; Should be pointed out that for those skilled in the art, under the prerequisite that does not break away from know-why of the present invention; Can also make some improvement and distortion, these improvement and distortion also should be regarded as protection scope of the present invention.
Claims (6)
1. a full life cycle management method that is used for the relay protection product is characterized in that, comprises following steps:
Step 1: relay protection production, processing, debugging, stock, transportation, operation, maintenance process are carried out analysis and evaluation;
Step 2: time point and operation conditions according to each process are provided with different weights;
Step 3: the type according to the relay protection product is classified it;
Step 4: the information of comprehensive above-mentioned steps, the life cycle calculations value of computer installation level, system-level interior each relay protection product is set up relay protection product station level, system-level management database.
2. a kind of full life cycle management method that is used for the relay protection product according to claim 1 is characterized in that the life cycle calculations value is calculated by following arithmetic expression:
A
kThe expression weight is used for indicating various process to the products-hardware effect on service life, is provided with according to being operating experience, can adjust according to actual conditions;
T
kRepresenting operation time, is unit with actual fate.
3. a kind of full life cycle management method that is used for the relay protection product according to claim 2; It is characterized in that; Through to the arithmetic expression accumulating operation; A life cycle calculations value and an expection setting value are compared, when the calculated value of certain relay protection product reaches the expection setting value, notify the user that the relay protection product is upgraded, safeguarded or changes.
4. a kind of full life cycle management method that is used for the relay protection product according to claim 3 is characterized in that, also comprises the retired time of relay protection product, reprocesses the step that maintenance time is planned in advance.
5. a kind of full life cycle management method that is used for the relay protection product according to claim 3 is characterized in that, with the form prior notice user of report output.
6. a kind of full life cycle management method that is used for the relay protection product according to claim 1 is characterized in that, according to the type of relay protection product it is divided into conventional plug-in unit, rapid wear plug-in unit or alternative plug-in unit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102755229A CN102346883A (en) | 2011-09-16 | 2011-09-16 | Total life cycle management method for relay protection products |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102755229A CN102346883A (en) | 2011-09-16 | 2011-09-16 | Total life cycle management method for relay protection products |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102346883A true CN102346883A (en) | 2012-02-08 |
Family
ID=45545534
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102755229A Pending CN102346883A (en) | 2011-09-16 | 2011-09-16 | Total life cycle management method for relay protection products |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102346883A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107925671A (en) * | 2015-06-15 | 2018-04-17 | 相信环球有限公司 | Universal remote life cycle management |
CN110443385A (en) * | 2019-08-01 | 2019-11-12 | 南京信业能源科技有限公司 | A kind of waste incineration special equipment life cycle management and analysis method |
-
2011
- 2011-09-16 CN CN2011102755229A patent/CN102346883A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107925671A (en) * | 2015-06-15 | 2018-04-17 | 相信环球有限公司 | Universal remote life cycle management |
CN107925671B (en) * | 2015-06-15 | 2021-06-25 | 相信环球有限公司 | Universal remote device lifecycle management |
CN110443385A (en) * | 2019-08-01 | 2019-11-12 | 南京信业能源科技有限公司 | A kind of waste incineration special equipment life cycle management and analysis method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Danilczyk et al. | ANGEL: An intelligent digital twin framework for microgrid security | |
CN103197177B (en) | A kind of transformer fault diagnosis analytical approach based on Bayesian network | |
CN104504525A (en) | Method for realizing power-grid equipment failure prewarning through big data mining technology | |
CN102324068A (en) | Power secondary equipment risk assessment method and system thereof | |
CN105023109A (en) | Reliability evaluation method and system of nuclear power station system or equipment | |
CN103711645A (en) | Wind generating set state evaluation method based on modeling parameter feature analysis | |
CN104616092A (en) | Distributed log analysis based distributed mode handling method | |
CN110320893B (en) | Thermal power generating unit equipment maintenance method based on RCM | |
CN104933477A (en) | Method for optimizing maintenance strategy by using risk assessment of power transmission and transformation equipment | |
CN103914951A (en) | Method for natural disaster data information mining and early warning response analysis based on GIS power grid | |
CN105184521A (en) | Method, device and system for evaluating risk of power grid operation mode with equipment health state | |
CN105447657A (en) | Risk-based operation and maintenance management system of 750KV power equipment | |
CN104346691A (en) | Power enterprise field operation risk analysis method based on fault tree analysis | |
Vlasov et al. | Technological platform for innovative social infrastructure development on basis of smart machines and principles of internet of things | |
CN113448763A (en) | Dynamic expansion grouping alarm service method for full life cycle management | |
US20230060002A1 (en) | Method for predictive maintenance of equipment via distribution chart | |
CN115826469A (en) | Automatic valve control method and system | |
JP5621414B2 (en) | Equipment management method | |
CN105958652A (en) | Unattended operation transformer substation pre-warning system and method based on big data analysis | |
CN105334472A (en) | Online remaining life prediction method for mining intrinsic safety power supply | |
CN102346883A (en) | Total life cycle management method for relay protection products | |
Zhao et al. | Battery safety: Fault diagnosis from laboratory to real world | |
CN103163402B (en) | Relay protection device state monitoring apparatus based on secondary circuit and monitoring method | |
CN105404962A (en) | Modification strategy of electric power system relay protection device and generation system thereof | |
CN104766183A (en) | Power grid real time fault event flow management system and adopted management method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20120208 |