CN102331722B - Simulation system for emergency plan of multi-T cable line trip - Google Patents

Simulation system for emergency plan of multi-T cable line trip Download PDF

Info

Publication number
CN102331722B
CN102331722B CN 201110300899 CN201110300899A CN102331722B CN 102331722 B CN102331722 B CN 102331722B CN 201110300899 CN201110300899 CN 201110300899 CN 201110300899 A CN201110300899 A CN 201110300899A CN 102331722 B CN102331722 B CN 102331722B
Authority
CN
China
Prior art keywords
emulation
line
many
cable line
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110300899
Other languages
Chinese (zh)
Other versions
CN102331722A (en
Inventor
卞佳音
贺智涛
吴倩
陆浩臻
陈文教
来立永
庞远峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority to CN 201110300899 priority Critical patent/CN102331722B/en
Publication of CN102331722A publication Critical patent/CN102331722A/en
Application granted granted Critical
Publication of CN102331722B publication Critical patent/CN102331722B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The invention discloses a simulation system for an emergency plan of multi-T cable line trip, wherein a team line patrol module, an emergency repair preparing module, a fault detecting module, an unwinding mode module and a fault emergency repair module respectively correspond to a simulation item and are used for respectively simulating corresponding links involved in on-site emergency repair. By utilizing the simulation system, emergency repaire personnel can know which materials are needed to be prepared for emergency repair and how to perform emergency repair in advance, thereby improving the efficiency and accuracy of on-site emergency repair and reducing emergency repair time.

Description

Many T cable line tripping operation emergency preplan analogue system
Technical field
The present invention relates to the electric power system fault processing technology field, particularly a kind of many T cable line tripping operation emergency preplan analogue system.
Background technology
The cable line that connects three and above transformer station is called many T cable line.Compare the cable line that connects two transformer stations, the wiring situation of many T cable line is complicated, operational factor is numerous.When many T line tripping, the staff carries out the time and efforts that fault detect and repairing need labor to the scene.
Summary of the invention
The present invention proposes a kind of many T cable line tripping operation emergency preplan analogue system, to the many T cable line after the tripping operation carry out emergency preplan emulation, to reduce the time of scene rush to repair, improve the repairing success ratio.
Many T of the present invention cable line tripping operation emergency preplan analogue system comprises:
Load module is used for receiving and treats many T of emulation cable line and treat the emulation project, and many T of emulation cable line of treating that will receive mails to and the module that the emulation project is corresponding of treating that receives;
Database is used to store the basic service data and the wiring diagram of many T cable line;
Teams and groups' line walking module, be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data in the said database and wiring diagram the teams and groups that treat many T of emulation cable line line walking path profile is provided;
The repairing preparation module; Be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data in the said database and wiring diagram circuit wiring diagram, cable technology parameter, cable termination information, cable jacket wiring diagram and the environmental aspect along the line of treating many T of emulation cable line is provided;
Fault is surveyed and to be sought module, be used for receive that said load module sends treat many T of emulation cable line after, provide according to the basic service data in the said database and wiring diagram and to treat to be suitable near many T of emulation cable line position and power supply that the fault car parks and get the place;
Separate the line operational module, be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data and the wiring diagram in the said database, and adopt the Flash poster presentation to treat the line mode of separating of many T of emulation cable line;
The breakdown repair module; Be used for receive that said load module sends treat many T of emulation cable line after; According to basic service data and the wiring diagram in the said database, provide repairing job instruction, the required Work tool inventory of repairing, repairing troop and the material of treating many T of emulation cable line to form;
The said emulation project of treating comprises that emulation is prepared in the repairing of teams and groups' line walking emulation of corresponding teams and groups line walking module, corresponding repairing preparation module, corresponding fault is surveyed the fault of seeking module and surveyed the breakdown repair emulation of separating line operational simulation and corresponding breakdown repair module of seeking emulation, homographic solution line operational module.
Preferably; Said teams and groups line walking module also be used for receive that said load module sends treat many T of emulation cable line after, provide according to the basic service data in the said database and wiring diagram and to treat many T of emulation cable line and carry out the required time of teams and groups' line walking.
Many T of the present invention cable line tripping operation emergency preplan analogue system; Wherein, Line mode module and the corresponding a kind of emulation project of breakdown repair module difference are surveyed and seek module, separated to teams and groups' line walking module, repairing preparation module, fault, separately the corresponding link that scene rush to repair relates to carried out emulation.The repairing personnel can understand the material of the required preparation of repairing in advance through native system and how to rush to repair, thereby have improved the efficient and the accuracy rate of scene rush to repair, have reduced the repairing time.
Description of drawings
Fig. 1 is the structural representation of many T of the present invention cable line tripping operation emergency preplan analogue system.
Embodiment
After the tripping operation of many T cable line; Before the staff implements scene rush to repair; Earlier the repairing scheme is carried out emulation, how can to understand teams and groups' line walking intuitively, need to prepare which instrument, where the fault car is parked in, separate the line operation how to carry out or the like through many T cable line emergency preplan analogue system of the present invention.Like this, after reaching the spot, can implement repairing more rapidly more accurately.Below in conjunction with the present invention of accompanying drawing illustrated in detail.
Many T of the present invention cable line tripping operation emergency preplan analogue system, as shown in Figure 1, comprising:
Load module is used for receiving and treats many T of emulation cable line and treat the emulation project, and many T of emulation cable line of treating that will receive mails to and the module that the emulation project is corresponding of treating that receives;
Database is used to store the basic service data and the wiring diagram of many T cable line;
Teams and groups' line walking module, be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data in the said database and wiring diagram the teams and groups that treat many T of emulation cable line line walking path profile is provided;
The repairing preparation module; Be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data in the said database and wiring diagram circuit wiring diagram, cable technology parameter, cable termination information, cable jacket wiring diagram and the environmental aspect along the line of treating many T of emulation cable line is provided;
Fault is surveyed and is sought module; Be used for receive that said load module sends treat many T of emulation cable line after; Provide according to the basic service data in the said database and wiring diagram and to treat to be suitable near many T of emulation cable line position and power supply that the fault car parks and get the place, and fault is surveyed target-seeking method step make Show Me animation;
Separate the line operational module; Be used for receive that said load module sends treat many T of emulation cable line after; According to basic service data and the wiring diagram in the said database; And adopting the Flash poster presentation to treat the line mode of separating of many T of emulation cable line, the mode of connection and the environment of circuit in each transformer station of detail knowledge are formulated the concrete line scheme of separating in detail targetedly;
The breakdown repair module; Be used for receive that said load module sends treat many T of emulation cable line after; According to basic service data and the wiring diagram in the said database, provide repairing job instruction, the required Work tool inventory of repairing, repairing troop and the material of treating many T of emulation cable line to form;
The said emulation project of treating comprises that the repairing of teams and groups' line walking emulation and/or the corresponding repairing preparation module of corresponding teams and groups line walking module prepares emulation and/or corresponding fault and survey the fault of seeking module and survey the breakdown repair emulation of separating line operational simulation and/or corresponding breakdown repair module of seeking emulation and/or homographic solution line operational module.
Repairing work comprises a plurality of links, the respectively corresponding emulation project of each emulation module of this analogue system, and the corresponding emulation link of each emulation project, the user can select one or more projects to carry out emulation as required.
Load module is equivalent to an interface, and the user can import T cable line more than a section that needs emulation and the project of wanting emulation through this interface.Database has then been stored basic service data and the wiring diagram of local all many T cable lines etc. in advance, for emulation provides the data basis.
When the user has selected T cable line more than a section through load module; And specify when this many T cable line carried out teams and groups' line walking emulation; Teams and groups' line walking module of native system will provide optimum teams and groups' line walking wiring diagram for the user, can also provide line walking about time spent, make teams and groups' line walking time saving and energy saving.
When preparation emulation is rushed to repair in user's appointment; The repairing preparation module of native system can access the details of many T cable line that the user selectes smoothly, comprising: circuit wiring diagram, cable technology parameter, cable termination information, cable segmentation and protective metal shell ground connection figure and to environmental assessment along the line etc.Wherein, circuit wiring diagram and cable jacket wiring diagram all are polar plots, amplify that dwindle not can distortion, are convenient to check.
Carry out fault and survey when seeking emulation when the user specifies, the fault of native system is surveyed and is sought module google map location is provided, and a glance just can be seen the geographic position of power transformation position.
When the user specifies when separating the line operational simulation, the line operational module of separating of native system adopts the flash technology, should untie which head, unties back which section outage, which section also can clearly show the thinking that need not advance complicatedly in operation on wiring diagram.
When breakdown repair emulation was carried out in user's appointment, the breakdown repair module of native system wove the job instruction to many T cable line tripping operation of user's select segment, configures the repairing Work tool, can also arrange repairing troop properly.
Native system utilizes interactivity, the vividness of flash technology, how to rush to repair when the displaying of image is tripped, and particularly separates the line operation.Passing way all is to enumerate information such as separating the line mode out with the form of word document, checks very hard.Native system then can the image tell which head we should untie, untie the back which section outage, which the section also the operation, the thinking that need not advance complicatedly.Traditional method when needs are checked circuit wiring diagram and cable jacket wiring diagram, all will be installed the software (CAD etc.) of specialty and just can check, otherwise can only check with sectional drawing, amplifies the meeting distortion, and is smudgy.Flash technical support polar plot amplifies that dwindle not can distortion, is convenient to check.
Above-described embodiment of the present invention does not constitute the qualification to protection domain of the present invention.Any modification of within spirit of the present invention and principle, being done, be equal to replacement and improvement etc., all should be included within the claim protection domain of the present invention.

Claims (2)

1. the tripping operation of T cable line more than kind emergency preplan analogue system is characterized in that, comprising:
Load module is used for receiving and treats many T of emulation cable line and to treat the emulation project, and many T of emulation cable line of treating that will receive mails to and the module that the emulation project is corresponding of treating that receives, and this many T cable line is the cable line of three of connections and above transformer station;
Database is used to store the basic service data and the wiring diagram of many T cable line;
Teams and groups' line walking module, be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data in the said database and wiring diagram the teams and groups that treat many T of emulation cable line line walking path profile is provided;
The repairing preparation module; Be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data in the said database and wiring diagram circuit wiring diagram, cable technology parameter, cable termination information, cable jacket wiring diagram and the environmental aspect along the line of treating many T of emulation cable line is provided;
Fault is surveyed and to be sought module, be used for receive that said load module sends treat many T of emulation cable line after, provide according to the basic service data in the said database and wiring diagram and to treat to be suitable near many T of emulation cable line position and power supply that the fault car parks and get the place;
Separate the line operational module, be used for receive that said load module sends treat many T of emulation cable line after, according to basic service data and the wiring diagram in the said database, and adopt the Flash poster presentation to treat the line mode of separating of many T of emulation cable line;
The breakdown repair module; Be used for receive that said load module sends treat many T of emulation cable line after; According to basic service data and the wiring diagram in the said database, provide repairing job instruction, the required Work tool inventory of repairing, repairing troop and the material of treating many T of emulation cable line to form;
The said emulation project of treating comprises that emulation is prepared in the repairing of teams and groups' line walking emulation of corresponding teams and groups line walking module, corresponding repairing preparation module, corresponding fault is surveyed the fault of seeking module and surveyed the breakdown repair emulation of separating line operational simulation, corresponding breakdown repair module of seeking emulation, homographic solution line operational module.
2. many T cable line tripping operation emergency preplan analogue system according to claim 1; It is characterized in that; Said teams and groups line walking module also be used for receive that said load module sends treat many T of emulation cable line after, provide according to the basic service data in the said database and wiring diagram and to treat many T of emulation cable line and carry out the required time of teams and groups' line walking.
CN 201110300899 2011-09-29 2011-09-29 Simulation system for emergency plan of multi-T cable line trip Active CN102331722B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110300899 CN102331722B (en) 2011-09-29 2011-09-29 Simulation system for emergency plan of multi-T cable line trip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110300899 CN102331722B (en) 2011-09-29 2011-09-29 Simulation system for emergency plan of multi-T cable line trip

Publications (2)

Publication Number Publication Date
CN102331722A CN102331722A (en) 2012-01-25
CN102331722B true CN102331722B (en) 2012-12-05

Family

ID=45483537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110300899 Active CN102331722B (en) 2011-09-29 2011-09-29 Simulation system for emergency plan of multi-T cable line trip

Country Status (1)

Country Link
CN (1) CN102331722B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1632783A (en) * 2004-12-22 2005-06-29 华北电力大学(北京) Actual measurement based load modeling system
CN101236575A (en) * 2008-01-30 2008-08-06 山东大学 Black start assistant decision making support/training system and its method
CN102054386A (en) * 2011-01-07 2011-05-11 广东电网公司电力科学研究院 Transformer station simulation training system based on mixed digital/analogy simulation technology

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100934398B1 (en) * 2007-11-21 2009-12-29 한국전기연구원 Tripping generator number determination system and method for stabilization control
JP5359106B2 (en) * 2008-08-08 2013-12-04 株式会社戸上電機製作所 Ground fault relay test equipment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1632783A (en) * 2004-12-22 2005-06-29 华北电力大学(北京) Actual measurement based load modeling system
CN101236575A (en) * 2008-01-30 2008-08-06 山东大学 Black start assistant decision making support/training system and its method
CN102054386A (en) * 2011-01-07 2011-05-11 广东电网公司电力科学研究院 Transformer station simulation training system based on mixed digital/analogy simulation technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开2010-43873A 2010.02.25

Also Published As

Publication number Publication date
CN102331722A (en) 2012-01-25

Similar Documents

Publication Publication Date Title
CN103837796B (en) The transmission line malfunction visualization report method of a kind of sing on web and GIS and system
CN103093024B (en) A kind of planning power grid visualization methods of exhibiting based on WEBGIS
CN103093008A (en) System and method for power transmission and transformation project three-dimensional-aided preliminary design
CN109583108B (en) Extra-high voltage transmission line scene construction method based on GIS
CN102760059B (en) Automatic generating method for standardized test scripts of relay protection device of electrical system
CN204303029U (en) For the BIM Database Systems of subway pipeline collision detection and later stage operation maintenance
CN111462316B (en) Three-dimensional panoramic monitoring method and device for photovoltaic power station
CN106841908A (en) The visual presentation method of the distribution network failure positioning based on power grid GIS
CN106463945A (en) Systems and methods for identifying faulted segments in multiphase power networks
CN104299464B (en) Electric power safety technical ability simulation training system
CN106058695A (en) Relay protection visual overhauling safety measure system based on substation configuration description (SCD) and implementation method thereof
CN102567572A (en) Sand-table exercising system for power grid simulation
CN102129498A (en) System and method for aided design of power transmission and transformation geographic information
CN102331722B (en) Simulation system for emergency plan of multi-T cable line trip
CN105825272A (en) Transformer substation management system and management method
CN108952734A (en) A kind of shield-tunneling construction plane vertical section information mobile phone end real-time exhibition method
JP2010183703A (en) Large region power system simulator and simulation method
CN104346756A (en) Method and system for constructing power grid planning platform
CN103400514A (en) Simulation training system of digital substation
Saretta et al. Digitalization as a driver for supporting PV deployment and cost reduction
CN103440595A (en) Method for recording hidden danger of trees
CN111652389B (en) Distribution network primary equipment grounding overhaul layout method, device, equipment and medium
Huang Electricity distribution network planning considering distributed generation
CN104951487B (en) The electronic sand table method and system disposed for power emergency
Rodrigues et al. Estimation of lightning vulnerability points on wind power plants using the rolling sphere method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 510620, No. two, No. 2, Tianhe South Road, Guangzhou, Guangdong, Tianhe District

Patentee after: Guangzhou Power Supply Bureau of Guangdong Power Grid Co.,Ltd.

Address before: 510620, No. two, No. 2, Tianhe South Road, Guangzhou, Guangdong, Tianhe District

Patentee before: Guangzhou Power Supply Bureau of Guangdong Power Grid Co.,Ltd.