CN102275304A - Integrated filling and forming process for single shearing rib of fan blade - Google Patents

Integrated filling and forming process for single shearing rib of fan blade Download PDF

Info

Publication number
CN102275304A
CN102275304A CN2011101106989A CN201110110698A CN102275304A CN 102275304 A CN102275304 A CN 102275304A CN 2011101106989 A CN2011101106989 A CN 2011101106989A CN 201110110698 A CN201110110698 A CN 201110110698A CN 102275304 A CN102275304 A CN 102275304A
Authority
CN
China
Prior art keywords
shearing ribs
fan blade
housing
girder cap
shearing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101106989A
Other languages
Chinese (zh)
Inventor
刘培文
杨益锋
李秀凯
高伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Air Damper Power Technology Co Ltd Kunshan China
Original Assignee
Air Damper Power Technology Co Ltd Kunshan China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Air Damper Power Technology Co Ltd Kunshan China filed Critical Air Damper Power Technology Co Ltd Kunshan China
Priority to CN2011101106989A priority Critical patent/CN102275304A/en
Publication of CN102275304A publication Critical patent/CN102275304A/en
Pending legal-status Critical Current

Links

Landscapes

  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The invention discloses an integrated filling and forming process for a single shearing rib of a fan blade. According to the integrated filling and forming process for the single shearing rib of the fan blade, work efficiency during preparing the fan blade is raised. The process is specifically characterized in that: only an end of the shearing rib is fixed through adding an adhesive, the other end of the shearing rib is fixed through biaxial glass fiber cloth, such that the use amount of the adhesive is reduced; in addition, the shearing rib is placed in a center position of a main spar cap, such that the shearing rib can be ensured to be positioned exactly, and the offset phenomenon is not generated during a moulding process.

Description

Fan blade monolithic shearing ribs one pouring and forming process
Technical field
The present invention relates to a kind of fan blade one pouring and forming process, particularly relate to a kind of fan blade monolithic shearing ribs one pouring and forming process.
Background technology
The fan blade that is used for wind-driven generator is the shell structure that a kind of composite is made, and every generator generally has many blades.In the prior art, the fan blade mould before matched moulds need applying glue on the end face of upper and lower mould shearing ribs with the girder cap that shearing ribs is bonded to the blade inwall on.But, in order to guarantee the bonding thickness of bonding region, note the use of adhesive, if adhesive easily causes the phenomenon of shearing ribs starved with having lacked, thereby cause inefficiency, the adhesive use amount is big.In addition, in the prior art, the precision when shearing ribs is located is relatively poor, and shift phenomenon easily takes place in the matched moulds process.
In sum, problem demanding prompt solution is, need to existing fan blade particularly the manufacturing process of fan blade monolithic shearing ribs improve, to reduce the use amount of shearing ribs being carried out adhesive when bonding, improve the positioning accuracy of shearing ribs.
Summary of the invention
Technical problem to be solved by this invention is, a kind of fan blade monolithic shearing ribs one pouring and forming process is provided, it need use a large amount of adhesives when having solved in the prior art bonding shearing ribs, easily produces starved behind matched moulds, and the relatively poor problem of precision when shearing ribs located.
For solving the problems of the technologies described above, the technical solution used in the present invention is: a kind of fan blade monolithic shearing ribs one pouring and forming process, and this technology may further comprise the steps:
A. in the upper die and lower die of fan blade mould, lay working face housing and pneumatic face-piece body respectively;
B. shearing ribs being carried out precuring handles;
C. in the upper die and lower die of fan blade mould, lay girder cap, core, second layer housing successively, one end of the described shearing ribs that will handle through precuring is installed on the center of counterdie girder cap to form stiff end, makes the center line of shearing ribs and the central lines of girder cap up and down;
D. the stiff end that is installed in the shearing ribs on described counterdie girder cap or the patrix girder cap is carried out tool locating;
E. utilize twin shaft to glass cloth the stiff end of described shearing ribs to be fixed, glass cloth must be fitted with shearing ribs and girder cap;
F. after finish described shearing ribs location, remove frock, coat adhesive, blade counterdie and patrix are carried out matched moulds, finish glued curing at the not stiff end of described shearing ribs.
In the described fan blade monolithic shearing ribs one pouring and forming process, the thickness of described shearing ribs is 60cm.
In the described step (e) of described fan blade monolithic shearing ribs one pouring and forming process, it is that the twin shaft of 100mm is fixed it to glass cloth that one deck width is respectively adopted in the stiff end both sides of described shearing ribs.
In the described step (f) of described fan blade monolithic shearing ribs one pouring and forming process, finish described shearing ribs location, remove after the frock, on the blade shell inwall, lay barrier film with holes, water conservancy diversion net successively, treat that pressure is evacuated to 100mbar perfusion resin when following to form vacuum systems, after perfusion is finished, heating mould to 75 ℃ is incubated and stops heating after 4 hours, coats adhesive at the not stiff end of described shearing ribs, blade counterdie and patrix are carried out matched moulds, finish glued curing.
Advantage of the present invention is, disclosed fan blade monolithic shearing ribs one pouring and forming process has improved the operating efficiency when making fan blade, particularly, this technology only needs to fix in an end applying glue of shearing ribs, the other end is then fixed to glass cloth by twin shaft, thereby has reduced the use amount of adhesive.In addition, this technology is placed on girder cap center with shearing ribs can guarantee the shearing ribs accurate positioning, and shift phenomenon does not take place in the matched moulds process.
Description of drawings
Fig. 1 is the process chart of fan blade monolithic shearing ribs one pouring and forming process of the present invention;
Fig. 2 is the cross-sectional structure schematic diagram of the made product of fan blade monolithic shearing ribs one pouring and forming process of the present invention.
The specific embodiment
For further disclosing technical scheme of the present invention, be described with reference to the accompanying drawings embodiments of the present invention now.
Fig. 1 is the process chart of fan blade monolithic shearing ribs one pouring and forming process of the present invention, illustrates technological process of the present invention but the present invention is not limited to above-mentioned technological process under the situation based on same idea below in conjunction with Fig. 1.
At first utilize existing mould to produce shearing ribs, the thickness of this shearing ribs can be made 60cm; In the upper die and lower die of fan blade mould, lay working face housing 10 and pneumatic face-piece body 20 respectively, promptly lay the ground floor housing; Shearing ribs 31 is carried out precuring to be handled; In the upper die and lower die of fan blade mould, lay girder cap, core, second layer housing successively, one end of the described shearing ribs 31 that will handle through precuring is installed on the center of counterdie girder cap 22 forming stiff end, and makes the central lines of center line and girder cap of shearing ribs 31; The stiff end that is installed in the shearing ribs 31 on the described counterdie girder cap 22 is positioned by prefabricated frock, guarantee that shearing ribs 31 centers and following girder cap center overlap; Utilize twin shaft to glass cloth the stiff end of described shearing ribs 31 to be fixed, glass cloth must be fitted with shearing ribs and girder cap, and preferably, it is that the twin shaft of 100mm is fixed it to glass cloth that one deck width is respectively adopted in the stiff end both sides of described shearing ribs 31; After finish described shearing ribs 31 location, remove frock, coat adhesive, blade counterdie and patrix are carried out matched moulds, make the not stiff end of edge shearing ribs 31 and girder cap bond together, finish glued curing at the not stiff end of described shearing ribs 31.
For the further processing technology to elaboration of the present invention is optimized, finish stiff end location to described shearing ribs 31 in the described step (f), remove after the frock, on the blade shell inwall, lay barrier film with holes, water conservancy diversion net successively to form vacuum systems, the whole blade housing is vacuumized, treat that pressure is evacuated to 100mbar perfusion resin when following, after perfusion is finished, heating mould to 75 ℃, be incubated and stop heating after 4 hours, not stiff end at described shearing ribs 31 is coated adhesive, and blade counterdie and patrix are carried out matched moulds, finishes glued curing.More specifically, can lay multilayer glass cloth between ground floor housing and the second layer housing as enhancement layer.
Fig. 2 is the cross-sectional structure schematic diagram of the made product of fan blade monolithic shearing ribs one pouring and forming process of the present invention, finishes the fan blade that can generate after the above-mentioned technology as shown in Figure 2, and this fan blade comprises: working face housing 10; Pneumatic face-piece body 20, it coincide with described working face housing 10 and is connected; Patrix core 11, it is layed in the part except that the girder cap between working face housing 10 and the second layer housing; Part between the counterdie core 21, that it is layed in described pneumatic face-piece body 20 and second layer housing except that the girder cap; Patrix girder cap 12, it is layed on the inwall of described working face housing 10; Counterdie girder cap 22, it is layed on the inwall of described pneumatic face-piece body 20; And shearing ribs 31, its two ends are individually fixed on the center of described mould girder cap 12 and counterdie girder cap 22, the central lines of the center line of this shearing ribs 31 and girder cap.Wherein, above-mentioned patrix core 11 and counterdie core 21 all are made up of PVC foam and cork wood.
More than, the basic ideas and basic principles of the present invention have been set forth by description of listed embodiment.But the present invention never is limited to above-mentioned listed embodiment, and every equivalent variations, improvement and deliberately of inferior quality behavior of doing based on technical scheme of the present invention of change all should belong to protection scope of the present invention.

Claims (6)

1. fan blade monolithic shearing ribs one pouring and forming process, this technology may further comprise the steps:
In the upper die and lower die of fan blade mould, lay working face housing (10) respectively and promptly lay the ground floor housing with pneumatic face-piece body (20);
Shearing ribs (31) is carried out precuring to be handled;
In the upper die and lower die of fan blade mould, lay girder cap, core, second layer housing successively, one end of the described shearing ribs (31) that will handle through precuring is installed on the center of counterdie girder cap (22) to form stiff end, makes the central lines of center line and girder cap of shearing ribs (31);
The stiff end that is installed in the shearing ribs (31) on the described counterdie girder cap (22) is carried out tool locating;
Utilize twin shaft to glass cloth the stiff end of described shearing ribs (31) to be fixed, glass cloth must be fitted with shearing ribs and girder cap;
After finish described shearing ribs (31) location, remove frock, coat adhesive, blade counterdie and patrix are carried out matched moulds, finish glued curing at the not stiff end of described shearing ribs (31).
2. fan blade monolithic shearing ribs one pouring and forming process according to claim 1 is characterized in that the thickness of described shearing ribs (31) is 60cm.
3. fan blade monolithic shearing ribs one pouring and forming process according to claim 1 is characterized in that, it is that the twin shaft of 100mm is fixed it to glass cloth that one deck width is respectively adopted in the stiff end both sides of shearing ribs (31) described in the described step (e).
4. fan blade monolithic shearing ribs one pouring and forming process according to claim 1, it is characterized in that, finish the location of shearing ribs (31) described in the described step (f), remove after the frock, on the blade shell inwall, lay barrier film with holes successively, the water conservancy diversion net is to form vacuum systems, the whole blade housing is vacuumized, treat that pressure is evacuated to 100mbar perfusion resin when following, after perfusion is finished, heating mould to 75 ℃ is incubated and stops heating after 4 hours, coats adhesive at the not stiff end of described shearing ribs (31), blade counterdie and patrix are carried out matched moulds, finish glued curing.
5. a fan blade that utilizes the described fan blade monolithic of claim 1 shearing ribs one pouring and forming process to make is characterized in that this fan blade comprises: working face housing (10); Pneumatic face-piece body (20), it coincide with described working face housing (10) and is connected; Patrix core (11), it is layed in the part except that the girder cap between working face housing (10) and the second layer housing; Part between the counterdie core (21), that it is layed in described pneumatic face-piece body (20) and second layer housing except that the girder cap; Patrix girder cap (12), it is layed on the inwall of described working face housing (10); Counterdie girder cap (22), it is layed on the inwall of described pneumatic face-piece body (20); And shearing ribs (31), its two ends are individually fixed on the center of described mould girder cap (12) and counterdie girder cap (22), the center line of this shearing ribs (31) and the central lines of girder cap up and down.
6. fan blade according to claim 5 is characterized in that, is equipped with glass cloth as enhancement layer between ground floor housing and the second layer housing.
CN2011101106989A 2011-04-29 2011-04-29 Integrated filling and forming process for single shearing rib of fan blade Pending CN102275304A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101106989A CN102275304A (en) 2011-04-29 2011-04-29 Integrated filling and forming process for single shearing rib of fan blade

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101106989A CN102275304A (en) 2011-04-29 2011-04-29 Integrated filling and forming process for single shearing rib of fan blade

Publications (1)

Publication Number Publication Date
CN102275304A true CN102275304A (en) 2011-12-14

Family

ID=45101185

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101106989A Pending CN102275304A (en) 2011-04-29 2011-04-29 Integrated filling and forming process for single shearing rib of fan blade

Country Status (1)

Country Link
CN (1) CN102275304A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104416923A (en) * 2013-08-28 2015-03-18 上海艾郎风电科技发展有限公司 Method for paving fiber clothes
CN108638541A (en) * 2018-05-02 2018-10-12 江苏金风科技有限公司 Blade shell and web are integrally formed and the method for blade forming
CN109397722A (en) * 2018-11-30 2019-03-01 深圳寰球乐飞技术有限公司 A kind of connection method and connection structure of the prefabricated web and blade shell of wind electricity blade

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101387263A (en) * 2008-10-24 2009-03-18 常州伯龙三维复合材料有限公司 Wind mill blade prepared by spacing structure weaving process and method thereof
CN101695871A (en) * 2009-11-12 2010-04-21 江苏九鼎新材料股份有限公司 Large wind force blade and manufacturing process thereof
CN101905538A (en) * 2010-01-14 2010-12-08 连云港中复连众复合材料集团有限公司 Process for integrally manufacturing megawatt wind turbine blade

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101387263A (en) * 2008-10-24 2009-03-18 常州伯龙三维复合材料有限公司 Wind mill blade prepared by spacing structure weaving process and method thereof
CN101695871A (en) * 2009-11-12 2010-04-21 江苏九鼎新材料股份有限公司 Large wind force blade and manufacturing process thereof
CN101905538A (en) * 2010-01-14 2010-12-08 连云港中复连众复合材料集团有限公司 Process for integrally manufacturing megawatt wind turbine blade

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104416923A (en) * 2013-08-28 2015-03-18 上海艾郎风电科技发展有限公司 Method for paving fiber clothes
CN108638541A (en) * 2018-05-02 2018-10-12 江苏金风科技有限公司 Blade shell and web are integrally formed and the method for blade forming
CN109397722A (en) * 2018-11-30 2019-03-01 深圳寰球乐飞技术有限公司 A kind of connection method and connection structure of the prefabricated web and blade shell of wind electricity blade
CN109397722B (en) * 2018-11-30 2024-02-09 深圳寰球乐飞技术有限公司 Connection method and connection structure of prefabricated web plate and blade shell of wind power blade

Similar Documents

Publication Publication Date Title
CN104029397B (en) The preparation facilities of a kind of technique for aircraft composite fuselage wallboard and preparation method
CN105128358A (en) Manufacturing method for wind power blade
CN102114706B (en) Method for forming frame, stringer and covering of composite material component through integrated co-curing
US7097731B2 (en) Method of manufacturing a hollow section, grid stiffened panel
CN101804714A (en) Composite material member with surface functional layer and RTM preparation method thereof
CN102220936A (en) Blade root structure made of bamboo composite material and manufacturing method thereof
CN106863874A (en) A kind of honeycomb method for shaping of complex-curved honeycomb sandwich construction
CN105856592A (en) Formation method of multi-beam multi-rib composite wallboard
CN106945308A (en) A kind of vacuum aided infiltration molding process method of insert-molded article
EP3019332B1 (en) Wind turbine blade
CN106965456A (en) A kind of leafy composite propeller forming method
CN106184744A (en) A kind of manufacture method of the bionical Insect wings of light-high-strength
CN107471682A (en) A kind of advanced composite material (ACM) cover plate available for the manufacture of honeycomb interlayer part
CN104441693A (en) Molding process method for novel composite material adhesive film of wind power generation blades
CN102275304A (en) Integrated filling and forming process for single shearing rib of fan blade
CN202071360U (en) Fan blade manufactured using fan blade shearing rib integral infusion forming technology
CN206718516U (en) Wind electricity blade leading edge bonds flange mould fast-positioning device
CN102672978B (en) Technique for manufacturing blade of wind-driven generator
CN106881879A (en) A kind of method that use second bonding technique manufactures adhesive bonding of composites structure
CN109203516B (en) Manufacturing method of wind power blade
CN106671316A (en) Making method for bonding angle mold for wind power generator vanes
JP2014527473A5 (en)
CN108688193A (en) The dimension shape method and its semi-finished product of structural foam, the method for mechanical processing and its structural foam forming part
CN101767469A (en) Integral moulding technology for large scale wind blade
CN202073721U (en) Fan blade made of single shear rib with integral filling and molding processes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20111214