Summary of the invention
Technical problem to be solved by this invention is to provide a kind of basement rock fractured formation mixed drilling well completion process.
The technical scheme that the present invention solves its technical problem is:
Basement rock fractured formation mixed drilling well completion process, its processing step is: 1. top unconsolidated formation to horizon d certain depth uses the mud normal circulation technology to creep into, be lowered to surface pipe after boring and use cement sealing, 2. horizon d uses air latent drift reverse circular technique to creep into, after 3. being drilled into the aquifer, when water column produces back pressure and affects drilling efficiency down-hole hammer to the hole, using gas lift reverse circulation technique instead creeps into, until target zone, 4. acidizing flushing
The piston well-flushing,
Air circulation,
The pumping for water pump completion, dive pumping for water pump at once after namely air circulation finishes is until pumping test is completed.
Preferably, after described acidizing flushing is the drilling well end-of-job, first carry out electrical measurement and sentence layer, determine the position, crack of target zone according to electrical measurement result and the data of sieving residue log, then calculate the hydrochloric acid consumption, determine concentration of hydrochloric acid, re-use the slush pump acid filling, static certain hour after acid filling makes hydrochloric acid and gapfiller that chemical reaction fully occur, decompose or softening filler, then inject and the clear water of hydrochloric acid content with volume in the hole from the aperture.
Preferably, during acid filling first with under the acid filling drilling tool at the bottom of the hole, the water filling pressure testing checks acid filling pipeline seal, then begins water filling, measures to inject clear water amount and aperture whether rout up the water yield consistent, if it is consistent with injection clear water amount to rout up the water yield, adopt disposable acid filling at the bottom of the hole, if inconsistent, adopt at the bottom of the hole first layer position, crack to begin successively upwards in each layer position, crack acid filling respectively, after acid filling finishes, drilling tool in the hole is proposed.
Preferably, concentration of hydrochloric acid is 15%~30%, and concentration of hydrochloric acid is generally 20% left and right, if the more repeatedly acid filling of filler or strengthen concentration of hydrochloric acid in the crack, but concentration can not surpass 30%, and be 4~8 hours quiescent time.
Preferably, described piston well-flushing has namely been annotated lower piston in clear water backward hole, when the piston depth of setting guarantees to draw piston on piston starting point below hydrostatic level, draw continuously piston or intermittently draw piston all can, the piston rising or falling speed is 1~3 meter per second, draws the piston cumulative time to be not less than 12 hours.
Preferably, the piston depth of setting is following 30 meters~50 meters of hydrostatic level.
Preferably, described air circulation is namely after the piston well-flushing finishes, employing is lowered to common drilling tool air compressor machine well-flushing or is lowered to the both arms drilling tool and common drilling tool employing gas lift reverse circulation well-flushing, less Kong Zhongke adopts foam blocking to coordinate air circulation in the water yield, to form larger suction force, the well-flushing duration reaches " water is clear husky clean " as principle take the aperture water outlet.
Know-why of the present invention:
Bedrock Crevice Water is composed the fracture zone of fracture that exists joint, structural fracture, weathering fissures and separation fracture to grow.2~3 millimeters of general Fracture Widths, 10~20 millimeters of large persons, rice more than long number rice to ten, watery is uneven, and the water yield is poor.Some gapfillers of filling usually in the crack, impact or stop up the charge for remittance passage causes water yield of well less.
The crack is less originally for basement rock fractured formation, the water yield is poor, usually bringing out mud and drilling cuttings when utilizing the conventional drilling construction technology stops up, long because of the common process drilling period again, Cheng Jinghou drilling cuttings, mud cake and charges are difficult for coming out, cause the less or anhydrous dry hole that becomes of single hole water yield, make drilling well lose meaning.For avoiding stopping up the less or anhydrous result of the water yield that causes, only have the research one novel drilling process of cover, avoid artificially stopping up the crack, also to as much as possible strengthen simultaneously the permeability in crack.
Method is exactly: the anti-blocking yield-increasing technology of basement rock fractured formation well (adopt air reverse circulation drilling, get into acidizing flushing after target zone, piston well-flushing, gas lift reverse circulation well-flushing or air compressor machine well-flushing).
Adopt air reverse circulation drilling, can avoid mud cake to stop up; Adopt air reverse circulation drilling can also guarantee drilling cuttings in the very first time from hole on bottom, avoid the repetition fragmentation that the part drilling cuttings is ground in borehole wall crack; Adopt air reverse circulation drilling can also rinse, carry out the charges in the crack, to increase the crack water permeable area.Make to greatest extent every crack all become the charge for remittance passage, to realize the single hole max water yield, reduce construction risk, reduce unnecessary investment, the environment pollution of avoiding mud to cause, fresh-water-saving resource.
Acidizing flushing is the effective measures of volume increase, and particularly the carbonate strata effect is very remarkable.Utilize hydrochloric acid to the chemical action of stratum and gapfiller, form a kind of extension crack and strengthen the crack, to reach the purpose that increases water yield.Acidizing flushing should be better in conjunction with the water filling working effect.
The piston well-flushing is the more creviced formation of the effective measures of getting through the crack passage, particularly filler.The piston well-flushing can be with the filler in the crack or the drilling cuttings fallen in the crack when creeping into release, to get through the purpose that the crack passage reaches increases water yield.
Gas lift reverse circulation well-flushing, air compressor machine well-flushing can be discharged wellhole with the sediment in boring, to guarantee effective drilling depth, avoid affecting water yield.
The anti-blocking yield-increasing technology points for attention of basement rock fractured formation water and technical essential:
Top unconsolidated formation or unconformable horizon d must be lowered to surface pipe or pump chamber pipe, and fixed with cement paste.
The reverse circulation drilling of air latent drift can only used without water hole section or the stratum that goes out a small amount of water section.If the stratum water yield is larger, anti-circulation can not be discharged to water outlet outside the hole again, and when the hole internal water accumulation was flowed or blow over and cover completely the down-hole hammer certain altitude, the down-hole hammer operating efficiency reduced, and when down-hole hammer creeps into efficient lower than 2 m/hs, pull out of hole and use gas lift reverse circulation technique instead and continue to creep into.
Gas lift reverse circulation creeps into, the sinking ratio of gas-water mixer can not be less than 1/5(sinking ratio: refer to that gas-water mixer imbeds the ratio that under water the degree of depth and gas-water mixer to air water tap top exports distance, sinking is than larger, and it is larger that generation pressure reduction forms reverse circulating ability).In time recharge clear water in the hole, make the aperture water level steady, guarantee larger sinking ratio.
Gas-water mixer is generally 3~4 times of gas-water mixer submersible depth with the drilling tool length down to drill bit, generally be no more than 7 times.
Acidizing flushing.The acid filling amount is that the target zone hole segment body of 2 times is long-pending.
Calculate hydrochloric acid consumption: Q=r
2Π 2H,
Q in formula---hydrochloric acid content (m3)
R---boring radius (m)
Π---pi
H---need acid filling hole segment length (m)
Determine concentration of hydrochloric acid.For guaranteeing safe acid filling, concentration of hydrochloric acid is generally 20% left and right, if the more repeatedly acid filling of filler or strengthen concentration of hydrochloric acid in the crack, but concentration can not surpass 30%.
Use the slush pump acid filling, first that acid filling drilling tool (or oil pipe) is lower at the bottom of the hole, water filling pressure testing (pressure test pressure should be when replacing hydrochloric acid pressure 50%) checks acid filling pipeline seal.Then begin water filling, whether measure injecting clear water amount and aperture, to rout up the water yield consistent.If inconsistent, acid filling can not be disposable firmly complete at the bottom of the hole, should begin to inject hydrochloric acid in first layer position, crack at the bottom of the hole, successively upwards in each layer position, crack difference acid filling.
After acid filling finishes, drilling tool (or oil pipe) in the hole is proposed, static 4~8 hours, make hydrochloric acid and gapfiller that chemical reaction fully occur, decompose or softening filler.Then inject and the clear water of hydrochloric acid content with volume in the hole from the aperture.Annotated lower piston in clear water backward hole.
5, piston well-flushing.The piston depth of setting is 30 meters~50 meters (on piston, starting point gets final product below hydrostatic level when drawing piston) below hydrostatic level.The piston rising or falling speed is 1~3 meter per second.Draw the piston cumulative time to be not less than 12 hours.
6, gas lift reverse circulation well-flushing, air compressor machine well-flushing.Adopt the gas lift reverse circulation well-flushing, the drilling tool water inlet will be positioned at the crack layer, and from going up most crack layer well-flushing successively downwards, until clean at the bottom of the hole.
Be lowered to common drilling tool air compressor machine well-flushing, the drilling tool depth of setting is determined according to the air compressor machine ability to bear, turns over the air water post as long as can form, and produces suction force and gets final product.Less Kong Zhongke adopts foam blocking to coordinate air circulation in the water yield, has formed larger suction force.The well-flushing duration reaches " water is clear husky clean " as principle take the aperture water outlet.
Gas lift reverse circulation well-flushing, air compressor machine well-flushing can be discharged wellhole with the sediment in boring, to guarantee effective drilling depth, avoid affecting water yield.
Compared with prior art, have the following advantages:
1, avoid or reduce the appearance of dry hole, reduce construction risk.
2, shorten well construction period, reduce unnecessary investment, reduce production costs.
3, do not use mud, fresh-water-saving resource, the environment pollution of avoiding mud construction or discharging to cause.
4, make to greatest extent every crack all become the charge for remittance passage, to realize the single hole max water yield.
The specific embodiment
Basement rock fractured formation mixed drilling well completion process, its processing step is: 1. top unconsolidated formation to horizon d certain depth uses the mud normal circulation technology to creep into, be lowered to surface pipe after boring and use cement sealing, 2. horizon d uses air latent drift reverse circular technique to creep into, after 3. being drilled into the aquifer, when water column produces back pressure and affects drilling efficiency down-hole hammer to the hole, using gas lift reverse circulation technique instead creeps into, until target zone, 4. acidizing flushing
The piston well-flushing,
Air circulation,
The pumping for water pump completion, dive pumping for water pump at once after namely air circulation finishes is until pumping test is completed.
After described acidizing flushing is the drilling well end-of-job, first carry out electrical measurement and sentence layer, determine the position, crack of target zone according to electrical measurement result and the data of sieving residue log, then calculate the hydrochloric acid consumption, determine concentration of hydrochloric acid, re-use the slush pump acid filling, static certain hour after acid filling, make hydrochloric acid and gapfiller that chemical reaction fully occur, decompose or softening filler, then inject and the clear water of hydrochloric acid content with volume in the hole from the aperture.
During acid filling first with under the acid filling drilling tool at the bottom of the hole, the water filling pressure testing checks acid filling pipeline seal, then begin water filling, whether measure injecting clear water amount and aperture, to rout up the water yield consistent, if rout up the water yield and inject that the clear water amount is consistent adopts disposable acid filling at the bottom of the hole, if inconsistent, adopt at the bottom of the hole first layer position, crack to begin successively upwards in each layer position, crack acid filling respectively, after acid filling finishes, drilling tool in the hole is proposed.
Concentration of hydrochloric acid is 15%~30%, and concentration of hydrochloric acid is generally 20% left and right, if the more repeatedly acid filling of filler or strengthen concentration of hydrochloric acid in the crack, but concentration can not surpass 30%, and be 4~8 hours quiescent time.
Described piston well-flushing has namely been annotated lower piston in clear water backward hole, when the piston depth of setting guarantees to draw piston on piston starting point below hydrostatic level, draw continuously piston or intermittently draw piston all can, the piston rising or falling speed is 1~3 meter per second, draws the piston cumulative time to be not less than 12 hours.
The piston depth of setting is following 30 meters~50 meters of hydrostatic level.
Described air circulation is namely after the piston well-flushing finishes, employing is lowered to common drilling tool air compressor machine well-flushing or is lowered to the both arms drilling tool and common drilling tool employing gas lift reverse circulation well-flushing, less Kong Zhongke adopts foam blocking to coordinate air circulation in the water yield, to form larger suction force, the well-flushing duration reaches " water is clear husky clean " as principle take the aperture water outlet.