CN102248985A - Ship body assembling method - Google Patents
Ship body assembling method Download PDFInfo
- Publication number
- CN102248985A CN102248985A CN2011101458916A CN201110145891A CN102248985A CN 102248985 A CN102248985 A CN 102248985A CN 2011101458916 A CN2011101458916 A CN 2011101458916A CN 201110145891 A CN201110145891 A CN 201110145891A CN 102248985 A CN102248985 A CN 102248985A
- Authority
- CN
- China
- Prior art keywords
- ship body
- integral assembly
- total
- shipyard
- always
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Revetment (AREA)
Abstract
The invention provides a ship body assembling method. After a ship body is constructed in a segmented way, all parts are integrally assembled. In the integral assembly process, all the parts are subjected to front and rear integral assembly on an integral assembly platform in advance, then are hoisted into a shipyard and are subjected to up-and-down integral assembly in the shipyard. Compared with the prior art, the method has the advantages that: welding time in the shipyard is shortened, the production safety of a welder is improved, and the using amount of supporting objects is reduced.
Description
Technical field
What the present invention relates to is a kind of total group of methods of dock of hull assemble method, especially hull, belongs to shipbuilding technical field in the traffic.
Background technology
Raising along with production-scale expansion and load-carrying ability, be extensive use of the technology of total group in the sectional construction depressed place in the shipbuilding, this technology is to shorten direct and effective method of building berth () cycle in the depressed place in, what generally use at present is always to organize up and down on total group platform earlier, total prescription case of total group before and after carry out in the depressed place back.It is still longer that this scheme the time takies in the depressed place time in assembling.
Summary of the invention
At above-mentioned deficiency, the technical problem to be solved in the present invention is to take the time in the depressed place when how further to reduce ship building, and proposes the shorter hull assemble method of a kind of depressed place intercycle.
Hull assemble method provided by the invention is always organized behind the sectional construction, and wherein always the group process is to carry out the total group in front and back on total group platform earlier, hangs in dock again and always organizes up and down in the depressed place.
Compared with prior art, the present invention has following advantage: since the weld length of total up and down group be shorter than before and after the weld length of total group, therefore after total up and down group just can shorten weld time in the depressed place.Welder position height is identical with the component height of total group platform composition during welding in the depressed place during total group, and can not side fall at the depressed place inner component, promptly can not will highly reduce, after the top of the highest position of weld after total group of total up and down group drop to waist, even a large amount of aloft work of welder becomes non-aloft work, improved welder's production safety.In the assembling of total group platform, because height relationships, the upholder of total group Duo one times than the upholder of total group of front and back up and down, and in the depressed place in the assembling because of having back always to organize, so used upholder can reduce and reduction can surpass half, then total upholder consumption reduces.
The specific embodiment
A kind of hull assemble method for each segmenting unit that completes, carries out the front and back assembling earlier on total group platform, promptly a plurality of unit of earlier front and back of same aspect being cut apart are assembled into the long section of this aspect.In dock, assemble up and down again, be about to the long section of different aspects, be assembled into multifaceted section from bottom to top, always dress up hull again.
If load-carrying ability is enough, said long section is the longest can be full captain, is exactly the combination for the aspect up and down of whole ship when then assembling up and down.
Claims (1)
1. a hull assemble method is always organized behind the sectional construction, it is characterized in that always the group process is to carry out the total group in front and back on total group platform earlier, hangs in dock again and always organizes up and down in the depressed place.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101458916A CN102248985A (en) | 2011-06-01 | 2011-06-01 | Ship body assembling method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101458916A CN102248985A (en) | 2011-06-01 | 2011-06-01 | Ship body assembling method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102248985A true CN102248985A (en) | 2011-11-23 |
Family
ID=44976640
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011101458916A Pending CN102248985A (en) | 2011-06-01 | 2011-06-01 | Ship body assembling method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102248985A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102874388A (en) * | 2012-10-23 | 2013-01-16 | 江苏省镇江船厂(集团)有限公司 | Rotatable towboat structure with superstructure built based on modularization |
CN105499818A (en) * | 2015-12-28 | 2016-04-20 | 广船国际有限公司 | Segmental manufacturing method for deck |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101439754A (en) * | 2008-12-18 | 2009-05-27 | 中国长江航运集团江东船厂 | Hull section non-allowance healing accuracy control process |
CN101811555A (en) * | 2009-12-21 | 2010-08-25 | 南通中远船务工程有限公司 | Section assembly control method of bulk freighter body in floating dock |
-
2011
- 2011-06-01 CN CN2011101458916A patent/CN102248985A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101439754A (en) * | 2008-12-18 | 2009-05-27 | 中国长江航运集团江东船厂 | Hull section non-allowance healing accuracy control process |
CN101811555A (en) * | 2009-12-21 | 2010-08-25 | 南通中远船务工程有限公司 | Section assembly control method of bulk freighter body in floating dock |
Non-Patent Citations (7)
Title |
---|
《广船科技》 20050625 但家华等 推进分段总组 缩短船台周期 , 第02期 * |
《广船科技》 20110331 李巧娜 实施串联造船 缩短船坞周期 , 第01期 * |
丁伟康: "巨型总段造船法介绍", 《中国造船工程学会造船工艺学术委员会壳舾涂一体化学组2008年学术会议论文集》 * |
但家华等: "推进分段总组 缩短船台周期", 《广船科技》 * |
冯运檀: "层式建造法在船台安装中的应用", 《造船技术》 * |
李寄明等: "优化造船流程,缩短船台周期", 《上海造船》 * |
李巧娜: "实施串联造船 缩短船坞周期", 《广船科技》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102874388A (en) * | 2012-10-23 | 2013-01-16 | 江苏省镇江船厂(集团)有限公司 | Rotatable towboat structure with superstructure built based on modularization |
CN105499818A (en) * | 2015-12-28 | 2016-04-20 | 广船国际有限公司 | Segmental manufacturing method for deck |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104627319B (en) | A kind of 27000DWT Chemical/Product Oil Tankers molten stainless steel cargo hold building technology | |
CN102582784A (en) | Process for sectionally putting up ship berths or docks | |
CN104588921B (en) | A kind of plate sheet welding anti-deforming structure and process | |
CN204771269U (en) | A special bed -jig for making boats and ships forecastle bulwark | |
CN103350735A (en) | Rudder horn and stern part segmentation installation process | |
CN102248985A (en) | Ship body assembling method | |
CN109277710A (en) | A kind of Large Container Ship case foot reinforced structure and process | |
CN202667896U (en) | Welding spatter proof device | |
CN203003355U (en) | Combined type welding backing unit | |
CN202295224U (en) | Embedded bracket tool for positioning and mounting tail fin of ship | |
CN106826087B (en) | A kind of Large Container Ship crack arrest steel construction method | |
CN102756973A (en) | Novel welded sling structure | |
CN204956504U (en) | Framework of a cast joint body structure | |
CN204846288U (en) | Hedge skin | |
CN204735939U (en) | Prefabricated workstation of barrel reinforcing ring | |
CN105108329A (en) | Self-adaptive double-side static shaft shoulder stirring head | |
CN106043593A (en) | Stiffening-U-rib both-side welding structure of orthotropic stiffening plate | |
CN202186838U (en) | Movable lifting eye | |
CN101844265A (en) | Wheel stern main machine axle tube subsection shell plating vertical fold welding line welding process | |
CN105002830B (en) | A kind of manufacture method of the small section of head tower | |
CN204184445U (en) | Aluminium alloy bicycle frame | |
CN204739366U (en) | Vertical slewing device's base | |
CN203832633U (en) | Novel vehicle basket | |
CN104401451B (en) | A kind of boats and ships moon pool manufacture method | |
CN203511978U (en) | Combined type side girder for oil tanker refit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20111123 |