CN102218650A - Process flow for manufacturing heat exchange circulating device of air conditioner external unit - Google Patents

Process flow for manufacturing heat exchange circulating device of air conditioner external unit Download PDF

Info

Publication number
CN102218650A
CN102218650A CN2011101299746A CN201110129974A CN102218650A CN 102218650 A CN102218650 A CN 102218650A CN 2011101299746 A CN2011101299746 A CN 2011101299746A CN 201110129974 A CN201110129974 A CN 201110129974A CN 102218650 A CN102218650 A CN 102218650A
Authority
CN
China
Prior art keywords
workpiece
time
press
bending
machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101299746A
Other languages
Chinese (zh)
Inventor
王起森
仕玉福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO HONGSEN HEAVY INDUSTRY Co Ltd
Original Assignee
QINGDAO HONGSEN HEAVY INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO HONGSEN HEAVY INDUSTRY Co Ltd filed Critical QINGDAO HONGSEN HEAVY INDUSTRY Co Ltd
Priority to CN2011101299746A priority Critical patent/CN102218650A/en
Publication of CN102218650A publication Critical patent/CN102218650A/en
Pending legal-status Critical Current

Links

Abstract

The invention relates to a process flow for manufacturing a heat exchange circulating device of an air conditioner external unit. The process flow comprises the following steps of: blanking by utilizing a plate shearing machine; punching and edging a die by utilizing a press machine; bending by utilizing a bending machine, and welding by utilizing an electric welding machine, wherein the power range of the press machine is 30-35 KW/h, and the power range of the bending machine is 5.5-7.5 KW/h. The process flow solves the welding locating mode and the problems of low efficiency of adhering a label plate, easiness of distortion of the label plate, and the like, and is beneficial to improving the product precision and quality and avoiding the phenomenon of hole flanging deflection and waste adhesion occurring in a screw thread flanging hole on a parent part.

Description

A kind of outdoor machine of air-conditioner heat exchange EGR manufacture craft flow process
Technical field
The invention belongs to household electrical appliances and make the field, be specifically related to a kind of outdoor machine of air-conditioner heat exchange EGR manufacture craft flow process.
Background technology
The heat exchange EGR belongs to automatically controlled part principal organ in outdoor machine of air-conditioner, the required precision height, welding sequence is many, and there is big problem in existing each operation of technological process, it is unreasonable at first to weld locate mode, have hidden danger of quality, secondly, process sequence is unreasonable, influence product precision and quality, once more, some operation such as label stickup process efficiency are low, and the product of formation is easily distorted.The heat exchange EGR exists electric elements quantity many, and product is had strict demand, and the waste material lay special stress on that produces during especially to machining screw flange hole can not have adhesion; The vibrations that produce because of when work can make the adhesion waste material come off, and cause electrical short-circuit and damage whole device.Thread Pilot hole Sheet Metal Forming Technology on the parent part generally takes flat punch to dash a hole flanging moulding in advance; But exist flat punch in advance towards the time waste material adhesion phenomenon that produces.
Summary of the invention
The present invention has overcome the deficiencies in the prior art, proposed a kind of outdoor machine of air-conditioner heat exchange EGR manufacture craft flow process, described technological process has solved the welding locate mode, has improved product precision and quality, it is low to have solved stickup label process efficiency, problems such as easy distortion; Stopped hole flanging deflection and waste material adhesion phenomenon are appearred in screw thread flange hole on the parent part.
Technical scheme of the present invention is: a kind of outdoor machine of air-conditioner heat exchange EGR manufacture craft flow process, described technological process utilizes plate shearing machine to carry out blanking, utilize press to carry out mould punching press and deburring, utilize bender to carry out bending, utilize electric welding machine to weld, the power bracket of described press is 30KW/h-35KW/h, and the power bracket of described bender is 5.5KW/h-7.5KW/h;
Described technological process comprises following operation:
Operation 1. is utilized the plate shearing machine blanking according to Workpiece structure;
Operation 2. utilizes press that workpiece is carried out the mould beading, and the compacting time of staying is 30-60 second;
Operation 3. utilizes press that workpiece is carried out the die trimming punching, adopts cross pierce punch, and described cross pierce punch can be divided into the pre-punched hole waste material four parts, makes adhesion firm, difficult drop-off, trimming and piercing die time: 15-30 second;
Operation 4. utilizes press that workpiece is carried out mould bending up and down, and the bending time of staying is 30-70 second up and down;
Operation 5. utilizes bender that workpiece is carried out bending, and the bending time is 22-30 second;
Operation 6. utilizes electric welding machine that workpiece is positioned and welds, and be 18-30 second weld interval;
7. pairs of workpiece mounting brackets of operation;
8. pairs of workpiece of operation are pasted the terminal warning sign;
9. pairs of workpiece solder joints of operation place carries out antirust paint and handles, time 65-85 second;
Operation 10. entruckings warehouse-in.
For operation 3, the thread Pilot hole Sheet Metal Forming Technology is: carry out the thread Pilot hole hole flanging after the punching again, make the one-shot forming of thread Pilot hole hole flanging, turn over inclined to one side phenomenon when solving the screw thread hole flanging.
The present invention has following beneficial effect:
1) the present invention has reduced operation, increases work efficiency greatly.
2) the present invention improves product percent of pass greatly.
3) thread Pilot hole Sheet Metal Forming Technology of the present invention is: carry out the thread Pilot hole hole flanging after the punching again, make the one-shot forming of thread Pilot hole hole flanging, turn over inclined to one side phenomenon when solving the screw thread hole flanging.
4) the present invention changes the pierce punch end into " cross " shape with original " plane ", because of " cross " shape drift can be divided into original pre-punched hole waste material four parts, makes adhesion firm, difficult drop-off.
The specific embodiment
Embodiment 1:
Operation 1. plate shearing machine blankings;
Operation 2. mould beadings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/40 seconds);
Operation 3. die trimming punchings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/19 seconds);
The bending (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/50 seconds) up and down of operation 4. moulds;
Operation 5. bendings (equipment W67K-40/1250 bender, main motor current 5.5KW/h) (production efficiency 1 time/26 seconds);
Operation 6. weldering hooks (2 of quantity, production efficiency 1 time/20 seconds);
Operation 7. weldering Location resilient pieces (with welding tooling location, production efficiency 1 time/25 seconds);
Mounting bracket (3 on screw, production efficiency 1 time/32 seconds);
Operation 8. is pasted " terminal warning sign " (with " mark " positioning mode, production efficiency 1 time/14 seconds);
Antirust paint (production efficiency 1 time/65 seconds) is smeared at operation 9. butt welding point places;
Operation 10. entruckings warehouse-in.
Embodiment 2:
Operation 1. plate shearing machine blankings;
Operation 2. mould beadings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/39 seconds);
Operation 3. die trimming punchings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/21 seconds);
The bending (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/41 seconds) up and down of operation 4. moulds;
Operation 5. bendings (equipment W67K-40/1250 bender, main motor current 5.5KW/h) (production efficiency 1 time/26 seconds);
Operation 6. weldering hooks (2 of quantity, production efficiency 1 time/20 seconds);
Operation 7. weldering Location resilient pieces (with welding tooling location, production efficiency 1 time/23 seconds);
Mounting bracket (3 on screw, production efficiency 1 time/32 seconds);
Operation 8. is pasted " terminal warning sign " (with " mark " positioning mode, production efficiency 1 time/15 seconds);
Antirust paint (production efficiency 1 time/76 seconds) is smeared at operation 9. butt welding point places;
Operation 10. entruckings warehouse-in.
Existing technological process: 1. reduced operation (former operation 4. thread Pilot hole hole flangings); 2. increase work efficiency; 3. improve the quality of products (the screw thread hole flanging is inclined to one side, and waste material adhesion and problem such as come off solve).
Embodiment 3:
Operation 1. plate shearing machine blankings;
Operation 2. mould beadings; (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/60 seconds);
Operation 3. die trimming punchings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/21 seconds);
The bending (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/60 seconds) up and down of operation 4. moulds;
Operation 5. bendings (equipment W67K-40/1250 bender, main motor current 5.5KW/h) (production efficiency 1 time/26 seconds);
Operation 6. weldering hooks (2 of quantity, production efficiency 1 time/20 seconds);
Operation 7. weldering Location resilient pieces (with welding tooling location, production efficiency 1 time/23 seconds);
Mounting bracket (3 on screw, production efficiency 1 time/32 seconds);
Operation 8. is pasted " terminal warning sign " (with " mark " positioning mode, production efficiency 1 time/16 seconds);
Antirust paint (production efficiency 1 time/75 seconds) is smeared at operation 9. butt welding point places;
Operation 10. entruckings warehouse-in.
Existing technological process: 1. reduced operation (former operation 4. thread Pilot hole hole flangings); 2. increase work efficiency (operation 9 reaches 50%); 3. improve the quality of products (the screw thread hole flanging is inclined to one side, and waste material adhesion and problem such as come off solve).
Embodiment 4:
Operation 1. plate shearing machine blankings;
Operation 2. mould beadings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/38 seconds);
Operation 3. die trimming punchings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/21 seconds);
The bending (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/69 seconds) up and down of operation 4. moulds;
Operation 5. bendings (equipment W67K-40/1250 bender, main motor current 5.5KW/h) (production efficiency 1 time/26 seconds);
Operation 6. weldering hooks (2 of quantity, production efficiency 1 time/20 seconds);
Operation 7. weldering Location resilient pieces (with welding tooling location, production efficiency 1 time/23 seconds);
Mounting bracket (3 on screw, production efficiency 1 time/30 seconds);
Operation 8. is pasted " terminal warning sign " (with " mark " positioning mode, production efficiency 1 time/14 seconds);
Antirust paint (production efficiency 1 time/76 seconds) is smeared at operation 9. butt welding point places;
Operation 10. entruckings warehouse-in.
Existing technological process: 1. reduced operation (former operation 4. thread Pilot hole hole flangings); 2. increase work efficiency (operation 9 reaches 70%); 3. improve the quality of products (the screw thread hole flanging is inclined to one side, and waste material adhesion and problem such as come off solve).
Embodiment 5:
Operation 1. plate shearing machine blankings;
Operation 2. mould beadings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/58 seconds);
Operation 3. die trimming punchings (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/21 seconds);
The bending (equipment J31-315 press, main motor current 30KW/h) (production efficiency 1 time/30 seconds) up and down of operation 4. moulds;
Operation 5. bendings (equipment W67K-40/1250 bender, main motor current 5.5KW/h) (production efficiency 1 time/26 seconds);
Operation 6. weldering hooks (2 of quantity, production efficiency 1 time/21 seconds);
Operation 7. weldering Location resilient pieces (with welding tooling location, production efficiency 1 time/23 seconds);
Mounting bracket (3 on screw, production efficiency 1 time/30 seconds);
Operation 8. is pasted " terminal warning sign " (with " mark " positioning mode, production efficiency 1 time/13 seconds);
Antirust paint (production efficiency 1 time/66 seconds) is smeared at operation 9. butt welding point places;
Operation 10. entruckings warehouse-in.
Existing technological process: 1. reduced operation (former operation 4. thread Pilot hole hole flangings); 2. increase work efficiency (operation 9 reaches 84%); 3. improve the quality of products (the screw thread hole flanging is inclined to one side, and waste material adhesion and problem such as come off solve).

Claims (2)

1. outdoor machine of air-conditioner heat exchange EGR manufacture craft flow process, it is characterized in that: described technological process utilizes plate shearing machine to carry out blanking, utilize press to carry out mould punching press and deburring, utilize bender to carry out bending, utilize electric welding machine to weld, the power bracket of described press is 30KW/h-35KW/h, and the power bracket of described bender is 5.5KW/h-7.5KW/h;
Described technological process comprises following operation:
Operation 1. is utilized the plate shearing machine blanking according to Workpiece structure;
Operation 2. utilizes press that workpiece is carried out the mould beading, and the compacting time of staying is 30-60 second;
Operation 3. utilizes press that workpiece is carried out the die trimming punching, adopts cross pierce punch, and described cross pierce punch can be divided into the pre-punched hole waste material four parts, makes adhesion firm, difficult drop-off, trimming and piercing die time: 15-30 second;
Operation 4. utilizes press that workpiece is carried out mould bending up and down, and the bending time of staying is 30-70 second up and down;
Operation 5. utilizes bender that workpiece is carried out bending, and the bending time is 22-30 second;
Operation 6. utilizes electric welding machine that workpiece is positioned and welds, and be 18-30 second weld interval;
7. pairs of workpiece mounting brackets of operation;
8. pairs of workpiece of operation are pasted the terminal warning sign;
9. pairs of workpiece butt welding point of operation place carries out antirust paint and handles, time 65-85 second;
Operation 10. entruckings warehouse-in.
2. outdoor machine of air-conditioner heat exchange EGR manufacture craft flow process according to claim 1, it is characterized in that: for operation 3, the thread Pilot hole Sheet Metal Forming Technology is: carry out the thread Pilot hole hole flanging after the punching again, make the one-shot forming of thread Pilot hole hole flanging, turn over inclined to one side phenomenon when solving the screw thread hole flanging.
CN2011101299746A 2011-05-19 2011-05-19 Process flow for manufacturing heat exchange circulating device of air conditioner external unit Pending CN102218650A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101299746A CN102218650A (en) 2011-05-19 2011-05-19 Process flow for manufacturing heat exchange circulating device of air conditioner external unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101299746A CN102218650A (en) 2011-05-19 2011-05-19 Process flow for manufacturing heat exchange circulating device of air conditioner external unit

Publications (1)

Publication Number Publication Date
CN102218650A true CN102218650A (en) 2011-10-19

Family

ID=44775489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101299746A Pending CN102218650A (en) 2011-05-19 2011-05-19 Process flow for manufacturing heat exchange circulating device of air conditioner external unit

Country Status (1)

Country Link
CN (1) CN102218650A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104786024A (en) * 2015-04-14 2015-07-22 青岛鸿森重工股份有限公司 Manufacturing technological process of valve supporting device
CN104786023A (en) * 2015-04-14 2015-07-22 青岛鸿森重工股份有限公司 Air conditioner motor support manufacturing technological process
CN106002094A (en) * 2016-06-08 2016-10-12 洛阳三信石化设备有限公司 Process for manufacturing spiral baffle plate of shell-and-tube heat exchanger
CN106584015A (en) * 2016-11-23 2017-04-26 滁州聚保利电装有限公司 Processing technology for reinforcements for refrigerator compressor

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030183377A1 (en) * 2002-03-28 2003-10-02 Carrier Corporation High fin density coil design utilizing precoated fin stock
CN1943973A (en) * 2006-11-07 2007-04-11 管保清 Method for producing aluminum plate-fin heat exchanger
US20100139094A1 (en) * 2009-01-23 2010-06-10 Goodman Global, Inc. Method and System for Manufacturing Aluminum Tube and Fin Heat Exchanger Using Open Flame Brazing, and Product Produced Thereby
CN102003841A (en) * 2010-09-30 2011-04-06 广东美的电器股份有限公司 Heat exchanger and manufacturing method thereof and room air conditioner with heat exchanger

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030183377A1 (en) * 2002-03-28 2003-10-02 Carrier Corporation High fin density coil design utilizing precoated fin stock
CN1943973A (en) * 2006-11-07 2007-04-11 管保清 Method for producing aluminum plate-fin heat exchanger
US20100139094A1 (en) * 2009-01-23 2010-06-10 Goodman Global, Inc. Method and System for Manufacturing Aluminum Tube and Fin Heat Exchanger Using Open Flame Brazing, and Product Produced Thereby
CN102003841A (en) * 2010-09-30 2011-04-06 广东美的电器股份有限公司 Heat exchanger and manufacturing method thereof and room air conditioner with heat exchanger

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104786024A (en) * 2015-04-14 2015-07-22 青岛鸿森重工股份有限公司 Manufacturing technological process of valve supporting device
CN104786023A (en) * 2015-04-14 2015-07-22 青岛鸿森重工股份有限公司 Air conditioner motor support manufacturing technological process
CN106002094A (en) * 2016-06-08 2016-10-12 洛阳三信石化设备有限公司 Process for manufacturing spiral baffle plate of shell-and-tube heat exchanger
CN106584015A (en) * 2016-11-23 2017-04-26 滁州聚保利电装有限公司 Processing technology for reinforcements for refrigerator compressor

Similar Documents

Publication Publication Date Title
CN104841761B (en) A kind of alloy sheets electromagnetism piercing and flanging manufacturing process and device
CN108080901A (en) Electric motor end cap manufacturing method
CN102218650A (en) Process flow for manufacturing heat exchange circulating device of air conditioner external unit
CN102161149A (en) Technical process of manufacturing sheet metal components of automobile left and right wind guide covers
CN102913657B (en) A kind of plate flange air valve body and preparation method thereof altogether
CN202411248U (en) Rivetless riveting assembly
CN103264260B (en) Processing technology and mold of electrical oil heater seal cover spot-welding part
CN103182606A (en) Method for producing laser welding tailored blanks with different thicknesses
CN104786024A (en) Manufacturing technological process of valve supporting device
CN104723043A (en) Manufacturing technological process for fan supporting plate
CN104440003A (en) Manufacture process of air-conditioner outdoor unit heat-exchange cycle device
CN104227331A (en) Production technology process for heat exchange circulation device of air-conditioner external unit
CN200951448Y (en) Pattern die for puncture plate materials
CN106624681A (en) Production process for heat exchange circulation device
CN207463883U (en) Automatic bending machine for battery lug structure
CN102198581B (en) Manufacturing process for air temperature adjusting bottom plate mechanism
CN208991506U (en) A kind of attached type compensation rectifier of stamping parts multiple spot
CN107755972A (en) A kind of electrical box preparation method
CN104439905A (en) Manufacture process of air temperature regulation baseplate mechanism
CN201841410U (en) High-frequency welded tube punching set
CN201267079Y (en) Metal framework of display screen panel
CN204365848U (en) Anode steel claw Bending Die for Cross Beam tool
CN201750305U (en) Rotor coil lead wire bending module
CN104786023A (en) Air conditioner motor support manufacturing technological process
CN202655781U (en) Brake shoe roll projection welding machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111019