CN102208779A - Method for rapidly inserting cable into sleeve - Google Patents
Method for rapidly inserting cable into sleeve Download PDFInfo
- Publication number
- CN102208779A CN102208779A CN2011100360639A CN201110036063A CN102208779A CN 102208779 A CN102208779 A CN 102208779A CN 2011100360639 A CN2011100360639 A CN 2011100360639A CN 201110036063 A CN201110036063 A CN 201110036063A CN 102208779 A CN102208779 A CN 102208779A
- Authority
- CN
- China
- Prior art keywords
- cable
- spool
- rope
- line pipe
- pull rope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The invention discloses a method for rapidly inserting a cable into a sleeve, which belongs to a construction method for paving the cables and aims to achieve convenience of construction, high efficiency, low cost and capability of inserting the cable into the plastic sleeve. The method comprises the following specific steps of: drilling a threading hole on a pipe wall close to the inlet end of a line pipe; inserting a guide rope into the threading hole, and connecting the guide rope with a piston arranged in the line pipe; introducing compressed air from the inlet end of the line pipe until the piston is pushed out of the outlet end of the line pipe; leading the tail end of the guide rope out of the inlet end of the line pipe, connecting the guide rope with a pulling rope, and pulling the rope end of the pulling rope to the outlet end of the line pipe by using the guide rope; and fixedly connecting the tail end of the pulling rope with the end of the cable, and pulling the end of the cable out of the outlet end of the line pipe by using the pulling rope. The method has a plurality of advantages of convenience of construction, labor saving, high efficiency, low cost and the like, and is ideal for inserting the cable into the protection sleeve.
Description
Technical field: the present invention relates to a kind of cable be penetrated the method for protective casing, belong to the construction method of cable laying line.
Background technology: along with the development of urban service, the cable of infrastructure such as universal demand electric power, telecommunications is gone into operation in the ground; In order to protect cable, in burying the work progress of cable underground, require usually cable is penetrated in the plastic bushing.At present, generally all be to utilize bamboo pole to come the pilot cable line to penetrate plastic bushing, though operation sequence is simple,, thereby there is defective because this method is more original:
1) because of the restriction of bamboo pole length, can only segmentation wear; Not only efficient is lower, and the consumption of pipe joint is also more, construction cost is higher;
2) big, the poling of the resistance that wears many cables simultaneously difficulty relatively;
3) wear in the process because bamboo pole need occupy bigger space, therefore need to increase the diameter of plastic bushing, thereby cause construction cost to rise;
4) because bamboo pole is hard, the relatively difficulty of turning, therefore require the radius of turn of plastic bushing bigger, increased the consumption of difficulty of construction and plastic bushing.
Summary of the invention: at the above-mentioned defective that exists in the prior art, the present invention aims to provide a kind of easy construction, efficient height, the quick poling method of cable that cost is low.
To achieve these goals, the present invention by the following technical solutions, concrete steps are as follows:
1) boring through wires hole near on the tube wall of spool arrival end;
2) strop being passed above-mentioned through wires hole is connected with the piston that places described spool;
3) arrival end from spool feeds compressed air, until described piston is released from the port of export of spool;
4) end of described strop is drawn with pull rope from the arrival end of spool be connected, the fag end of described pull rope is pulled to the port of export of spool by strop;
5) end of pull rope is fixedlyed connected with the termination of cable, the termination of described cable is pulled out from the port of export of spool by this pull rope.
On the basis of technique scheme, through wires hole is obliquely installed along the direction of motion of piston.
Compared with the prior art, the technique scheme that the present invention adopts has plurality of advantages, makes a concrete analysis of as follows:
1) owing to substitute bamboo pole with pull rope, therefore every section poling distance can be prolonged significantly, has both improved efficiency of construction, reduced again pipe joint consumption, reduced construction cost;
2) substitute bamboo pole with pull rope, become the pulling force of the reasoning of bamboo pole into pull rope, therefore easy to operate, laborsaving;
3) substitute bamboo pole with pull rope and can also overcome the bamboo pole big defective that takes up space, thereby make the plastic bushing of same diameter can hold more or thicker cable, reduced construction cost;
4) because pull rope is soft, so turning resistance is less, and the radius of turn of plastic bushing also can reduce thereupon, not only convenient construction, but also save the consumption of plastic bushing.
Description of drawings:
Fig. 1 is the operation schematic diagram of strop poling in the work progress of the present invention;
Fig. 2 is the operation schematic diagram of pull rope poling in the work progress of the present invention;
Fig. 3 is the operation schematic diagram of cable poling in the work progress of the present invention.
Among the figure: spool 1 piston 2 strops 3 through wires holes 4 compressed air hoses 5 pull ropes 6 cables 7
Embodiment: the invention will be further described below in conjunction with accompanying drawing and specific embodiment:
Shown in Fig. 1~3, concrete steps are as follows:
1) bores through wires hole 4 at tube wall place near spool 1 arrival end;
2) strop 3 being passed through wires hole 4 is connected with the piston 2 that places spool 1;
3) with the arrival end of compressed air hose 5 insertion spools 1, feed compressed air promotion piston 2 and travel forward, deviate from from the port of export of spool 1 until this piston;
4) extract compressed air hose 5, the end of strop 3 is drawn from the arrival end of spool 1; Then strop 3 is connected with pull rope 6, the fag end of pull rope 6 is pulled to the port of export of spool 1 by strop 3;
5) end of pull rope 6 is fixedlyed connected with the termination of cable 7, the termination of cable 7 is pulled out from the port of export of spool 1 by this pull rope 6.
Above-mentioned be among the embodiment, in order to reduce the resistance of strop 3 in the poling process, through wires hole 4 preferably is obliquely installed along the directions of motion of piston 2.
Claims (2)
1. quick poling method of cable is characterized in that concrete steps are as follows:
1) bores through wires hole at tube wall place near the spool arrival end;
2) strop being passed above-mentioned through wires hole is connected with the piston that places described spool;
3) arrival end from spool feeds compressed air, until described piston is released from the port of export of spool;
4) end of described strop is drawn with pull rope from the arrival end of spool be connected, the fag end of described pull rope is pulled to the port of export of spool by strop;
5) end of pull rope is fixedlyed connected with the termination of cable, the termination of described cable is pulled out from the port of export of spool by this pull rope.
2. the quick poling method of cable according to claim 1, it is characterized in that: through wires hole is obliquely installed along the direction of motion of piston.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100360639A CN102208779A (en) | 2011-02-11 | 2011-02-11 | Method for rapidly inserting cable into sleeve |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100360639A CN102208779A (en) | 2011-02-11 | 2011-02-11 | Method for rapidly inserting cable into sleeve |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102208779A true CN102208779A (en) | 2011-10-05 |
Family
ID=44697488
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011100360639A Pending CN102208779A (en) | 2011-02-11 | 2011-02-11 | Method for rapidly inserting cable into sleeve |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102208779A (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103364907A (en) * | 2013-07-23 | 2013-10-23 | 国家电网公司 | Method enabling optical fibers to penetrate into tube |
CN103646728A (en) * | 2013-12-11 | 2014-03-19 | 中国船舶重工集团公司第七〇五研究所 | Threading method for super length-diameter ratio cable |
CN103775062A (en) * | 2013-07-25 | 2014-05-07 | 中国石油天然气股份有限公司 | Coiled tubing pressure piston conveying device and method |
CN104092153A (en) * | 2014-07-29 | 2014-10-08 | 中国海洋石油总公司 | Method for allowing plurality of submarine cables to penetrate through same J-shaped pipe |
CN104516078A (en) * | 2013-09-27 | 2015-04-15 | 国家电网公司 | Method and special-purpose tool for enabling fiber to penetrate into flexible metal conduit |
CN104538903A (en) * | 2015-01-19 | 2015-04-22 | 吴申龙 | Pipe penetrating device for wire |
CN106374395A (en) * | 2016-10-13 | 2017-02-01 | 山东钢铁股份有限公司 | Cable traction device used for conduits and cable pipe installation paving method |
CN108387990A (en) * | 2018-03-30 | 2018-08-10 | 深圳市创鑫激光股份有限公司 | Gas-pushing pipeline self-threading method and apparatus |
CN110202326A (en) * | 2019-07-01 | 2019-09-06 | 浙江国际海运职业技术学院 | A kind of stern seal of tube oil pipe mounting structure and installation method |
CN110401144A (en) * | 2019-06-14 | 2019-11-01 | 国网河南省电力公司灵宝市供电公司 | A method of cable penetration cable tunnel is guided using brake trotter sling |
CN110474258A (en) * | 2019-08-22 | 2019-11-19 | 台州市岩土工程有限公司 | A kind of high-efficiency pipeline threading system and construction method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN87200811U (en) * | 1987-01-27 | 1988-02-17 | 周俊明 | High speed piston pin for cable laying |
US6651959B1 (en) * | 2002-05-28 | 2003-11-25 | Michael Whitmer | Mechanical cable threader |
-
2011
- 2011-02-11 CN CN2011100360639A patent/CN102208779A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN87200811U (en) * | 1987-01-27 | 1988-02-17 | 周俊明 | High speed piston pin for cable laying |
US6651959B1 (en) * | 2002-05-28 | 2003-11-25 | Michael Whitmer | Mechanical cable threader |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103364907B (en) * | 2013-07-23 | 2015-08-26 | 国家电网公司 | A kind of optical fiber pipe penetration method |
CN103364907A (en) * | 2013-07-23 | 2013-10-23 | 国家电网公司 | Method enabling optical fibers to penetrate into tube |
CN103775062A (en) * | 2013-07-25 | 2014-05-07 | 中国石油天然气股份有限公司 | Coiled tubing pressure piston conveying device and method |
CN104516078B (en) * | 2013-09-27 | 2018-02-06 | 国家电网公司 | Optical fiber is penetrated into armoured method and its specific purpose tool |
CN104516078A (en) * | 2013-09-27 | 2015-04-15 | 国家电网公司 | Method and special-purpose tool for enabling fiber to penetrate into flexible metal conduit |
CN103646728A (en) * | 2013-12-11 | 2014-03-19 | 中国船舶重工集团公司第七〇五研究所 | Threading method for super length-diameter ratio cable |
CN104092153A (en) * | 2014-07-29 | 2014-10-08 | 中国海洋石油总公司 | Method for allowing plurality of submarine cables to penetrate through same J-shaped pipe |
CN104092153B (en) * | 2014-07-29 | 2016-09-14 | 中国海洋石油总公司 | A plurality of sea cable shares the pipe penetration method of a J-shaped pipe |
CN104538903A (en) * | 2015-01-19 | 2015-04-22 | 吴申龙 | Pipe penetrating device for wire |
CN106374395A (en) * | 2016-10-13 | 2017-02-01 | 山东钢铁股份有限公司 | Cable traction device used for conduits and cable pipe installation paving method |
CN108387990A (en) * | 2018-03-30 | 2018-08-10 | 深圳市创鑫激光股份有限公司 | Gas-pushing pipeline self-threading method and apparatus |
CN110401144A (en) * | 2019-06-14 | 2019-11-01 | 国网河南省电力公司灵宝市供电公司 | A method of cable penetration cable tunnel is guided using brake trotter sling |
CN110202326A (en) * | 2019-07-01 | 2019-09-06 | 浙江国际海运职业技术学院 | A kind of stern seal of tube oil pipe mounting structure and installation method |
CN110474258A (en) * | 2019-08-22 | 2019-11-19 | 台州市岩土工程有限公司 | A kind of high-efficiency pipeline threading system and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102208779A (en) | Method for rapidly inserting cable into sleeve | |
CN101257196B (en) | Electric gas tube lead wire penetrating method | |
CN202473321U (en) | High-intensity, curve-resistant, abrasion-resistant, flame-retardant and flexible cable of coal mining machine | |
CN106099771B (en) | Cable guide device | |
CN112490949A (en) | Pipe penetrating device for laying underground cable of electric power and electric appliance cabinet | |
CN101599622A (en) | A kind of method of threading in pipe | |
CN204729005U (en) | Two drilling rod horizontal directional drilling machine | |
CN109004579A (en) | A kind of network engineering threading apparatus | |
CN106229894A (en) | Crane span structure threading traction apparatus | |
CN206820369U (en) | Power cable float-ball type pipe perforator | |
CN206931937U (en) | A kind of multi-functional threading apparatus | |
CN102522718A (en) | Method for cable to penetrate into protection tube by using Dyneema rope | |
CN202206072U (en) | Cable pipeline dredging device | |
CN203516030U (en) | Non-metallic pipe oil-submersible screw pump oil production plant | |
CN204905774U (en) | Wiring threading apparatus | |
CN111682453B (en) | Efficient auxiliary operation's electric wire netting wiring equipment | |
CN202273477U (en) | Hollow steel continuous sucker rod | |
CN104213628B (en) | Jacking mechanism for underground pipe culvert engineering | |
CN207039088U (en) | A kind of water conservancy construction cable, which buries, puts support meanss | |
CN206775012U (en) | Multi-purpose seeker | |
CN105710093A (en) | Self-driving type cable tube bank cleaning device | |
CN201764159U (en) | Fast-assembled pipe fitting | |
CN107086501A (en) | Multi-purpose seeker | |
CN103441463A (en) | Long-distance cluster PE pipeline non-excavation crossing method | |
CN201075612Y (en) | Cable laying equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20111005 |