CN102168493A - Foldable protective barrier near side of building - Google Patents

Foldable protective barrier near side of building Download PDF

Info

Publication number
CN102168493A
CN102168493A CN 201110064780 CN201110064780A CN102168493A CN 102168493 A CN102168493 A CN 102168493A CN 201110064780 CN201110064780 CN 201110064780 CN 201110064780 A CN201110064780 A CN 201110064780A CN 102168493 A CN102168493 A CN 102168493A
Authority
CN
China
Prior art keywords
protective barrier
cross bar
building
column
connecting cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201110064780
Other languages
Chinese (zh)
Inventor
袁勇
符云钢
陈红
王安立
黎锐
王亚宁
李友叨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NORNOVA GROUP
Original Assignee
NORNOVA GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NORNOVA GROUP filed Critical NORNOVA GROUP
Priority to CN 201110064780 priority Critical patent/CN102168493A/en
Publication of CN102168493A publication Critical patent/CN102168493A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The invention discloses a foldable protective barrier near one side of a building. The foldable protective barrier comprises a plurality of upright pillars, wherein the bottom of each upright pillar is fixedly connected with a building surface; the upright pillars are sequentially connected in a hinged way by transverse bars at the top; and the axes of rotating shafts connected in a hinged way are parallel to one another. The size and the specification of parts take the prior art as reference, large-scale change is not needed. In the whole connection system of the protective barrier, the connection type of traditional steel pipe fastener is abandoned, fastener connection is completely given up, the cost is saved greatly and the whole weight of the protective barrier is reduced. A hinge connection structure is adopted between the upright pillars and the transverse bars at the top, so that the protective barrier is can be folded during transport and storage processes, the transport space is saved, fastener connection is not needed, and the transported weight and the storage space are reduced. During the installation of the foldable protective barrier, only hinges are rotated to a proper angle and the upright pillars are fixed on the building surface; both installation and detachment are convenient and time and labor force are saved greatly.

Description

Collapsible building is faced the frontier defense guard rail rod
Technical field
The invention belongs to technical field of building construction, be specifically related to a kind of be applied to the building main body construction stage face the frontier defense guard rail rod.
Background technology
In building construction process, according to safety standard and civilized construction requirement, make a large amount of four-hole five and face frontier defense and protect, for example the limit is faced at the hole, the stair limit, exterior wall faces limit etc., and its general structure all comprises vertical rod and cross bar, all adopts the steel pipe of φ 48X3.5mm usually, be formed by connecting by fastener between vertical rod and the cross bar, its steel quantity consumption is bigger, and steel pipe is a 3.85kg/ rice, and fastener is 1.25kg/.And as facing the cross bar that frontier defense is protected, its requirement for bearing capacity is not high, stipulate according to JGJ80-91 " building operations high-rise working technical specification of security ", facing the cross bar length of frontier defense in protecting is 2 meters, load requires to be 1000N, and the φ 48X3.5 steel pipe that adopts now, its intensity is considerably beyond instructions for use.Present building is faced the frontier defense guardrail and is existed problems such as transportation is inconvenient, installing/dismounting is loaded down with trivial details.
Summary of the invention
The object of the present invention is to provide a kind of convenient transportation, the building of being convenient to mount and dismount is faced the frontier defense guard rail rod.
For achieving the above object, the technical solution adopted in the present invention is: a kind of collapsible building is faced the frontier defense guard rail rod, comprise the column of fixedlying connected with flooring in a plurality of bottoms, be articulated and connected in turn by top cross bar between the column that the described shaft axis that is articulated and connected is parallel to each other.
Adopt the technique effect that technique scheme reached to be: the size of parts and specification all are to be benchmark with the prior art, do not need to do large-scale change.And abandoned the connected mode of traditional steel tube fastener in the linked system of whole protection railing, thoroughly abandoned the fastener connection, saved cost greatly, and alleviated the overall weight of guard rail.Adopt hinged structure between column of this guard rail and the top cross bar, made in the process of transporting and depositing, can fold, saved transport space; And do not need fastener to connect, alleviated the weight of transportation and the space of depositing.When installing, only need column be fixed on flooring get final product with hinge through to suitable angle, all very convenient in the time of installation and removal, saved time and labour greatly.
Further, for the overall structure that makes protective guard is more stable, also be provided with the stage casing cross bar in use, described column is provided with connecting cylinder, stage casing cross bar and connecting cylinder socket connection.The stage casing cross bar is separated with column, can further compress shared space, folding back, be convenient to transport and deposit, and the installation and removal of telescopic mounting structure are convenient and swift.
Further, described connecting cylinder crosswise fixed also can vertically be fixed on the column on the column.The stage casing cross bar only needs according to the direction of connecting cylinder cooperation to be installed and gets final product.
Further, be provided with the reed of chucking stage casing cross bar in the described connecting cylinder.Reed is set in connecting cylinder prevents that the stage casing cross bar from skidding off in connecting cylinder.
Description of drawings
The present invention is further detailed explanation below in conjunction with drawings and Examples:
Fig. 1 is the structural representation of the embodiment of the invention 1;
Fig. 2 is the structural representation of the embodiment of the invention 2;
Fig. 3 is the structural representation of the embodiment of the invention 3;
Fig. 4 is the A-A section enlarged diagram of the embodiment of the invention 3.
The specific embodiment
Embodiment 1:
As shown in Figure 1, the invention provides a kind of building and face the frontier defense guard rail rod, comprise that column 1, the top cross bar 2 made by the steel pipe commonly used of φ 48X3.5 are 38mm with the diameter of stage casing cross bar 3, holder has been welded in column 1 bottom, and the expansion bolt on the holder is fixed on column 1 on the flooring.Being hinge 4 between column 1 and top cross bar and the stage casing cross bar 3 connects.Column 1, top cross bar 2 and stage casing cross bar 3 form a parallelogram sturcutre by hinge 4, can fold placement in transportation with when depositing, and have saved a large amount of spaces.
Embodiment 2:
As shown in Figure 2, the structure of embodiment 2 is substantially the same manner as Example 1, still adopt hinge 4 to connect between its central post 1 and the top cross bar 2, its distinctive points is that the stage casing of present embodiment central post 1 welded a steel pipe as connecting cylinder 41, connecting cylinder 41 diameters are 41mm, and stage casing cross bar 3 inserts and forms protective guard in the connecting cylinder 41.Column 1 and top cross bar 2 stored collapsed when transporting and depositing, and stage casing cross bar 3 is deposited separately.
Embodiment 3:
As shown in Figure 3, Figure 4, the structure of embodiment 3 is substantially the same manner as Example 1, still adopt hinge 4 to connect between its central post 1 and the top cross bar 2, its distinctive points is that the stage casing of present embodiment central post 1 welded a steel pipe as connecting cylinder 42, connecting cylinder 42 diameters are 41mm, be provided with reed 43 in the connecting cylinder 42, it is capable that the end of stage casing cross bar 3 is L, inserts connecting cylinder 42 interior back natures and clamped by reed 43.
Above-described only is preferred implementation of the present invention; should be understood that; for a person skilled in the art; under the prerequisite that does not break away from structure of the present invention; can also make some distortion and improvement; these also should be considered as protection scope of the present invention, and these can not influence effect of the invention process and practical applicability.

Claims (5)

1. a collapsible building is faced the frontier defense guard rail rod, comprises the column of fixedlying connected with flooring in a plurality of bottoms, is articulated and connected in turn by top cross bar between the column, it is characterized in that, the described shaft axis that is articulated and connected is parallel to each other.
2. collapsible building as claimed in claim 1 is faced the frontier defense guard rail rod, it is characterized in that, also is provided with the stage casing cross bar, and described column is provided with connecting cylinder, stage casing cross bar and connecting cylinder socket connection.
3. collapsible building as claimed in claim 2 is faced the frontier defense guard rail rod, it is characterized in that, described connecting cylinder crosswise fixed is on column.
4. collapsible building as claimed in claim 3 is faced the frontier defense guard rail rod, it is characterized in that, described connecting cylinder vertically is fixed on the column.
5. face the frontier defense guard rail rod as claim 3 or 4 described collapsible buildings, it is characterized in that, be provided with the reed of chucking stage casing cross bar in the described connecting cylinder.
CN 201110064780 2011-03-17 2011-03-17 Foldable protective barrier near side of building Pending CN102168493A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110064780 CN102168493A (en) 2011-03-17 2011-03-17 Foldable protective barrier near side of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110064780 CN102168493A (en) 2011-03-17 2011-03-17 Foldable protective barrier near side of building

Publications (1)

Publication Number Publication Date
CN102168493A true CN102168493A (en) 2011-08-31

Family

ID=44489797

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110064780 Pending CN102168493A (en) 2011-03-17 2011-03-17 Foldable protective barrier near side of building

Country Status (1)

Country Link
CN (1) CN102168493A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102644383A (en) * 2012-05-08 2012-08-22 广西建工集团第五建筑工程有限责任公司 Assembly type floor protecting rail
CN114458034A (en) * 2021-12-20 2022-05-10 上海建工一建集团有限公司 Foldable lifting shielding wall and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006226077A (en) * 2005-02-21 2006-08-31 Shimizu Corp Guard fence
CN2841842Y (en) * 2005-11-11 2006-11-29 张克军 Protective guard
CN201280837Y (en) * 2008-09-11 2009-07-29 南京建工集团有限公司 Inserting type enclosure towards the limb for construction engineering
CN201411912Y (en) * 2009-05-14 2010-02-24 张恒亮 Corridor safety guard rail
CN201531113U (en) * 2009-10-13 2010-07-21 新疆天山汽车制造有限公司 Gas spring supporting movable guard bar
CN201567780U (en) * 2010-01-01 2010-09-01 王后忠 Lifting guardrail
CN201687149U (en) * 2010-05-27 2010-12-29 苏州万里铁艺制品厂 Connecting and fixing device for stair railings
CN201991243U (en) * 2011-03-17 2011-09-28 北城致远集团有限公司 Foldable border guard rail for building

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006226077A (en) * 2005-02-21 2006-08-31 Shimizu Corp Guard fence
CN2841842Y (en) * 2005-11-11 2006-11-29 张克军 Protective guard
CN201280837Y (en) * 2008-09-11 2009-07-29 南京建工集团有限公司 Inserting type enclosure towards the limb for construction engineering
CN201411912Y (en) * 2009-05-14 2010-02-24 张恒亮 Corridor safety guard rail
CN201531113U (en) * 2009-10-13 2010-07-21 新疆天山汽车制造有限公司 Gas spring supporting movable guard bar
CN201567780U (en) * 2010-01-01 2010-09-01 王后忠 Lifting guardrail
CN201687149U (en) * 2010-05-27 2010-12-29 苏州万里铁艺制品厂 Connecting and fixing device for stair railings
CN201991243U (en) * 2011-03-17 2011-09-28 北城致远集团有限公司 Foldable border guard rail for building

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102644383A (en) * 2012-05-08 2012-08-22 广西建工集团第五建筑工程有限责任公司 Assembly type floor protecting rail
CN102644383B (en) * 2012-05-08 2014-08-13 广西建工集团第五建筑工程有限责任公司 Assembly type floor protecting rail
CN114458034A (en) * 2021-12-20 2022-05-10 上海建工一建集团有限公司 Foldable lifting shielding wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN106499202B (en) The portable edge protection column of box-type for safety management in construction site
CN202272318U (en) Folding scaffold steel tube packing support
CN102168493A (en) Foldable protective barrier near side of building
CN105333634B (en) Rack of solar water heater foldable structure and solar water heater
CN201991243U (en) Foldable border guard rail for building
CN203066844U (en) Folding protective-type climbing ladder
CN205531248U (en) Construction scaffolding component
CN201691385U (en) Combined frame
CN105253460A (en) Adjustable multi-star shaped tool for large cylinder
CN204006760U (en) Rack of solar water heater foldable structure and solar water heater
CN211229427U (en) Scaffold for building construction
CN205203744U (en) Many meters word frocks with adjustable large -scale barrel is used
CN202272317U (en) Packaging rack for steel pipes of scaffold
CN109205482A (en) The hanging apparatus of curtain wall lighting roof
KR101359246B1 (en) Structure for connecting column in silo and silo using the same
CN202755632U (en) Scaffold
CN102561716A (en) Construction protecting rack
CN111997380A (en) Assembled discharging platform for high-rise building construction and construction method thereof
CN205602291U (en) Diesel oil pump, motor -driven pump water pipe containerized storage and transportation device
CN207568632U (en) A kind of telescopic wall supporting net strut
CN207633609U (en) A kind of connection structure for steel construction curtain wall
CN205531490U (en) Combined truss
CN204827517U (en) Emergent lifesaving cabin of mine
CN210828290U (en) Pole setting bottom connecting piece structure special for scaffold
CN112158747B (en) Truck-mounted crane rear supporting leg with departure angle

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110831