CN102155262B - Method for filling gas near roadway of coal mine gob-side entry retaining - Google Patents
Method for filling gas near roadway of coal mine gob-side entry retaining Download PDFInfo
- Publication number
- CN102155262B CN102155262B CN2011100579523A CN201110057952A CN102155262B CN 102155262 B CN102155262 B CN 102155262B CN 2011100579523 A CN2011100579523 A CN 2011100579523A CN 201110057952 A CN201110057952 A CN 201110057952A CN 102155262 B CN102155262 B CN 102155262B
- Authority
- CN
- China
- Prior art keywords
- cylinder rubber
- pneumatic bag
- rubber pneumatic
- gas
- goaf
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000003245 coal Substances 0.000 title claims abstract description 23
- 238000000034 method Methods 0.000 title claims abstract description 13
- 239000011435 rock Substances 0.000 claims abstract description 10
- 238000005065 mining Methods 0.000 claims abstract description 7
- 239000007789 gas Substances 0.000 claims description 34
- 238000009412 basement excavation Methods 0.000 claims description 8
- IJGRMHOSHXDMSA-UHFFFAOYSA-N Atomic nitrogen Chemical compound N#N IJGRMHOSHXDMSA-UHFFFAOYSA-N 0.000 claims description 6
- 101100008049 Caenorhabditis elegans cut-5 gene Proteins 0.000 claims description 3
- 229910052757 nitrogen Inorganic materials 0.000 claims description 3
- 230000008093 supporting effect Effects 0.000 abstract description 6
- 230000008901 benefit Effects 0.000 abstract description 4
- 210000004712 air sac Anatomy 0.000 abstract 6
- 238000005273 aeration Methods 0.000 abstract 1
- 238000007789 sealing Methods 0.000 abstract 1
- 239000000463 material Substances 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000000605 extraction Methods 0.000 description 2
- 238000012856 packing Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 239000006210 lotion Substances 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Abstract
The invention discloses a method for filling a gas near a roadway of coal mine gob-side entry retaining, comprising the following steps: firstly, arranging a gas pressurization room on the ground; then, arranging a gas booster pump in an underground mining area haulage roadway 3; arranging a cylinder rubber air sac as high as the mining height on one side close to a goaf along the gob-side entry retaining behind a coal face; aerating the cylinder rubber air sac arranged on one side close to a goaf by the gas booster pump until roof contacting; when the pressure gage of the gas booster pump displays that the pressure reaches the stress of a primary rock, stopping aerating, sealing the cylinder rubber air sac to finish the aeration operation of one cylinder rubber air sac; and when the coal face is continuously advanced, continuously arranging one cylinder rubber air sac behind one aerated cylinder rubber air sac every time the coal face is advanced by one step, and aerating one by one until one exhausting body on one side of the goaf 5 along the gob-side entry retaining 6 is filled and supported. The method is simple, is convenient to operate and has the advantages of small labor intensity of workers and good supporting effect.
Description
Technical field
The present invention relates to the other gas filling method in a kind of coal mine gob-side entry retaining lane, be particularly useful for the other filling in coal mining work plane gob side entry retaining lane.
Background technology
Gob side entry retaining is after the upper curtate work plane is adopted, and through adding strong supporting or adopt other effective ways, a crossheading of upper curtate work plane is remained, and uses as a crossheading when supplying the lower curtate working face extraction.As the major reform of production practice, gob side entry retaining utilization rate abroad is higher, but technology popularization speed just at the early-stage at home is not high.Gob side entry retaining have improve the coal resources rate of extraction, reduce drivage ratio, alleviate alternately nervous between the digging back production, reduce the work plane removal charge, improve remarkable advantage such as safety production condition, be to fail to find suitable gob-side entry retaining support material but restrict the main cause that this technology promotes the use of in China.The roadside packing material of domestic main use at present has spoil, concrete lotion, high percentage of water rapid solidifying material etc.But these materials also come with some shortcomings in stowing operation, and, obturation not enough like obturation early anti pressured intension time of setting, oversize, filler difficulty of transportation, filling cost were high excessively.
Summary of the invention
The objective of the invention is to overcome the problem that exists in the prior art, provide that a kind of method is simple, the obturation early strength high, save support material, reduce the other gas filling method in coal mine gob-side entry retaining lane of labour intensity.
The other gas filling method in coal mine gob-side entry retaining of the present invention lane comprises the steps:
A., the gas boosting room is set near the auxiliary shaft of ground, in the gas boosting room, settles ground gas boosting pump and the high pressure tank that 0.8~1Mpa gases at high pressure are housed;
B. in the exploiting field haulage way of down-hole coal excavation work plane the place ahead 5~20m, arrange the mine gas booster pump that links to each other with ground high pressure tank pipeline;
C. when coal-face advance distance open-off cut 5~8m; A height and the highly identical cylinder rubber pneumatic bag of mining are laid near goaf one side in the empty tunnel that keeps on the edge at coal-face rear, and the diameter of cylinder rubber pneumatic bag and its ratio highly are 0.4~0.6;
D. by the road the empty tunnel that keeps, the edge that is laid in the coal-face rear is inflated near the cylinder rubber pneumatic bag of goaf one side through the mine gas booster pump, until connecing the top;
E. when the pressure meter of mine gas booster pump shows that pressure reaches the stress of primary rock, stop inflation, the cylinder rubber pneumatic bag is sealed;
F. along with coal-face is pushed ahead a step pitch, continue to lay a cylinder rubber pneumatic bag along the empty tunnel that keeps near goaf one side at the coal-face rear;
G. repeating step d, e, f constantly carry out the inflation of next row's cylinder rubber pneumatic bag, until accomplishing the gas filling supporting that keeps the tunnel near goaf one side along empty.
The described stress of primary rock=adopt deeply * the overlying rock body force; It is said that inflation is air or nitrogen to the cylinder rubber pneumatic bag.
Beneficial effect:
1) the present invention utilizes gases at high pressure to charge into rubber pneumatic bag to form obturation and carry out the supporting of gob side entry retaining roadside packing, and process links is few, and filling procedure is few, and labor strength is little, and produce influence to mining few.
2) obturation that forms has the early strength height, initiatively connects the advantage of top supporting roof, and the obturation internal pressure can increase and the characteristics of increase along with roof pressure, has better supporting effect.
3) only need in the main tunnel of mine, to lay gas pipeline, filling gas can be carried in the pipeline high speed, and cost of transportation is low, has reduced worker's labour intensity.
4) through gas filling, improve coal recovery rate, reduced the tunnelling rate, increased economic benefit.
Description of drawings
Fig. 1 is the floor map of the other gas filling method in gob side entry retaining lane, coal seam of the present invention.
Among the figure: 1-coal-face, 2-cylinder rubber pneumatic bag, 3-exploiting field haulage way, 4-gas boosting pump, 5-goaf.
The specific embodiment
Below in conjunction with accompanying drawing one embodiment of the present of invention are done further to describe:
The other gas filling method in coal mine gob-side entry retaining of the present invention lane at first is provided with the gas boosting room near the auxiliary shaft of ground, in the gas boosting room, settle ground gas boosting pump and the high pressure tank that 0.8~1Mpa gases at high pressure are housed; In the exploiting field haulage way 3 of down-hole coal excavation work plane 1 the place ahead 5~20m, arrange the mine gas booster pump 4 that links to each other with ground high pressure tank pipeline then; When coal-face 1 advance distance open-off cut 5~8m; A height and the highly identical cylinder rubber pneumatic bag 2 of mining are laid near goaf 5 one sides in the empty tunnel 6 that keeps on the edge at coal-face 1 rear, and the diameter of cylinder rubber pneumatic bag 2 and its ratio highly are 0.4~0.6; By the road to being laid in inflating near the cylinder rubber pneumatic bag 2 of goaf 5 one sides along the empty tunnel 6 that keeps of coal-face 1 rear, until connecing the top, 2 inflations are air or nitrogen to the cylinder rubber pneumatic bag through mine gas booster pump 4; When the pressure meter of mine gas booster pump 4 shows that pressure reaches the stress of primary rock, stop inflation, cylinder rubber pneumatic bag 2 is sealed, accomplish the inflation of a cylinder rubber pneumatic bag 2; The stress of primary rock=adopt deeply * the overlying rock body force.Along with constantly pushing ahead of coal-face 1; Whenever push ahead a step pitch; After the cylinder rubber pneumatic bag 2 that inflation is before accomplished, continue to lay a cylinder rubber pneumatic bag 2; And inflation one by one, until accomplishing an exhaust body filling and support that keeps tunnel 6 near goaf 5 one sides along empty.
Claims (1)
1. the other gas filling method in coal mine gob-side entry retaining lane is characterized in that: comprise the steps:
A., the gas boosting room is set near the auxiliary shaft of ground, in the gas boosting room, settles ground gas boosting pump and the high pressure tank that 0.8~1Mpa gases at high pressure are housed;
B. in the exploiting field haulage way (3) of down-hole coal excavation work plane (1) the place ahead 5~20m, arrange the mine gas booster pump (4) that links to each other with ground high pressure tank pipeline;
C. when down-hole coal excavation work plane (1) advance distance open-off cut 5~8m; A height and the highly identical cylinder rubber pneumatic bag (2) of mining are laid near goaf (5) one sides in the empty tunnel (6) that keeps on the edge at down-hole coal excavation work plane (1) rear, and the diameter of cylinder rubber pneumatic bag (2) and its ratio highly are 0.4~0.6;
D. by the road the cylinder rubber pneumatic bag (2) near goaf (5) one sides along empty reservation tunnel (6) that is laid in down-hole coal excavation work plane (1) rear is inflated through mine gas booster pump (4), until connecing the top;
E. when the pressure meter of mine gas booster pump (4) shows that pressure reaches the stress of primary rock, stop inflation, cylinder rubber pneumatic bag (2) is sealed, the described stress of primary rock=adopt deeply * the overlying rock body force;
F. along with down-hole coal excavation work plane (1) is pushed ahead a step pitch; Down-hole coal excavation work plane (1) rear continue to lay a cylinder rubber pneumatic bag (2) along the empty tunnel (6) that keeps near goaf (5) one sides, inflation is air or nitrogen to said cylinder rubber pneumatic bag (2);
G. repeating step d, e, f constantly carry out the inflation of next row's cylinder rubber pneumatic bag (2), until accomplishing an exhaust body filling and support that keeps tunnel (6) near goaf (5) one sides along empty.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100579523A CN102155262B (en) | 2011-03-11 | 2011-03-11 | Method for filling gas near roadway of coal mine gob-side entry retaining |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100579523A CN102155262B (en) | 2011-03-11 | 2011-03-11 | Method for filling gas near roadway of coal mine gob-side entry retaining |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102155262A CN102155262A (en) | 2011-08-17 |
CN102155262B true CN102155262B (en) | 2012-11-14 |
Family
ID=44436906
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011100579523A Expired - Fee Related CN102155262B (en) | 2011-03-11 | 2011-03-11 | Method for filling gas near roadway of coal mine gob-side entry retaining |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102155262B (en) |
Families Citing this family (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103953390B (en) * | 2014-05-08 | 2016-02-10 | 中国矿业大学 | The water-retaining production Tight filling method of control overlying mining rock crack and subsidence |
CN104074542B (en) * | 2014-05-10 | 2016-02-03 | 河北充填采矿技术有限公司 | A kind of colliery C0 2concrete formula placement method |
CN104405440B (en) * | 2014-10-21 | 2016-04-06 | 河南理工大学 | A kind of coal mine gob filling system and placement method |
CN104453997B (en) * | 2014-10-21 | 2016-04-06 | 河南理工大学 | A kind of filling bladder spacer device of coal mine gob-side entry retaining |
CN104806289B (en) * | 2015-04-08 | 2017-10-10 | 兖州煤业股份有限公司 | A kind of coal-face tip-segment band device for filling and method |
CN105240048B (en) * | 2015-10-26 | 2019-07-23 | 山东科技大学 | A kind of gas filling method based on paste body filling |
CN105673039B (en) * | 2016-02-02 | 2017-11-14 | 安徽理工大学 | Soft strong carrying constructing structure and its construction method by a kind of gob side entry retaining lane |
CN106382118B (en) * | 2016-11-30 | 2018-04-17 | 长沙矿山研究院有限责任公司 | No divider wall actively connects the roof formula method of mining by the way of filling |
CN106988780B (en) * | 2017-05-09 | 2018-12-14 | 山东科技大学 | A kind of girdle goaf paste body filling construction method |
CN110566269A (en) * | 2019-08-19 | 2019-12-13 | 西北矿冶研究院 | Truss type filling method for underground goaf |
CN112459781B (en) * | 2020-10-29 | 2021-11-05 | 煤炭科学研究总院 | Full-automatic pillar filling mining control method and control device |
CN112664269B (en) * | 2020-12-17 | 2024-01-30 | 华能煤炭技术研究有限公司 | Gob-side entry retaining goaf side sealing structure and side air leakage preventing method |
CN112746863B (en) * | 2021-02-04 | 2023-02-21 | 太原理工大学 | Rapid closing device and method for mine roof cutting gob-side entry retaining goaf |
CN114033449B (en) * | 2021-10-11 | 2024-02-27 | 中煤科工集团沈阳设计研究院有限公司 | End slope coal mining roadway air bag supporting device and method |
CN114562329B (en) * | 2022-04-02 | 2023-03-24 | 中国矿业大学 | Non-closed overlying strata grouting, filling and isolating method |
CN115013049B (en) * | 2022-06-24 | 2023-12-15 | 福州大学 | Goaf filling reserved roadway device and construction process thereof |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1260461C (en) * | 2003-08-08 | 2006-06-21 | 中南大学 | Continuous mining method of stepped sectional extruding and ore caving followed by filling |
RU2277170C1 (en) * | 2005-04-20 | 2006-05-27 | Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт им. Г.В. Плеханова (технический университет)" | Development method for composite formations having gob interlayers |
DE202005015134U1 (en) * | 2005-09-24 | 2005-12-01 | GFR Gesellschaft für die Aufbereitung und Verwertung von Reststoffen mbH | Hydraulically-transportable, self-leveling mine backfilling material, used for filling underground rock salt caverns, contains residue from (quasi)dry flue gas desulfurization of coal-fired power station plus binder, salt and mixing water |
CN101701526B (en) * | 2009-11-05 | 2011-07-06 | 冀中能源邯郸矿业集团有限公司 | Goaf bag-type packing method |
CN101749020A (en) * | 2010-01-26 | 2010-06-23 | 淄博市王庄煤矿 | Forward coal mining by filling method |
-
2011
- 2011-03-11 CN CN2011100579523A patent/CN102155262B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN102155262A (en) | 2011-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102155262B (en) | Method for filling gas near roadway of coal mine gob-side entry retaining | |
CN102155225B (en) | Filling and mining method of coal gases | |
CN103742148B (en) | The soft coal-mining method covering the descending waste filling of supporting of a kind of half-edge coal seam | |
CN102493838B (en) | Method for fully mechanized continuously-filling coal mining of steeply pitching coal seam | |
CN101725368B (en) | Thick seam large mining height working face gob-side entry retaining method | |
CN102155260B (en) | Method for filling heavy-pitch coal bed goaf | |
CN103758567B (en) | A kind of breaking roof Collapsed zone grouting filling method | |
CN101858215B (en) | Road retained method for extrusion molding of waste rock | |
CN104564137B (en) | Handling method and device for double-medium stacked supporting and hard top plate type mined-out area | |
CN102996131A (en) | Solid-filling coal mining method with two pre-excavating tunnels for advancing | |
CN102146794B (en) | Grouting, consolidating and gob-side tunneling process method | |
CN103195390A (en) | Mining-coal bed nearly horizontal gas extraction borehole sealing method | |
CN101749020A (en) | Forward coal mining by filling method | |
CN102337925B (en) | Method for enlarging, filling and supporting coal-pillar-free mining roadway for fully-mechanized top coal caving | |
CN102877848B (en) | Method for performing coal mining and gangue cementation stripe filling simultaneously | |
CN106968676A (en) | The method that cavity is passed through in tunnelling | |
CN110259449A (en) | A kind of super high seam strip-type filling mining method for relying on telescoping steel form | |
CN109630112A (en) | A kind of N00 mining codes for cutting top filling | |
CN103161498B (en) | Method for filling coal pillar beside roadway in steep coal seam section | |
CN102287211A (en) | Gob roadway end part hydraulic support frame and gob roadway coal mining method thereof | |
CN105649673A (en) | Roadside gangue mixture filling and gob-side entry retaining method for large-dip angle coal seams | |
CN113236254B (en) | Filling mining method for end slope thick coal seam with large inclination angle of strip mine | |
CN105240012A (en) | F-type section coal-mining method allowing commingled mining of coal pillars | |
CN113756868A (en) | Geotechnical engineering underground side wall construction method | |
CN204283488U (en) | A kind of constant-resistance allows presses gob side entry retaining filling air bag |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |