CN102101596A - Novel powder storage bin - Google Patents
Novel powder storage bin Download PDFInfo
- Publication number
- CN102101596A CN102101596A CN2009102636773A CN200910263677A CN102101596A CN 102101596 A CN102101596 A CN 102101596A CN 2009102636773 A CN2009102636773 A CN 2009102636773A CN 200910263677 A CN200910263677 A CN 200910263677A CN 102101596 A CN102101596 A CN 102101596A
- Authority
- CN
- China
- Prior art keywords
- feed bin
- charge level
- measuring charge
- storage bin
- discharge port
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Measurement Of Levels Of Liquids Or Fluent Solid Materials (AREA)
Abstract
The invention discloses a novel powder storage bin. A discharge opening of the powder storage bin is arranged on the upper half part position of the side wall of the powder storage bin; a dust collecting device is arranged on the top of the powder storage bin; a baffle plate is arranged in the powder storage bin and between the dust collecting device and the discharge opening; a gap is remained between the bottom edge of the baffle plate and the bottom edge inside the powder storage bin; the lower half part position of the side wall of the powder storage bin is provided with a level measuring device connecting pipe; and a level measuring device is arranged in the level measuring device connecting pipe. The invention not only has the advantage of reducing the influence of dust rise inside the powder storage bin on the dust collecting device and the level measuring device, but also has the advantages of level measurement accuracy enhancement, cost saving, pollution reduction, simple structure, convenience and fastness for use, safety, reliability, and the like.
Description
Technical field
The present invention relates to a kind of novel powder feed bin that is used for chemical industry, metallurgy industry, belong to the feed bin technical field.
Background technology
At chemical industry, in the industries such as metallurgy, many proportioning processes all need the powder feed bin to carry out the storage of powder material, carry and mix, little in light weight in the blending process owing to various powder material density, and discharge rate is fast, in traditional feed bin, just therefore produce very big " dirt is raised " phenomenon, this phenomenon can make the interior powder of feed bin fly upward everywhere, cause false material level to report to the police for the apparatus for measuring charge level that has stuff level switch, and cause burden to dust arrester installation, because dust arrester installation can absorb a large amount of powder, influence dust collection effect, and cause the material waste, thereby influence normally carrying out of technological process, but also environment has been caused pollution.So the result of use of existing powder feed bin still is not ideal enough.
Summary of the invention
The objective of the invention is: provide a kind of dirt that can reduce to raise influence, and can improve level gauging precision and novel powder feed bin simple in structure, easy to use, to overcome the deficiencies in the prior art to dust arrester installation and apparatus for measuring charge level.
The present invention is achieved in that a kind of novel powder feed bin of the present invention comprises existing feed bin, dust arrester installation and has the apparatus for measuring charge level of stuff level switch, the discharge port of its feed bin is arranged on the sidewall first half position of feed bin, dust arrester installation is arranged on the top of feed bin, in feed bin, between dust arrester installation and the discharge port, be provided with dividing plate, and leave between the base in the base of dividing plate and the feed bin at interval, be provided with apparatus for measuring charge level and take on the sidewall lower part position of feed bin, apparatus for measuring charge level is installed in the apparatus for measuring charge level adapter.
The center of above-mentioned discharge port to the distance at feed bin top greater than the pipe radius that is installed in the conveying pipeline on the discharge port and less than the pipe diameter of 2 times of conveying pipelines.
Aforementioned barriers is installed in the position apart from discharge port 1/2~3/4 feed bin top diameter, and the spacing distance between the base in the base of dividing plate and the feed bin is 1/2~3/4 of a feed bin inner height.
It is the unitized construction of cuing open the semi-steel pipe of half for all steel pipe, another section that above-mentioned apparatus for measuring charge level adapter is one section, an end of taking over all steel pipe at apparatus for measuring charge level is provided with the erection joint that is used to connect apparatus for measuring charge level, and the length of the semi-steel pipe of apparatus for measuring charge level adapter is greater than the sounding rod length of apparatus for measuring charge level.
The center height that the hole that apparatus for measuring charge level takes over is installed on feed bin is equal to or less than the height on dividing plate base, and the angle of the line of centers taken over of apparatus for measuring charge level and horizontal angle α is 10 °≤α≤30 °.
Owing to adopted technique scheme, the present invention is arranged on the discharge port of feed bin on the sidewall first half position of feed bin, and in feed bin, between dust arrester installation and the discharge port, dividing plate is set, can solve the impact of feed bin interior " dirt is raised " so effectively to dust arrester installation, thereby significantly reduced the burden of dust arrester installation, prolonged the service life of dust arrester installation; And the present invention is arranged on apparatus for measuring charge level on the sidewall lower part position of feed bin, has reduced the influence of feed bin interior " dirt is raised " to apparatus for measuring charge level effectively, thereby has improved the level gauging precision of apparatus for measuring charge level preferably.See that through the in-place test result of use the present invention has good level gauging precision and higher dust-collecting efficiency, can reduce pollution to a great extent.Therefore, the present invention compared with prior art, the present invention not only has and can reduce dirt in the feed bin and raise advantage to dust arrester installation and apparatus for measuring charge level influence, can improve that level gauging precision, cost saving, minimizing are polluted, advantage such as simple in structure, easy to use, quick, safe, reliable but also have.
Description of drawings
Fig. 1 is a feed bin structural representation of the prior art;
Fig. 2 is a structural representation of the present invention;
Fig. 3 is an apparatus for measuring charge level joint pipe structure scheme drawing of the present invention.
The specific embodiment
The present invention is described in further detail below in conjunction with drawings and Examples, but not as limitation of the present invention.
Embodiments of the invention: when making the powder feed bin, adopt a kind of novel powder feed bin structure of the present invention to make (as shown in Figures 2 and 3), feed bin 1, dust arrester installation 3 and the apparatus for measuring charge level 4 that has a stuff level switch can adopt finished product of the prior art, during making, the discharge port 6 of feed bin 1 is arranged on the sidewall first half position of feed bin 1, and the center that preferably makes discharge port 6 is controlled at greater than in pipe radius that is installed in the conveying pipeline 7 on the discharge port 6 and the scope less than the pipe diameter of 2 times of conveying pipelines 7 to the distance at feed bin 1 top; Dust arrester installation 3 is installed in the top of feed bin 1, and mouthful line of centers that gathers dust that makes dust arrester installation 3 is to the distance of the discharge port scope at the top, storehouse of 3/5~3/4 feed bin 1 diameter length, in feed bin 1, between dust arrester installation 3 and the discharge port 6, install dividing plate 2, preferably dividing plate 2 is installed in length apart from discharge port 6 and is in 1/2~3/4 the scope of feed bin 1 top diameter, and make between the base in the base of dividing plate 2 and the feed bin 1 and leave at interval, this spacing distance preferably is controlled at 3/5~3/4 scope of feed bin 1 inner height; On the sidewall lower part position of feed bin 1, open a hole and install and fix an apparatus for measuring charge level and take over 5, the center height of feed bin 1 being installed the hole of apparatus for measuring charge level adapter 5 is controlled at the height that is equal to or less than dividing plate 2 bases, and the angle of apparatus for measuring charge level being taken over 5 line of centers and horizontal angle α is controlled at the scope of 10 °≤α≤30 °, then apparatus for measuring charge level 4 is installed in apparatus for measuring charge level and takes over 5 interior.
In order to reach better result of use, during making, apparatus for measuring charge level can be taken over 5 and adopt the steel pipe manufacturing that is of a size of DN80, and it is made as a segment length is 200 millimeters complete all steel pipe 5-1, and the steel pipe of another section removed the unitized construction form that is made into all steel pipe 5-1 and the semi-steel pipe 5-2 of semi-steel pipe 5-2 after half, help the measurement of apparatus for measuring charge level 4 like this, take over erection joint 8 that is used to connect apparatus for measuring charge level 4 of end welding of 5 all steel pipe 5-1 then at apparatus for measuring charge level, apparatus for measuring charge level is taken over the sounding rod length that the length of 5 semi-steel pipe 5-2 is made into greater than apparatus for measuring charge level 4 and got final product.
Claims (5)
1. novel powder feed bin, comprise feed bin (1), dust arrester installation (3) and have the apparatus for measuring charge level (4) of stuff level switch, it is characterized in that: the discharge port (6) of feed bin (1) is arranged on the sidewall first half position of feed bin (1), dust arrester installation (3) is arranged on the top of feed bin (1), in feed bin (1), be provided with dividing plate (2) between dust arrester installation (3) and the discharge port (6), and leave between the base in the base of dividing plate (2) and the feed bin (1) at interval, be provided with apparatus for measuring charge level and take over (5) on the sidewall lower part position of feed bin (1), apparatus for measuring charge level (4) is installed in apparatus for measuring charge level and takes in (5).
2. novel powder feed bin according to claim 1 is characterized in that: the center of discharge port (6) to feed bin (1) distance from top greater than the pipe radius that is installed in the conveying pipeline (7) on the discharge port (6) and less than the pipe diameter of 2 times of conveying pipelines (7).
3. novel powder feed bin according to claim 1, it is characterized in that: dividing plate (2) is installed in the position apart from discharge port (6) 1/2~3/4 feed bin (1) top diameters, and the spacing distance between the base of dividing plate (2) and the interior base of feed bin (1) is 3/5~3/4 of feed bin (a 1) inner height.
4. novel powder feed bin according to claim 1, it is characterized in that: it is the unitized construction of cuing open the semi-steel pipe (5-2) of half for all steel pipe (5-1), another section that apparatus for measuring charge level adapter (5) is one section, an end of taking over all steel pipe (5-1) of (5) at apparatus for measuring charge level is provided with the erection joint (8) that is used to connect apparatus for measuring charge level (4), and the length of the semi-steel pipe (5-2) of apparatus for measuring charge level adapter (5) is greater than the sounding rod length of apparatus for measuring charge level (4).
5. novel powder feed bin according to claim 1, it is characterized in that: feed bin (1) is installed apparatus for measuring charge level and is taken over the height that the center height in the hole of (5) is equal to or less than dividing plate (2) base, and the apparatus for measuring charge level angle of taking over the line of centers of (5) and horizontal angle (α) is 10 °≤α≤30 °.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009102636773A CN102101596A (en) | 2009-12-16 | 2009-12-16 | Novel powder storage bin |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009102636773A CN102101596A (en) | 2009-12-16 | 2009-12-16 | Novel powder storage bin |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102101596A true CN102101596A (en) | 2011-06-22 |
Family
ID=44154702
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009102636773A Pending CN102101596A (en) | 2009-12-16 | 2009-12-16 | Novel powder storage bin |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102101596A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102506955A (en) * | 2011-10-12 | 2012-06-20 | 上海凡宜科技电子有限公司 | Adjusting device for installation structure of level meter |
CN102627192A (en) * | 2012-01-17 | 2012-08-08 | 刘延武 | Medicine chest of medicine arrangement machine |
CN102700961A (en) * | 2012-06-22 | 2012-10-03 | 江苏泓明达机械有限公司 | Bulk ship device |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0245384A (en) * | 1988-07-23 | 1990-02-15 | Amusetsuku:Kk | Damper feeder |
CN2734816Y (en) * | 2004-08-02 | 2005-10-19 | 珠海市长陆工业自动控制系统有限公司 | Metering device for materials level in hot aggregate bin of bituminous concrete station |
CN2741914Y (en) * | 2004-09-28 | 2005-11-23 | 贵阳铝镁设计研究院 | Anti-collapse bunker |
CN200957961Y (en) * | 2006-09-11 | 2007-10-10 | 青铜峡铝业集团有限公司 | Storage bin with inspector |
CN201102905Y (en) * | 2007-08-31 | 2008-08-20 | 沈阳铝镁设计研究院 | Measurable storage hopper |
CN201335720Y (en) * | 2008-12-17 | 2009-10-28 | 贵阳铝镁设计研究院 | Mounting structure for radar charge level indicator on storage bin |
CN201587679U (en) * | 2009-12-16 | 2010-09-22 | 贵阳铝镁设计研究院 | Novel powder storage bin |
-
2009
- 2009-12-16 CN CN2009102636773A patent/CN102101596A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0245384A (en) * | 1988-07-23 | 1990-02-15 | Amusetsuku:Kk | Damper feeder |
CN2734816Y (en) * | 2004-08-02 | 2005-10-19 | 珠海市长陆工业自动控制系统有限公司 | Metering device for materials level in hot aggregate bin of bituminous concrete station |
CN2741914Y (en) * | 2004-09-28 | 2005-11-23 | 贵阳铝镁设计研究院 | Anti-collapse bunker |
CN200957961Y (en) * | 2006-09-11 | 2007-10-10 | 青铜峡铝业集团有限公司 | Storage bin with inspector |
CN201102905Y (en) * | 2007-08-31 | 2008-08-20 | 沈阳铝镁设计研究院 | Measurable storage hopper |
CN201335720Y (en) * | 2008-12-17 | 2009-10-28 | 贵阳铝镁设计研究院 | Mounting structure for radar charge level indicator on storage bin |
CN201587679U (en) * | 2009-12-16 | 2010-09-22 | 贵阳铝镁设计研究院 | Novel powder storage bin |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102506955A (en) * | 2011-10-12 | 2012-06-20 | 上海凡宜科技电子有限公司 | Adjusting device for installation structure of level meter |
CN102506955B (en) * | 2011-10-12 | 2014-05-14 | 上海凡宜科技电子有限公司 | Adjusting device for installation structure of level meter |
CN102627192A (en) * | 2012-01-17 | 2012-08-08 | 刘延武 | Medicine chest of medicine arrangement machine |
CN102627192B (en) * | 2012-01-17 | 2015-04-01 | 刘延武 | Medicine chest of medicine arrangement machine |
CN102700961A (en) * | 2012-06-22 | 2012-10-03 | 江苏泓明达机械有限公司 | Bulk ship device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201686711U (en) | Ash storage bin for matching with blast furnace gas full-dry dedusting system | |
CN102398745B (en) | Powder material collecting cabin | |
CN102101596A (en) | Novel powder storage bin | |
CN201587679U (en) | Novel powder storage bin | |
CN202072219U (en) | Sliding barrel with buffering function for loading and unloading bulk material | |
CN105888529A (en) | Inspection well mouth ladder stand | |
CN201760393U (en) | Beneficiation machine of steel ball | |
CN202546237U (en) | Wet industrial tail gas collecting cabinet | |
CN220077469U (en) | Round vertical blanking pipe with buffer structure | |
CN204400235U (en) | Filler bin dust arrester installation and use the filler bin device of this dust arrester installation | |
CN206577484U (en) | A kind of fuel tank Concentric Reducers moisture trap | |
CN205593608U (en) | Prevent doublestage material level measuring device that blocks up | |
CN203790722U (en) | Vehicle-mounted purifier | |
CN206505519U (en) | A kind of square tube Material Staging Area material lack warning device | |
CN203017881U (en) | Desulfurizing tower internally provided with swirl tubes | |
CN219308382U (en) | Comprehensive device of blanking equipment in limestone-gypsum flue gas desulfurization process | |
CN210461671U (en) | Pressure container | |
CN204365073U (en) | A kind of flue gas shunting device | |
CN204587783U (en) | Namely formula cement bin structure is stopped based on contact induction | |
CN204381293U (en) | A kind of core sand Storing and conveying device | |
CN210311866U (en) | Biomass storage bin | |
CN210699471U (en) | Oil-gas pressure pipeline | |
CN214058683U (en) | Limestone powder storehouse material level detection device | |
CN212502103U (en) | Liquid level measuring device, storage tank and storage tank system | |
CN208805506U (en) | A kind of methane transducer calibration equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20110622 |