CN102071961B CN201010604328A CN201010604328A CN102071961B CN 102071961 B CN102071961 B CN 102071961B CN 201010604328 A CN201010604328 A CN 201010604328A CN 201010604328 A CN201010604328 A CN 201010604328A CN 102071961 B CN102071961 B CN 102071961B
Authority
CN
China
Prior art keywords
hole
steel sleeve
sleeve pipe
descending
coal seam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201010604328A
Other languages
English (en)
Other versions
CN102071961A (zh
Inventor
屈永安
林柏泉
师永贵
杨威
李建民
赵武强
姜永明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Shaanxi Coal Mining Hancheng Mining Co Ltd
Original Assignee
China University of Mining and Technology CUMT
Shaanxi Coal Mining Hancheng Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT, Shaanxi Coal Mining Hancheng Mining Co Ltd filed Critical China University of Mining and Technology CUMT
Priority to CN201010604328A priority Critical patent/CN102071961B/zh
Publication of CN102071961A publication Critical patent/CN102071961A/zh
Application granted granted Critical
Publication of CN102071961B publication Critical patent/CN102071961B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Examining Or Testing Airtightness (AREA)
  • Earth Drilling (AREA)

Abstract

一种下行瓦斯抽放钻孔和测压钻孔封孔方法,从巷道往下方煤层方向施工一个下行孔,下行孔钻至煤层顶板时停止钻进,退出钻杆;在下行孔内安设钢质套管,使钢质套管的前端距离下行孔孔底约1m处;在钢质套管与下行孔的间隙内间隔插装楔形木塞;向下行孔和钢质套管之间的空隙内和钢质套管内注入浆液;在钢质套管内部沿下行孔方向施工内孔,直至进入煤层或穿过煤层后退出钻杆;继续向下行孔和钢质套管之间的空隙内注入浆液,直至注满空隙完成封孔。通过两次施工钻孔,能有效抵抗钻孔的收缩变形,确保钻孔周围的煤岩体不会发生卸压和位移,避免产生裂隙而发生漏气现象;不需要进行挡浆,瓦斯抽放孔的抽放浓度在70%以上,其方法简单,易操作,密封效果好。

Description

一种下行瓦斯抽放钻孔和测压钻孔封孔方法
技术领域
本发明涉及一种下行瓦斯抽放钻孔和测压钻孔封孔方法,尤其适用于下行钻孔抽放煤层瓦斯和测试煤层瓦斯压力的钻孔。
背景技术
煤层瓦斯是导致矿井瓦斯爆炸和煤与瓦斯突出的主要因素之一,为了确保在回采过程中避免工作面瓦斯超限,消除工作面的突出危险性,抽放煤层瓦斯为主要的措施之一。而抽放效果和钻孔的密封效果密切相关,钻孔密封较差时,会产生漏气现象,钻孔负压一般较低,抽放瓦斯能力降低。为此,为了提高钻孔抽放瓦斯的效果,必须提高钻孔密封质量。
采用下行钻孔抽放煤层瓦斯在矿井中应用比较普遍,目前,下行钻孔可以采用聚氨酯或水泥砂浆等材料进行密封。但是,聚氨酯封孔长度普遍较短,密封深度比较浅,不能很好的密封裂隙,容易漏气;而采用水泥砂浆等液体材料进行封孔时,需要采用胶囊等充填物放置在钻孔内部用于挡浆液,由于无法看见挡浆的效果,因此,这种密封的效果不能得到保证。钻孔密封之后,还将会在地应力的作用下发生变形,同时产生大量的次生裂隙,最终可能导致钻孔漏气,降低了瓦斯抽放能力。此外,煤层瓦斯压力也为煤层的主要参数之一,我国相关煤矿法规规定,煤层在开采之前必须要首先测试煤层的瓦斯压力。测试煤层瓦斯压力最好使用上行孔,但是很多条件下不具备上行孔施工条件,必须采用下行钻孔测试,同样会受到挡浆和地应力演变破坏钻孔的影响,导致不能准确测试煤层瓦斯压力。因此,下行瓦斯抽放孔和测压孔的封孔效果普遍不理想。
发明内容
技术问题:本发明的目的是克服已有技术中的不足,提供一种方法简单、易操作、封孔效果好的下行瓦斯抽放钻孔和测压钻孔封孔方法。
技术方案:本发明的下行瓦斯抽放钻孔和测压钻孔封孔方法,包括如下步骤:
a、从巷道往下方煤层方向施工一个孔径为90mm~200mm的下行孔,下行孔钻至煤层顶板距离煤层约1m位置时停止钻进,退出钻杆;
b、在下行孔内安设钢质套管,使钢质套管的前端距离下行孔的孔底约1 m处;
c、在钢质套管与下行孔孔口处的间隙内间隔插装楔形木塞,使钢质套管固定于下行孔的中间位置;
d、向下行孔和钢质套管之间的空隙内和钢质套管内注入浆液,浆液注入的深度约为下行孔深度的一半;
e、浆液凝固之后,在钢质套管内部沿下行孔方向施工内孔,直至进入煤层不低于1 m或穿过煤层,之后退出钻杆;
f、继续向下行孔和钢质套管之间的空隙内注入浆液,直至注满空隙,完成封孔。
有益效果:本发明通过采用“二次钻孔+钢质套管+二次密封”的方法,有效抵抗了地应力演化对钻孔的破坏作用,消除了挡浆的困难,确保了钻孔的密封效果。通过两次施工钻孔,为安设钢质套管和进行二次密封提供了条件:将钢质套管安设在钻孔中,通过其自身的强度,可以有效抵抗钻孔的收缩变形,确保钻孔周围的煤岩体不会发生卸压和位移,避免产生裂隙而发生漏气现象;通过对钢质套管与下行孔之间间隙的二次密封,可以有效密封钻孔周围可能会产生的新裂隙,起到双保险的作用,确保密封质量。同时由于封孔过程中,不需要进行挡浆,所有操作难度较小,施工质量高,可以保证瓦斯抽放孔的抽放浓度普遍在70%以上,不论是在瓦斯抽放还是在煤层瓦斯压力测试等方面都具有推广价值。其方法简单,密封效果好,省时省力,工效高,具有广泛的实用性。
附图说明
图1是本发明下行瓦斯抽放钻孔和测压钻孔封孔方法施工工艺示意图。
图2是图1中的A-A结构示意图。
图中:1-钢质套管;2-楔形木塞;3-下行孔;4-法兰;5-内孔;6-浆液。
具体实施方式
下面结合附图中的实施例对本发明作进一步的描述:
如图1所示,本发明的下行瓦斯抽放钻孔和测压钻孔封孔方法:首先使用已有的常规下行钻孔施工方法,从巷道往下方煤层方向施工一个孔径为90mm~200mm的下行孔3,当下行孔3钻至煤层顶板距离煤层约1m位置时停止钻进,退出钻杆;然后在下行孔3内安装钢质套管1,钢质套管1的连接处需要缠生料带等密封材料,确保钢质套管1密封不漏气;进入下行孔3内的钢质套管1的长度以钢质套管1的前端距离下行孔3的孔底约1 m处为准,并在留设在下行孔3的孔口外露钢质套管1的端头安设法兰4,或者采用本身带有法兰4的套管。钢质套管1全部送入下行孔3之后,用楔形木塞2固定钢质套管1,在钢质套管1与下行孔3的间隙内间隔插装楔形木塞2,如图2所示为三个楔形木塞2,使钢质套管1固定于下行孔3的中间位置;向下行孔3和钢质套管1之间的空隙内和钢质套管1内注入浆液6,浆液6注入的深度约为下行孔3深度的一半;待浆液6凝固之后,在钢质套管1内部按已有的常规钻孔方法向下行孔3方向施工内孔5,内孔5从凝固的浆液中穿过,直至进入煤层不低于1 m或穿过煤层,内孔5施工完成之后退出钻杆,继续向下行孔3和钢质套管1之间的空隙内注入浆液6,直至注满空隙,完成封孔。钢质套管1经法兰4连接瓦斯抽放管路可进行瓦斯抽放,或连接压力表可测试瓦斯压力。

Claims (1)

1.一种下行瓦斯抽放钻孔和测压钻孔封孔方法,其特征在于包括如下步骤:
a、从巷道往下方煤层方向施工一个孔径为90mm~200mm的下行孔(3),下行孔(3)钻至煤层顶板距离煤层约1m位置时停止钻进,退出钻杆;
b、在下行孔(3)内安设钢质套管(1),使钢质套管(1)的前端距离下行孔(3)的孔底约1 m处,并在留设在下行孔(3)的孔口外露钢质套管(1)的端头安设法兰(4),或者采用本身带有法兰(4)的套管;
c、在钢质套管(1)与下行孔(3)孔口处的间隙内间隔插装楔形木塞(2),使钢质套管(1)固定于下行孔(3)的中间位置;
d、向下行孔(3)和钢质套管(1)之间的空隙内和钢质套管(1)内注入浆液(6),浆液(6)注入的深度约为下行孔(3)深度的一半;
e、浆液(6)凝固之后,在钢质套管(1)内部沿下行孔(3)方向施工内孔(5),直至进入煤层不低于1 m或穿过煤层,之后退出钻杆;
f、继续向下行孔(3)和钢质套管(1)之间的空隙内注入浆液(6),直至注满空隙,完成封孔。
CN201010604328A 2010-12-24 2010-12-24 一种下行瓦斯抽放钻孔和测压钻孔封孔方法 Expired - Fee Related CN102071961B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010604328A CN102071961B (zh) 2010-12-24 2010-12-24 一种下行瓦斯抽放钻孔和测压钻孔封孔方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010604328A CN102071961B (zh) 2010-12-24 2010-12-24 一种下行瓦斯抽放钻孔和测压钻孔封孔方法

Publications (2)

Publication Number Publication Date
CN102071961A CN102071961A (zh) 2011-05-25
CN102071961B true CN102071961B (zh) 2012-09-05

Family

ID=44030697

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010604328A Expired - Fee Related CN102071961B (zh) 2010-12-24 2010-12-24 一种下行瓦斯抽放钻孔和测压钻孔封孔方法

Country Status (1)

Country Link
CN (1) CN102071961B (zh)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953749B (zh) * 2011-08-19 2015-06-03 淮南矿业(集团)有限责任公司 抽采钻孔封堵装置及方法
CN102628345B (zh) * 2012-04-23 2014-07-16 山西潞安环保能源开发股份有限公司 一种高密封性的近水平钻孔密封方法
CN103015984A (zh) * 2012-12-19 2013-04-03 河南焦煤能源有限公司科学技术研究所 套管高压封孔法测定煤层瓦斯压力的方法
CN103696729B (zh) * 2013-12-30 2016-04-27 河北联合大学 矿井瓦斯抽放钻孔封孔的方法
CN104500042B (zh) * 2014-10-16 2017-05-03 山东科技大学 含水煤岩下行钻孔瓦斯压力观测系统的测定方法
CN105298433B (zh) * 2015-09-21 2017-10-10 河南理工大学 一种水力压、冲、抽一体化封孔装置及方法
CN105781607A (zh) * 2016-03-02 2016-07-20 重庆大学 一种大倾角下向瓦斯压力测定钻孔封孔方法
CN105804692B (zh) * 2016-03-29 2018-05-08 中国矿业大学(北京) 一种新式煤矿瓦斯压力测定注浆封孔方法
CN105840231B (zh) * 2016-04-12 2018-02-23 中国矿业大学 一种井下高应力松软煤层可重复掏孔抽采瓦斯方法
CN107842350B (zh) * 2017-11-07 2019-08-02 河南理工大学 一种煤矿井下高残余瓦斯含量煤层提高抽采率的方法
CN109162635A (zh) * 2018-09-19 2019-01-08 淮北矿业股份有限公司 一种新的测压钻孔施工工艺

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4316814A (en) * 1978-09-13 1982-02-23 Gesellschaft Fur Strahlen-Und Umweltforschung Mbh Seal for a storage bore hole accommodating radioactive waste and method of applying the seal
WO2000066878A1 (en) * 1999-04-30 2000-11-09 The Regents Of The University Of California Downhole sealing method and composition
CN101285396A (zh) * 2008-06-03 2008-10-15 铁岭兵山煤业设备仪器制造有限公司 压力扩张封孔瓦斯抽取器
CN101482026A (zh) * 2009-02-10 2009-07-15 河南理工大学 瓦斯抽采二次高压注浆封孔装置及其封孔方法
CN201351479Y (zh) * 2009-02-10 2009-11-25 河南理工大学 瓦斯抽采二次高压注浆封孔装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4316814A (en) * 1978-09-13 1982-02-23 Gesellschaft Fur Strahlen-Und Umweltforschung Mbh Seal for a storage bore hole accommodating radioactive waste and method of applying the seal
WO2000066878A1 (en) * 1999-04-30 2000-11-09 The Regents Of The University Of California Downhole sealing method and composition
CN101285396A (zh) * 2008-06-03 2008-10-15 铁岭兵山煤业设备仪器制造有限公司 压力扩张封孔瓦斯抽取器
CN101482026A (zh) * 2009-02-10 2009-07-15 河南理工大学 瓦斯抽采二次高压注浆封孔装置及其封孔方法
CN201351479Y (zh) * 2009-02-10 2009-11-25 河南理工大学 瓦斯抽采二次高压注浆封孔装置

Also Published As

Publication number Publication date
CN102071961A (zh) 2011-05-25

Similar Documents

Publication Publication Date Title
CN102071961B (zh) 一种下行瓦斯抽放钻孔和测压钻孔封孔方法
CN103742129B (zh) 松软煤层钻孔测定煤层瓦斯压力的方法
CN103075148B (zh) 上向远距离钻孔快速测定煤层瓦斯压力的方法及其装置
CN103821544B (zh) 隧道与地下工程高压大流量突涌水治理方法
CN105756599A (zh) 煤矿用两头气堵及中间水封穿层钻孔封孔装置及封孔方法
CN202250166U (zh) 二次高压注浆封孔器
CN105952475A (zh) 一种煤矿残采区冒落废巷注浆加固工艺与方法
CN201412140Y (zh) 顺层孔测定煤层瓦斯压力装置
CN103557012B (zh) 一种大变形巷道围岩注浆紧固承载结构及施工方法
CN106285628A (zh) 一种监测无煤柱沿空留巷底板裂隙发育的探测系统及方法
CN109372572A (zh) 一种低渗透性煤层瓦斯高效抽采方法
CN102200002A (zh) 上向孔分段高压封孔方法及装置
CN108301811A (zh) 一种低渗透性煤层瓦斯高效抽采方法
CN110439497A (zh) 钻孔多段封堵、致裂、注浆、注水一体化设备及使用方法
CN106050302A (zh) 一种煤矿永久密闭墙构筑系统及方法
CN104948133A (zh) 一种适合高压大流量钻孔涌水的注浆封堵装置及其工艺
CN108756883A (zh) 一种煤矿坚硬顶板注浆压裂方法及系统
CN103939075B (zh) 一种提高煤矿瓦斯抽采效果的压裂方法及装置
CN103742098A (zh) 一种煤矿低抽巷穿层钻孔返渣封孔装置及方法
CN203145925U (zh) 上向远距离钻孔快速测定煤层瓦斯压力的装置
CN106968664A (zh) 一种工作面底板破坏带深度钻孔注水探测方法
CN116428004A (zh) 一种废弃老采空区储碳空间的开发方法
CN105781606A (zh) 一种大倾角下向穿层瓦斯抽放钻孔封孔方法
CN112459779A (zh) 一种改造复合顶板预裂卸压方法
CN104790900A (zh) 一种以煤岩屑为封孔材料封堵瓦斯抽采钻孔的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120905

Termination date: 20141224