Pile-driving machinery and drilling bucket thereof Download PDF

Info

Publication number
CN102061884A
CN102061884A CN2010105861189A CN201010586118A CN102061884A CN 102061884 A CN102061884 A CN 102061884A CN 2010105861189 A CN2010105861189 A CN 2010105861189A CN 201010586118 A CN201010586118 A CN 201010586118A CN 102061884 A CN102061884 A CN 102061884A
Authority
CN
China
Prior art keywords
drilling
drilling bucket
arm
assembly
tie
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010105861189A
Other languages
Chinese (zh)
Other versions
CN102061884B (en
Inventor
陈朝晖
水俊峰
王磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Sany Heavy Machinery Co Ltd
Sany Heavy Machinery Ltd
Original Assignee
Beijing Sany Heavy Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Sany Heavy Machinery Co Ltd filed Critical Beijing Sany Heavy Machinery Co Ltd
Priority to CN 201010586118 priority Critical patent/CN102061884B/en
Publication of CN102061884A publication Critical patent/CN102061884A/en
Application granted granted Critical
Publication of CN102061884B publication Critical patent/CN102061884B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention provides a drilling bucket of pile-driving machinery. The drilling bucket comprises a drilling top and a pressure bar, wherein, the drilling top is connected with a drill stem of the pile-driving machinery, a cylinder is arranged on the lower end of the drilling top, and a drilling bottom is hinged on the lower end of the cylinder; the pressure bar passes through the drilling top along the axial direction of the cylinder, the top end of the pressure bar is contacted with or separated from an unlocking pressure plate and moves along the axial direction of the cylinder, and the bottom end of the pressure bar acts on a rocker arm mechanism; the rocker arm mechanism is arranged on the drilling top; one end of a pulling plate assembly is connected with the rocker arm mechanism, and the other end of the pulling plate assembly is connected with a lock hook assembly of a lock hook mechanism; the lock hook assembly is hinged with the cylinder through a second hinged shaft; and the tail end of the lock hook assembly is selectively connected with a fastener of the drilling bottom. The drilling bucket has the advantages that as components mainly bear tension action during the process of opening the drilling bucket, the needed rigidity of the components is smaller, and the structural size of the components can be correspondingly reduced, thus improving the volumetric efficiency of the drilling bucket, avoiding damage caused by deformation of the components under the action of compressive stress owing to insufficient rigidity, and prolonging the service life of the drilling bucket. The invention further discloses the pile-driving machinery comprising the drilling bucket.

Description

A kind of piling machinery and drilling bucket thereof
Technical field
The present invention relates to field of mechanical technique, particularly a kind of drilling bucket that is used for piling machinery.The invention still further relates to a kind of piling machinery that comprises above-mentioned drilling bucket.
Background technology
Along with the fast development of China's economic construction, market increases day by day for the demand of various piling machinerys.
The work progress of modern construction engineering generally all begins with pile foundation construction, therefore, it is particularly important that pile hole construction seems, with the rotary drilling rig is example, in the work progress of rotary drilling rig, and can be according to the difference of the geological conditions that runs into, select to use various drilling tool, for example various drill bits or drilling bucket etc., rotary drilling rig need the boring mud in its drilling bucket is derived after creeping into a period of time, and need open drilling bucket this moment.
Please refer to Fig. 1, Fig. 1 is a kind of structural representation of typical rotary drilling rig.
The typical rotary drilling rig of this kind comprises equipment 11, equipment 11 hauls drilling rod 12, and drives and to carry on the drilling rod 12 or descend, and the rotation of drilling rod 12 and creeping into by unit head 14 drives, pressurization oil cylinder 13 drives the rising and the decline of unit head, and the end of drilling rod 12 is equipped with drilling bucket 15.Drilling bucket 15 is to use one of comparatively frequent drilling tool in the rotary drilling rig, it is a kind of drilling and forming hole device, cylindrical substantially straight tube of the profile of drilling bucket 15 or taper, it bores the end and can open fully, on the bottom cutting teeth and sluice gate are arranged, the soil that will cut when rotary drilling is considered to be worth doing in the bucket of packing into, can all take the soil bits out of bored hole after filling in the bucket, and the soil that will get out bits are from the bottom discharge of drilling bucket.When the soil bits under drilling bucket 15 is drilled fill up, rotary drilling rig need be outwelled soil, at this moment, equipment 11 will be carried on drilling rod 12 and the drilling bucket 15 earlier, forwards down the position of soil then to by revolution, and pressurization oil cylinder 13 presses down unit head 14, be provided with push rod between at the bottom of the release platen of unit head 14 and the brill of drilling bucket 15, one side of boring the end and drill body is hinged, and push rod moves downward and promotes hook lock with unit head 14 and opens drilling bucket, and the soil bits are poured out; And when drilling bucket is closed, rotary drilling rig need return back to suitable position (slope position that for example has the suitable gradient), 14 orders of rotational power head are bored the opening at the end and are in suitable position (position that for example deviates from the slope), equipment 11 is transferred drilling rod 12 and drilling bucket 15 then, provide impulse force upwards at the bottom of giving the brill of drilling bucket 15, and the hook lock that bores between end and the drill body by the order of this impulse force catches on, and closes thereby drive drilling bucket.
In above-mentioned rotary drilling rig, the unlatching of drilling bucket realizes by catch bar, because the power end of catch bar is far away with the distance of boring the end, this just requires the external diameter of catch bar enough big, has higher flexural strength to guarantee it, and the external diameter of catch bar is bigger, it is promptly bigger in the inner occupation space of drilling bucket, thereby influences the smooth degree that sand enters drilling bucket inside, and the utilization rate of steel is also very low simultaneously, if sand contains bigger sillar, may make then that depression bar is stuck can't to move; And if the external diameter of catch bar is less, can cause the catch bar easy deformation again, be easy to damage, the fault rate of drilling bucket is higher, and job stability is lower.
Therefore, how to improve the operating efficiency of drilling bucket switch, reduce its fault rate, improve job stability, just become the problem that those skilled in the art need solve.
Summary of the invention
The purpose of this invention is to provide a kind of drilling bucket that is used for piling machinery, it has higher unlatching efficient, and fault rate is lower, and job stability is higher.Another object of the present invention provides a kind of piling machinery that comprises above-mentioned drilling bucket.
For solving the problems of the technologies described above, the invention provides a kind of drilling bucket of piling machinery, comprise the brill top that is connected with the drilling rod of described piling machinery, lower end, described brill top is equipped with cylindrical shell, the lower end of described cylindrical shell is hinged with bores at the end, also comprise along the depression bar on the described brill of axially passing of described cylindrical shell top, the top of described depression bar contacts with the release platen of described piling machinery or separates, and axially-movable at the described cylindrical shell in the effect lower edge of described release platen, the bottom of described depression bar is supported on the arm-tie assembly, described arm-tie assembly by perpendicular to described drum shaft to first jointed shaft be articulated in described cylindrical shell, and its end away from described depression bar is equipped with lock hook assembly, described hook lock assembly is articulated in described cylindrical shell by second jointed shaft that is parallel to described first jointed shaft, and the end of described lock hook assembly is connected with fastener at the bottom of the described brill or disconnects connection.
Preferably, described arm-tie assembly comprises the arm-tie body and is articulated in the rocking arm of described cylindrical shell by described first jointed shaft; The described depression bar of one end bearing of described rocking arm, an end of its other end and described arm-tie body is hinged, and the other end of described arm-tie body is connected with described lock hook assembly.
Preferably, described rocking arm comprises first section with the described depression bar of one end bearing, with second section that is connected with described arm-tie body with the one end, described first section forms predetermined angle with described second section axis, and described first jointed shaft is positioned at the corner of described first section and described second section formation.
Preferably, described predetermined angle is 90 °.
Preferably, described arm-tie assembly also comprises bracing frame, and described rocking arm is installed on described cylindrical shell by support frame as described above.
Preferably, described lock hook assembly comprises latch hook support and latch hook body, and an end of described latch hook body is installed on described arm-tie assembly, and its other end is hinged by described second jointed shaft and described latch hook support.
Preferably, the tie point of described latch hook body and described arm-tie assembly is to the distance of described second jointed shaft, is the twice of the distance of the end of described latch hook body and described second jointed shaft.
Preferably, between described arm-tie assembly and the described lock hook assembly return element is installed.
Preferably, described return element is a spring, and described spring disconnects the moment that is connected at described hook lock assembly and described fastener and is in elongation state.
The present invention also provides a kind of piling machinery, comprises drilling rod and the drilling bucket that is installed on described drilling rod lower end, and described drilling bucket is as above-mentioned each described drilling bucket.
The drilling bucket that is used for piling machinery provided by the invention comprises the brill top that is connected with the drilling rod of described piling machinery, bore the lower end, top cylindrical shell is installed, the lower end of cylindrical shell is hinged with bores at the end, this drilling bucket also comprises along the depression bar on the described brill of axially passing of cylindrical shell top, the top of depression bar contacts with the release platen of piling machinery or separates, and axially-movable at the effect lower edge of release platen cylindrical shell, the bottom supporting of depression bar also acts on the arm-tie assembly, the arm-tie assembly by perpendicular to drum shaft to first jointed shaft be articulated in cylindrical shell, and its end away from depression bar is equipped with lock hook assembly, the hook lock assembly is articulated in cylindrical shell by second jointed shaft that is parallel to first jointed shaft, and the end of lock hook assembly is connected with the fastener that bores the end or disconnects connection.
In the time need opening at the bottom of the brill of drilling bucket, the release platen moves downward under the effect of unit head, and the promotion depression bar is along the axial downward movement of cylindrical shell, because arm-tie assembly and cylindrical shell are hinged, and end connection is also acted on depression bar, then when depression bar moves downward, the arm-tie assembly rotates around first jointed shaft, the end that the arm-tie assembly is connected with lock hook assembly is connected under the drive of an end of depression bar to the direction motion away from the hook lock assembly at it, thereby driving lock hook assembly rotates around second jointed shaft, the end of hook lock assembly is deviate from from fastener, opened under the effect of brill end gravity of boring mud in self gravitation and drilling bucket; Like this, because in the opening procedure of drilling bucket, what each assembly mainly bore all is the effect of pulling force, and mainly bear the depression bar of pressure effect and the close together between its press member release platen, then the required rigidity of each parts is less, the physical dimension of each parts can correspondingly reduce, and flexibility is better, thereby has improved the unlatching efficient of drilling bucket; Simultaneously, because the effect that is not stressed of each parts, avoid the damage that causes owing to the parts insufficient rigidity, thereby reduced fault rate, improved the application life of drilling bucket.
A kind of preferred embodiment in, arm-tie assembly provided by the present invention comprises the arm-tie body and is articulated in the rocking arm of cylindrical shell by first jointed shaft; an end of rocking arm is supported with depression bar, and an end of its other end and arm-tie body is hinged, and the other end of arm-tie body is connected with hook assembly; Rocking arm comprises first section of downward active force that bears described depression bar with the one end, with second section that is connected with described arm-tie body with the one end, first section axis with second section forms predetermined angle, and first jointed shaft is positioned at the corner of first section and second section formation; Like this, when under the effect of rocking arm at depression bar when first jointed shaft rotates, by choose reasonable; second section of rocking arm is connected the rectilinear motion that an end can realize not having rotation with the pull bar body to angle between first section and second section of rocking arm and both length; thus drive the rectilinear motion that the arm-tie main body only has predetermined direction; thus improved the validity that pulling force transmits, further improved the efficient of drilling bucket unlatching.
In the another kind of specific embodiment, lock hook assembly provided by the present invention comprises latch hook support and latch hook body, one end of latch hook body is installed on the arm-tie assembly, its other end is hinged by described second jointed shaft and described latch hook support, the distance of the tie point of latch hook body and described arm-tie assembly and described second jointed shaft is the twice of the distance of the end of described latch hook body and described second jointed shaft; Like this, it is the lever construction of fulcrum with second jointed shaft that the hook lock assembly has just formed one, thereby the pulling force that rocker assembly can be passed to the latch hook body amplifies, and has further improved the validity that pulling force transmits, and then has further improved the efficient that drilling bucket is opened.
Description of drawings
Fig. 1 is a kind of structural representation of typical rotary drilling rig;
Fig. 2 is the structural representation of a kind of specific embodiment of opening mechanism of drilling bucket provided by the present invention;
Fig. 3 is for being in the structural representation of closed condition in a kind of specific embodiment of drilling bucket provided by the present invention;
Fig. 4 is in the structural representation of opening for drilling bucket shown in Figure 3.
The specific embodiment
Core of the present invention provides a kind of drilling bucket that is used for piling machinery, and it has higher unlatching efficient, and fault rate is lower, and job stability is higher.Another core of the present invention provides a kind of piling machinery that comprises above-mentioned drilling bucket.
In order to make those skilled in the art person understand technical scheme of the present invention better, the present invention is described in further detail below in conjunction with the drawings and specific embodiments.
Please refer to Fig. 2, Fig. 3 and Fig. 4; Fig. 2 is the structural representation of a kind of specific embodiment of opening mechanism of drilling bucket provided by the present invention; Fig. 3 is for being in the structural representation of closed condition in a kind of specific embodiment of drilling bucket provided by the present invention; Fig. 4 is in the structural representation of opening for drilling bucket shown in Figure 3.
In a kind of specific embodiment, drilling bucket provided by the present invention is used for piling machinery, this drilling bucket comprises brill top 21, cylindrical shell 22 and bores at the end 23, wherein bore between the end 23 and the cylindrical shell 22 and be connected by hinge or jointed shaft, bore the end 23 under the driving of power can around its with cylindrical shell 22 between hinge or jointed shaft rotation, thereby realize the unlatching of drilling bucket or close, boring top 21 fixedlys connected with the drilling rod of this piling machinery, bore 21 lower ends, top cylindrical shell 22 is installed, the lower end of cylindrical shell 22 is hinged with bores at the end 23; This drilling bucket also comprises depression bar 3, this depression bar 3 bores top 21 along axially passing of described cylindrical shell 22, the top of depression bar 3 contacts with the release platen of piling machinery or separates, the release platen is the inherent structure of piling machinery, it is driven by unit head usually, can be with unit head axially making progress or moving downward along drilling rod, when the release platen moves downward to assigned address, can contact with depression bar 3, and along with the release platen continue move downward, promote depression bar 3 motions, depression bar 3 is axial the effect lower edge of release platen drilling rod, also be the axially-movable of cylindrical shell 22, the bottom of depression bar 3 is supported on the arm-tie assembly, and the arm-tie assembly is by being articulated in described cylindrical shell 22 perpendicular to the cylindrical shell 22 first axial jointed shafts 41, and the arm-tie assembly is equipped with lock hook assembly away from an end of depression bar 3, this hook lock assembly is articulated in described cylindrical shell 22, the first jointed shafts 41 by second jointed shaft 42 and is parallel to second jointed shaft 42, and the end of lock hook assembly is connected with the fastener 5 that bores the end 23 or disconnects connection.
Apparently, the piling machinery that above-mentioned drilling bucket was applied to is to have openable drilling bucket, and need open or close the plant equipment of drilling bucket in different duties, for example drilling bucket of rotary drilling rig etc.
It is pointed out that the nouns of locality such as " upper and lower, left and right, top, bottoms " mentioned herein only represents each parts direction of motion or present position in the accompanying drawings, be not limited to its direction of motion and present position in normal use.In addition, during predetermined angle mentioned herein and preset distance etc. were described, specifically should determining according to the mode of occupation of reality of angle and distance do not done qualification at this.
When at the bottom of the brill of drilling bucket 23 when opening, the release platen moves downward under the effect of unit head, and promotion depression bar 3 is along the axial downward movement of cylindrical shell 22, because arm-tie assembly and cylindrical shell 22 are hinged, an and end bearing depression bar 3, then when depression bar 3 moves downward, the arm-tie assembly rotates counterclockwise around first jointed shaft 41, the end that the arm-tie assembly is connected with lock hook assembly is supported under the drive of an end of depression bar 3 to the direction motion away from the hook lock assembly at it, thereby driving lock hook assembly rotates counterclockwise around second jointed shaft 42, the end of hook lock assembly is deviate from from fastener, opened under the effect of the brill end 23 gravity of boring mud in self gravitation and drilling bucket; Like this, because in the opening procedure of drilling bucket, what each assembly mainly bore all is the effect of pulling force, and mainly bear the depression bar 3 of pressure effect and the close together between its press member release platen, then the required rigidity of each parts is less, the physical dimension of each parts can correspondingly reduce, and flexibility is better, thereby has improved the unlatching efficient of drilling bucket; Simultaneously, the effect because each parts is not stressed has been avoided because insufficient rigidity is out of shape the damage that causes under action of compressive stress, thereby has been reduced fault rate, has improved the application life of drilling bucket.
Can also be further improved the drilling bucket that is used for piling machinery provided by the present invention.
Arm-tie assembly provided by the present invention can comprise arm-tie body 61 and rocking arm 62, and the arm-tie assembly is connected with lock hook assembly by arm-tie body 61, is connected with cylindrical shell 22 by rocking arm 62, and particularly, rocking arm 62 is articulated in cylindrical shell 22 by above-mentioned first jointed shaft 41; One end bearing depression bar 3 of this rocking arm 62, an end of its other end and arm-tie body 61 is hinged, and the other end of arm-tie body 61 is connected with lock hook assembly.
The arm-tie assembly also is not limited to above-mentioned concrete structure, it also can be other structures, for example, its rocking arm 62 and arm-tie body 61 can have integral structure, what be about to also that rocking arm 62 does is longer, as long as can realize spurring the purpose that lock hook assembly rotates counterclockwise around second jointed shaft 42, its specific constructive form should not be subjected to the qualification of the specific embodiment of the invention.
Above-mentioned rocking arm 62 comprises first section and second section, wherein first section with the one end bearing in depression bar 3, second section is connected with arm-tie body 61 with the one end, and first section axis with second section forms predetermined angle, and first jointed shaft 41 is positioned at the corner of first section and second section formation; Like this, when rocking arm 62 under the effect of depression bar 3 when first jointed shaft 41 rotates, by choose reasonable; second section of rocking arm 62 is connected the rectilinear motion that an end can realize not having rotation with the pull bar body to angle between first section and second section of rocking arm 62 and both length; thus drive the rectilinear motion that the arm-tie main body only has predetermined direction; thus improved the validity that pulling force transmits, further improved the efficient of drilling bucket unlatching.
Above-mentioned predetermined angle can be 90 °, when this predetermined angular is 90 °, is easier to realize the only purpose of moving linearly of pull bar body; Apparently, this predetermined angle also is not limited to 90 °, also can be other angles, has the motion perpendicular to the direction of cylindrical shell 22 axis as long as can realize the pull bar body, and its concrete angle is not done qualification at this.
Above-mentioned arm-tie assembly can also comprise bracing frame 63, and described rocking arm 62 is installed on cylindrical shell 22 by this bracing frame 63, thereby is convenient to being connected of rocking arm 62 and cylindrical shell 22, and improves the reliability that rocking arm 62 is connected with cylindrical shell 22.This bracing frame 63 can be the support body of hollow, and first jointed shaft 41 passes bracing frame 63 and arm-tie assembly and is installed on the cylindrical shell 22, to realize arm-tie assembly being connected by bracing frame 63 and cylindrical shell 22.Simultaneously, rocking arm 62 and the hollow support body inside that being connected of arm-tie body 61 also can be formed at bracing frame 63.
Apparently, the arm-tie assembly also can not comprise bracing frame 63, and rocking arm 62 can directly be installed on cylindrical shell 22 by second jointed shaft 42.
On the basis of above-mentioned each specific embodiment, can also be further improved drilling bucket provided by the present invention.
Lock hook assembly provided by the present invention can comprise latch hook support 71 and latch hook body 72, and wherein an end of latch hook support 71 is installed on the arm-tie assembly, and its other end is hinged with latch hook body 72 by second jointed shaft 42.
Apparently, lock hook assembly also is not limited to above-mentioned specific constructive form, and its latch hook support 71 and latch hook body 72 also can be the structure of integral type.
The tie point of above-mentioned latch hook body 72 and arm-tie assembly is to the distance of second jointed shaft 42, is the twice of the distance of the end of latch hook body 72 and second jointed shaft 42; Like this, it is the lever construction of fulcrum with second jointed shaft 42 that the hook lock assembly has just formed one, the pulling force that thereby rocker assembly can be passed to latch hook body 72 passes to the hook lock body tip with the size of twice, further improve the validity that pulling force transmits, and then further improved the efficient that drilling bucket is opened.
Between above-mentioned arm-tie assembly and the lock hook assembly return element can be installed, like this, after breaking away from the top of depression bar 3 when moving upward under the effect of release platen at unit head, lock hook assembly can be returned to original position under the effect of return element, like this, after colliding with, the end 23 and ground can realize closing of drilling bucket when boring.
Above-mentioned return element is a spring 8, and spring 8 disconnects the moment that is connected at hook lock assembly and fastener and is in elongation state, and the cost of spring 8 is lower, and functional reliability can guarantee.Above-mentioned return element also is not limited to spring 8, also can realize return purpose element or mechanism for other.
Also can be provided with return spring on depression bar 3, after the effect disappearance of release platen to depression bar 3, depression bar 3 can be returned to original position under the effect of this return spring.
Except above-mentioned drilling bucket, the present invention also provides a kind of piling machinery that comprises above-mentioned drilling bucket, and other each several part structures of this piling machinery please refer to prior art, do not repeat them here.
Particularly, this piling machinery can be rotary drilling rig.
More than a kind of piling machinery provided by the present invention and drilling bucket thereof are described in detail.Used specific case herein principle of the present invention and embodiment are set forth, the explanation of above embodiment just is used for helping to understand method of the present invention and core concept thereof.Should be pointed out that for those skilled in the art, under the prerequisite that does not break away from the principle of the invention, can also carry out some improvement and modification to the present invention, these improvement and modification also fall in the protection domain of claim of the present invention.

Claims (10)

1. the drilling bucket of a piling machinery comprises the brill top (21) that is connected with the drilling rod of described piling machinery, and (21) lower end, described brill top is equipped with cylindrical shell (22), and described cylindrical shell (22) lower end is hinged with bores at the end (23); It is characterized in that, also comprise along the depression bar (3) on the described brill top of axially passing of described cylindrical shell (22) (21), the top of described depression bar (3) contacts with the release platen of described piling machinery or separates, and axially-movable at the described cylindrical shell in the effect lower edge of described release platen (22), the bottom of described depression bar (3) is supported on the arm-tie assembly, described arm-tie assembly is by being articulated in described cylindrical shell (22) perpendicular to axial first jointed shaft (41) of described cylindrical shell (22), and its end away from described depression bar (3) is equipped with lock hook assembly, described lock hook assembly is articulated in described cylindrical shell (22) by second jointed shaft (42) that is parallel to described first jointed shaft (41), and the end of described lock hook assembly is connected with the fastener (5) of (23) at the bottom of the described brill or disconnects connection.
2. the drilling bucket of piling machinery according to claim 1 is characterized in that, described arm-tie assembly comprises arm-tie body (61) and is articulated in the rocking arm (62) of described cylindrical shell (22) by described first jointed shaft (41); The described depression bar of one end bearing (3) of described rocking arm (62), an end of its other end and described arm-tie body (61) is hinged, and the other end of described arm-tie body (61) is connected with described lock hook assembly.
3. the drilling bucket of piling machinery according to claim 2, it is characterized in that, described rocking arm (62) comprises first section with the described depression bar of one end bearing (3), with second section that is connected with described arm-tie body (61) with the one end, described first section forms predetermined angle with described second section axis, and described first jointed shaft (41) is positioned at the corner of described first section and described second section formation.
4. the drilling bucket of piling machinery according to claim 3 is characterized in that, described predetermined angle is 90 °.
5. the drilling bucket of piling machinery according to claim 4 is characterized in that, described arm-tie assembly also comprises bracing frame (63), and described rocking arm (62) is installed on described cylindrical shell (22) by support frame as described above (63).
6. the drilling bucket of piling machinery according to claim 1, it is characterized in that, described lock hook assembly comprises latch hook support (71) and latch hook body (72), one end of described latch hook body (72) is installed on described arm-tie assembly, and its other end is hinged by described second jointed shaft (42) and described latch hook support (71).
7. the drilling bucket of piling machinery according to claim 6, it is characterized in that, the tie point of described latch hook body (72) and described arm-tie assembly is to the distance of described second jointed shaft (42), is the twice of the distance of the end of described latch hook body (72) and described second jointed shaft (42).
8. according to the drilling bucket of each described piling machinery of claim 1 to 7, it is characterized in that, between described arm-tie assembly and the described lock hook assembly return element is installed.
9. the drilling bucket of piling machinery according to claim 8 is characterized in that, described return element is spring (8), and described spring (8) disconnects the moment that is connected at described lock hook assembly and described fastener and is in elongation state.
10. a piling machinery comprises drilling rod and the drilling bucket that is installed on described drilling rod lower end, it is characterized in that described drilling bucket is as each described drilling bucket of claim 1 to 9.
CN 201010586118 2010-12-13 2010-12-13 Pile-driving machinery and drilling bucket thereof Expired - Fee Related CN102061884B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010586118 CN102061884B (en) 2010-12-13 2010-12-13 Pile-driving machinery and drilling bucket thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010586118 CN102061884B (en) 2010-12-13 2010-12-13 Pile-driving machinery and drilling bucket thereof

Publications (2)

Publication Number Publication Date
CN102061884A true CN102061884A (en) 2011-05-18
CN102061884B CN102061884B (en) 2013-10-30

Family

ID=43997358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010586118 Expired - Fee Related CN102061884B (en) 2010-12-13 2010-12-13 Pile-driving machinery and drilling bucket thereof

Country Status (1)

Country Link
CN (1) CN102061884B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013063900A1 (en) * 2011-11-01 2013-05-10 湖南三一智能控制设备有限公司 Drilling tool and rotary drilling rig having same
CN103573187A (en) * 2013-11-12 2014-02-12 上海中联重科桩工机械有限公司 Shock attenuation is bored and is fought and dig rig soon
WO2018213941A1 (en) * 2017-05-22 2018-11-29 邵忠 Full-casing drilling tool
CN109882070A (en) * 2019-03-27 2019-06-14 中地君豪建筑工程有限公司 The cylinder drillstring component of rotary drilling rig and the method for unloading soil using the component

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08270360A (en) * 1995-03-28 1996-10-15 Hitachi Constr Mach Co Ltd Method for constructing manhole, and drilling bucket and drilling machine for it
CN2542816Y (en) * 2002-04-25 2003-04-02 倪立新 Axial integral opening rotary drilling digger
CN2878656Y (en) * 2005-12-23 2007-03-14 北京市三一重机有限公司 Open-type drill hopper
JP2010185188A (en) * 2009-02-10 2010-08-26 Hoei Sangyo Kk Drilling bucket

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08270360A (en) * 1995-03-28 1996-10-15 Hitachi Constr Mach Co Ltd Method for constructing manhole, and drilling bucket and drilling machine for it
CN2542816Y (en) * 2002-04-25 2003-04-02 倪立新 Axial integral opening rotary drilling digger
CN2878656Y (en) * 2005-12-23 2007-03-14 北京市三一重机有限公司 Open-type drill hopper
JP2010185188A (en) * 2009-02-10 2010-08-26 Hoei Sangyo Kk Drilling bucket

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013063900A1 (en) * 2011-11-01 2013-05-10 湖南三一智能控制设备有限公司 Drilling tool and rotary drilling rig having same
CN103573187A (en) * 2013-11-12 2014-02-12 上海中联重科桩工机械有限公司 Shock attenuation is bored and is fought and dig rig soon
CN103573187B (en) * 2013-11-12 2016-05-25 上海中联重科桩工机械有限公司 Shock attenuation is bored and is fought and dig rig soon
WO2018213941A1 (en) * 2017-05-22 2018-11-29 邵忠 Full-casing drilling tool
CN109882070A (en) * 2019-03-27 2019-06-14 中地君豪建筑工程有限公司 The cylinder drillstring component of rotary drilling rig and the method for unloading soil using the component
CN109882070B (en) * 2019-03-27 2024-05-03 广州君豪岩土工程有限公司 Barrel drilling assembly of rotary drilling rig and method for unloading soil by utilizing barrel drilling assembly

Also Published As

Publication number Publication date
CN102061884B (en) 2013-10-30

Similar Documents

Publication Publication Date Title
CN102061884B (en) Pile-driving machinery and drilling bucket thereof
KR101355053B1 (en) An auger with a movable gouge for making a borehole
CN102304922B (en) Full-pile casing construction device
CN101228334A (en) Apparatus and method for driving casing or conductor pipe
CN201363089Y (en) Rotary-excavating drill bit of sand
CN104453704A (en) Top hammer type impact rotary power head of hydraulic drilling machine
CN201474610U (en) Injection rock excitation device of rotary drilling rig
CN102168528B (en) Drill bucket capable of opening bucket door continuously to discharge soil forcibly
KR101374612B1 (en) Method and rock drilling rig for hole drilling
CN202100199U (en) Drilling bucket capable of opening bucket door continuously and unloading soil forcefully
CN104389515B (en) A kind of hydraulic drill rig jump bit
CN101832100B (en) Piling machinery and sluice gate device thereof
CN214532807U (en) Drilling bucket and rotary drilling rig with same
CN201306132Y (en) Tripping and eccentric wear preventing centralizer of oil well pump
CN212296221U (en) Pushing device and lifting appliance
CN201288500Y (en) Rotary drilling hydraulic power head with vibrator
CN112267505B (en) Continuous wall grab bucket device and control method thereof
CN208650819U (en) A kind of flat fishing sand borer of controllable bottom door folding
US8316960B2 (en) Hammer device
CN207924159U (en) A kind of body strain instrument erection device
CN202117583U (en) Compression mechanism for drill rod of engineering driller
CN102900391B (en) Drilling bucket and use the rotary drilling rig of this drilling bucket
KR20170083182A (en) Hydraulic breaker having one body type casing
CN204266914U (en) A kind of hydraulic drill rig jump bit
CN219638773U (en) Auxiliary reaming device for casing pipe discharging and additionally installed with rotary drilling bit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131030

Termination date: 20181213

CF01 Termination of patent right due to non-payment of annual fee