CN102003191B - 一种矿山帷幕注浆效果判定方法 - Google Patents

一种矿山帷幕注浆效果判定方法 Download PDF

Info

Publication number
CN102003191B
CN102003191B CN201010508003A CN201010508003A CN102003191B CN 102003191 B CN102003191 B CN 102003191B CN 201010508003 A CN201010508003 A CN 201010508003A CN 201010508003 A CN201010508003 A CN 201010508003A CN 102003191 B CN102003191 B CN 102003191B
Authority
CN
China
Prior art keywords
grouting
curtain
hole
qualified
preface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201010508003A
Other languages
English (en)
Other versions
CN102003191A (zh
Inventor
梅宝峰
李贞芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Iron and Steel Group Mining Co Ltd
HBIS Co Ltd
Hebei Iron and Steel Group Co Ltd
Original Assignee
HBIS Co Ltd
Hebei Iron and Steel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HBIS Co Ltd, Hebei Iron and Steel Group Co Ltd filed Critical HBIS Co Ltd
Priority to CN201010508003A priority Critical patent/CN102003191B/zh
Publication of CN102003191A publication Critical patent/CN102003191A/zh
Application granted granted Critical
Publication of CN102003191B publication Critical patent/CN102003191B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

一种矿山帷幕注浆效果判定方法,属采矿技术领域,用于解决帷幕注浆效果判定方法严重滞后于工程质量管理问题。技术方案是,它按照如下步骤实施:a.确定矿山帷幕注浆导水岩层为结晶灰岩层;b.根据结晶灰岩层地质构造特性确定浆液在注浆压力作用下的两种主要运动模式及特点;c.确定各序孔分段注浆“管道流”持续时间T与“渗透流”持续时间t的比值,d.打孔注浆过程中各序孔单段按照C步骤标准判断注浆效果是否合格。本方法可以在帷幕注浆单孔单段阶段,根据注浆量和注浆压力的变化实时做出注浆效果判断,对不符合注浆条件的及时采取补救措施,使工程质量管理与工程进度同步进行,有效加快工程进度,提高工程管理水平。

Description

一种矿山帷幕注浆效果判定方法
技术领域
本发明涉及一种矿山帷幕注浆工程技术,特别是矿山帷幕注浆效果确定方法,属采矿技术领域。
背景技术
帷幕注浆是指通过地质钻孔后,以一定压力将注浆材料经所钻孔注入岩石裂隙中,构筑帷幕以堵截地下水的一种防治水方法。利用帷幕注浆防治矿山地下水不仅可以提高企业经济效益、保护矿区水文地质环境,而且可以消除大水矿山的安全隐患,该技术已被大水矿山逐步采用。目前,帷幕注浆工艺、技术还处于完善提高阶段,对注浆效果的判定方法如下:不同序次打孔分别注浆(常规是三序次),待全部注浆完成后,以各序次孔中注浆量的变化为依据判定注浆效果是否合格,即由I序孔至III序孔若单孔平均注灰量依次减少30%~60%即可认为达到注浆效果,若达不到上述要求则通过加密孔补注等措施补救。这种方法存在的问题是:必须完成一个完整序次(通常是4-5个注浆孔)才能分析确定注浆效果及采取的措施,因此使工程质量管理严重滞后于工程进度。此外,一直以来矿山帷幕注浆钻孔孔径均取108mm或90mm,孔径偏大,钻进效率低,增加了注浆次数及帷幕注浆的工程投资。
发明内容
本发明目的在于克服已有技术的缺陷而提供一种可对矿山帷幕注浆效果做出实时判断以便及时处理的矿山帷幕注浆效果判定方法。
本发明所称问题是由以下技术方案解决的:
一种矿山帷幕注浆效果判定方法,其特别之处是,它按照如下步骤实施:
a.确定矿山帷幕注浆导水岩层为结晶灰岩层;
b.根据结晶灰岩层地质构造特性确定浆液在注浆压力作用下的两种主要运动模式及特点:其一,浆液沿主要构造裂隙方向以“管道流”方式运动,此时注浆流量大、注浆压力小且相对稳定;其二,浆液沿次生构造裂隙以“渗透流”向外均匀扩散,此时注浆压力逐渐增大至稳定,注浆流量逐渐减少,直至注浆结束;
c.确定各序孔分段注浆“管道流”持续时间T与“渗透流”持续时间t的比值,其中:I序孔T1/t1为5-45;II序孔T2/t2为3-25;III序孔T3/t3为0-6,各序孔的对应段需满足T1/t1≥T2/t2≥T3/t3;
d.打孔注浆过程中各序孔单段按照C步骤标准判断注浆效果是否合格。
上述矿山帷幕注浆效果判定方法,所述d步骤中钻孔直径为75毫米、108毫米或90毫米。
上述矿山帷幕注浆效果判定方法,所述各序孔分段长度≤30米。
本发明方法针对目前帷幕注浆效果的判定方法严重滞后于工程质量管理的问题进行了改进,该方法根据地质构造、浆液运动方式及运动规律建立矿山帷幕单孔单段注浆浆液运动模型,在该模型基础上提出矿山帷幕注浆效果判定标准,采用本方法可以在单孔单段阶段,根据注浆量和注浆压力的变化实时做出注浆效果判断,对不符合注浆条件的及时采取补救措施,使工程质量管理与工程进度同步进行,可有效加快工程进度。此外,本方法注浆孔采用75毫米直径小孔,在达到注浆目的、保证工程质量的基础上,提高了钻机钻进效率和注浆效率,减少工程投资。
附图说明
图1是帷幕注浆序孔示意图;
图2是单孔单段浆液运动规律示意图。
附图中标号表示如下:1.I序孔,2.II序孔,3.III序孔,4.注浆帷幕线。
具体实施方式
本发明根据地质构造、浆液运动方式及运动规律建立矿山帷幕单孔单段注浆浆液运动模型,并以其判断矿山帷幕注浆单孔单段工程质量,弥补了以往以不同序次单孔注浆(灰)量变化分析工程质量、工程质量管理严重滞后于工程施工进度的不足。
本发明方法按如下步骤实施:
1.确定导水岩层及性质:矿山帷幕注浆导水岩层为结晶灰岩,结晶灰岩地质特性为:高序次为主要构造裂隙,低序次为次生构造裂隙,裂隙之间相互贯通。
2.根据结晶灰岩层地质构造特性确定浆液在注浆压力作用下的两种主要运动模式及特点,参看图2,(1)浆液沿主要构造裂隙方向以″管道流″方式运动,此方式时注浆流量大、注浆压力小且相对稳定;(2)浆液沿次生构造裂隙以“渗透流”向外均匀扩散,此时注浆压力逐渐增大至稳定,注浆流量逐渐减少,直至注浆结束。
3.根据浆液两种主要运动模式及特点,确定各序孔分段注浆“管道流”持续时间T与“渗透流”持续时间t的比值,图1所示为帷幕注浆序孔示意图。I序孔、II序孔单孔单段注浆开始阶段浆液以管道流充填,随主要裂隙被充填逐渐转为渗透流充填;III序孔管道流充填时间明显降低,有些注浆段只出现渗透流方式,直至注浆结束。据此,确定各序孔分段注浆“管道流”持续时间T与“渗透流”持续时间t的比值如下:I序孔T1/t1为5-45;II序孔T2/t2为3-25;III序孔T3/t3为0-6,且各序孔的对应段应满足条件T1/t1≥T2/t2≥T3/t3。
4.打孔注浆过程中各序孔单孔单段按照上述“管道流”持续时间T与“渗透流”持续时间t的比值标准判断注浆效果是否合格,符合标准的为合格注浆段,否则即判定注浆质量不合格,进而采取调整浆液浓度或补打加密孔等补救措施。
以下提供具体实施例:
中关铁矿矿体围岩为结晶灰岩,浆液运动符合″管道流″和″渗透流″运动方式和规律,采用本发明方法进行帷幕注浆质量管理取得了理想的效果,质量达到设计要求。
实施例1:钻孔直径90毫米,各序孔分别为7段,分段长度30米,各序孔分段注浆特性见表1。
表1
  孔号   段号   T(min)   T(min)   T/t   质量评述
  K-1(I序孔)   K-1-(1)   2835   64   44.3   合格
  K-1-(2)   3187   75   42.5   合格
  K-1-(3)   2529   90   28.1   合格
  K-1-(4)   1934   73   26.5   合格
  K-1-(5)   2318   76   30.5   合格
  K-1-(6)   1450   89   16.3   合格
  K-1-(7)   1329   88   15.1   合格
  K-2(II序孔)   K-2-(1)   198   64   3.1   合格
  K-2-(2)   218   68   3.2   合格
  K-2-(3)   234   65   3.6   合格
  K-2-(4)   317   66   4.8   合格
  K-2-(5)   1108   78   14.2   合格
  K-2-(6)   1094   81   13.5   合格
  K-2-(7)  787   64   12.3   合格
  K-3(III序孔)   K-3-(1)  0   64   0   合格
  K-3-(2)  0   63   0   合格
  K-3-(3)  0   71   0   合格
  K-3-(4)  245   68   3.6   合格
  K-3-(5)  348   59   5.9   合格
  K-3-(6)  269   64   4.2   合格
  K-3-(7)  0   61   0   合格
实施例2:钻孔直径90毫米,各序孔分别为6段,分段长度30米,各序孔分段注浆特征见表2:
表2
  孔号   段号   T(min)   T(min)   T/t   质量评述
  K-82(I序孔)   K-82-(1)   2285   67   34.1   合格
  K-82-(2)   3003   78   38.5   合格
  K-82-(3)   3588   81   44.3   合格
  K-82-(4)   4802   87   55.2   不合格
  K-82-(5)   470   87   5.4   不合格
  K-82-(6)   657   62   10.6   合格
  K-83(II序孔)   K-83-(1)   1104   80   13.8   合格
  K-83-(2)   787   61   12.9   合格
  K-83-(3)   750   62   12.1   合格
  K-83-(4)   700   68   10.3   合格
  K-83-(5)   547   74   7.4   不合格
  K-83-(6)   758   79   9.6   合格
  K-84(III序孔)   K-84-(1)   0   61   0   合格
  K-84-(2)   192   62   3.1   合格
  K-84-(3)   353   62   5.7   合格
  K-84-(4)   347   71   4.9   合格
  K-84-(5)   435   75   5.8   不合格
  K-84-(6)   444   78   5.7   合格
K-82-(4)段T/t=55.2,大于标准值45,判断为不合格注浆段;K-82-(5)段、K-83-(5)、K-84-(5)段不符合各序孔对应段T1/t1≥T2/t2≥T3/t3的要求,判断其为不合格注浆段,对上述不合格注浆段采取了加密补注措施。
实施例3:中关铁矿对帷幕注浆采用75毫米小孔径钻机进行了试验,各序孔分别为6段,分段长度30米。试验过程为:先进行I序孔注浆试验,通过浆液运动模型判断已施工注浆段质量,如其浆液运动符合浆液运动模型,则进行其下注浆段试验,如I序孔注浆质量合格再进行II序孔注浆试验,II序孔合格再进行III序孔试验。结果表明:75mm孔径进行帷幕注浆,其注浆压力、流量与所建立的浆液运动模型相符合(见表3),经检查孔检测表明:采用小孔径进行矿山帷幕注浆可保证工程质量,技术可行。
表3中关铁矿75mm孔径注浆试验数据
  孔号   段号   T(min)   t(min)   T/t   质量评述
  SY-1(I序孔)   SY-1-(1)   2463   69   35.7   合格
  SY-1-(2)   2870   78   36.8   合格
  SY-1-(3)   3620   84   43.1   合格
  SY-1-(4)   2216   83   26.7   合格
  SY-1-(5)   1931   68   28.4   合格
  SY-1-(6)   2246   64   35.1   合格
  SY-2(II序孔)   SY-2-(1)   1043   74   14.1   合格
  SY-2-(2)   990   75   13.2   合格
  SY-2-(3)   678   64   10.6   合格
  SY-2-(4)   302   63   4.8   合格
  SY-2-(5)   378   64   5.9   合格
  SY-2-(6)   870   68   12.8   合格
  SY-3(III序孔)   SY-2-(1)   143   68   2.1   合格
  SY-2-(2)   0   65   0   合格
  SY-2-(3)   0   63   0   合格
  SY-2-(4)   100   59   1.7   合格
  SY-2-(5)   109   64   1.7   合格
  SY-2-(6)   85   61   1.4   合格

Claims (3)

1.一种矿山帷幕注浆效果判定方法,其特征在于,它按照如下步骤实施:
a.确定矿山帷幕注浆导水岩层为结晶灰岩层;
b.根据结晶灰岩层地质构造特性确定浆液在注浆压力作用下的两种主要运动模式及特点:其一,浆液沿主要构造裂隙方向以“管道流”方式运动,此时注浆流量大、注浆压力小且相对稳定;其二,浆液沿次生构造裂隙以“渗透流”向外均匀扩散,此时注浆压力逐渐增大至稳定,注浆流量逐渐减少,直至注浆结束;
c.确定各序孔分段注浆“管道流”持续时间T与“渗透流”持续时间t的比值,其中:I序孔T1/t1为5-45;II序孔T2/t2为3-25;III序孔T3/t3为0-6,各序孔的对应段需满足条件T1/t1≥T2/t2≥T3/t3;
d.打孔注浆过程中各序孔单段按照c步骤标准判断注浆效果是否合格。
2.根据权利要求1所述的矿山帷幕注浆效果判定方法,其特征在于:所述d步骤中各序孔直径75毫米、108毫米或90毫米。
3.根据权利要求2所述的矿山帷幕注浆效果判定方法,其特征在于:所述各序孔分段长度≤30米。
CN201010508003A 2010-10-15 2010-10-15 一种矿山帷幕注浆效果判定方法 Expired - Fee Related CN102003191B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010508003A CN102003191B (zh) 2010-10-15 2010-10-15 一种矿山帷幕注浆效果判定方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010508003A CN102003191B (zh) 2010-10-15 2010-10-15 一种矿山帷幕注浆效果判定方法

Publications (2)

Publication Number Publication Date
CN102003191A CN102003191A (zh) 2011-04-06
CN102003191B true CN102003191B (zh) 2012-10-10

Family

ID=43810861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010508003A Expired - Fee Related CN102003191B (zh) 2010-10-15 2010-10-15 一种矿山帷幕注浆效果判定方法

Country Status (1)

Country Link
CN (1) CN102003191B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825264B (zh) * 2018-05-30 2020-03-06 中煤科工集团西安研究院有限公司 一种浅埋近水平烧变岩含水层的帷幕注浆方法
CN111878094B (zh) * 2020-08-06 2022-02-15 中铁九局集团有限公司 一种地铁破碎带帷幕注浆后安全性判定方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1257569A (zh) * 1969-03-13 1971-12-22
RU2333320C1 (ru) * 2006-12-11 2008-09-10 Юрий Викторович Пономаренко Способ защиты горных работ от обводнения, водных ресурсов от загрязнения нефтепродуктами в трещиноватых водоносных пластах
CN201400890Y (zh) * 2009-04-15 2010-02-10 深圳市市政工程总公司 复合止水帷幕结构
CN101638987B (zh) * 2009-07-24 2013-05-01 中铁二十一局集团有限公司 用帷幕注浆加止浆墙穿越高压富水断裂带的隧道施工方法
CN101781889B (zh) * 2010-01-29 2014-10-08 中铁四局集团第五工程有限公司 一种h型止水帷幕施工工艺

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘福东等.矿山尾矿坝基础防渗化学注浆技术研究.《矿冶工程》.2007,第27卷(第3期),11-14. *
白聚波等.矿山帷幕注浆及其效果测试.《金属矿山》.2008,(第5期),83-85,109. *
韩贵雷等.矿山帷幕注浆方案研究及堵水效果综合分析.《矿业研究与开发》.2010,第30卷(第3期),95-98. *

Also Published As

Publication number Publication date
CN102003191A (zh) 2011-04-06

Similar Documents

Publication Publication Date Title
CN101915083B (zh) 煤矿井上下联合抽采煤层气的方法
CN103821544B (zh) 隧道与地下工程高压大流量突涌水治理方法
CN104989403A (zh) 底板灰岩含水层改造成自然人工复合完整隔水层的方法
CN103867229A (zh) 一种煤矿大采深与下组煤开采防治水综合治理方法
CN102720528A (zh) 煤矿井下重复脉动水力压裂强化瓦斯抽采方法
CN106593300A (zh) 一种薄层灰岩地面定向钻进水平多级分支注浆钻孔
PL237727B1 (pl) Sposób określania indeksów rozróżnienia strukturalnego górnych stref wypełnienia wapienia ordowiku
CN105952427A (zh) 一种低渗透油藏注水诱导裂缝的预测与评价方法
Vu Solutions to prevent face spall and roof falling in fully mechanized longwall at underground mines, Vietnam.
CN103233738A (zh) 一种急倾斜特厚煤层顶煤综合弱化方法
CN109900232B (zh) 缝面含可溶盐裂缝性地层钻井液防漏方法
CN105756700A (zh) 超大断面隧道穿煤系地层段的施工方法及封孔结构
CN111119996A (zh) 一种煤炭开采突水溃沙防治方法
CN108757043A (zh) 一种针对采掘工作面防治水方法
CN108442378A (zh) 一种引水隧洞钢筋混凝土衬砌段固结灌浆工法
CN102003191B (zh) 一种矿山帷幕注浆效果判定方法
CN106014419B (zh) 多分支孔地面预注浆堵水施工方法
CN104712286A (zh) 一种利用煤层底板含水层单孔放水试验成果分类注浆方法
CN111720116B (zh) 一种缝洞型油藏单元氮气驱气窜判定方法及注采防窜方法
CN115419384B (zh) 一种采动覆岩完全破断型的含水层动态注浆截流堵水方法
Zhang et al. Directional drainage grouting technology of coal mine water damage treatment
CN109917463A (zh) 基于钻孔信息库的注浆工作面底板突水危险性评价体系
CN114738011B (zh) 一种矿井老突水点封堵方法
CN103175947B (zh) 一种缝洞型碳酸盐油气藏水体分析系统和方法
CN111472839B (zh) 基于综合渗控的富水隧洞施工排水量定量计算方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121010

Termination date: 20151015

EXPY Termination of patent right or utility model