CN101967884A - Method for controlling concrete planeness of large-area steel bar truss template - Google Patents

Method for controlling concrete planeness of large-area steel bar truss template Download PDF

Info

Publication number
CN101967884A
CN101967884A CN 201010282311 CN201010282311A CN101967884A CN 101967884 A CN101967884 A CN 101967884A CN 201010282311 CN201010282311 CN 201010282311 CN 201010282311 A CN201010282311 A CN 201010282311A CN 101967884 A CN101967884 A CN 101967884A
Authority
CN
China
Prior art keywords
concrete
guide rail
steel
angle steel
steel guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010282311
Other languages
Chinese (zh)
Other versions
CN101967884B (en
Inventor
吴银国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongan Huali Construction Group Co.,Ltd.
Original Assignee
ANHUI HUALI CONSTRUCTION GROUP CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI HUALI CONSTRUCTION GROUP CO LTD filed Critical ANHUI HUALI CONSTRUCTION GROUP CO LTD
Priority to CN2010102823113A priority Critical patent/CN101967884B/en
Publication of CN101967884A publication Critical patent/CN101967884A/en
Application granted granted Critical
Publication of CN101967884B publication Critical patent/CN101967884B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention belongs to the technical field of building construction, in particular relating to a method for controlling concrete planeness of a large-area steel bar truss template. The method for controlling concrete planeness of the large-area steel bar truss template comprises the following steps of: firstly, arranging a horizontal angle steel guide rail, i.e. carrying out spot welding installation on the horizontal angle steel guide rail and a vertical short angle steel; then arranging the angle steel guide rail according to width of a steel beam; and then pouring structural concrete, compactly vibrating, and flat-pressing and compacting the vibrated concrete by using a roller along an angle steel track in a reciprocating way. In the method for controlling concrete planeness of the large-area steel bar truss template, the truss template and a concrete cast-in-place plate are combined as a structural layer and the planeness is arranged in a pouring region to control the angle steel guide rail, therefore, the planeness of a cast-in-place plate of the large-area steel bar truss template is effectively ensured about 2mm to 2m and the qualified rate is more than 90 percent when the large-area concrete is poured, and the laying precision of floor concrete of a large factory is enhanced.

Description

Large tracts of land reinforcing bar truss mould concrete roughness control method
Technical field
The present invention relates to a kind of large tracts of land reinforcing bar truss mould concrete roughness control method, belong to technical field of building construction.
Background technology
What large area concrete job practices utilization at present was more is to divide the storehouse construction method, being about to concrete is not more than 6000mm by width and carries out lattice, concrete both sides formwork, the method for in minute storehouse, carrying out concreting and the concrete surface planeness being carried out quality control.As adopt ground layer to beat steel bar end or welded reinforcement head, the high method of controlling the top of concrete absolute altitude of top mark with steel bar end, this method is fanned out from point to area, constructing operation is easy, concrete ground surface evenness after these class methods are poured into a mould is at 5~15mm/2m, but its operative skill to the workman is had relatively high expectations, it is many that roughness control artificially reaches the instrument factor, random big, construction quality depends primarily on workman's operant level, roughness control is often undesirable, in practice, often because workman's operative skill difference, and cause the construction results of concrete surface to differ greatly, about investigating this method small size planeness qualification rate to have only 80% even lower, large tracts of land is often defective.Moreover, fast development along with China's process industry, large span large tracts of land warehouse or workshop object of construction production also order become to increasing, high precision apparatus is installed the concrete surface roughness control is also had higher requirement, as a lot of plant and equipments the requirement of ground flat degree is reached 2mm/2m, otherwise can cause follow-up epoxy resin surface layer quality out of control.
Summary of the invention
The lower problem of planeness qualification rate had proposed a kind of large tracts of land reinforcing bar truss mould concrete roughness control method when the present invention laid large tracts of land reinforcing bar truss mould concrete at present for solving, and this method comprises the steps:
(1) after laying the steel bar girder mould on the girder steel, with the roofing column is benchmark, the structural concrete thickness of Pu Sheing carries out absolute altitude control as required, on girder steel along truss mould direction, straight line is provided with vertical angle cleat, be with steel wire on the angle cleat after having surveyed absolute altitude,, again the horizontal corner steel guide rail carried out spot welding with vertical angle cleat and install with control guide rail level; Wherein, described vertical angle cleat is welded on the girder steel, and the thickness of the structural concrete of the required laying of its aspect ratio hangs down 3~5mm; A limit of angle steel guide rail is placed straight up and is welded mutually with a face of vertical angle cleat, the another side horizontal positioned of angle steel guide rail, and vertical angle cleat termination is suitable for reading a little less than horizontal corner steel guide rail limit;
(2) according to the method for step (1), press girder steel fabric width 5000-8000mm, an angle steel guide rail is set on the every girder steel;
(3) setting completed for the angle steel guide rail, the pouring structure concrete, vibration compacting, use cylinder with fabric width along the angle steel track back and forth with the compacting of vibrated concrete rolling.
Described vertical angle cleat termination is lower than horizontal corner steel guide rail limit 3mm at least suitable for reading; Receive Seterolithography with mechanical photoreceiver before the concrete final set after the rolling compacting.
The specification of described angle steel guide rail is
Figure BSA00000270754300021
25 * 25 * 3.
Large tracts of land reinforcing bar truss mould concrete roughness control method of the present invention adopts and combines with concrete cast-in-place slab as the mode of deck with truss mould plate; and roughness control angle steel guide rail is set in the pouring area; can be when large area concrete be built; the planeness that has effectively guaranteed large tracts of land reinforcing bar truss module and cast-in-situ plate about 2mm/2m and qualification rate more than 90%, improved the concrete laying precision of floor of large-scale factory.
Description of drawings
Fig. 1 is an angle steel guide rail scheme of installation;
Fig. 2 arranges schematic diagram for the angle steel guide level.
The specific embodiment
Embodiment: new website development zone, Hefei City floor two-layer structure concrete construction example.
This engineering making area is 43248M 2, area is big, roofing column spacing 17000*12000mm, girder steel fabric width 6000mm.
(1) on girder steel, installs the steel bar girder support shuttering; With roofing column 4 is benchmark, be as the criterion with the thickness 150mm of the structural concrete of required laying and carry out absolute altitude control, and on girder steel along truss mould direction, a vertical angle cleat 2 is set and is with absolute altitude control wire every the 2000mm straight line, vertical angle cleat 2 adopts and is welded on the girder steel 3, straight line along vertical angle cleat 2 is provided with direction then, will
Figure BSA00000270754300031
25*25*3 angle steel guide rail 1 carries out spot welding with vertical angle cleat 2 and installs, a limit of angle steel guide rail 1 is placed straight up and is welded mutually with a face of vertical angle cleat 2, the another side horizontal positioned of angle steel guide rail 1, vertical angle cleat 2 terminations are lower than horizontal corner steel guide rail limit 3mm at least suitable for reading; During the installation of vertical angle cleat 2, can be earlier with two
Figure BSA00000270754300032
The tension of absolute altitude control wire is with in 25*25 angle cleat welding location, and the angle steel bottom is leveled up in advance with lumps of wood cushion block, and established angle steel guide rail 1 and angle cleat spot welding under the control of level gauge are fixed according to spacing 2000mm then again, and the weldering of limit calibration edge point is installed; After the angle steel track was installed the leveling end, the available water leveling ruler carried out the repetition measurement examination.
(2), every 6000mm one angle steel guide rail is set by the fabric width of girder steel 3 according to the method for step (1);
(3) setting completed for the angle steel guide rail, builds the floor structure concrete, uses small-sized poker vibrator to insert soon and pull out slowly, and slotting point is evenly distributed, and pointwise one is moving, and order is carried out, and must not omit, and accomplishes even jolt ramming.Moving interval is not more than 1.5 times (being generally 30-40cm) of the operating radius that vibrates.The moving interval of external vibrator should guarantee that the flat board of vibrator covers the edge of the part of jolt ramming.Then in the both sides of building the width of cloth with two human 6.5M cylinders along the angle steel track back and forth with the compacting of vibrated concrete rolling, before concrete final set, receiving Seterolithography with mechanical photoreceiver.
The layout of horizontal corner steel guide rail and concreting are arranged as shown in Figure 2, in building floor structure concrete process, as when meeting the horizontal corner steel guide rail and placing the situation of position, ater-casting 6, reinforcing band position 5 etc., can earlier ater-casting, reinforcing band partly be reserved not concreting, treat to unify again to build after the moulding of floor basal plane.For guaranteeing the Concrete Construction quality, after concrete construction finishes, carry out the cover film moisture-keeping maintaining in the 12h; Reach 1.2N/mm at concrete strength 2After could go up the people, and add a cover the thick veneer of 9mm and carry out finished product protection.After treating concrete setting, adopt planeness that 2M guiding ruler actual measurement steel bar girder props up hold mode concrete structure ground all about 2mm, the planeness qualification rate is more than 90%.

Claims (4)

1. large tracts of land reinforcing bar truss mould concrete roughness control method is characterized in that: comprise the steps:
(1) after laying the steel bar girder mould on the girder steel, with the roofing column is benchmark, the structural concrete thickness of Pu Sheing carries out absolute altitude as required, on girder steel along the direction of truss mould, straight line is provided with vertical angle cleat, be with steel wire on the angle cleat after having surveyed absolute altitude,, again the horizontal corner steel guide rail carried out spot welding with vertical angle cleat and install with control guide rail level; Wherein, an end of described vertical angle cleat is welded on the girder steel, and the thickness of the structural concrete of the required laying of its aspect ratio hangs down 3~5mm; A limit of angle steel guide rail is placed straight up and is welded mutually with a face of vertical angle cleat, the another side horizontal positioned of angle steel guide rail, and vertical angle cleat termination is suitable for reading a little less than horizontal corner steel guide rail limit;
(2) according to the method for step (1), press girder steel fabric width 5000-8000mm, an angle steel guide rail is set on the every girder steel;
(3) setting completed for the angle steel guide rail, the pouring structure concrete, and vibration compacting is used with the fabric width cylinder along the angle steel guide rail back and forth with the compacting of vibrated concrete rolling.
2. large tracts of land reinforcing bar truss mould concrete roughness control method according to claim 1 is characterized in that: vertical angle cleat termination is lower than horizontal corner steel guide rail limit 3mm at least suitable for reading, and is with absolute altitude control wire.
3. large tracts of land reinforcing bar truss mould concrete roughness control method according to claim 1 is characterized in that: receive Seterolithography with mechanical photoreceiver before the concrete final set after the rolling compacting.
4. large tracts of land reinforcing bar truss mould concrete roughness control method according to claim 1, it is characterized in that: the specification of described angle steel guide rail is
Figure FSA00000270754200011
CN2010102823113A 2010-09-10 2010-09-10 Method for controlling concrete planeness of large-area steel bar truss template Active CN101967884B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102823113A CN101967884B (en) 2010-09-10 2010-09-10 Method for controlling concrete planeness of large-area steel bar truss template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102823113A CN101967884B (en) 2010-09-10 2010-09-10 Method for controlling concrete planeness of large-area steel bar truss template

Publications (2)

Publication Number Publication Date
CN101967884A true CN101967884A (en) 2011-02-09
CN101967884B CN101967884B (en) 2012-03-28

Family

ID=43547099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102823113A Active CN101967884B (en) 2010-09-10 2010-09-10 Method for controlling concrete planeness of large-area steel bar truss template

Country Status (1)

Country Link
CN (1) CN101967884B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109098449A (en) * 2017-06-21 2018-12-28 五冶集团上海有限公司 Angle steel guide rail system and its application method for large area concrete ground construction
CN109914666A (en) * 2019-04-03 2019-06-21 江铃汽车集团江西工程建设有限公司 Profiled sheet Combined concrete flooring large area pouring construction method
CN110512872A (en) * 2019-08-12 2019-11-29 世源科技工程有限公司 Concrete-face closure flatness control methods
CN111561041A (en) * 2020-05-21 2020-08-21 浙江世润建创科技发展有限公司 Cast-in-place concrete pool bottom plate and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004218221A (en) * 2003-01-10 2004-08-05 Tadatoshi Mannouji Method for constructing foundation and auxiliary tool for constructing foundation
CA2424603A1 (en) * 2003-04-04 2004-10-04 Paul Parenteau Guide post for masonry construction
CN2825832Y (en) * 2005-07-22 2006-10-11 中国第二十冶金建设公司 Surface level control device for concrete casting
CN101492965A (en) * 2008-05-16 2009-07-29 中冶天工上海十三冶建设有限公司 Large area cast-in-situ concrete plate flatness control method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004218221A (en) * 2003-01-10 2004-08-05 Tadatoshi Mannouji Method for constructing foundation and auxiliary tool for constructing foundation
CA2424603A1 (en) * 2003-04-04 2004-10-04 Paul Parenteau Guide post for masonry construction
CN2825832Y (en) * 2005-07-22 2006-10-11 中国第二十冶金建设公司 Surface level control device for concrete casting
CN101492965A (en) * 2008-05-16 2009-07-29 中冶天工上海十三冶建设有限公司 Large area cast-in-situ concrete plate flatness control method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109098449A (en) * 2017-06-21 2018-12-28 五冶集团上海有限公司 Angle steel guide rail system and its application method for large area concrete ground construction
CN109914666A (en) * 2019-04-03 2019-06-21 江铃汽车集团江西工程建设有限公司 Profiled sheet Combined concrete flooring large area pouring construction method
CN110512872A (en) * 2019-08-12 2019-11-29 世源科技工程有限公司 Concrete-face closure flatness control methods
CN111561041A (en) * 2020-05-21 2020-08-21 浙江世润建创科技发展有限公司 Cast-in-place concrete pool bottom plate and construction method thereof
CN111561041B (en) * 2020-05-21 2021-07-06 浙江世润建创科技发展有限公司 Cast-in-place concrete pool bottom plate and construction method thereof

Also Published As

Publication number Publication date
CN101967884B (en) 2012-03-28

Similar Documents

Publication Publication Date Title
CN103938796B (en) Cast-in-situ reinforced concrete column construction
CN103590602B (en) The construction method of cast-in-place concrete hollow building roof
CN201649459U (en) Slope roof cast-in-place concrete structure
CN103615110B (en) Random oblique netted nine-squares beam Hyperbolic Roof construction method
CN101701439B (en) Steel reinforcement cage track skeleton method construction process of steel spring floating plate track
CN104372890A (en) Construction method of bare concrete prefabricated box beam with complicated structure
CN104234012B (en) A kind of concrete loose rock dam ultra-long concrete sliding formwork body and construction method thereof
CN106592426A (en) Prefabricated template system for transverse pre-stress overall width reinforced concrete bridge deck and construction method
CN105178604A (en) Construction method of assembly type superimposed floor slab
CN103758348B (en) Profile steel framework structure concrete floor slab suspension mould pouring construction method
CN102720362B (en) A kind of high accuracy steel concrete counter force wall construction technology
CN106121236B (en) Floor bar protective layer and structural elevation integrated control method
CN101967884B (en) Method for controlling concrete planeness of large-area steel bar truss template
CN102433996A (en) Method for constructing wafer board with SMC (Sheet Molding Compound) hole forming mould
CN103410269A (en) Unbonded prestress cast-in-place reinforced concrete hollow slab construction structure and method
CN105442629B (en) A kind of large scale equipment T stage vibration isolation mounts construction
CN107476567A (en) It is a kind of to control the pitched roof gradient and the construction method and track-type facilities of thickness
CN101614039B (en) Inverted construction method for template engineering of cast-in-place shear wall structure system
CN204039902U (en) Bridge precast beam plate lower support structure and levelling device
CN205955223U (en) Cast -in -place concrete floor once only pours guide tracked flattening system
CN102888809B (en) Highly-efficient leveling method for construction of large-area concrete ground floor
CN115749193A (en) Flatness and anti-cracking control construction method for super-large-area terrace
CN208220108U (en) Assembled angle steel hangs mold device
CN113833003A (en) Construction method of raft plate of oversized clean workshop
CN109291208B (en) Large-span prestressed concrete double-T-plate construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 230000 No.16 Qianshan North Road, Luyang District, Hefei City, Anhui Province

Patentee after: Zhongan Huali Construction Group Co.,Ltd.

Address before: 230022 No. 116, Wangjiang West Road, Hefei City, Anhui Province

Patentee before: ANHUI HUALI CONSTRUCTION Group Co.