CN101955100A - The parts that the parts of elevator improve planning system and elevator improve method of planning - Google Patents

The parts that the parts of elevator improve planning system and elevator improve method of planning Download PDF

Info

Publication number
CN101955100A
CN101955100A CN2010102302031A CN201010230203A CN101955100A CN 101955100 A CN101955100 A CN 101955100A CN 2010102302031 A CN2010102302031 A CN 2010102302031A CN 201010230203 A CN201010230203 A CN 201010230203A CN 101955100 A CN101955100 A CN 101955100A
Authority
CN
China
Prior art keywords
parts
information
mentioned
object parts
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010102302031A
Other languages
Chinese (zh)
Other versions
CN101955100B (en
Inventor
森本浩行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Elevator and Building Systems Corp
Original Assignee
Toshiba Elevator Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Elevator Co Ltd filed Critical Toshiba Elevator Co Ltd
Publication of CN101955100A publication Critical patent/CN101955100A/en
Application granted granted Critical
Publication of CN101955100B publication Critical patent/CN101955100B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The parts that the parts that the invention provides elevator improve planning system and elevator improve method of planning.This system possesses: various data banks, and management constitutes each parts of elevator; Information extraction portion extracts Shipping Information and repair message; Operational part is asked for the shipping table number that the object parts of same delivery destination are given in delivery; Analyzing and processing portion, based on shipping table number and fault generation information, the CCS casual clearing station number of calculating object parts, utilize a plurality of fail-safe analyses to generate fail-safe analysis information with function, the enforcement Weibull is analyzed, and the fault of calculating object parts is changed opportunity, extracts information, environment for use information, delivery test figures and makes record information based on the maintenance of object parts, understand the environment for use of object parts or make resume and analyzing failure cause, calculate fault and change replacing prediction opportunity before on opportunity; And management department, approach to change prediction during opportunity, the replacing opportunity of notify object parts in the operational situation data of the object parts of collecting at any time.

Description

The parts that the parts of elevator improve planning system and elevator improve method of planning
Technical field
The parts that the parts that the present invention relates to a kind of elevator improve planning system and elevator improve method of planning, are used for the replacing of each parts of constituting elevator is improved opportunity.
Background technology
For the elevator that is arranged in mansion etc.,, implement the maintenance inspection of elevator termly by the maintenance personnel for accident etc. is prevented trouble before it happens.At this moment, to the parts place under repair or the replacing that for example reach the life-span in each parts that constitutes elevator because of long-term use.
In recent years, as the system of the maintenance inspection that is used for elevator is known following system arranged, promptly except the customer data of the delivery destination that shows each parts, will show that also the repair message on fault opportunity etc. of the Shipping Information of time of run etc. of elevator or display unit carries out the system of data base system.In repair message, include the replacing resume that hinder the parts that wait and change for some reason.Replacing opportunity of parts is based on being included in replacing resume in this repair message etc. and be set.
In addition, Shipping Information or repair message are collected from elevator control device by maintenance personnel's input of elevator or by remote operation, and by data base system.Shipping Information behind the data base system or repair message can be confirmed on network.Thus, the related personnel who comprises the maintenance personnel can confirm the specification of the own elevator of being managed or the replacing situation of each parts etc.
In addition, in the delivery test of circuit substrate that constitutes elevator or parts,, carry out the quality judgement by the inputoutput data that utilizes the circuit substrate that tester collects or characteristic data and the predefined determinating reference value of parts are compared.
And then the preparation of parts becomes: the maker of parts is logined in advance, visit maker equipment on network, and transmit block order data also can be obtained the pattern framework of required parts.
Technology as about the replacing of each parts of constituting elevator discloses, and can be dependent on the replacing of parts running condition and can alleviate the technology (with reference to Japanese kokai publication hei 6-345348 communique) of maintenance personnel's burden.
In system in the past, Shipping Information or repair message that elevator mainteinance utilized are stored in data bank, manage.But,, can not grasp the integral status of a plurality of elevators though can confirm the state of each elevator according to the Shipping Information behind the data base system or repair message.
That is, have in hypothesis under the situation of many elevators that are arranged at each department, can not grasp the faulty condition etc. of each parts of these elevators.In addition, being arranged under the situation of many elevators as object of particular locality, can not grasp the faulty condition of these parts etc.
In addition, the replacing of each parts is set based on being included in the replacing resume in the repair message opportunity.But although diversified parts are arranged, and replacing is fixed opportunity.On the contrary, the setting of in most cases changing opportunity is subjected to the influence of maintenance personnel's experience, therefore, even also different opportunity because of identical from different places its replacing of parts of the setting of elevator sometimes.
In addition, the replacing resume that include the parts that hinder for some reason and change in the repair message behind data base system.But, under the situation of the reason of investigating fault, postpone owing to the investigation spended time makes reply.
In addition, setting based on the replacing resume of parts under the replacing situation on opportunity, the time that the part replacement of carrying out opportunity in this replacing is required or, parts cost etc. is different because of object, can not simply tackle alike.
In addition, because the setting on replacing opportunity of parts is difficult, therefore, predict that in advance fault is difficult.As a result, can expect, also might fault just take place parts before part replacement.
In addition, also exist between the used life that makes parts because of the environment for use of parts or using method are incorrect and shorten to situation.In this case, since agnogenio true, therefore, can not fundamentally improve, have to tackle by part replacement.
In addition, when in parts undesirable condition having taken place, the number needs that the parts of same undesirable condition have taken place GPRS is wanted spended time.And then, for the generation of the undesirable condition of parts,, therefore can expect owing to unclearly will guarantee to have how much to change parts better, exist and change the inadequate possibility of parts.
In addition, even do not exist in the characteristic data when parts are delivered (delivery test figures) unusually, but undesirable condition also might take place in parts after delivery.In this case, can't stop the delivery of parts, the undesirable condition that the delivery back can not be taken place is prevented trouble before it happens.
Therefore, need a kind of fault cause, the parts that the parts that correctly calculate the necessary elevator that improves content of replacing prediction opportunity before the fault and prompting improve planning system and elevator that can the analytic target parts to improve method of planning.
Summary of the invention
According to present embodiment, provide a kind of parts of elevator to improve planning system, it is characterized in that, possess: the Shipping Information storage part, storage Shipping Information, described Shipping Information include the customer identification information that is used to discern the component identification information of each parts that comprises circuit substrate that constitute elevator and represents the delivery destination of above-mentioned each parts; The repair message storage part, with the component identification information that Shipping Information comprised that is stored in the Shipping Information storage part accordingly storage package contain the repair message of the fault generation information that the fault of representing above-mentioned each parts takes place; The environment for use information storage part, the component identification information that is comprised with above-mentioned Shipping Information is the environment for use information of the running condition of above-mentioned each parts of storage representation accordingly; Delivery test figures storage part, the component identification information that is comprised with above-mentioned Shipping Information is stored the delivery test figures of above-mentioned each parts accordingly; Make the record information storage part, the component identification information that is comprised with above-mentioned Shipping Information is stored the manufacturing record information of above-mentioned each parts accordingly; Information extraction portion, based on object parts data by maintenance personnel's indication, extract the Shipping Information that includes with the customer identification information of the same delivery of the corresponding expression of the component identification information destination of object parts from above-mentioned Shipping Information storage part, as the delivery information extraction, and, the repair message of the fault generation information that the fault that includes the indicated object parts from above-mentioned repair message storage part extraction takes place is as the maintenance information extraction; Operational part based on the delivery information extraction of the object parts that extracted by this information extraction portion, is obtained the shipping table number to the object parts of same delivery destination delivery; The CCS casual clearing station number of above-mentioned object parts based on above-mentioned fault generation information and by the shipping table number that this operational part is obtained, calculates in the first analyzing and processing portion; The second analyzing and processing portion utilizes a plurality of fail-safe analyses to generate fail-safe analysis information with function, and, implement the Weibull analysis, calculate the fault of above-mentioned object parts and change opportunity; The 3rd analyzing and processing portion, maintenance information extraction, environment for use information, delivery test figures and manufacturing record information based on above-mentioned object parts, understand the environment for use of these object parts or make resume, analyzing failure cause calculates above-mentioned fault and changes replacing prediction opportunity before on opportunity; And management department, during opportunity, notify the replacing opportunity of these object parts near above-mentioned replacing prediction in the operational situation data of the object parts of collecting at any time.
In addition, according to present embodiment, provide a kind of parts of elevator to improve method of planning, the parts of this elevator improve method of planning to be carried out by computer system, this computer system possesses: the Shipping Information storage part, storage Shipping Information, described Shipping Information include the customer identification information that is used to discern the component identification information of each parts that comprises circuit substrate that constitute elevator and represents the delivery destination of above-mentioned each parts; The repair message storage part, with the component identification information that Shipping Information contained that is stored in this Shipping Information storage part accordingly storage package contain the repair message of the fault generation information that the fault of representing above-mentioned each parts takes place; The environment for use information storage part, the component identification information that is contained with above-mentioned Shipping Information is the environment for use information of the running condition of above-mentioned each parts of storage representation accordingly; Delivery test figures storage part, the component identification information that is contained with above-mentioned Shipping Information is stored the delivery test figures of above-mentioned each parts accordingly; And make the record information storage part, the component identification information that is contained with above-mentioned Shipping Information is stored the manufacturing record information of above-mentioned each parts accordingly; The parts of this elevator improve method of planning and are characterised in that, comprise: the information extraction step, based on object parts data by maintenance personnel's appointment, extract the Shipping Information that includes with the customer identification information of the same delivery of the corresponding expression of the component identification information destination of object parts from above-mentioned Shipping Information storage part, as the delivery information extraction, and, the repair message of the fault generation information that the fault that includes the indicated object parts from above-mentioned repair message storage part extraction takes place is as the maintenance information extraction; Calculation step based on the delivery information extraction of the object parts that extract, is obtained the shipping table number to the object parts of same delivery destination delivery in this information extraction step; The first analyzing and processing step based on above-mentioned fault generation information and the shipping table number obtained, is calculated the CCS casual clearing station number of above-mentioned object parts in calculation step; The second analyzing and processing step utilizes a plurality of fail-safe analyses to generate fail-safe analysis information with function, and, implement the Weibull analysis, calculate the fault of above-mentioned object parts and change opportunity; The 3rd analyzing and processing step, maintenance information extraction, environment for use information, delivery test figures and manufacturing record information based on above-mentioned object parts, understand the environment for use of these object parts or make resume, analyzing failure cause calculates above-mentioned fault and changes replacing prediction opportunity before on opportunity; And management process, approach above-mentioned replacing prediction during opportunity in the operational situation data of the object parts of collecting at any time, notify the replacing opportunity of these object parts.
Description of drawings
Fig. 1 is the block diagram that the parts of the related elevator of expression present embodiment improve the structure of planning system.
Fig. 2 is the figure of the example that is stored in the data structure of extracting the delivery information extraction in the result database in this embodiment of expression.
Fig. 3 is the figure of the example that is stored in the data structure of extracting the maintenance information extraction in the result database in this embodiment of expression.
Fig. 4 is the diagram of circuit of the flow process of the parts that are used for illustrating the elevator of this embodiment processing that improves planning system.
Fig. 5 is the figure of an example of the parts that pass through elevator of expression in this embodiment data structure of improving the fail-safe analysis information that planning system generates.
Fig. 6 is the figure based on the analysis result of unreliability function F (t) of expression in this embodiment.
Fig. 7 is the figure based on the analysis result of fault probability of occurrence density function f (t) of expression in this embodiment.
Fig. 8 is the analysis result figure based on Weibull analysis (Weibull Analysis) in this embodiment of expression.
Fig. 9 be used for illustrating this embodiment consideration the figure on replacing opportunity of object parts of risk.
Figure 10 is the figure of the example of the result who utilizes the analysis of MT method in this embodiment of expression.
Figure 11 is the figure of the example of the result who utilizes analysis software in this embodiment.
Figure 12 is the figure that expression each reason in this embodiment is given the influence that the time of run of object parts brings.
Figure 13 be expression in this embodiment at the notify object parts to the figure of an example of the display frame that shows when changing opportunity.
Figure 14 is the figure that is used for illustrating the processing of management department when collecting the image information of the object parts that obtained by sensor or surveillance camera of this embodiment.
Reference numeral
11 ... the Shipping Information data bank, 12 ... the repair message data bank, 13 ... the environment for use information database, 14 ... the risk management data bank, 15 ... the delivery experimental data base, 16 ... make the record information data bank, 17 ... parts improve plan auxiliary process portion, 17A ... information extraction portion, 17B ... female group operational part, 17C ... analyzing and processing portion, 17D ... management department, 18 ... input part, 19 ... display part, 20 ... extract result database, 20a ... the delivery information extraction, 20b ... the maintenance information extraction, 20c ... the female group information that comprises the shipping table number, 21 ... the fail-safe analysis data bank, 22 ... internal network, 231~23n ... elevator control controller, 24 ... parts are prepared system, 301~30n ... the elevator of various places, 311~31n ... measurement sensor, 321~32n~surveillance camera, 171 ... image collection portion, 172 ... the data comparing section, 173 ... abnormality juding portion.
The specific embodiment
Below, with reference to the description of drawings present embodiment.
Fig. 1 is the block diagram that the parts of the related elevator of expression present embodiment improve the structure of planning system.
The parts of the elevator of present embodiment improve planning system to be realized by the computer system that is made of CPU, ROM, RAM etc.The parts of this elevator improve planning system to be possessed Shipping Information data bank 11, repair message data bank 12, environment for use information database 13, risk pipe (riskmanagement) data bank 14, delivery experimental data base 15, manufacturing record information data bank 16, parts improvement plan auxiliary process portion 17, input part 18, display part 19, extracts result database 20 and fail-safe analysis data bank 21.
In addition, the parts at this elevator improve planning system via LAN, the network 22 of WAN etc. and the elevator 30 in various places 1Control panel that is provided with among~the 30n or elevator monitoring arrangement (below be called " elevator control use controller ") 23 1~23 nConnect, and be connected with parts preparation system 24.
Store the relevant Shipping Information of delivery in the Shipping Information data bank 11 with each parts (comprising circuit substrate) that constitute elevator.The quilt that include the component identification information that is used to discern each parts in this Shipping Information, is used to discern these parts client's (delivery destination) extremely the customer identification information etc. of delivering.
Store the relevant repair message of maintenance (maintenance) in the repair message data bank 12 with each parts that constitutes elevator.This repair message and the component identification information corresponding stored that is included in the Shipping Information.In addition, include fault generation information that the fault of the parts that expression identifies by component identification information takes place etc. in this repair message.
In the environment for use information database 13, corresponding with the component identification information in being included in the Shipping Information that is stored in the Shipping Information data bank 11, store the environment for use information of the environment for use of the parts that expression identifies by this component identification information.Include in this specification environmental information with the running in each elevator 30 1The area of~30n, equipment, parts, it is provided with relevant data of life-span of hardness, stress data, parts of the temperature and humidity in place, the number of starts of elevator (constituting each parts of elevator), the voltage and current that puts on parts, parts etc.
The hardness of temperature, humidity, parts, stress data are arranged on each elevator 30 by use 1~30 nIn measurement sensor 31 1~31 nCan collect at any time.The data of collecting are from elevator control controller 23 1..., 23 nBe sent to environment for use information database 13 via network 22.
In addition, number of starts, electric current, voltage is not via above-mentioned measurement sensor 31 1~31 nAnd by elevator control controller 23 1..., 23 nDirectly measure, and be sent to environment for use information database 13.
In addition, also can have the function of collecting data to parts self setting.For example, use under the state of the function of the various data that can collect temperature, humidity, number of starts, voltage, electric current etc. to pack in the inside of relay circuit or battery.
And then, each elevator 30 1~30 nIn be respectively arranged with surveillance camera 32 1~32 nThus, for example can collect circuit substrate or the heat distribution of parts or the image or the image of parts installation region that constitutes elevator.By this image of collecting or image, can be often monitor whether unusual condition having taken place.
In addition, according to the heat distribution or the installation site of each parts, can freely change the configuration of various sensors.Delivering letters from the data of various sensors, method is for example wired or wireless all can.When the measurement of data,, also take temporary transient power cut-off sometimes or make processing such as elevator stops according to measuring content.
In risk management data bank 14, corresponding with the component identification information that is used to discern each parts that constitutes elevator, store the required replacing production time of the replacing operation of each parts, represent the crisis management information of the lead time (lead time) of each parts.In addition, about changing production time, for example collect automatically from the data bank of changing production time management system (not shown).In addition, about the leading time, collect automatically from the data bank of producer's management system (not shown).
In addition, can at random set the opportunity that environment for use information and crisis management information are sent to environment for use information database 13 and risk management data bank 14.
In addition, each identifying information such as serial number of each parts of environment for use information and crisis management information and formation elevator is stored accordingly.
In delivery experimental data base 15, delivery test figures and component identification information when circuit substrate or parts delivery are stored accordingly.In the delivery test figures, test determinating reference Value Data etc. when including the inputoutput data of circuit substrate, the characteristic data of parts (for example if relay then is contact resistance, electrical current, rated current etc.), data relevant, delivery with the action of circuit substrate or parts.
Component manufacturer or specific Testing institute are implemented test by utilize tester testing sequence according to the rules before the parts delivery, obtain the delivery test figures.And this delivery test figures sends to parts with component identification information via network 22 and improves planning system, perhaps sends to parts with the form of testing the achievement book and improves planning system.
Improve in the planning system at parts, if receive the delivery test figures via network, the test figures of then automatically should delivering is stored in delivery experimental data base 15.In addition, receiving under the situation of delivery test figures, operating and be sent to delivery experimental data base 15 from input part 18 by the maintenance personnel in form with test achievement book.
In making record information data bank 16, constitute the circuit substrate of elevator or the manufacturing record information and the component identification information of parts and be stored accordingly.Make temperature and humidity, device information, manufacturing bulk information when including in the record information, the data that the action of manufacturing environment, Fabrication procedure, parts etc. is relevant etc. with circuit substrate and parts manufacturing.
It is the same with the delivery test figures to make record information, via network 22 or be sent to parts with the form of Books face and improve planning system, and is stored in manufacturing record information data bank 16.
Parts improvement plan auxiliary process portion 17 is made of CPU, the processing that puts rules into practice according to the analysis tool (program) that is stored in the storage medium (not shown).Be provided with information extraction portion 17A, the operational part 17B of female group (population), the 17C of analyzing and processing portion and the 17D of management department in this parts improvement plan auxiliary process portion 17.
Information extraction portion 17A from Shipping Information data bank 11 extract with by the object parts relevant project data of maintenance personnel from input part 18 appointments.At this moment, information extraction portion 17A carries out to extract and handles based on the component identification information that is included in the Shipping Information that is stored in Shipping Information data bank 11.Include customer identification information that in the Shipping Information that is stored in Shipping Information data bank 11, contains etc. in this project data.The a plurality of project datas that extract from Shipping Information data bank 11 are stored in as the delivery information extraction 20a of object parts (Fig. 2 with reference to) and extract result database 20 and managed.
In addition, information extraction portion 17A from repair message data bank 12 extract with by the object parts relevant project data of maintenance personnel from input part 18 appointments.Include fault generation information that in the repair message that is stored in repair message data bank 12, contains etc. in this project data.The a plurality of project datas that extract from repair message data bank 12 are stored in as the maintenance information extraction 20b (with reference to Fig. 3) of object parts and extract result database 20 and managed.
In addition, the extraction of Shipping Information or repair message for example also can be to carry out according to system unit, device unit, the model unit of product, the model unit of parts.
Female operational part 17B of group calculates the shipping table number to the object parts of same client (delivery destination) delivery based on the delivery information extraction 20a by the object parts that extract result database 20 management.Under the situation of the parts of substrate that is possessed same form by the equipment of the formation elevator of being delivered or same form, the numerical value that utilizes the substrate number that shipping table number and this equipment contained of this equipment or component count to multiply each other and obtain calculates the shipping table number of each parts (substrate).
And, by female operational part 17B of group calculate to the shipping table number (female number) of the object parts of same client delivery as the female information 20c of group that includes the shipping table number of object parts, be stored in and extract result database 20 and managed.Include expression among female information 20c of group as the information on client's title of delivery destination and delivery opportunity etc.
The 17C of analyzing and processing portion is if classify according to processing, and the fault that then can be divided into first 17C-1 of analyzing and processing portion, the calculating object parts of the CCS casual clearing station number of calculating object parts is changed the fault cause of second 17C-2 of analyzing and processing portion on opportunity and analytic target parts and calculated the 3rd 17C-3 of analyzing and processing portion that fault is changed the replacing prediction opportunity before opportunity.
Promptly, the 17C of analyzing and processing portion counts information based on the shipping table that is included in the fault generation information among the maintenance information extraction 20b that is stored in the object parts that extract result database 20 and be included among female information 20c of group, is calculated to the platform number (CCS casual clearing station number) that the object parts of fault have taken place till this fail-safe analysis constantly shown in this fault generation information.
At this moment, the 17C of analyzing and processing portion counts CCS casual clearing station number poor of the shipping table number of the object parts shown in the information and the object parts that aforementioned calculation goes out according to being included in shipping table among female information 20c of group, calculates the platform number of the object parts of regular event at the scene.
At this moment, the 17C of analyzing and processing portion calculates the ratio of CCS casual clearing station number with respect to the shipping table number of object parts.In addition, the 17C of analyzing and processing portion should use as censored data (censored data) according to the time of time on analyzing and processing date and running time Start Date calculating object parts regular event the time.
In addition, the 17C of analyzing and processing portion utilizes the shipping table that is included among female information 20c of group to count the CCS casual clearing station number of the shipping table number of the object parts shown in the information and the object parts that aforementioned calculation goes out, and generates fail-safe analysis information.At this moment, utilize H (t) function of etc.ing of reliability function R (t), unreliability function F (t) about the object parts, fault probability of occurrence density function f (t), accumulation dangerous function, generation fail-safe analysis information.The fail-safe analysis information of this generation is stored in fail-safe analysis data bank 21.
In addition, the 17C of analyzing and processing portion utilizes reliability function R (t) and unreliability function F (t), is applicable to Weibull danger (Weibull Hazard) paper.By implementing the Weibull analysis, determine to come the time of run of calculating object parts, fault to change opportunity based on scale parameter η and the form parameter m of the Napier's logarithm lnH (t) of the accumulation dangerous function H (t) of object parts and this accumulation dangerous function H (t).
The time of run of object parts is also different because of the environment for use of parts etc.Therefore, the 17C of analyzing and processing portion obtains environment for use information that is stored in environment for use information database 13 or the crisis management information that is stored in risk management data bank 14, to the unreliability or accumulation dangerous function H (t) the enforcement weighting of object parts.
In addition, the 17C of analyzing and processing portion obtains the delivery test figures (inputoutput data of circuit substrate, the characteristic data of parts etc.) of the object parts that are stored in delivery experimental data base 15 and is stored in the manufacturing record information (device information, manufacturing environment, Fabrication procedure etc.) of the object parts of making record information data bank 16, and analyze the causal relationship of delivering between test figures and the manufacturing record information, opportunity is predicted in the replacing of calculating object parts.Its analysis result is managed in fail-safe analysis data bank 21 as the fail-safe analysis information storage.
And then, taken place under the unusual situation in the fabrication phase or under the situation of having extracted abnormal data when testing of delivering or after delivering, the 17C of analyzing and processing portion comes the part that goes wrong is analyzed according to bulk information, manufacturing environment, the using method of object parts.And, the 17C of analyzing and processing portion with its analysis result as the fail-safe analysis information storage in fail-safe analysis data bank 21.In addition, the 17C of analyzing and processing portion prepares system 24 via 17D of management department and parts, and the improvement method efficiently that can access analysis result offers component manufacturer.
And then, the 17C of analyzing and processing portion is by the delivery information extraction 20a and the maintenance information extraction 20b of comparison other parts, grasp the shipping table number of the object parts relevant, the stockpile number of object parts that need to change with fault, via the 17D of management department parts are prepared system's 24 transmit block and prepare information such as number and quantity, the preparation of the parts that needs are changed is indicated.
The fail-safe analysis information that the 17D of management department will be stored in fail-safe analysis data bank 21 is presented on the display part 19.In addition, the 17D of management department is based on fail-safe analysis information, according to the field data of collecting at any time (field data, the data of the operational situation of the object parts of the formation elevator in the expression real-world operation), judge that the object parts are approaching opportunity near the replacing of life-span or object parts, and this situation is shown in display part 19 and is notified to the maintenance personnel.
In addition, the 17D of management department is taken into by the elevator 30 in various places 1~30 nThe surveillance camera 32 that is provided with 1~32 nThe thermal map picture of the object parts of being made a video recording or the image of parts installation region, and be shown in display part 19.Thus, error state that always can the monitored object parts.
Prepare in the system 24 at parts, prepare number to the addresses of items of mail of component manufacturer should be arranged according to each parts.Parts are prepared system 24 if prepare number and quantity from the 17D of management department receiving-member, then the addresses of items of mail transmit block of this component manufacturer are prepared number and incremental data, carry out replenishing of object parts.
Then, explain the action of this embodiment.
Fig. 4 is the diagram of circuit of the flow process of the parts that are used to the to illustrate elevator processing that improves planning system.
At first, if the maintenance personnel is via input part 18 designated analysis object parts (following is called " object parts "), then the parts information extraction portion 17A that improves plan auxiliary process portion 17 is by extracting the project data of object parts from Shipping Information data bank 11, the delivery information extraction 20a of object parts is stored in extracts result database 20 (step S1).
One example of the data structure that is stored in the delivery information extraction 20a that extracts result database 20 has been shown among Fig. 2.
In this delivery information extraction 20a, include the component identification information (component names), building name (customer identification information), project number, maintenance job number, number machine of order number (ccasual number), object parts, roughly specification, running beginning date etc.In addition, also can be that the project data that appends number of element types replaces component identification information, determines the object parts according to this number of element types.
In addition, information extraction portion 17A is according to the project data of mantenance data storehouse 12 extraction object parts, and the maintenance information extraction 20b with the object parts is stored in extraction result database 20 (step S2) thus.
Fig. 3 shows an example of the data structure that is stored in the maintenance information extraction 20b that extracts result database 20.
In this maintenance information extraction 20b, include building name (the building name N that official puts on record), order number (ccasual number), component identification information (component names), maintenance job number (number of setting), roughly specification, running beginning date, fault take place, are used a year number date, the moment, fault number take place fault, take on the CD of business quarters, fault is accepted the date etc.In addition, under the situation of the project of deleting component identification information, also can find component form, determine the object parts according to " order number ".
That is, in this maintenance information extraction 20b, include the fault generation information (for example more than any one in fault generation date, the fault generation moment, the fault number) that fault has taken place the indicated object parts.In addition, fault generation information is for example with representing fault year number by (fault take place date-running begins the date) * 24 times that calculate.
Female operational part 17B of group obtains shipping table number (female number) Ni to the object parts of same client's delivery based on the delivery information extraction 20a of the object parts of store management in extracting result database 20.And the female operational part 17B of group extracts female information 20c of group of shipping table number (female number) Ni that includes client's title, delivery opportunity, object parts, and is stored in and extracts result database 20 (step S3).
Then, the 17C of analyzing and processing portion extracts the shipping table that fault generation information that the maintenance information extraction 20b in the result database 20 contained and female information 20c of group contained and counts information based on being stored in, calculate that shipping table is counted in the middle of the shipping table number of the object parts shown in the information, the generation shown in the fault generation information platform number (CCS casual clearing station number) (step S4) of object parts of fault.
Thus, the 17C of analyzing and processing portion counts the CCS casual clearing station number of obtaining among Ni and the above-mentioned steps S4 according to the shipping table of obtaining among the above-mentioned steps S3, calculates the platform number of the object parts of regular event at the scene.That is to say, count Ni, can implement to accumulate hazard analysis, can correctly calculate fault rate according to the ratio that the CCS casual clearing station number is counted Ni with respect to shipping table by correctly grasping by delivery to the shipping table of on-the-spot object parts.
The 17C of analyzing and processing portion utilizes accumulation dangerous function H (t), reliability function R (t), unreliability function F (t) and fault probability of occurrence density function f (t) etc., carries out the generation of fail-safe analysis information and handles (step S5).
At this, the formula (1) below accumulation dangerous function H (t) utilizes is represented.
H (t)=∑ σ i/Ni ... formula (1)
In above-mentioned formula (1), Ni represents the shipping table number of the object parts that calculated by female operational part 17B of group, and σ i represents whether each object parts fault has taken place.For example, do not have at the object parts to be expressed as σ i=0 under the situation of et out of order, under the situation of the positive et out of order of object parts, be expressed as σ i=1.
Formula (2) below reliability function R (t) utilizes is represented.
R (t)=exp (H (t)) ... formula (2)
Formula (3) below unreliability function F (t) utilizes is represented.
F (t)=1-R (t) ... formula (3)
Therefore, the 17C of analyzing and processing portion carries out the Weibull analyzing and processing.That is, the 17C of analyzing and processing portion derives following formula (4) according to above-mentioned formula (2), formula (3).
LnH (t)=-ln (ln (1-F (t)) ... formula (4)
And, be applicable to have transverse axis X, on the dangerous paper of the Weibull of the system of axes of longitudinal axis Y, generate following approximant (5) and (6) by linear approximation, determine η, m.η is the parameter of decision yardstick, and m is as the form parameter of the slope of straight line (Weibull modulus).
H (t)=(t/ η) m ... formula (5)
Ln H (t)=m lnt-m ln η ... formula (6)
The 17C of analyzing and processing portion generates fail-safe analysis information (step S51) shown in Figure 5 by implementing above-mentioned analyzing and processing.
In addition, the 17C of analyzing and processing portion obtains the necessary Functional Analysis result (step S52) of the analysis result (with reference to Fig. 6) of unreliability function F (t) and the analysis result (with reference to Fig. 7) of fault probability of occurrence density function f (t) etc., and, importing by the Weibull analysis obtains Weibull analysis result (with reference to Fig. 8) (step S53), and then calculate replacing opportunity (with reference to Fig. 9) (step S54) of the object parts of having considered risk, and these results are stored in the fail-safe analysis data bank 21 manage.
Particularly Fig. 5 to Fig. 9 is described.
Fig. 5 is the data structure example that is stored in the fail-safe analysis information in the fail-safe analysis data bank 21.
In fail-safe analysis information, each object parts includes time, Ln (t) (the transverse axis value of the Weibull analysis chart of Fig. 8), σ i, dangerous values h (t), H (t), F (t) and LnH (t) etc.In addition, though illustrate, but in fail-safe analysis information, also include client's title (customer identification information), the component identification information that is used for the identifying object parts and the fault probability of occurrence density function f (t) etc. that are used for the client that the identifying object parts are sent to.
In addition.With the situation of corresponding σ i=0 of time under the object parts do not have fault, so normal operating time of indicated object parts.Fault has taken place in the object parts under the situation of σ i=1, so the fault of indicated object parts (time of origin).
Ln (t) is and this Ln Napier's logarithm of (t) corresponding time, corresponding to the transverse axis of the Weibull analysis chart of Fig. 8.LnH (t) is the Napier's logarithm of H (t), corresponding to the longitudinal axis of the Weibull analysis chart of Fig. 8.
Fig. 6 is the coordinate diagram of analysis result that is illustrated in the unreliability function F (t) of the object parts that comprise in the fail-safe analysis information.In this coordinate diagram, show and the cooresponding unreliability F of the time of run of object parts (t) according to each product (type of elevator).
Curve 31 expressions constitute the unreliability F (t) of the object parts of first elevator.Curve 32 expressions constitute the unreliability F (t) of the object parts of the second other elevator.In addition, at the unreliability F (t)=1 shown in the longitudinal axis of coordinate diagram o'clock, the thorough fault of indicated object parts.
According to this coordinate diagram, confirm passing according to the CCS casual clearing station number of the object parts of each time of run, thereby can calculate as the time of run (replacing opportunity) in life-span of the object parts that constitute first and second elevator etc. with adding up.
Fig. 7 is the coordinate diagram of analysis result that is illustrated in the fault probability of occurrence density function f (t) of the object parts that contain in the fail-safe analysis information.In this coordinate diagram, the same with the coordinate diagram of Fig. 6, show value with the cooresponding fault probability of occurrence of the time of run of object parts density function f (t) according to each product (type of elevator).
The value of the fault probability of occurrence density function f (t) of the object parts of broken line 41 expression formations first elevator.The value of the fault probability of occurrence density function f (t) of the object parts of second elevator that broken line 42 expression formations are other.
The calculating of this fault probability of occurrence density function f (t) utilizes downtime and unreliability function F (t) to carry out.For example, obtain maxim F (nT) Max (n is a positive integer) of F (t) according to each time of failure interval T, the value that fault probability of occurrence density function f (t) obtains for the maxim in the interval of the maxim from current interval before deducting, i.e. f (t)=F (nT)-F ((n-1) T).Wherein, set F (0)=0.
In addition, in the example shown in the coordinate diagram of Fig. 7, the mean down time MTBF till the object parts et out of order (Mean Time Between Failure) as aviation value be 140400 (hour).
Therefore,, confirm to constitute mean down time etc. of the object parts of first, second elevator, can calculate replacing opportunity of these object parts etc. thus according to this coordinate diagram.
Fig. 8 is illustrated in that the accumulation dangerous function H (t) to the object parts that contains in the fail-safe analysis information carries out the Weibull analysis and the figure of the analysis result that obtains.In the figure, show drawing (plot) value with the cooresponding LnH of Napier's logarithm Ln (t) (t) of the time of run of object parts.
The drawing value becomes linear approximation as above-mentioned formula (4)~formula (6) is illustrated, draw according to its slope, and the value of m is 1.6327.
Analyze by this Weibull, the lifetime data that can access with wider range is the result of object.In addition, according to the value of m, the failure mode of incipient failure type (m<1) that can the object-aware parts, chance failure type (m=1), wear out failure type (m>1).
For example, therefore the form parameter m=1.6327 of object parts shown in Figure 8, is the failure mode of wear out failure type as can be known.The form parameter m of object parts also can be stored in fail-safe analysis data bank 21.
In addition, can expect, according to the environment for use of parts promptly for example the installation site of parts, the time of starting with, change the difference of production time etc., can have influence on time of failure.Therefore, the 17C of analyzing and processing portion obtains environment for use information that is stored in environment for use information database 13 or the crisis management information that is stored in risk management data bank 14, and the value that the unreliability function F (t) that utilizes the object parts or accumulation dangerous function H (t) are calculated is weighted.
Fig. 9 implements risk management and determines the replacing figure on opportunity the value of the unreliability function F (t) of the object parts that comprise in fail-safe analysis information.
This figure is the figure that has appended risk curve 51 in the coordinate diagram of Fig. 6.Risk curve 51 expression is multiplied by the cost of the related substrate of object parts or maintenance personnel's unit price etc., the cost that replacing spent of expression and the cooresponding object parts of each time of run.
By appending such risk curve 51, compare with the coordinate diagram of Fig. 6, can remove and calculate the more suitably replacing opportunity (step S54) of object parts, can realize the optimization on the opportunity of changing.
On the replacing opportunity that the 17C of analyzing and processing portion goes out temperature, humidity, number of starts or the aforementioned calculation that contains in the specification environmental information (replacing Best Times) etc., in fail-safe analysis data bank 21, apply flexibly the seat limit data as the fail-safe analysis information storage.Judge the replacing opportunity of object parts etc. based on this limit data (fail-safe analysis information).
That is, by a series of processing of above-mentioned steps S5, can determine the object parts that constitute elevator with the year number et out of order of what degree, be fault year number.
But, even calculate year number that is out of order, this in fault year number be the data after the fault.Therefore, the analytic target parts are why to plant reason fault has taken place, if change these object parts before fault, just can elevator device not brought influence and it is turned round safely.
Therefore, the 17C of analyzing and processing portion is extracted in problematic part in environment for use or the using method according to repair message and environment for use analyzing failure cause (1).And the 17C of analyzing and processing portion is that the basis is shown in display part 19 with the improvement method with this extraction result, and feeds back to elevator setting scene (step S6).
Promptly, the 17C of analyzing and processing portion obtains maintenance information extraction 20b that is stored in the object parts that extract result database 20 and the environment for use information that is stored in the object parts of environment for use information database 13, utilize MT (Mahalanobis-Taguchi) method or analysis software etc., analyze the fault cause that brings influence to the fault of object parts.Thus, extract the fault cause of the stronger reason of degree of influence, find out the long-term improvement method that is used to realize the object parts, and should the improvement method feed back to maker as the object parts.
In addition, in the analysis of fault cause, also can use certain in MT method or the analysis software.
And then the 17C of analyzing and processing portion comes analyzing failure cause (2) (step S7) according to delivery test figures and manufacturing record information.
Promptly, the 17C of analyzing and processing portion obtains the delivery test figures (inputoutput data of circuit, the characteristic data of parts etc.) of the object parts that are stored in delivery experimental data base 15 and is stored in the manufacturing record information (device information, manufacturing environment, Fabrication procedure etc.) of the object parts of making record information data bank 16, by utilizing MT method or analysis software etc., analyze the causal relationship between delivery test figures and the manufacturing record information, and with its analysis result as the fail-safe analysis information storage in fail-safe analysis data bank 21.
At this moment, the 17C of analyzing and processing portion is if extract abnormal data when fabrication phase and delivery, then unusual object parts have taken place refusal, and, extract the causal relationship between delivery test figures and the manufacturing record information, analyze unusual reason (fault cause) takes place.For example, at fault cause is to have occurred under the situation of problem in the batch of object parts or manufacturing environment, using method, the manufacturing record information of fault cause that will become these object parts as the fail-safe analysis information storage in fail-safe analysis data bank 21, and, above-mentioned manufacturing record information is fed back to the maker of object parts, impel maker that the undesirable condition that takes place when the object parts are delivered is implemented to improve.
In addition, even be not the stage of delivery test but in the object parts, found equally in object parts delivery back under the unusual situation also be, the 17C of analyzing and processing portion extracts the causal relationship between delivery test figures and the manufacturing record information, implement to take place the analysis of unusual reason (fault cause), with its analysis result as the fail-safe analysis information storage in fail-safe analysis data bank 21, and, above-mentioned manufacturing record information is fed back to the maker of object parts, impel maker that the undesirable condition that takes place when the object parts are delivered is implemented to improve.
Like this, by analyzing failure cause, as shown in Figure 12, the 17C of analyzing and processing portion can calculate before fault and change prediction opportunity (step S8).
Figure 10 to Figure 12 is the figure that is used to illustrate the result who utilizes MT method or analysis software.
Figure 10 is the figure that expression utilizes the result's that the MT method analyzes a example.In the example of Figure 10, illustrated by the Reference data of the 17C of analyzing and processing portion making and the relation between object components A~D.These objects components A~D is the same parts that constitute different respectively elevators, is the current parts that turning round.
What on the other hand, the middle section of Figure 10 was represented is the Reference data (reference space) of being made by the 17C of analyzing and processing portion.That is to say that the MT method is according to the position of object components A~D and judges the method for each object components A~D undesirable condition separately as the distance relation between the Reference data at center.
Particularly, for example the position of object components A is in position away from Reference data.This expression with the benchmark that does not have et out of order away from, can be judged to be the generation undesirable condition the possibility height.On the other hand, the position of object parts C is in the position near Reference data.Therefore, can be judged to be among the object parts C undesirable condition does not take place, and in running normally.
Thus, the environment (environment for use) that the object parts of undesirable condition are used understand to take place or make record information etc., can analyzing failure cause (1), (2).
Figure 11 is the figure of visual example that expression utilizes the result of analysis software.2 coordinate Figure 61,62 have been shown in this Figure 11.
The distribution of time of run according to each type of the elevator that coordinate Figure 61 indicated object parts are constituted (year number) and number of starts.The distribution according to the time of run of delivery year number of coordinate Figure 62 indicated object parts.Thus, the environment that the object parts of lacking by understanding running year number are used etc. can analyzing failure cause.
Figure 12 is the analysis result based on above-mentioned Figure 11, the figure of the influence that brings according to the time of run of reason indicated object parts (year number), to satisfaction.The content of this Figure 12 is shown in display part 19, is prompted to the maintenance personnel.
Illustrated under X=2000 hour the situation of time of run according to each product (fault is changed opportunity) among Figure 12, given value that the time of run of object parts brings each reason of influence, be worth cooresponding time of run and satisfaction with this at the object parts.At this, bring the reason of influence as the time of run of giving the object parts, include till check day during, average number of starts (moon), accumulate number of starts, travel distance (monthly average), stop floor etc.
Illustrated in the example of Figure 12 during till check day for " 1947 ", average number of starts (moon) for " 38627 ", accumulation number of starts for " 2064358 ", travel distance (monthly average) for " 277.3311 ", when stopping floor and being " 2.503704 ", the time of run of object parts has reached 2000 hours the situation that sets.Under the situation of these values, satisfaction is 1.00.
In addition, the time of run of these object parts can change, and for example under the time of run of these object parts is set to 3000 hours situation, the value with cooresponding each reason of this time of run will be shown.
According to the example of this Figure 12 as can be known, the few degree of satisfaction De Minus be sharply to reduce under the situation that the accumulation cranking time reduces, and, the slope between greatly time the in the running, compare the influence that the time of run to the object parts brings with travel distance bigger.That is, we can say under the situation that the value that makes each reason changes that when the variation of satisfaction or time of run was fierce, the influence that its reason brings for the time of run of object parts was big.On the contrary, we can say under the situation that the value that makes reason changes that if the variation of this satisfaction or time of run is more slow, then the influence of bringing for the time of run of object parts of this reason is little.
In addition, investigate the influence that the time of run to the object parts brings, then can find out several reasons with considerable influence if for example increase the reason project of specification, temperature, humidity, manufacturing resume etc. roughly.
Thus, the big reason of influence can be investigated out, failure prediction opportunity (step S8) can be before fault, more correctly calculated.This failure prediction opportunity as the fail-safe analysis information storage in fail-safe analysis data bank 21.
In addition, the 17D of management department comes the field data with reference to the operational situation of expression elevator (constituting the object parts of elevator) to be stored in fail-safe analysis information in the fail-safe analysis data bank 21 or various analysis results.And data in advance arrives failure prediction during opportunity at the scene, the 17D of management department has shown arriving of pairing object parts on display part 19 situation on replacing opportunity, and the activating alarm that perhaps rings is notified the maintenance personnel (step S9).
The example of display frame 19a when Figure 13 shows the situation that the notify object parts have arrived the replacing prediction opportunity before the fault.
The map that has shown expression Service Management area on this display frame 19a.In the example of Figure 13, show the whole map of Japan.When the replacing prediction of object parts arrives opportunity, wait area (イ), (ロ) that shows as the delivery destination of these object parts with redness.
At this, if area (イ) for example, the area that the maintenance personnel clicks the conduct delivery destination that shows with redness etc., then can confirm the details of the elevator of this area.Thus, the maintenance personnel can with visual confirmation be on earth elevator which parts near replacing prediction opportunity, can promptly take replies such as part replacement.
At this moment, can confirm by other picture according to 15 pairs of situations of confirming that delivery is tested of delivery experimental data base simultaneously, can improve in the stage more early.
Figure 14 is the figure that is used to illustrate the processing example that the 17D of management department handles the image information of the object parts that are taken into by measurement sensor or surveillance camera.
The 17D of management department includes image collection portion 171, data comparing section 172, abnormality juding portion 173.
Image collection portion 171 is from being arranged at elevator measurement sensor 31 everywhere 1~31 nOr surveillance camera 32 1~32 n, by elevator control controller 23 1..., 23 n, be taken into circuit substrate or the heat distribution of parts and sensor output image 81a, the pick up camera output image 82a of A-stage of the initial stage of elevator running, and be stored in environment for use information database 13.
And then image collection portion 171 is according to (cycle) during predefined, by elevator control controller 23 1..., 23 n, from measurement sensor 31 1~31 nOr surveillance camera 32 1~32 n, be taken into the heat distribution of circuit substrate or parts and sensor output image 81b, the pick up camera output image 82b of effluxion state, and be stored in environment for use information database 13.
The 17D of management department starts data comparing section 1721 after being taken into the sensor output image 81b of effluxion state, pick up camera output image 82b.
Data comparing section 172 is read sensor output image 81a, the pick up camera output image 82a of A-stage, the sensor output image 81b and the pick up camera output image 82b of effluxion state from environment for use information database 13, be shown in the display frame 19a of display part 19, come these view data are compared.
Abnormality juding portion 173 is based on the comparative result of view data, and whether judgement time surpasses the size or the scope of predefined thermal distortion through sensor output image 81b, the pick up camera output image 82b of state.That is, monitor whether circuit substrate or parts as object unusual omen has taken place.
In addition, even the 17D of management department does not show sensor output image, pick up camera output image on the display frame 19a of display part 19, also can investigate whether there is in-to-in heat distribution variation.
According to above-described present embodiment, change opportunity at the unsettled fault of obtaining according to the fault generation information of the object parts of being delivered in same delivery destination, by utilizing environment for use information, repair message, delivery Test Information and making record information, analyze the fault cause of environment for use or using method etc., and extract the big reason of influence in the middle of the fault cause, can obtain more accurate replacing in the stage till fault replacing opportunity and predict opportunity.Thus, can be in due course and carry out part replacement, can prevent situation to change between short-term.
In addition,, can grasp high-precision replacing opportunity by carrying out risk management, and, by showing that the object parts near changing the situation on opportunity, can make the maintenance personnel grasp the situation of each elevator, can promptly tackle.
In addition, can change the preparation of parts by undesirable condition in the delivery test of prompting object parts or prompting in advance near replacing opportunity in advance.And then, can therefore, can major failure be prevented trouble before it happens in the situations such as characteristic of the stage of delivery test grasp parts by carrying out part replacement before taking place in fault.
In addition, maintenance personnel or concern that department etc. can confirm the analysis result (Fig. 6, Fig. 7) of necessary function, the result (Fig. 8) that Weibull is analyzed, the analysis result of fault cause etc.Therefore, can grasp the failure mode of each parts, in addition, taken place in existence under the situation of parts of incipient failure, though perhaps but existence is wear out failure is under the situation of time of failure parts early, the enforcement design of feedback can be improved in the stage more early.
In addition, the result who analyzes is confirmed, and the situation at scene between do not have under the situation of matching, carry out the affirmation and the correction of environment for use information or risk information, can plan more accurate replacing opportunity.
In addition, exist near changing under the situation of parts (comprising circuit substrate) on prediction opportunity, the mark by regulation on map shows the area that is provided with of the elevator that is assembled with pairing parts.By clicking this mark, can grasp detailed information, which parts that can be confirmed to be the elevator in the running can carry out the preparation of part replacement etc. near replacing prediction opportunity.
In addition, in the above-described embodiment, various analysis results is stored in fail-safe analysis data bank 21, but also can be, for example the maintenance personnel is from the affirmation indication of input part 18 input analysis results, and information and the analysis result obtained to the processing of major general by step S6 and S7 are shown in display part 19.Thus, analyze required data when insufficient being judged as, append the data that it lacks, just can more correctly calculate replacing prediction opportunity as long as set from input part 18.
In addition, elevator control controller 23 1..., 23 nFeasible will be according to the rules during from measurement sensor 32 1~32 nThe environment for use information storage of collecting still also can constitute in environment for use information database 13, for example is stored in and elevator control controller 23 1..., 23 nThe Mishap Database that bonded assembly is not shown, the collection indication according to improve plan auxiliary process portion 17 from parts obtains environment for use information from this Mishap Database, is stored in environment for use information database 13.
In addition, the invention is not restricted to above-mentioned embodiment, can in the scope that does not break away from its aim, carry out various distortion.
According to the present invention, the parts that can provide a kind of parts of elevator to improve planning system and elevator improve method of planning, fault at the object parts that utilize fail-safe analysis information to obtain is changed opportunity, the fault cause of analytic target parts, can correctly calculate the prediction opportunity changed in the stage before this fault replacing opportunity, and find out according to analysis result and to improve scheme efficiently and point out.

Claims (12)

1. the parts of an elevator improve planning system, it is characterized in that, possess:
Shipping Information storage part, storage Shipping Information, described Shipping Information include the customer identification information that is used to discern the component identification information of each parts that comprises circuit substrate that constitute elevator and represents the delivery destination of above-mentioned each parts;
The repair message storage part, with the component identification information that Shipping Information comprised that is stored in this Shipping Information storage part accordingly storage package contain the repair message of the fault generation information that the fault of representing above-mentioned each parts takes place;
The environment for use information storage part, the component identification information that is comprised with above-mentioned Shipping Information is the environment for use information of the running condition of above-mentioned each parts of storage representation accordingly;
Delivery test figures storage part, the component identification information that is comprised with above-mentioned Shipping Information is stored the delivery test figures of above-mentioned each parts accordingly;
Make the record information storage part, the component identification information that is comprised with above-mentioned Shipping Information is stored the manufacturing record information of above-mentioned each parts accordingly;
Information extraction portion, based on object parts data by maintenance personnel's appointment, from above-mentioned Shipping Information storage part, extract the Shipping Information include with the customer identification information of the same delivery of the corresponding expression of the component identification information destination of object parts, as the delivery information extraction, and, from above-mentioned repair message storage part, extract the repair message of the fault generation information of the fault generation that includes the indicated object parts, as the maintenance information extraction;
Operational part based on the delivery information extraction of the object parts that extracted by this information extraction portion, is obtained the shipping table number to the object parts of same delivery destination delivery;
The CCS casual clearing station number of above-mentioned object parts based on above-mentioned fault generation information and by the shipping table number that this operational part is obtained, calculates in the first analyzing and processing portion;
The second analyzing and processing portion utilizes a plurality of fail-safe analyses to generate fail-safe analysis information with function, and, implement the Weibull analysis, calculate the fault of above-mentioned object parts and change opportunity;
The 3rd analyzing and processing portion, maintenance information extraction, environment for use information, delivery test figures and manufacturing record information based on above-mentioned object parts, understand the environment for use of these object parts or make resume, analyzing failure cause calculates above-mentioned fault and changes replacing prediction opportunity before on opportunity; And
Management department during opportunity, notifies the replacing opportunity of these object parts near above-mentioned replacing prediction in the operational situation data of the object parts of collecting at any time.
2. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
Above-mentioned the 3rd analyzing and processing portion is based on the delivery test figures and the manufacturing record information of above-mentioned object parts, determine the fault generation part, send expression to above-mentioned management department and need the platform number of the parts changed, change the information of stockpile number of priority, each parts of prediction opportunity, part replacement
Above-mentioned management department includes the information that parts are prepared number, the preparation of the parts that indication need be changed based on the information that receives from above-mentioned the 3rd analyzing and processing portion at least to sending with internal network bonded assembly parts preparation system.
3. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
Above-mentioned the 3rd analyzing and processing portion analyzes and brings the fault cause of influence for the fault of above-mentioned object parts based on the delivery test figures and the manufacturing record information of above-mentioned object parts, and extracts the big reason of influence from fault cause,
Above-mentioned management department shows the big reason of being extracted by above-mentioned the 3rd analyzing and processing portion of influence.
4. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
Above-mentioned the 3rd analyzing and processing portion,
When in the fabrication phase of above-mentioned object parts or the test of delivering, extracting under the situation of abnormal data, analysis becomes the part of problem in the batch of above-mentioned object parts, manufacturing environment, using method, to offer maker according to the actv. improvement method that this analysis result obtains via above-mentioned management department, and
When the analysis result according to the fault cause that obtains based on the causal relationship between above-mentioned delivery test figures and the above-mentioned manufacturing record information is judged as delivery unusual after testing, will offer maker according to the actv. improvement method that this analysis result obtains via above-mentioned management department.
5. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
Possess data instrumentation collection unit, this data instrumentation collection unit instrumentation is also collected the data relevant with the life-span of above-mentioned each parts, with these collected data as above-mentioned environment for use information storage in above-mentioned environment for use information storage part,
Above-mentioned the 3rd analyzing and processing portion,
Above-mentioned environment for use information is used in replacing prediction before calculating above-mentioned fault replacing opportunity during opportunity.
6. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
The value of the unreliability function of the object parts that the above-mentioned second analyzing and processing portion is comprised above-mentioned fail-safe analysis information implements to have considered replacing production time, the component costs of object parts, the risk management of maintenance personnel's unit price, obtains the fault of above-mentioned object parts according to this risk management and changes opportunity.
7. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
Above-mentioned the 3rd analyzing and processing portion is according to the maintenance information extraction and the environment for use information of above-mentioned object parts, analyze the reason of above-mentioned object parts et out of order, be extracted in in-problem part in environment for use or the using method, based on this extraction result, obtain the improvement method on the replacing opportunity that is used to prolong above-mentioned object parts.
8. the parts of elevator as claimed in claim 7 improve planning system, it is characterized in that,
Above-mentioned the 3rd analyzing and processing portion utilizes the MT method, determines the reference space of above-mentioned object parts based on above-mentioned environment for use information, according to the distance with respect to the said reference space of the parts identical with above-mentioned object parts of other elevators, analyzes undesirable condition in advance.
9. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
Have display part, this display part shows information and the analysis result obtained by above-mentioned the 3rd analyzing and processing portion at least based on the affirmation indication of maintenance personnel's analysis result, under the situation of analyzing required data deficiencies, urges these not enough data of input.
10. the parts of elevator as claimed in claim 5 improve planning system, it is characterized in that,
Above-mentioned data instrumentation collection unit has:
Measurement sensor comes instrumentation environment for use information according to the measurement point that place, equipment, parts are set of elevator in the running; And
Elevator control controller receives and collects the environment for use information by this measurement sensor instrumentation, and does not regularly receive and collect environment for use information via above-mentioned measurement sensor ground.
11. the parts of elevator as claimed in claim 1 improve planning system, it is characterized in that,
At least be provided with 1 measurement sensor and surveillance camera that is used to monitor the installation region of the heat distribution that place, equipment, object parts are set of elevator, above-mentioned object parts, relatively information that obtains by these measurement sensors, surveillance camera and the information set when initial, what monitor above-mentioned elevator is provided with place, equipment, and whether the object parts have taken place unusually.
12. the parts of an elevator improve method of planning, carry out by computer system, this computer system possesses:
Shipping Information storage part, storage Shipping Information, described Shipping Information include the customer identification information that is used to discern the component identification information of each parts that comprises circuit substrate that constitute elevator and represents the delivery destination of above-mentioned each parts;
The repair message storage part, with the component identification information that Shipping Information contained that is stored in this Shipping Information storage part accordingly storage package contain the repair message of the fault generation information that the fault of representing above-mentioned each parts takes place;
The environment for use information storage part, the component identification information that is contained with above-mentioned Shipping Information is the environment for use information of the running condition of above-mentioned each parts of storage representation accordingly;
Delivery test figures storage part, the component identification information that is contained with above-mentioned Shipping Information is stored the delivery test figures of above-mentioned each parts accordingly; And
Make the record information storage part, the component identification information that is contained with above-mentioned Shipping Information is stored the manufacturing record information of above-mentioned each parts accordingly;
The parts of this elevator improve method of planning and are characterised in that, comprising:
The information extraction step, based on object parts data by maintenance personnel's appointment, from above-mentioned Shipping Information storage part, extract the Shipping Information include with the customer identification information of the same delivery of the corresponding expression of the component identification information destination of object parts, as the delivery information extraction, and, from above-mentioned repair message storage part, extract the repair message of the fault generation information of the fault generation that includes the indicated object parts, as the maintenance information extraction;
Calculation step based on the delivery information extraction of the object parts that extract, is obtained the shipping table number to the object parts of same delivery destination delivery in this information extraction step;
The first analyzing and processing step based on above-mentioned fault generation information and the shipping table number obtained, is calculated the CCS casual clearing station number of above-mentioned object parts in this calculation step;
The second analyzing and processing step utilizes a plurality of fail-safe analyses to generate fail-safe analysis information with function, and, implement the Weibull analysis, calculate the fault of above-mentioned object parts and change opportunity;
The 3rd analyzing and processing step, maintenance information extraction, environment for use information, delivery test figures and manufacturing record information based on above-mentioned object parts, understand the environment for use of these object parts or make resume, analyzing failure cause calculates above-mentioned fault and changes replacing prediction opportunity before on opportunity; And
Management process approaches above-mentioned replacing prediction during opportunity in the operational situation data of the object parts of collecting at any time, notifies the replacing opportunity of these object parts.
CN 201010230203 2009-07-13 2010-07-13 Elevator component improvement plan system and elevator component improvement plan method Expired - Fee Related CN101955100B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2009164995A JP5388060B2 (en) 2009-07-13 2009-07-13 Elevator parts improvement planning system and parts improvement planning method thereof
JP164995/2009 2009-07-13

Publications (2)

Publication Number Publication Date
CN101955100A true CN101955100A (en) 2011-01-26
CN101955100B CN101955100B (en) 2013-06-12

Family

ID=43482740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010230203 Expired - Fee Related CN101955100B (en) 2009-07-13 2010-07-13 Elevator component improvement plan system and elevator component improvement plan method

Country Status (2)

Country Link
JP (1) JP5388060B2 (en)
CN (1) CN101955100B (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103733214A (en) * 2011-09-26 2014-04-16 三菱重工业株式会社 Demand forecasting device, demand forecasting method, and demand forecasting program
CN105912437A (en) * 2015-02-19 2016-08-31 发那科株式会社 Failure prediction system of controller
CN106185507A (en) * 2015-03-10 2016-12-07 东芝电梯株式会社 Maintenance work auxiliary device, system and the method for elevator
CN107337045A (en) * 2017-09-04 2017-11-10 安徽爱她有果电子商务有限公司 A kind of elevator installation maintaining management system based on internet
CN107408227A (en) * 2015-06-18 2017-11-28 日立建机株式会社 The replacing part management system of engineering machinery
CN107934710A (en) * 2017-11-08 2018-04-20 广州赛意信息科技股份有限公司 A kind of system and method for generating elevator dynamic maintenance project
CN108016962A (en) * 2016-11-04 2018-05-11 东芝电梯株式会社 Maintenance and Repair schedule optimizes device
CN108205300A (en) * 2016-12-19 2018-06-26 发那科株式会社 Apparatus of repair parts managing device, apparatus of repair parts management method and computer-readable medium
CN108357997A (en) * 2018-01-04 2018-08-03 日立电梯(中国)有限公司 Life cycle detection method, device, system and elevator
CN109074524A (en) * 2016-09-29 2018-12-21 三菱电机大楼技术服务株式会社 The replacement period computing device and replacement period calculation method of component
CN109146114A (en) * 2017-06-26 2019-01-04 株式会社日立大厦系统 Part replacement prediction meanss, part replacement forecasting system and part replacement prediction technique
CN110035970A (en) * 2016-12-15 2019-07-19 三菱电机株式会社 The update plan making device of elevator
CN110040596A (en) * 2019-04-26 2019-07-23 江苏正一物联科技有限公司 Elevator accessory remote monitoring system for status and method
CN110654948A (en) * 2018-06-29 2020-01-07 哈尔滨工业大学 Method for determining safe remaining service life of elevator under maintenance-free condition
CN110654949A (en) * 2018-06-29 2020-01-07 哈尔滨工业大学 Method for determining safe remaining service life of elevator under maintenance condition
CN114408694A (en) * 2022-03-04 2022-04-29 深圳市爱丰达盛科技有限公司 Elevator fault prediction system and prediction method thereof
US11597629B2 (en) 2018-12-27 2023-03-07 Otis Elevator Company Elevator system operation adjustment based on component monitoring

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9336238B2 (en) * 2012-06-16 2016-05-10 Evrio, Inc. Mobile wireless object recognition and control
JP6033115B2 (en) * 2013-02-21 2016-11-30 三菱重工業株式会社 Maintenance work timing judgment device, maintenance work timing judgment system, maintenance work timing judgment method and program
JP6686339B2 (en) * 2014-09-30 2020-04-22 株式会社リコー System, information processing device, service determination method and program
KR101880353B1 (en) * 2016-07-22 2018-07-19 현대엘리베이터주식회사 System for prognosticating failure of elevator
JP6536755B2 (en) 2016-12-26 2019-07-03 三菱電機ビルテクノサービス株式会社 Elevator control device
CN107500068A (en) * 2017-07-11 2017-12-22 福建意昂机电股份公司 A kind of elevator management method
WO2019146041A1 (en) * 2018-01-25 2019-08-01 三菱電機株式会社 Elevator component replacement management system
JP6833152B2 (en) * 2019-02-14 2021-02-24 三菱電機株式会社 Failure support device, failure support program and failure support method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6220065U (en) * 1985-07-19 1987-02-06
JPH02215686A (en) * 1989-02-17 1990-08-28 Mitsubishi Electric Corp Door control device of elevator
JPH06345348A (en) * 1993-06-04 1994-12-20 Hitachi Building Syst Eng & Service Co Ltd Part replacement indicating system for elevator

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63306180A (en) * 1987-06-05 1988-12-14 株式会社東芝 Trouble analyzer for elevator
JPH0816914B2 (en) * 1989-04-12 1996-02-21 滋 後藤 Equipment renewal time evaluation advice device
JP3573559B2 (en) * 1996-03-04 2004-10-06 株式会社日立製作所 Maintenance support system
JP2001084021A (en) * 1999-09-17 2001-03-30 Pfu Ltd Preventative maintenance system
JP2002324143A (en) * 2001-04-25 2002-11-08 Fujitsu Ten Ltd Product management system and terminal device for the same
JP2003192248A (en) * 2001-12-25 2003-07-09 Mitsubishi Electric Corp Remote maintenance system for elevator
JP2003238041A (en) * 2002-02-14 2003-08-27 Hitachi Building Systems Co Ltd Elevator maintenance device
JP2004133553A (en) * 2002-10-08 2004-04-30 Toshiba Corp Diagnostic device for equipment
JP2004323162A (en) * 2003-04-24 2004-11-18 Hitachi Ltd Maintenance business simulator, maintenance service planning support system and maintenance business support system
JP2005339142A (en) * 2004-05-26 2005-12-08 Tokyo Electric Power Co Inc:The Facility maintenance supporting device
JP2009155043A (en) * 2007-12-26 2009-07-16 Toshiba Elevator Co Ltd Elevator component improvement schedule system and elevator component improvement schedule method
JP2009155041A (en) * 2007-12-26 2009-07-16 Toshiba Elevator Co Ltd Automatic replacement schedule system for elevator life-limited component and automatic replacement schedule method for elevator life-limited component

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6220065U (en) * 1985-07-19 1987-02-06
JPH02215686A (en) * 1989-02-17 1990-08-28 Mitsubishi Electric Corp Door control device of elevator
JPH06345348A (en) * 1993-06-04 1994-12-20 Hitachi Building Syst Eng & Service Co Ltd Part replacement indicating system for elevator

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103733214A (en) * 2011-09-26 2014-04-16 三菱重工业株式会社 Demand forecasting device, demand forecasting method, and demand forecasting program
CN105912437A (en) * 2015-02-19 2016-08-31 发那科株式会社 Failure prediction system of controller
CN105912437B (en) * 2015-02-19 2019-01-01 发那科株式会社 The failure prediction system of control device
CN106185507A (en) * 2015-03-10 2016-12-07 东芝电梯株式会社 Maintenance work auxiliary device, system and the method for elevator
CN106185507B (en) * 2015-03-10 2019-03-01 东芝电梯株式会社 Maintenance work auxiliary device, system and the method for elevator
CN107408227B (en) * 2015-06-18 2021-01-26 日立建机株式会社 Replacement management system for construction machine
CN107408227A (en) * 2015-06-18 2017-11-28 日立建机株式会社 The replacing part management system of engineering machinery
CN109074524A (en) * 2016-09-29 2018-12-21 三菱电机大楼技术服务株式会社 The replacement period computing device and replacement period calculation method of component
CN108016962A (en) * 2016-11-04 2018-05-11 东芝电梯株式会社 Maintenance and Repair schedule optimizes device
CN108016962B (en) * 2016-11-04 2019-08-30 东芝电梯株式会社 Maintenance and Repair schedule optimizes device
CN110035970A (en) * 2016-12-15 2019-07-19 三菱电机株式会社 The update plan making device of elevator
CN108205300A (en) * 2016-12-19 2018-06-26 发那科株式会社 Apparatus of repair parts managing device, apparatus of repair parts management method and computer-readable medium
CN108205300B (en) * 2016-12-19 2020-09-18 发那科株式会社 Maintenance component management device, maintenance component management method, and computer-readable medium
CN109146114A (en) * 2017-06-26 2019-01-04 株式会社日立大厦系统 Part replacement prediction meanss, part replacement forecasting system and part replacement prediction technique
CN107337045A (en) * 2017-09-04 2017-11-10 安徽爱她有果电子商务有限公司 A kind of elevator installation maintaining management system based on internet
CN107934710A (en) * 2017-11-08 2018-04-20 广州赛意信息科技股份有限公司 A kind of system and method for generating elevator dynamic maintenance project
CN108357997A (en) * 2018-01-04 2018-08-03 日立电梯(中国)有限公司 Life cycle detection method, device, system and elevator
CN110654949A (en) * 2018-06-29 2020-01-07 哈尔滨工业大学 Method for determining safe remaining service life of elevator under maintenance condition
CN110654948A (en) * 2018-06-29 2020-01-07 哈尔滨工业大学 Method for determining safe remaining service life of elevator under maintenance-free condition
CN110654948B (en) * 2018-06-29 2021-02-19 哈尔滨工业大学 Method for determining safe remaining service life of elevator under maintenance-free condition
CN110654949B (en) * 2018-06-29 2021-02-19 哈尔滨工业大学 Method for determining safe remaining service life of elevator under maintenance condition
US11597629B2 (en) 2018-12-27 2023-03-07 Otis Elevator Company Elevator system operation adjustment based on component monitoring
CN110040596A (en) * 2019-04-26 2019-07-23 江苏正一物联科技有限公司 Elevator accessory remote monitoring system for status and method
CN114408694A (en) * 2022-03-04 2022-04-29 深圳市爱丰达盛科技有限公司 Elevator fault prediction system and prediction method thereof
CN114408694B (en) * 2022-03-04 2023-06-23 深圳市爱丰达盛科技有限公司 Elevator fault prediction system and prediction method thereof

Also Published As

Publication number Publication date
CN101955100B (en) 2013-06-12
JP2011020758A (en) 2011-02-03
JP5388060B2 (en) 2014-01-15

Similar Documents

Publication Publication Date Title
CN101955100B (en) Elevator component improvement plan system and elevator component improvement plan method
CN108510221B (en) Inventory management system having functions of inventory management and preventive maintenance
US10732619B2 (en) Method for monitoring driving unit of car body assembly line, and device therefor
JP6865189B2 (en) Failure probability evaluation system and method
JP5027053B2 (en) Work analysis apparatus, production management method, and production management system
JP6152499B1 (en) Manufacturing apparatus online maintenance system and method
CN106896779B (en) Maintenance period forecasting system and maintenance period prediction meanss
US20120290497A1 (en) Failure diagnosis system, failure diagnosis device and failure diagnosis program
WO2017038749A1 (en) Degradation diagnosis device, degradation diagnosis method, and degradation diagnosis system for batteries
JP2018169161A (en) Deterioration diagnosis apparatus, deterioration diagnosis method, and deterioration diagnosis system for battery
CN104764595A (en) Remote diagnostic system
JP2009155043A (en) Elevator component improvement schedule system and elevator component improvement schedule method
CN103154904A (en) Operations management device, operations management method, and program
EP1898361A1 (en) Arrangement, method and computer program product for enhanced prognostics
US7357571B2 (en) Infrared inspection and reporting process
CN108921305A (en) A kind of component lifetime monitoring method
CN110914771B (en) Quality analysis device and quality analysis method
US20160210580A1 (en) Method of determining availability and reliability of facility equipment
US9518862B2 (en) Weighing apparatus rezero fault prediction and remote alerting
CN109598172A (en) A kind of collector sorting operation system and method based on mobile operation
US20100324700A1 (en) Facilities control device and facilities control method
CN113950697A (en) Maintenance support method, maintenance support system, maintenance support device, and computer program
JP2009155041A (en) Automatic replacement schedule system for elevator life-limited component and automatic replacement schedule method for elevator life-limited component
CN111796981A (en) Information processing apparatus, information processing method, and learning apparatus
CN108205300B (en) Maintenance component management device, maintenance component management method, and computer-readable medium

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130612

Termination date: 20150713

EXPY Termination of patent right or utility model