- Prior art keywords
- ceiling
- matrix
- production process
- cooling
- product
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Vehicle Interior And Exterior Ornaments, Soundproofing, And Insulation (AREA)
Abstract
The invention relates to a one-step forming wet production process of an automobile calash, which comprises the steps of rolling plastic on a calash PU matrix, spraying demineralized water, combining a base material, press-forming, cooling, shaping, carrying out waterjet cutting, assembling accessories, inspecting, packaging and the like. The one-step forming wet production process eliminates the step of secondarily jointing a fabric with the base material in the prior art and directly coats the fabric on the base material for one-step press-forming, thereby reducing the process steps, shortening the operation time and improving the process conditions. The produced calash can lead the sound absorption to achieve the grade 3 international leading level, greatly reduce the weight of the calash and meet the requirement on lightweight design of a whole automobile; the product has high rigidity, and can not be broken off or droop; the product is produced by adopting an automatic production line during the whole production process, thereby greatly reducing the labor intensity of workers during the production process and improving the production efficiency; and the product does not produce hazardous substances during the whole production process, thereby being environment-friendly and pollution-free.
Description
Technical field
The present invention relates to a kind of automobile ceiling one-shot forming wet process technique, specifically be used to be installed in automobile top, play the ceiling of heat insulation, sound insulation and beautification function, belong to the automotive upholstery technical field.
Background technology
Automobile ceiling generally is installed on automobile top, the effect of playing heat insulation, sound insulation and beautifying.More and more pursuing high-performance, environment-friendly type, energy-saving, lightweight, personalized epoch, the interior trim of automobile is the same with the profile of automobile, becomes the key factor that people choose automobile.Therefore also more and more higher to the requirement of automotive upholstery.
In the prior art, performance indications such as the high sound-absorbing of ceiling, low grammes per square metre, high strength become bottleneck, are restricting the development of ceiling.Existing ceiling normally adopts compound PU (polyurethane) sheet material hot-forming, and then carries out the secondary applying of lining and base material.Many, the complicated operation of this kind moulding process process, the activity duration is long, production efficiency is low, product fraction defective height.
Summary of the invention
The present invention is directed to above-mentioned the deficiencies in the prior art, a kind of automobile ceiling one-shot forming wet process technique is provided, this technological operation is simple, production efficiency height, the qualification rate height of product.
According to technical scheme provided by the invention, a kind of automobile ceiling one-shot forming wet process technique may further comprise the steps:
(1) ceiling PU matrix plastic roll: adopt the plastic roll machine on ceiling PU matrix, to carry out two-sided plastic roll, the plastic roll motor speed: 35~40 rev/mins, plastic roll machine up-down roller spacing: 0.4~0.7mm; Every spread: 70~120g/m
2
(2) spray demineralized water: on the above-mentioned ceiling PU matrix that has rolled glue, evenly spray demineralized water, soften the water yield: 15~33g/m
2
(3) substrate combination: lay overlay film nonwoven and glass fibre successively on the feeding cardboard, to roll glue, spray the ceiling PU matrix lay of demineralized water on glass fibre, on this ceiling PU matrix, cover the last layer glass fibre more then, and send in the mold cavity;
(4) compression moulding: by fabric conveying mechanism lining is transmitted in the into above-mentioned mold cavity, directly be overlying on carry out on the good substrate combination of above-mentioned steps (3) lay hot-forming, forming temperature: 110~135 ℃ of patrixes, 120~145 ℃ of counterdies; Briquetting pressure: 6.5~10.5MPa, molding time: 40~100s;
(5) cooling and shaping: molding semi product is taken out from mould, be put on the cooling tool and carry out cooling and shaping, cool time: 35~65s;
(6) water cutter cutting: the molding semi product that cooling is finished is put to water cutter cutting tool and is carried out the cutting of water cutter; Cutting air pressure: 4~7bar; Cutting hydraulic pressure: 40000~50000PSI;
(7) enclosure group is upright: water cutter cutting semi-finished product are carried out the upright work of enclosure group;
(8) check vanning.
Described lining adopts knitted composite fabric.
The present invention compared with prior art has the following advantages: the present invention has cancelled the step that lining and base material secondary are fitted in the prior art, lining directly is overlying on the last compression moulding of base material, reduce process, shortened the activity duration, improved process conditions.The ceiling that the present invention produces, sound-absorbing has reached 3 grades of international forward position levels; Ceiling weight reduces greatly, has satisfied the requirement of car load light-weight design; The rigidity height of product can not fracture, sagging; Product is taked automatic assembly line production in whole process of production, greatly reduce working strength of workers in the production process, and has improved production efficiency; The product whole process of production does not have harmful substance to produce, and is environment friendly and pollution-free.
The specific embodiment
Below in conjunction with embodiment the present invention is further described.
Embodiment 1
The GA1 of production Guangzhou Automotive Group ceiling, its specification is: L1800 * W1400mm.
The production technology of this ceiling may further comprise the steps:
(1) ceiling PU matrix plastic roll: adopt the plastic roll machine on ceiling PU matrix, to carry out two-sided plastic roll, the plastic roll motor speed: 35 rev/mins, plastic roll machine up-down roller spacing: 0.4mm; Every spread: 90g/m
2
(2) spray demineralized water: adopt the demineralized water machine at even demineralized water in the sprinkling on the above-mentioned ceiling PU matrix that has rolled glue, demineralized water electric machine frequency: 40HZ; Roller spacing: 5.2mm; The softening water yield: 15g/m
2.;
(3) substrate combination: lay overlay film nonwoven and glass fibre successively on the feeding cardboard, to roll glue, spray the ceiling PU matrix lay of demineralized water on glass fibre, on this ceiling PU matrix, cover the last layer glass fibre more then, and send in the mold cavity;
(4) compression moulding: by fabric conveying mechanism knitted composite fabric is transmitted in the into above-mentioned mold cavity, directly be overlying on carry out on the good substrate combination of above-mentioned steps (3) lay hot-forming, forming temperature: 110 ℃ of patrixes, 135 ℃ of counterdies; Briquetting pressure: 6.5MPa, molding time: 100s;
(5) cooling and shaping: upper mould manually takes out molding semi product after rising from mould, is put on the cooling tool to carry out cooling and shaping, cool time: 65s; Sight check: surfacing, no bubble, no outer damage, defective such as break;
(6) water cutter cutting: the qualified molding semi product that cooling is finished is put to water cutter cutting tool and is carried out the cutting of water cutter; Cutting air pressure: 4bar; Cutting hydraulic pressure: 40000PSI;
(7) enclosure group is upright: water cutter cutting semi-finished product are positioned over carry out the upright work of enclosure group on the upright tool of group;
(8) check vanning: the upright ceiling of finishing of enclosure group is tested, answers surfacing during check, not damaged, break, fold, base material are concavo-convex, bubble, glue mark and the unequal defective of tone; Ceiling through checking is accurately cased according to the packing technique standard, presses 12pcs/ case warehouse-in.
Embodiment 2
Production Guangzhou Honda 2HC ceiling, its specification is: L1950 * W1450mm.
The production technology of this ceiling may further comprise the steps:
(1) ceiling PU matrix plastic roll: adopt the plastic roll machine on ceiling PU matrix, to carry out two-sided plastic roll, the plastic roll motor speed: 40 rev/mins, plastic roll machine up-down roller spacing: 0.7mm; Every spread: 120g/m
2
(2) spray demineralized water: adopt the demineralized water machine at even demineralized water in the sprinkling on the above-mentioned ceiling PU matrix that has rolled glue, demineralized water electric machine frequency: 42HZ; Roller spacing: 5.4mm; The softening water yield: 30g/m
2.;
(3) substrate combination: lay overlay film nonwoven and glass fibre successively on the feeding cardboard, to roll glue, spray the ceiling PU matrix lay of demineralized water on glass fibre, on this ceiling PU matrix, cover the last layer glass fibre more then, and send in the mold cavity;
(4) compression moulding: by fabric conveying mechanism knitted composite fabric is transmitted in the into above-mentioned mold cavity, directly be overlying on carry out on the good substrate combination of above-mentioned lay hot-forming, forming temperature: 135 ℃ of patrixes, 145 ℃ of counterdies; Briquetting pressure: 7.5MPa, molding time: 80s;
(5) cooling and shaping: upper mould manually takes out molding semi product after rising from mould, is put on the cooling tool to carry out cooling and shaping, cool time: 55s; Sight check: surfacing, no bubble, no outer damage, defective such as break;
(6) water cutter cutting: the qualified molding semi product that cooling is finished is put to water cutter cutting tool and is carried out the cutting of water cutter; Cutting air pressure: 7bar; Cutting hydraulic pressure: 50000PSI;
(7) enclosure group is upright: water cutter cutting semi-finished product are positioned over carry out the upright work of enclosure group on the upright tool of group;
(8) check vanning: the upright ceiling of finishing of enclosure group is tested, answers surfacing during check, not damaged, break, fold, base material are concavo-convex, bubble, glue mark and the unequal defective of tone; Ceiling through checking is accurately cased according to the packing technique standard, presses 12pcs/ case warehouse-in.
Embodiment 3
Production Guangzhou Honda GB1 ceiling, its specification is: L1950 * W1450mm.
The production technology of this ceiling may further comprise the steps:
(1) ceiling PU matrix plastic roll: adopt the plastic roll machine on ceiling PU matrix, to carry out two-sided plastic roll, the plastic roll motor speed: 38 rev/mins, plastic roll machine up-down roller spacing: 0.6mm; Every spread: 70g/m
2
(2) spray demineralized water: adopt the demineralized water machine at even demineralized water in the sprinkling on the above-mentioned ceiling PU matrix that has rolled glue, demineralized water electric machine frequency: 44HZ; Roller spacing: 5.3mm; The softening water yield: 33g/m
2.;
(3) substrate combination: lay overlay film nonwoven and glass fibre successively on the feeding cardboard, to roll glue, spray the ceiling PU matrix lay of demineralized water on glass fibre, on this ceiling PU matrix, cover the last layer glass fibre more then, and send in the mold cavity;
(4) compression moulding: by fabric conveying mechanism knitted composite fabric is transmitted in the into above-mentioned mold cavity, directly be overlying on carry out on the good substrate combination of above-mentioned lay hot-forming, forming temperature: 120 ℃ of patrixes, 120 ℃ of counterdies; Briquetting pressure: 10.5MPa, molding time: 40s;
(5) cooling and shaping: upper mould manually takes out molding semi product after rising from mould, is put on the cooling tool to carry out cooling and shaping, cool time: 35s; Sight check: surfacing, no bubble, no outer damage, defective such as break;
(6) water cutter cutting: the qualified molding semi product that cooling is finished is put to water cutter cutting tool and is carried out the cutting of water cutter; Cutting air pressure: 5bar; Cutting hydraulic pressure: 45000PSI;
(7) enclosure group is upright: water cutter cutting semi-finished product are positioned over carry out the upright work of enclosure group on the upright tool of group;
(8) check vanning: the upright ceiling of finishing of enclosure group is tested, answers surfacing during check, not damaged, break, fold, base material are concavo-convex, bubble, glue mark and the unequal defective of tone; Ceiling through checking is accurately cased according to the packing technique standard, presses 12pcs/ case warehouse-in.
The equipment and the material that adopt among the present invention are the commercially available prod.
Claims (2)
1. an automobile ceiling one-shot forming wet process technique is characterized in that, may further comprise the steps:
(1) ceiling PU matrix plastic roll: adopt the plastic roll machine on ceiling PU matrix, to carry out two-sided plastic roll, the plastic roll motor speed: 35~40 rev/mins, plastic roll machine up-down roller spacing: 0.4~0.7mm; Every spread: 70~120g/m
2
(2) spray demineralized water: on the above-mentioned ceiling PU matrix that has rolled glue, evenly spray demineralized water, soften the water yield: 15~33g/m
2.;
(3) substrate combination: lay overlay film nonwoven and glass fibre successively on the feeding cardboard, to roll glue, spray the ceiling PU matrix lay of demineralized water on glass fibre, on this ceiling PU matrix, cover the last layer glass fibre more then, and send in the mold cavity;
(4) compression moulding: by fabric conveying mechanism lining is transmitted in the into above-mentioned mold cavity, directly be overlying on carry out on the good substrate combination of above-mentioned lay hot-forming, forming temperature: 110~135 ℃ of patrixes, 120~145 ℃ of counterdies; Briquetting pressure: 6.5~10.5MPa, molding time: 40~100s;
(5) cooling and shaping: molding semi product is taken out from mould, be put on the cooling tool and carry out cooling and shaping, cool time: 35~65s;
(6) water cutter cutting: the molding semi product that cooling is finished is put to water cutter cutting tool and is carried out the cutting of water cutter; Cutting air pressure: 4~7bar; Cutting hydraulic pressure: 40000~50000PSI;
(7) enclosure group is upright: water cutter cutting semi-finished product are carried out the upright work of enclosure group;
(8) check vanning.
2. a kind of automobile ceiling one-shot forming wet process technique according to claim 1 is characterized in that: described lining adopts knitted composite fabric.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102536091A CN101947829A (en) | 2010-08-09 | 2010-08-09 | One-step forming wet production process of automobile calash |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102536091A CN101947829A (en) | 2010-08-09 | 2010-08-09 | One-step forming wet production process of automobile calash |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101947829A true CN101947829A (en) | 2011-01-19 |
Family
ID=43451514
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010102536091A Pending CN101947829A (en) | 2010-08-09 | 2010-08-09 | One-step forming wet production process of automobile calash |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101947829A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102303445A (en) * | 2011-07-04 | 2012-01-04 | 宁波市阳光汽车配件有限公司 | One-time automatic forming stream line and process for polyurethane (PU) composite material and formed piece thereof |
CN102442046A (en) * | 2011-09-10 | 2012-05-09 | 无锡吉兴汽车声学部件科技有限公司 | Production process for cutting and edge wrapping of once-formed skylight of automobile roof |
CN103303371A (en) * | 2013-06-13 | 2013-09-18 | 东莞市悠派户外用品制造有限公司 | Producing technology of vehicle canopy |
CN103434251A (en) * | 2013-08-09 | 2013-12-11 | 无锡吉兴汽车声学部件科技有限公司 | One-step forming process for roof by wet method |
CN103660498A (en) * | 2013-12-24 | 2014-03-26 | 芜湖正海汽车内饰件有限公司 | Production method and production dedicated tool for non-woven fabric skylight ceiling |
CN104029458A (en) * | 2014-06-18 | 2014-09-10 | 无锡吉兴汽车声学部件科技有限公司 | Production process for automobile roof laminated with low-VOC (volatile organic compound) non-woven fabric |
WO2016091146A1 (en) * | 2014-12-08 | 2016-06-16 | 中广核工程有限公司 | Method, apparatus and system for measuring hydrogen concentration in containment vessel of nuclear power station |
CN106003249A (en) * | 2016-05-19 | 2016-10-12 | 江苏新昌汽车部件有限公司 | Process for hot-melting perforation in automobile rear wall decorative board via air cylinders |
CN106184043A (en) * | 2016-07-04 | 2016-12-07 | 无锡吉兴汽车部件有限公司 | A kind of ultrasound riveting skylight frame and the automobile ceiling production method of mushroom hasp |
CN107757049A (en) * | 2017-10-23 | 2018-03-06 | 无锡吉兴汽车声学部件科技有限公司 | A kind of production method of automobile ceiling |
CN107916578A (en) * | 2017-11-30 | 2018-04-17 | 清远市齐力合成革有限公司 | A kind of production method of the two-sided Synthetic Leather of cashmere sense |
CN110356055A (en) * | 2019-06-20 | 2019-10-22 | 重庆敏特汽车零部件有限公司 | A kind of automobile knitting dry goods ceiling and its manufacturing process |
WO2024036842A1 (en) * | 2022-08-19 | 2024-02-22 | 无锡吉兴汽车声学部件科技有限公司 | Method for bonding microfiber fabric on roof |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101337526A (en) * | 2008-06-23 | 2009-01-07 | 刘明春 | Wet process technique of PU flexible foam top-liner |
CN101337434A (en) * | 2008-06-23 | 2009-01-07 | 刘明春 | Production method of automobile skylight sun-shield |
-
2010
- 2010-08-09 CN CN2010102536091A patent/CN101947829A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101337526A (en) * | 2008-06-23 | 2009-01-07 | 刘明春 | Wet process technique of PU flexible foam top-liner |
CN101337434A (en) * | 2008-06-23 | 2009-01-07 | 刘明春 | Production method of automobile skylight sun-shield |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102303445A (en) * | 2011-07-04 | 2012-01-04 | 宁波市阳光汽车配件有限公司 | One-time automatic forming stream line and process for polyurethane (PU) composite material and formed piece thereof |
CN102442046A (en) * | 2011-09-10 | 2012-05-09 | 无锡吉兴汽车声学部件科技有限公司 | Production process for cutting and edge wrapping of once-formed skylight of automobile roof |
CN102442046B (en) * | 2011-09-10 | 2014-10-08 | 无锡吉兴汽车声学部件科技有限公司 | Production process for cutting and edge wrapping of once-formed skylight of automobile roof |
CN103303371A (en) * | 2013-06-13 | 2013-09-18 | 东莞市悠派户外用品制造有限公司 | Producing technology of vehicle canopy |
CN103434251A (en) * | 2013-08-09 | 2013-12-11 | 无锡吉兴汽车声学部件科技有限公司 | One-step forming process for roof by wet method |
CN103660498A (en) * | 2013-12-24 | 2014-03-26 | 芜湖正海汽车内饰件有限公司 | Production method and production dedicated tool for non-woven fabric skylight ceiling |
CN103660498B (en) * | 2013-12-24 | 2015-10-21 | 芜湖正海汽车内饰件有限公司 | The production method of non-woven fabrics clearstory ceiling and production special tooling thereof |
CN104029458A (en) * | 2014-06-18 | 2014-09-10 | 无锡吉兴汽车声学部件科技有限公司 | Production process for automobile roof laminated with low-VOC (volatile organic compound) non-woven fabric |
WO2016091146A1 (en) * | 2014-12-08 | 2016-06-16 | 中广核工程有限公司 | Method, apparatus and system for measuring hydrogen concentration in containment vessel of nuclear power station |
CN106003249A (en) * | 2016-05-19 | 2016-10-12 | 江苏新昌汽车部件有限公司 | Process for hot-melting perforation in automobile rear wall decorative board via air cylinders |
CN106184043A (en) * | 2016-07-04 | 2016-12-07 | 无锡吉兴汽车部件有限公司 | A kind of ultrasound riveting skylight frame and the automobile ceiling production method of mushroom hasp |
CN107757049A (en) * | 2017-10-23 | 2018-03-06 | 无锡吉兴汽车声学部件科技有限公司 | A kind of production method of automobile ceiling |
CN107916578A (en) * | 2017-11-30 | 2018-04-17 | 清远市齐力合成革有限公司 | A kind of production method of the two-sided Synthetic Leather of cashmere sense |
CN107916578B (en) * | 2017-11-30 | 2020-05-05 | 清远市齐力合成革有限公司 | Method for manufacturing cashmere-feeling double-sided polyurethane synthetic leather |
CN110356055A (en) * | 2019-06-20 | 2019-10-22 | 重庆敏特汽车零部件有限公司 | A kind of automobile knitting dry goods ceiling and its manufacturing process |
WO2024036842A1 (en) * | 2022-08-19 | 2024-02-22 | 无锡吉兴汽车声学部件科技有限公司 | Method for bonding microfiber fabric on roof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101947829A (en) | One-step forming wet production process of automobile calash | |
CN101332791B (en) | Production method of vehicle top using wet treatment | |
CN101654080B (en) | Method for producing decorating part of car trunk lid | |
CN101337434B (en) | Production method of automobile skylight sun-shield | |
CN103707592B (en) | A kind of car engine compartment insulation mat and preparation method | |
CN102442046B (en) | Production process for cutting and edge wrapping of once-formed skylight of automobile roof | |
CN101654059A (en) | Method for producing roof sun visor of automobile | |
CN101954774B (en) | Productive technology of automobile rear shelf | |
CN104002879B (en) | Cover plate of spare tire of automobile and processing technique, process equipment | |
CN102673486A (en) | Method for producing automotive rear shelf by using fiberglass reinforcing honeycomb paper core as base materials | |
CN101332839A (en) | Production method of vehicle back-shelf board | |
CN104228298A (en) | Production method of automobile engine bottom protecting plate | |
CN107571578A (en) | A kind of preparation method of automotive upholstery composite sound-absorbing material | |
CN102416715A (en) | Production method of automobile skylight slide plate made of paper honeycomb-shape core material | |
CN100475528C (en) | Automobile ceiling producing process | |
CN102310613A (en) | Method for producing front wall sound insulation pad of automobile driving cabin | |
CN102107681A (en) | Method for producing fender of vehicle | |
CN103318103A (en) | Automobile roof decorating plate production method | |
CN103331581B (en) | The production method of vehicle engine hatch cover assembly | |
CN101659242B (en) | Method for producing reconstituted cotton type ceiling by high-temperature steam | |
CN109610090A (en) | The production method of sound insulating pad under a kind of blanket car carpeting | |
CN102896865A (en) | Method for producing automotive carpet with ethylene-vinyl acetate (EVA) layer | |
CN104191939A (en) | Automobile sunroof sun shield production method | |
CN109605902A (en) | A kind of processing method of automobile front wall auxiliary noise pad | |
CN102001318B (en) | Method for manufacturing automobile headliner by using natural fiber material as main material |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20110119 |