CN101864754B - 用于溢洪道或泄洪洞出口的挑流斜鼻坎 - Google Patents
用于溢洪道或泄洪洞出口的挑流斜鼻坎 Download PDFInfo
- Publication number
- CN101864754B CN101864754B CN2010101973221A CN201010197322A CN101864754B CN 101864754 B CN101864754 B CN 101864754B CN 2010101973221 A CN2010101973221 A CN 2010101973221A CN 201010197322 A CN201010197322 A CN 201010197322A CN 101864754 B CN101864754 B CN 101864754B
- Authority
- CN
- China
- Prior art keywords
- side wall
- flood
- wall
- discharge hole
- spillway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
一种用于溢洪道或泄洪洞出口的挑流斜鼻坎,由第一侧边墙、第二侧边墙和所述两侧边墙之间的底板构成;所述底板为变横坡比的扭曲面,所述第一侧边墙为直边墙,所述第二侧边墙由直墙段及与直墙段相切的圆弧段组成;第一侧边墙与第二侧边墙的相对位置:第一侧边墙的起始端端部与第二侧边墙直墙段的端部平齐,且第一侧边墙与第二侧边墙直墙段之间相隔一距离平行安装;使用时,第一侧边墙的起始端和第二侧边墙的直墙段端为水流的入口,第二侧边墙的圆弧段端部与第一侧边墙末端端部的连线为水流出口边缘线。此种挑流斜鼻坎形成的挑流水舌落点范围处于河槽中心,在配合下游消力池消能的情况下,其消能率可达80%以上。
Description
技术领域
本发明属于水利水电工程中使用的泄洪消能设施,特别涉及一种用于溢洪道或泄洪洞出口的挑流斜鼻坎。
背景技术
在水利水电工程中,泄洪消能是非常关键的技术问题。对大量实际工程资料的统计分析显示,泄洪消能设施的造价约占工程总造价的40%~50%,因此,选择合适的泄洪消能设施对优化枢纽布置、节约投资具有重要意义。
从自溢洪道或者泄洪洞流出的水流能量较大,因此需在自溢洪道或者泄洪洞出口设置消能设施,减轻水流对河道的冲刷。溢洪道或泄洪洞出口的消能设施,一般选择挑流消能方式,现有的挑流鼻坎以连续坎、差动坎、窄缝坎、高低坎、扩散坎、斜切坎、扭曲坎、舌型坎等挑坎体型应用最为广泛,但是对于溢洪道或者泄洪洞出口河道转向较大的工程,由于受地形地质条件和下游河道的限制,现有的挑流鼻坎无法满足消能防冲的要求,难以避免水流对出口河道左右岸的冲刷破坏。
发明内容
本发明的目的是提供一种适用于溢洪道或泄洪洞出口河道转向较大的特殊地形地质条件的挑流斜鼻坎,以减轻水流对出口河道和岸坡的冲刷破坏。
本发明所述用于溢洪道或泄洪洞出口的挑流斜鼻坎,由第一侧边墙、第二侧边墙和所述两侧边墙之间的底板构成;所述底板为变横坡比的扭曲面,所述第一侧边墙为直边墙,所述第二侧边墙由直墙段及与直墙段相切的圆弧段组成;第一侧边墙与第二侧边墙的相对位置:第一侧边墙的起始端端部与第二侧边墙直墙段的端部平齐,且第一侧边墙与第二侧边墙直墙段之间相隔一距离平行安装;使用时,第一侧边墙的起始端和第二侧边墙的直墙段端为水流的入口,第二侧边墙的圆弧段端部与第一侧边墙末端端部的连线为水流出口边缘线。
上述挑流斜鼻坎中,第一侧边墙的长度L1=1d~3d,所述d为第一侧边墙与第二侧边墙直墙段之间的距离,第二侧边墙圆弧段的半径r的取值以将溢洪道或泄洪洞的出口水流挑到下游河槽中心为限,在具体工程设计时,可结合水工模型确定,水流出口边缘线与溢洪道或泄洪洞轴线的夹角θ取值范围0~10°。
上述挑流斜鼻坎中,构成底板的变横坡比扭曲面由一圆柱面变形而来,其横坡比控制线为第一侧边墙的边脚线和该边脚线延长至第二侧边墙圆弧段所形成的弧线。
底板的横坡比i=(x-x0)i0/L0,式中,x为底板的任一点纵向桩号,x0为底板起始端纵向桩号,i0为底板末端的横坡比,控制i0=0.8~1.2,L0为底板的长度。
底板高程控制方程为:
z=z0+R-[R2-(x-x0)2]0.5+yi,式中,z为底板上任一点高程,x为该点的纵向桩号,y为该点的横向桩号,i为该点所在横剖面的横坡比,z0为横坡比控制线起始点高程,R为横坡比控制线半径,x0为底板起始端纵向桩号。
上述挑流斜鼻坎中,第一侧边墙与第二侧边墙直墙段之间的距离d=溢洪道或泄洪洞出口的宽度。
上述挑流斜鼻坎中,优选第二侧边墙直墙段与第一侧边墙的长度相同。
本发明所述挑流斜鼻坎设置在溢洪道或泄洪洞的出口处,第一侧边墙的起始端和第二侧边墙的直墙段端接溢洪道或泄洪洞的出口。
本发明具有以下有益效果:
1、在溢洪道或泄洪洞的出口处设置了本发明所述挑流斜鼻坎,可将进入该挑流斜鼻坎的水流形成窄而厚的水舌挑向空中,挑流水舌在空中继续向上、下扩散,纵向拉开,而横向扩散很小,落点范围处于河道的河槽中心,因而有效解决了出口河道转向较大的特殊地形地质条件下,来自溢洪道或泄洪洞的水流对出口河道左右岸的冲刷破坏,从而减少对河床和岸坡的保护措施,节约工程投资。
2、本发明所述挑流斜鼻坎,消能效果明显,在配合下游消力池消能的情况下,消能率可达80%以上,在下游河道中形成的冲坑较浅。
3、本发明所述挑流斜鼻坎,结构简单,易于制作,检修方便。
附图说明
图1是本发明所述用于溢洪道或泄洪洞出口的挑流斜鼻坎的形状构造示意图;
图2是图1的侧视图;
图3是图1的俯视图;
图4是图3的A-A剖视放大图;
图5是图3的B-B剖视放大图;
图6是图3的C-C剖视放大图;
图7是图3的D-D剖视放大图;
图8是本发明所述挑流斜鼻坎用于泄洪洞的一种安装布局图。
图中,1-底板、2-第一侧边墙、3-第二侧边墙直墙段、4-第二侧边墙圆弧段、5-水流出口边缘线、6-构成底板的变横坡比扭曲面的横坡比控制线、7-泄洪洞、8-泄洪洞边墙、9-河道边岸、10-河槽、11-挑流水舌落点范围。
具体实施方式
下面结合附图对本发明所述用于溢洪道或泄洪洞出口的挑流斜鼻坎的形状和构造作进一步说明。
本实施例中,挑流斜鼻坎应用的具体工程的泄洪洞轴线与河道中心线夹角大约为45°,挑坎出口位置的地质条件较为复杂,挑坎右岸地质条件较好,大部分为基岩,挑坎左岸为覆盖层堆积体,而且有一条公路从上经过,如果采用常规挑坎,水流将直冲左岸,影响岸坡稳定,因此需要设计合理的挑坎体型,使水流落点处于河道中心偏右岸,并且要减轻对河道和岸坡的冲刷。
本实施例中,挑流斜鼻坎的形状和构造如图1、图2、图3、图4、图5、图6、图7所示,由第一侧边墙2、第二侧边墙和所述两侧边墙之间的底板1构成;所述底板1为变横坡比的扭曲面,该扭曲面由一圆柱面变形而来,其横坡比控制线6为弧线,如图4所示,所述第一侧边墙2为矩形直边墙,所述第二侧边墙由直墙段3及与直墙段相切的圆弧段4组成,其直墙段3与第一侧边墙2的长度L1相同;第一侧边墙与第二侧边墙的相对位置:第一侧边墙2的起始端端部与第二侧边墙直墙段3的端部平齐,且第一侧边墙2与第二侧边墙直墙段之间相隔距离d平行安装。
本实施例中的挑流斜鼻坎与泄洪洞7配套使用,其与泄洪洞的安装布局见图8,从图8可以看出,所述挑流斜鼻坎设置在泄洪洞7的出口处,第一侧边墙2的起始端端部和第二侧边墙的直墙段3的端部接泄洪洞7的出口,第二侧边墙的圆弧段4端部与第一侧边墙2末端端部的连线为水流出口边缘线5。
本实施例所述挑流斜鼻坎采用钢筋混凝土制作,各相关尺寸如下:
第一侧边墙2的长度L1=10m,第二侧边墙圆弧段4的半径r=20m,水流出口边缘线5与泄洪洞轴线的夹角θ=5.5°,第一侧边墙2与第二侧边墙直墙段3之间的距离d=7.1m;底板的长度(也是本实施例中的挑流斜鼻坎的总长)L0=26.5m,底板横坡比i从水流进口至出口由0逐渐增大到1,即底板末端横坡比i0=1,底板横坡比控制线的半径R=150m。
模型试验表明,本实施例所述挑流斜鼻坎改变了进入该挑流斜鼻坎内的水流方向,形成的挑流水舌归槽效果理想,落点范围处于河道的河槽中心,在配合下游消力池消能的情况下,消能率可达80%以上,在下游河道中形成的冲坑较浅,达到了设计要求,适合泄洪洞出口河道转向较大的特殊地形地质条件下使用。
Claims (5)
1.一种用于溢洪道或泄洪洞出口的挑流斜鼻坎,由第一侧边墙(2)、第二侧边墙和所述两侧边墙之间的底板(1)构成,其特征在于所述底板(1)为变横坡比的扭曲面,所述第一侧边墙(2)为直边墙,所述第二侧边墙由直墙段(3)及与直墙段相切的圆弧段(4)组成,
第一侧边墙(2)的起始端端部与第二侧边墙直墙段(3)的端部平齐,且第一侧边墙(2)与第二侧边墙直墙段之间相隔一距离平行安装,第一侧边墙的起始端和第二侧边墙的直墙段端为水流的入口,第二侧边墙的圆弧段(4)端部与第一侧边墙(2)末端端部的连线为水流出口边缘线(5),
第一侧边墙的长度L1=1d~3d,所述d为第一侧边墙(2)与第二侧边墙直墙段(3)之间的距离,第二侧边墙圆弧段(4)的半径r的取值以将溢洪道或泄洪洞的出口水流挑到下游河槽中心为限,水流出口边缘线(5)与溢洪道或泄洪洞轴线的夹角θ取值范围0~10°。
2.根据权利要求1所述的用于溢洪道或泄洪洞出口的挑流斜鼻坎,其特征在于所述底板(1)的横坡比i=(x-x0)i0/L0,式中,x为底板的任一点纵向桩号,x0为底板起始端纵向桩号,i0为底板末端的横坡比,控制i0=0.8~1.2,L0为底板的长度。
3.根据权利要求1或2所述的用于溢洪道或泄洪洞出口的挑流斜鼻坎,其特征在于第一侧边墙(2)与第二侧边墙直墙段之间的距离d=溢洪道或泄洪洞出口的宽度。
4.根据权利要求1或2所述的用于溢洪道或泄洪洞出口的挑流斜鼻坎,其特征在于第二侧边墙直墙段(3)与第一侧边墙(2)的长度相同。
5.根据权利要求3所述的用于溢洪道或泄洪洞出口的挑流斜鼻坎,其特征在于第二侧边墙直墙段(3)与第一侧边墙(2)的长度相同。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101973221A CN101864754B (zh) | 2010-06-11 | 2010-06-11 | 用于溢洪道或泄洪洞出口的挑流斜鼻坎 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101973221A CN101864754B (zh) | 2010-06-11 | 2010-06-11 | 用于溢洪道或泄洪洞出口的挑流斜鼻坎 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101864754A CN101864754A (zh) | 2010-10-20 |
CN101864754B true CN101864754B (zh) | 2012-07-04 |
Family
ID=42956666
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010101973221A Expired - Fee Related CN101864754B (zh) | 2010-06-11 | 2010-06-11 | 用于溢洪道或泄洪洞出口的挑流斜鼻坎 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101864754B (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104652380B (zh) * | 2015-01-22 | 2016-09-28 | 河海大学 | 一种基于变坡度溢洪道的配套泄洪系统 |
CN104775393B (zh) * | 2015-02-13 | 2017-03-01 | 水利部交通运输部国家能源局南京水利科学研究院 | 一种异型反台阶整流消能方法及消力池 |
CN105369783A (zh) * | 2015-10-01 | 2016-03-02 | 中国水利水电科学研究院 | 一种挑流鼻坎 |
CN106498909B (zh) * | 2016-10-08 | 2018-12-21 | 四川大学 | 用于岸边溢洪道或泄洪洞出口的挑流鼻坎 |
CN107513985B (zh) * | 2017-08-10 | 2019-08-20 | 四川大学 | 一种尾部边墙后撤式挑流鼻坎 |
CN109750640A (zh) * | 2019-01-15 | 2019-05-14 | 中国电建集团北京勘测设计研究院有限公司 | 窄河谷岸边泄水建筑物出口消能结构 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1262000A1 (ru) * | 1984-12-21 | 1986-10-07 | Всесоюзный Государственный Ордена Трудового Красного Знамени Головной Проектно-Изыскательский И Научно-Исследовательский Институт По Переброске И Распределению Вод Северных И Сибирских Рек Им.Е.Е.Алексеевского "Союзгипроводхоз" | Устройство дл гашени энергии потока водосбросного сооружени |
CN2915940Y (zh) * | 2006-06-12 | 2007-06-27 | 河海大学 | 曲线型掺气坎 |
CN201459691U (zh) * | 2009-07-12 | 2010-05-12 | 吉林市水利水电勘测设计研究院 | 具有扭曲面底板的溢洪道 |
-
2010
- 2010-06-11 CN CN2010101973221A patent/CN101864754B/zh not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1262000A1 (ru) * | 1984-12-21 | 1986-10-07 | Всесоюзный Государственный Ордена Трудового Красного Знамени Головной Проектно-Изыскательский И Научно-Исследовательский Институт По Переброске И Распределению Вод Северных И Сибирских Рек Им.Е.Е.Алексеевского "Союзгипроводхоз" | Устройство дл гашени энергии потока водосбросного сооружени |
CN2915940Y (zh) * | 2006-06-12 | 2007-06-27 | 河海大学 | 曲线型掺气坎 |
CN201459691U (zh) * | 2009-07-12 | 2010-05-12 | 吉林市水利水电勘测设计研究院 | 具有扭曲面底板的溢洪道 |
Non-Patent Citations (2)
Title |
---|
程子兵等.构皮滩水电站泄洪消能试验研究.《人民长江》.2006,第37卷(第3期), * |
靳大雪.曲线型挑流鼻坎的水力特性研究.《大连理工大学硕士学位》.2008, * |
Also Published As
Publication number | Publication date |
---|---|
CN101864754A (zh) | 2010-10-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101864754B (zh) | 用于溢洪道或泄洪洞出口的挑流斜鼻坎 | |
CN106120673B (zh) | 适用于高弗劳德数下的转弯溢洪道 | |
CN101761057A (zh) | 一种水电工程泄洪消能工 | |
CN103498451B (zh) | 碰撞式组合底流消能工结构 | |
CN107022987A (zh) | 高坝溢流面射流控制结构 | |
CN205088648U (zh) | 高速水流泄洪用防空蚀泄洪洞 | |
CN210002360U (zh) | 一种高山峡谷筑坝泄洪结构 | |
CN202530433U (zh) | 水利水电工程泄洪消能系统中的宽尾墩结构 | |
CN106498909B (zh) | 用于岸边溢洪道或泄洪洞出口的挑流鼻坎 | |
CN103938592B (zh) | 在拦沙坎上开设分流孔进行截流分流的方法 | |
CN101538840A (zh) | 消力池内的挑流消能工 | |
CN202626947U (zh) | 溢流坝的挑流式宽尾墩 | |
CN101126232A (zh) | 拱坝泄洪消能结构 | |
CN203594005U (zh) | 适用于狭窄河谷高拱坝堰体的泄洪消能工结构 | |
CN203741791U (zh) | 一种泄洪消能防冲设施结构 | |
CN205636681U (zh) | 放水底孔挑流鼻坎 | |
CN203429607U (zh) | 具有挑流结构的组合式高低坎消力池 | |
CN204139139U (zh) | 泄洪消力池结构 | |
CN112095554B (zh) | 适用于窄深河谷的复合式挑跌流鼻坎 | |
CN102720171A (zh) | 倒坡式阶梯消能工 | |
CN203514274U (zh) | 碰撞式组合底流消能工结构 | |
CN207143879U (zh) | 缺口分流式二道坝结构 | |
CN201198568Y (zh) | 复式沉沙渠 | |
CN108517842A (zh) | 适用于弯曲溢洪道的非对称掺气方法 | |
CN209066395U (zh) | 一种具有组合式自耗能止水结构的消力池 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120704 Termination date: 20150611 |
|
EXPY | Termination of patent right or utility model |