CN101860042B - 风电场有功功率的协调控制方法 - Google Patents

风电场有功功率的协调控制方法 Download PDF

Info

Publication number
CN101860042B
CN101860042B CN2010101724708A CN201010172470A CN101860042B CN 101860042 B CN101860042 B CN 101860042B CN 2010101724708 A CN2010101724708 A CN 2010101724708A CN 201010172470 A CN201010172470 A CN 201010172470A CN 101860042 B CN101860042 B CN 101860042B
Authority
CN
China
Prior art keywords
power
active power
refout
wind energy
energy turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2010101724708A
Other languages
English (en)
Other versions
CN101860042A (zh
Inventor
雷宪章
吕志来
陆一川
吴晓明
曹辰
薛飞
卢润东
王炯
朱颖
张聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuji Group Co Ltd
Beijing Xuji Electric Co Ltd
Original Assignee
Xuji Group Co Ltd
Beijing Xuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuji Group Co Ltd, Beijing Xuji Electric Co Ltd filed Critical Xuji Group Co Ltd
Priority to CN2010101724708A priority Critical patent/CN101860042B/zh
Publication of CN101860042A publication Critical patent/CN101860042A/zh
Application granted granted Critical
Publication of CN101860042B publication Critical patent/CN101860042B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects

Abstract

本发明涉及风电场有功功率的协调控制方法,首先求得有功功率波动超额值,并与功率超标趋势作为逻辑控制器的输入,输出超额偏差值;然后与功率频率偏差值的差值作为PI控制器的输入,最后输出风电场电机有功参考值;本发明把单一的单机最大风能利用控制方法解环嵌入了风场整体协调控制,使得风机有可调度的裕度,从而最大限度的平抑风能的不稳定给电网造成的负荷波动,这种平抑作用将释放电网更多的空间,其有效输送负荷能力将得到提高;由于有功调解运算在预测风能的基础上,风机的自我保护也从被动调桨或解列式变为主动预防式,不但有效增加风机运行效率,也对减少对电网的冲击和对风机运行也起到了积极的保护。

Description

风电场有功功率的协调控制方法
技术领域
本发明涉及风电场有功功率的协调控制方法,属于风电场并网控制技术领域。
背景技术
风电场对系统频率的影响取决于风电场短路容量比,即风电场额定容量与该风电场与电力系统的连接点的短路容量之比。当短路比较大时,风电场输出有功功率的随机波动性对电网频率的影响会比较显著。目前国内风电场的风力发电机处在一种“自由运行”状态,其控制原则是风能利用最大化,其发出的有功功率完全由天气状况决定不受人工控制,由于风能的波动性所造成的风电机组的发电功率输出的波动性也非常大。大规模风场的接入系统,特别是区域性电网,其对系统频率等产生的影响将会变得严重。
发明内容
本发明的目的是提供一种风电场有功功率的协调控制方法,来协调风电机组所发的有功功率,实现整个风电场有功功率控制。
为实现上述目的,本发明的风电场有功功率的协调控制方法步骤如下:
(1)测量得到并网点有功功率测量值Pmea,根据负荷要求设定风电场并网点有功功率设定值Pref,将有功功率测量值Pmea与有功功率设定值Pref的差值记为有功功率偏差值ΔP′;
(2)风电场并网点频率测量值fmea与给定目标频率fref进行比较,将所得差值的绝对值记为频率偏差Δf,当频率偏差Δf小于频差阈值时,频率偏差Δf计为0,则返回起点;当频率偏差Δf大于频差阈值时,进入Kd模块计算有功功率频率调整目标ΔPf,ΔPf=Δf×S,其中,S是频率对有功功率的敏感度;
(3)将有功功率偏差值ΔP′与有功功率频率调整目标ΔPf比较,数值大者记为偏差ΔP,偏差ΔP与设定死区阈值比较,偏差ΔP小于设定死区阈值时计为0,返回起点;偏差ΔP大于设定死区阈值时,则进入增量计算模块;
(4)在增量计算模块中,在给定调整时间内,先计算风电场有功功率的变化率
Figure GDA0000134510290000021
再设定调整周期Tadj,计算出调整时间内有功功率增量ΔP/Tadj,并作为PI调节模块的输入量;
(5)有功功率增量经过PI调节模块的PI调节和延时限幅模块的限幅和延时后,输出调整时间内的有功功率值Prefout,其中PI调节模块中PI调节控制器的调整幅度为β,
Figure GDA0000134510290000022
P refout = β ( Δp ( t ) + 1 T ∫ 0 T Δp ( t ) dt ) + P ref ,
Δp(t)=pmea(t)-pref(t),
pmea(t)pref(t)分别为有功功率瞬时测量值,和与有功功率瞬时测量值对应的有功功率参考值,Δp(t)为有功功率瞬时测量值与有功功率参考值的偏差值,T为微积分常数,T越大积分作用越弱;
(6)将风电场实时区域预测风功率PW1、PW2…PWn,经过求和模块后,将求和总量与风电场输出总功率Prefout比较,输出风电场输出总功率Prefout P refout = K W 1 P W 1 + K W 2 P W 2 + . . . = Σ i = 1 n K Wi P Wi , 其中n为可调区域数,K为功率区域调解分配系数,当PW1+PW2...≥Prefout时, K = K W 1 + K W 2 + . . . = P W 1 P ref + P W 2 P ref + . . . , KWi为区域调整系数, K Wi = P Wi P refout ;
当PW1+PW2+...<Pref时,Ki=1;所有风机按最大方式;
(7)将风电场输出总功率值Prefout输入功率分配模块,转换成等风功率区域的功率调整指令Prefout-1=KW1PW1、Prefout-2=KW2PW2...向所属区域发送输入功率参考值,改变其相应有功功率输出;
(8)在发出调浆指令并经过调整周期Tadj后,再次比较偏差ΔP和设定死区阈值,如果偏差ΔP小于设定死区阈值,则本次调整周期结束;如果ΔP大于设定死区阈值,则再次返回调整周期直至结果收敛。
进一步的,所述步骤(1)中有功功率偏差值ΔP′是有功功率测量值Pmea经过延时模块后与有功功率设定值Pref的差值。
进一步的,所述步骤(2)中频率对有功功率的敏感度
Figure GDA0000134510290000032
进一步的,所述步骤(7)中整个风电场输出总功率Prefout转换成等功率区域风机的输入功率参考值Prefout-i,是采用等功率机群控制方式,根据风电场中风电机组排列位置和风速状况,把风电机组划分为若干群,同一机群采用相同的控制方式。
进一步的,所述步骤(7)中当PW1+PW2+...<Prefout时,KWi=1,此时所有风机按最大方式即风桨在最大迎风面状态,运行输出总功率值Prefout=PW1+PW2+...。
对于同一等功率机群,若有n台风机,Prefout-总为该机群总的有功功率输出参考值,Prefout-i为每台风机的输入功率参考值,则风电场该机群输出功率参考值Prefout-总与每台风机的输入功率参考值Prefout-i(i=1,2,...,n)之间的转换关系为:
Figure GDA0000134510290000041
Prefout-总=PWi P refout = K W 1 P W 1 + K W 2 P W 2 + . . . = Σ i = 1 n K Wi P Wi .
风电场按实时等功率机群控制,每一个机群为一个调节系数,输出相同的功率。
本发明求得偏差ΔP,以及功率超标趋势
Figure GDA0000134510290000043
后,将调整周期内的有功功率波动超额值ΔP/T并将其作为PI的输入,并经过延时限幅模块后输出新的有功功率目标值Prefout,再与风功率预测总量值比较后,得出风电场输出总功率Prefout,并按照相应的区域调整系数,向所述区域发送输入功率参考值,改变其相应有功功率输出。本协调控制方法在控制过程中,既保证允许最多的风机运行,又实现功率自动控制的目的,综合考虑风电场各台风机的运行状况以及各种制约因素,根据调度指令自动调节风电场风机的有功输出、协调控制,形成对风机有功功率的智能协调控制。本发明把单一的单机最大风能利用控制方法解环嵌入了风场整体协调控制,使得风机具有了可调度的裕度,风机不再呈自由状态向电网输送功率,从而最大限度的平抑风能的不稳定给电网造成的负荷波动,这种平抑作用将释放电网更多的空间,其有效输送负荷能力将得到提高;同时,由于有功调解运算在预测风能的基础上,风机的自我保护也将从被动调桨或解列式变为主动预防式,不但可有效增加风机运行效率,也将对减少对电网的冲击和对风机运行也起到了积极的保护。本发明改变风电机组各自为主的闭环调节情况,从电网的角度将风电场中的各个独立机组视为一个可协调节整体的部件,调动各机组可调功能平抑风能不稳定所带来的风电场有功功率输出不稳定。
附图说明
图1是本发明有功功率协调控制系统的原理框图;
图2是本发明风电场有功功率控制逻辑框图;
图3是本发明风电场有功功率协调控制流程图。
具体实施方式
本发明的控制系统原理框图如图1所示,风电场变电站SCADA系统从调度接到负荷指令,该负荷指令由调度根据风电场长期预测(年测)并结合本时段负荷下达。调度指令一般在风电场风能预测(月测)30%-60%范围内。变电站SCADA系统将指令下发给风电场协调控制系统,风电场协调控制系统根据由风电场SCADA系统上传的风电场风能(10秒内测)适时参数,按风能裕量大小对处于不同位置(风机位置是指等风能线所圈定的范围)的风电机组分别下达调节指令。
结合图2、图3说明本发明的风电场有功功率的协调控制方法,步骤如下:
(1)测量得到并网点有功功率测量值Pmea,根据负荷要求设定风电场并网点有功功率设定值Pref,将有功功率测量值Pmea经过延时模块1后与有功功率设定值Pref的差值记为有功功率偏差值ΔP′;
(2)风电场并网点频率测量值fmea与给定目标频率fref进行比较,将所得差值的绝对值记为频率偏差Δf,当频率偏差Δf小于频差阈值时,频率偏差Δf计为0,则返回起点;当频率偏差Δf大于频差阈值时,进入Kd模块2计算有功功率频率调整目标ΔPf,ΔPf=Δf×S,其中,
Figure GDA0000134510290000051
是频率对有功功率的敏感度,与风电场所处电网位置和电网当时运行方式有关,可从电网调度常年统计数据获得;
(3)将有功功率偏差值ΔP′与有功功率频率调整目标ΔPf比较,数值大者记为偏差ΔP,偏差ΔP与设定死区阈值比较,偏差ΔP小于设定死区阈值时计为0,返回起点;偏差ΔP大于设定死区阈值时,则进入增量计算模块3;
(4)在增量计算模块3中,在给定调整时间内,先计算风电场有功功率的变化率
Figure GDA0000134510290000052
再设定调整周期Tadj,计算出调整时间内有功功率增量ΔP/Tadj,并作为PI调节模块4的输入量;
(5)有功功率增量经过PI调节模块4的PI调节和延时限幅模块5的限幅和延时后,输出调整时间内的有功功率值Prefout,其中PI调节模块4中PI调节控制器的调整幅度为β,
P refout = β ( Δp ( t ) + 1 T ∫ 0 T Δp ( t ) dt ) + P ref ,
Δp(t)=pmea(t)-pref(t),
pmea(t)和pref(t)分别为有功功率瞬时测量值,和与有功功率瞬时测量值对应的有功功率参考值,Δp(t)为有功功率瞬时测量值与有功功率参考值的偏差值,T为微积分常数,T越大积分作用越弱;
(6)将风电场实时区域预测风功率PW1、PW2…PWn,经过求和模块6后,将求和总量与有功功率值Prefout比较,输出风电场输出总功率Prefout P refout = K W 1 P W 1 + K W 2 P W 2 + . . . = Σ i = 1 n K Wi P Wi , 其中n为可调区域数,K为功率区域调解分配系数,当PW1+PW2...≥Prefout时, K = K W 1 + K W 2 + . . . = P W 1 P ref + P W 2 P ref + . . . , KWi为区域调整系数, K Wi = P Wi P refout ;
当PW1+PW2+...<Pref时,Ki=1;
(7)将风电场输出总功率值Prefout输入功率分配模块7,转换成等风功率区域的功率调整指令Prefout-1=KW1PW1、Prefout-2=KW2PW2...向所属区域发送输入功率参考值,改变其相应有功功率输出,当PW1+PW2+...<Prefout时,KWi=1,此时所有风机按最大方式即风桨在最大迎风面状态,运行输出总功率值Prefout=Pw1+PW2+...;
(8)在发出调浆指令并经过调整周期Tadj后,再次比较偏差ΔP和设定死区阈值,如果偏差ΔP小于设定死区阈值,则本次调整周期结束;如果ΔP大于设定死区阈值,则再次返回调整周期直至结果收敛。
步骤(7)中整个风电场输出总功率Prefout转换成等功率区域风机的输入功率参考值Prefout-i,是采用等功率机群控制方式,根据风电场中风电机组排列位置和风速状况,把风电机组划分为若干群,同一机群采用相同的控制方式。
风电场按实时等功率机群控制,每一个机群为一个调节系数,输出相同的功率。需参与有功功率调整的风机是处于实时等功率风能区域的风机机群,如果风电场中各台风电机组型号相同,并且处于相同的运行状态,则整个风电场的特性就与单机特性基本一致,各台机组可以采用相同的控制策略。如果风电场机组类型不一致,或风电场分布范围较广,那么各台风电机组将处于不同的运行状态。在这种情况下可以采用机群控制的方法,具体而言就是根据风电场中风电机组排列位置和风速状况,把风电机组划分为若干群,同一机群可以采用相同的控制策略。
结合风电场风机的部署情况、分群情况以及风机本省的运行工况,基本原则是同一机群可满足调节要求的,本次只在本机群内进行调节,下一轮调节周期内再按照轮流值班的原则对其他机群进行调节。
对于同一等功率机群,若有n台风机,Prefout-总为该机群总的有功功率输出参考值,Prefout-i为每台风机的输入功率参考值,则风电场该机群输出功率参考值Prefout-总与每台风机的输入功率参考值Prefout-i(i=1,2,...,n)之间的转换关系为:
Figure GDA0000134510290000071
Prefout-总=PWi P refout = K W 1 P W 1 + K W 2 P W 2 + . . . = Σ i = 1 n K Wi P Wi .

Claims (7)

1.一种风电场有功功率的协调控制方法,其特征在于,该方法包括以下步骤:
(1)测量得到并网点有功功率测量值Pmea,根据负荷要求设定风电场并网点有功功率设定值Pref,将有功功率测量值Pmea与有功功率设定值Pref的差值记为有功功率偏差值ΔP′;
(2)风电场并网点频率测量值fmea与给定目标频率fref进行比较,将所得差值的绝对值记为频率偏差Δf,当频率偏差Δf小于频率偏差阈值时,频率偏差Δf计为0,则返回起点;当频率偏差Δf大于频率偏差阈值时,进入Kd模块计算有功功率频率调整目标ΔPf,ΔPf=Δf×S,其中,S是频率对有功功率的敏感度;
(3)将有功功率偏差值ΔP′与有功功率频率调整目标ΔPf比较,数值大者记为偏差ΔP,偏差ΔP与设定死区阈值比较,偏差ΔP小于设定死区阈值时计为0,返回起点;偏差ΔP大于设定死区阈值时,则进入增量计算模块;
(4)在增量计算模块中,在给定调整时间内,先计算风电场有功功率的变化率
Figure FDA00001605962400011
再设定调整周期Tadj,计算出调整时间内有功功率增量ΔP/Tadj,并作为PI调节模块的输入量;
(5)有功功率增量经过PI调节模块的PI调节和延时限幅模块的限幅和延时后,输出调整时间内的风电场输出总功率Prefout,其中PI调节模块中PI调节控制器的调整幅度为β,
Figure FDA00001605962400012
P refout = β ( Δp ( t ) + 1 T ∫ 0 T Δp ( t ) dt ) + P ref ,
ΔP(t)=pmea(t)-pref(t),
pmea(t)和pref(t)分别为有功功率瞬时测量值,和与有功功率瞬时测量值对应的有功功率参考值,T为微积分常数,T越大积分作用越弱;
(6)将风电场实时区域预测风功率PW1、PW2…PWn,经过求和模块后,将求和总量与风电场输出总功率Prefout比较,当PW1+PW2...≥Prefout时,输出风电场输出总功率Prefout
P refout = K W 1 P W 1 + K W 2 P W 2 + . . . = Σ i = 1 n K Wi P Wi , 其中n为可调区域数,K为功率区域
调解分配系数,
K = K W 1 + K W 2 + . . . = P W 1 P ref + P W 2 P ref + . . . , KWi为区域调整系数,
Figure FDA00001605962400023
当PW1+PW2+...<Pref时,Ki=1;所有风机按最大方式;
(7)将风电场输出总功率值Prefout输入功率分配模块,转换成等功率区域的功率调整指令Prefout-1=KW1PW1、Prefout-2=KW2PW2...向所属区域发送输入功率参考值,改变其相应有功功率输出;
(8)在发出调浆指令并经过调整周期Tadj后,再次比较偏差ΔP和设定死区阈值,如果偏差ΔP小于设定死区阈值,则本次调整周期结束;如果ΔP大于设定死区阈值,则再次返回调整周期直至结果收敛。
2.根据权利要求1所述的风电场有功功率的协调控制方法,其特征在于:所述步骤(1)中有功功率偏差值ΔP′是有功功率测量值Pmea经过延时模块后与有功功率设定值Pref的差值。
3.根据权利要求1或2所述的风电场有功功率的协调控制方法,其特征在于:所述步骤(2)中频率对有功功率的敏感度
Figure FDA00001605962400024
4.根据权利要求3所述的风电场有功功率的协调控制方法,其特征在于:所述步骤(7)中整个风电场输出总功率Prefout转换成等功率区域风机的输入功率参考值Prefout-i,是采用等功率机群控制方式,根据风电场中风电机组排列位置和风速状况,把风电机组划分为若干群,同一机群采用相同的控制方式。
5.根据权利要求4所述的风电场有功功率的协调控制方法,其特征在于:所述步骤(7)中当PW1+PW2+...<Prefout时,KWi=1,此时所有风机按最大方式即风桨在最大迎风面状态,运行输出总功率值Prefout=PW1+PW2+...。
6.根据权利要求5所述的风电场有功功率的协调控制方法,其特征在于:对于同一等功率机群,若有n台风机,Prefout-总为该机群总的有功功率输出参考值,Prefout-i为每台风机的输入功率参考值,则风电场该机群总的有功功率输出参考值Prefout-总与每台风机的输入功率参考值Prefout-i之间的转换关系为:
Prefout-总=PWi P refout = K W 1 P W 1 + K W 2 P W 2 + . . . = Σ i = 1 n K Wi P Wi , 其中i=1,2,…,n。
7.根据权利要求6所述的风电场有功功率协调控制方法,其特征在于,风电场按实时等功率机群控制,每一个机群为一个调节系数,输出相同的功率。
CN2010101724708A 2010-05-14 2010-05-14 风电场有功功率的协调控制方法 Active CN101860042B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101724708A CN101860042B (zh) 2010-05-14 2010-05-14 风电场有功功率的协调控制方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101724708A CN101860042B (zh) 2010-05-14 2010-05-14 风电场有功功率的协调控制方法

Publications (2)

Publication Number Publication Date
CN101860042A CN101860042A (zh) 2010-10-13
CN101860042B true CN101860042B (zh) 2012-09-26

Family

ID=42945765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101724708A Active CN101860042B (zh) 2010-05-14 2010-05-14 风电场有功功率的协调控制方法

Country Status (1)

Country Link
CN (1) CN101860042B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3367536A4 (en) * 2016-12-26 2019-05-08 Beijing Goldwind Science & Creation Windpower Equipment Co., Ltd. METHOD AND DEVICE FOR ASSIGNING THE EFFICIENCY OF A WIND ENERGY SYSTEM

Families Citing this family (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102013699B (zh) * 2010-10-25 2013-04-17 电子科技大学 一种风力发电场有功功率分配方法
CN102003349B (zh) * 2010-11-05 2013-02-06 甘肃省电力公司 风电受限状态下的大规模风电有功优化方法
CN102003337B (zh) * 2010-11-23 2012-08-15 西北电网有限公司 风电并网后主站端风电场有功功率控制方法
KR101093003B1 (ko) * 2011-02-09 2011-12-12 전북대학교산학협력단 급격한 풍속 변화시 풍력발전단지 제어 방법 및 시스템
CN102290824B (zh) * 2011-07-29 2014-08-13 沈阳工业大学自控技术研究所 一种平抑风电机组功率波动的控制方法
CN102355008B (zh) * 2011-09-29 2013-09-25 沈阳工业大学自控技术研究所 一种平抑风电场功率波动的控制方法
CN102606395B (zh) * 2012-03-20 2013-07-31 东南大学 基于功率预测信息的风电场有功优化控制方法
CN104285059B (zh) * 2012-05-11 2017-03-01 维斯塔斯风力系统集团公司 风力发电厂频率控制
CN102709939B (zh) * 2012-05-22 2014-04-30 中国电力科学研究院 一种提高风电场发电效率的风电场有功功率控制方法
CN103151804B (zh) * 2013-03-18 2018-08-21 国家电网公司 一种计及风电主动控制能力的风电备用量确定方法
CN103268136B (zh) * 2013-05-10 2015-01-14 国电南瑞南京控制系统有限公司 光伏电站有功功率控制方法
WO2014183421A1 (zh) * 2013-05-14 2014-11-20 许继集团有限公司 一种风电场并网发电输出有功功率的控制方法
CN103306902B (zh) * 2013-05-24 2015-03-25 长沙理工大学 一种风力发电装置电力输出值的平稳输出方法
CN103441537B (zh) * 2013-06-18 2018-04-13 国家电网公司 配有储能电站的分散式风电场有功优化调控方法
CN103296698B (zh) * 2013-06-19 2015-07-15 国家电网公司 一种风电场并网发电输出有功功率的控制方法
CN103441522B (zh) * 2013-07-04 2015-08-12 贵州大学 自动调节风电场中风机有功输出的方法
CN105550489A (zh) * 2014-10-30 2016-05-04 国家电网公司 一种电力输出值的计算方法
CN106100120A (zh) * 2016-06-22 2016-11-09 青岛华创风能有限公司 基于冗余系统的风电场功率调节系统及其智能切换方法
CN107769210B (zh) * 2017-09-22 2021-03-19 华锐风电科技(集团)股份有限公司 一种基于cs算法的双馈机组调频控制方法及系统
CN109494811B (zh) * 2018-10-19 2021-11-19 国网新疆电力有限公司电力科学研究院 一种风电场机组参与调频调压的功率控制方法与系统
CN109617136B (zh) * 2018-12-29 2022-10-11 串并联(重庆)能源科技有限公司 一种调整风电场输出功率的方法
CN109638885B (zh) * 2018-12-29 2020-08-28 河北建投新能源有限公司 一种新能源功率输出控制系统
CN109698510A (zh) * 2019-01-25 2019-04-30 国网江苏省电力有限公司电力科学研究院 抑制电力系统低频振荡的控制方法
CN110460111A (zh) * 2019-09-05 2019-11-15 国电联合动力技术有限公司 基于pi控制器的风电场级能量智能控制系统及方法
CN111509770B (zh) * 2020-04-21 2022-03-25 浙江运达风电股份有限公司 一种基于多工况专家策略的智能风电场有功功率控制方法
CN112260306B (zh) * 2020-09-09 2022-08-19 许继集团有限公司 一种新能源发电站均分群控发电控制方法及装置
US11411403B2 (en) * 2020-12-14 2022-08-09 Vestas Wind Systems A/S Controlling power distribution at deadband states
CN113541201B (zh) * 2021-07-21 2022-12-23 云南电网有限责任公司 一种风电集群并网时有功功率的调节方法及系统

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101483344A (zh) * 2007-12-27 2009-07-15 歌美飒创新技术公司 风力设备及其运行方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090055030A1 (en) * 2007-08-21 2009-02-26 Ingeteam, S.A. Control of active power reserve in a wind-farm

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101483344A (zh) * 2007-12-27 2009-07-15 歌美飒创新技术公司 风力设备及其运行方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙蕾等.双馈异步风力发电机组功率调控能力研究.《电力科学与工程》.2009,第25卷(第9期),1-6. *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3367536A4 (en) * 2016-12-26 2019-05-08 Beijing Goldwind Science & Creation Windpower Equipment Co., Ltd. METHOD AND DEVICE FOR ASSIGNING THE EFFICIENCY OF A WIND ENERGY SYSTEM

Also Published As

Publication number Publication date
CN101860042A (zh) 2010-10-13

Similar Documents

Publication Publication Date Title
CN101860042B (zh) 风电场有功功率的协调控制方法
CN102856925B (zh) 一种风电场功率综合分配方法
US10731629B2 (en) Wind power plant controller
CN101931241B (zh) 风电场并网协调控制方法
Lubosny et al. Supervisory control of a wind farm
CN102299527B (zh) 一种风电场无功功率控制方法和系统
CN100578911C (zh) 变速恒频风电机组风电场的电压无功快速控制方法
Li Power flow modeling to doubly-fed induction generators (DFIGs) under power regulation
CN104467030B (zh) 一种基于风电与火电联合发电的功率分配方法
CN103219732A (zh) 一种含变速恒频风电场的配电网无功电压控制方法
CN102518560B (zh) 一种风电场有功功率调节方法
CN104037805B (zh) 一种计及电网安全约束的光伏电站可发电裕度分配方法
CN106602613B (zh) 一种省地两级调度断面协调控制方法
CN108306312A (zh) 一种风电场一次调频控制方法
CN103346577A (zh) 降低风电场功率损耗的风电场avc无功控制系统及方法
CN101860044A (zh) 风电场无功电压的协调控制方法
CN107453411A (zh) 一种风电场有功功率控制方法及其系统
CN104682437A (zh) 一种风电场的有功/无功实时闭环下垂控制方法
CN106026198B (zh) “风-水”打捆外送的agc协调控制系统及控制方法
CN103545848A (zh) 光伏电站群有功功率协调控制方法
CN107968443A (zh) 一种风光火打捆直流外送的agc控制方法
CN105391096A (zh) 一种风机有功功率管理控制方法
CN202178583U (zh) 一种风电场无功功率控制系统
KR20160107877A (ko) 풍력발전단지에서의 배터리 에너지 저장 시스템에 기반한 풍력 발전 변동의 평활화 방법
CN103296698A (zh) 一种风电场并网发电输出有功功率的控制方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant