CN101858222B - 一种新建隧道零距离下穿既有地铁结构控制变形的方法 - Google Patents
一种新建隧道零距离下穿既有地铁结构控制变形的方法 Download PDFInfo
- Publication number
- CN101858222B CN101858222B CN2010101817562A CN201010181756A CN101858222B CN 101858222 B CN101858222 B CN 101858222B CN 2010101817562 A CN2010101817562 A CN 2010101817562A CN 201010181756 A CN201010181756 A CN 201010181756A CN 101858222 B CN101858222 B CN 101858222B
- Authority
- CN
- China
- Prior art keywords
- subway
- jack
- shaped steel
- existing structure
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
本发明公开了一种新建隧道零距离下穿既有地铁结构控制变形的方法,该方法在既有地铁结构底板与新建隧道侧墙之间加装千斤顶,充分利用隧道开挖的时空效应,及时施加顶升力,预先使新建隧道地基土体固结沉降,从而减少后期土体沉降以达到控制地铁结构变形的目的,同时通过远程监控,利用千斤顶实时调整控制既有地铁结构的变形,保证既有地铁的结构和运营安全。该方法在传统的浅埋暗挖法施工的基础上,首先对隧道开挖断面两侧及底部一定范围内的土体进行超前注浆加固,提高其承载力,进而在新建隧道初衬侧墙上对应上部地铁结构的若干位置布置千斤顶,并在千斤顶与既有地铁结构底板之间设置型钢顶梁,使千斤顶的顶升力比较均匀的作用至既有地铁结构上。
Description
技术领域
本发明涉及地下工程领域,尤其涉及一种新建隧道零距离下穿地铁结构控制变形的方法。
背景技术
随着城市轨道交通的日益网络化、规模化,轨道交通和市政设施同步快速发展,轨道交通之间、市政隧道(如电力、热力隧道)与既有运营地铁之间的空间交叉不可避免,周围环境或者设施等方面的限制又不得不使二者采用近距离或紧贴的交叉穿越方式,随着轨道交通网络化的发展,轨道交通的运力在不断提高,为了保证安全运营,对结构及轨道变形提出了越来越严格的要求。近距离穿越地铁工程如果设计或施工处理不当,轻则降低地铁结构的耐久性,重则影响地铁的正常运营甚至行车安全。例如北京地铁5号线崇文门站下穿地铁2号线的施工导致既有2号线洞体结构和轨道线路产生了较大的沉降,迫使2号线在北京站至崇文门站区间采取了严格的限速措施等,极大地影响了地铁的服务质量和运营能力。
隧道下穿既有地铁结构常采用浅埋暗挖法施工,浅埋暗挖法是一种在覆土较小的地下进行各种类型地下洞室暗挖施工的常用方法,施工中采用多种辅助措施和围岩加固技术,充分调动围岩的自承能力。开挖后及时支护,封闭成环,使其与围岩共同作用形成联合支护体系,是一种抑制围岩过大变形的综合配套施工技术,目前广泛应用于城市地下工程的施工中。该工法多在城市地区的松软地层中修建,围岩自身承载能力比较差,因此,控制围岩变形是浅埋暗挖法设计施工的核心问题。除了保证浅埋暗挖的十八字方针“管超前,严注浆,短进尺,强支护,快封闭,勤量测”之外,为控制地层变形而采取的措施还有增加注浆量,增加或加强临时支撑等。
但是,采用浅埋暗挖法或其它施工方法使新建隧道近距离下穿运营轨道交通线路时,开挖引起的地层应力释放、地层失水引起的二次沉降会对地表建筑物和地下构筑物的正常使用或其结构安全造成影响,就地铁结构而言,严重时会影响地铁列车运行的平稳性和安全性。因此很有必要对这种近距离的下穿地铁结构的隧道施工方法进行深入研究和优化,力求尽量减小隧道施工的既有地铁结构的变形,从而既能使新建工程顺利进行,又使其对地铁结构影响和运营影响降到最低。
发明内容
本发明所要解决的技术问题是提供一种新建隧道零距离下穿既有地铁结构的变形控制方法,该方法充分利用隧道开挖的时空效应,布设千斤顶施加顶升力,及时发挥初期支护的作用,预先使新建隧道的地基土发生固结,从而减少后期土体沉降以达到控制变形的目的。该方法在传统的浅埋暗挖法施工的基础上,预先对隧道开挖断面两侧及底部一定范围内的土体进行超前注浆加固,在新建隧道初衬侧墙上对应上部地铁结构的若干位置布置千斤顶,该处初衬钢格栅改为型钢,立柱型钢与顶部型钢采用螺栓连接。施加一定的预顶力压实初衬下方土体,使千斤顶与型钢顶梁、顶梁与既有地铁结构顶紧,在顶升过程中实时监测地铁结构的变形以实时调整顶升力,控制既有结构的变形。待变形稳定后,紧固立柱型钢与顶部型钢的螺栓,闭合初衬,进行壁后回填注浆,施作隧道防水和二衬结构。在本发明的方法中,预顶技术不仅可使初期支护尽早的发挥作用,提高围岩的承载能力,更主要的是压实新建隧道下方土体使土体预先沉降从而减小了后期沉降引起的地铁结构的变形。
此种方法能有效减小施工过程中因土体沉降引起的地铁结构的变形,提高既有地铁结构安全的可靠度,作为一种有效的控制变形的方法应用于零距离下穿既有地铁结构的工程实际中。
本发明解决技术问题所采取的技术方案为一种新建隧道零距离下穿地铁结构控制变形的方法,包括以下步骤:
步骤一:在新建隧道开挖面临近既有地铁结构时,对开挖断面两侧及底部一定范围内的土体进行全断面超前注浆预加固;注浆区域各侧距隧道断面不小于2m。
步骤二:开挖新建隧道内的土体,及时施作初衬结构,初衬结构主要采用间隔布置钢格栅,并在其表面喷射混凝土的形式,初衬结构在布置千斤顶的位置采用型钢立柱、型钢顶梁和底钢梁的形式;新建隧道的开挖采用台阶法开挖,并保留核心土,台阶长度≤3m。
步骤三:在新建隧道初衬结构的侧墙上对应上部既有地铁结构的若干位置布置千斤顶,并在千斤顶与既有地铁结构底板之间设置型钢立柱和型钢顶梁,使千斤顶的顶升力均匀地传给既有地铁结构;布置千斤顶的具体过程为:在待开挖到预设千斤顶位置时,将此处的钢格栅用型钢替换,底钢梁应采用宽翼板的型钢,以加大与地基的接触面积。
初衬结构中,各型钢的连接处均设有连接板,型钢立柱与型钢顶梁连接处的连接板采用螺栓连接,其他部位的连接板除采用螺栓连接外,还要沿连接板周边围焊牢固;除顶部钢梁外,其它型钢断面与钢格栅断面均采用纵向连接筋连接,增加隧道的纵向整体性,然后在立柱型钢顶部侧面布置千斤顶。
采用千斤顶施加一定的预顶力,以压实初衬结构下方的地基土,使千斤顶与型钢顶梁、型钢顶梁与既有地铁结构顶紧,此处的型钢顶梁不做喷射混凝土,同时,应保证千斤顶施加的预顶力不超过加固后的地基土承载力,从而避免地基土发生过大变形或破坏。
步骤四:在既有地铁结构内对应每台千斤顶位置布设测点,根据沉降监测值调整顶力大小,并在调整过程中加强对既有地铁结构的监测,所用千斤顶应具备单独调整顶力及整体同步调整顶力的功能。
步骤五:待沉降稳定后,紧固初衬结构的型钢立柱与型钢顶梁的螺栓,闭合初衬结构,并及时进行壁后回填注浆,使初衬结构与地铁结构周边密贴。
步骤六:待初衬结构贯通后,立即施作新建隧道的防水和二衬结构,先将该段底板二衬全部做完,再施工侧墙和顶板二衬,可将纵向施工步距缩短以配合千斤顶逐个断面拆除(千斤顶拆除与否视情况而定),也可将千斤顶浇入二衬结构内。
附图说明
图1是地铁结构下方隧道开挖注浆加固图。
图2是隧道开挖布置千斤顶图。
图3是开挖隧道布置千斤顶断面结构图。
图4是型钢顶梁处节点图。
图5是千斤顶布设图。
具体实施方式
下面结合一具体的工程实例进行说明。该工程实例是在本发明技术方案为前提下进行实施,给出具体的实施方案和操作流程,但本发明的保护范围不限于下述实例。
拟建市政热力隧道下穿地铁结构,新建隧道纵断为平坡,双洞,单侧净空尺寸1.8m×2.5m(宽×高),采用平顶直墙断面型式,复合式衬砌结构。上部地铁结构为明挖法施工的双洞矩形框架结构,宽9.8m~10.8m,高5.9m,覆土厚度3.827m~2.845m。
图1中,对地铁结构1下方的隧道开挖断面3两侧及底部进行全断面超前注浆加固,注浆区域2各侧距隧道断面周边不小于2m。注浆材料采用超细水泥浆,加固后土体无侧限抗压强度≥0.8Mpa,弹性模量≥200Mpa。
图2中,隧道采用台阶法开挖,并保留核心土5,台阶4的长度≤3m,挖除拟建隧道开挖面范围的土体,施作初衬结构6。初衬结构主要采用间隔布置钢格栅7,并在其表面施工喷射混凝土的形式,钢格栅7在下穿地铁结构的部分密排,间距为330mm。在对应地铁结构下方的隧道内布置千斤顶8,共6个断面,每个断面4台,千斤顶8应具备单独顶升和同步顶升的功能。为防止顶力超过地基承载力而发生地基变形,计算的单台千斤顶顶力不得大于45T。
图2中,在设置千斤顶8的断面,将初衬结构的钢格栅替换为HM220型钢9,底钢梁采用焊接的440mm宽的H型钢10,以加大与地基的接触面积。图3和图4中,型钢立柱11与型钢顶梁12只采用长杆螺栓13连接,而立柱中部、角部以及底板钢梁连接板除采用螺栓连接外,还要沿连接板16周边围焊牢固。除顶部钢梁外,型钢断面与钢格栅断面均采用纵向连接筋连接。
图3中,安装千斤顶8,及时施加30T预顶力,压实下部土体,并使初衬结构与地铁结构顶紧,该处顶梁不做喷射混凝土。在地铁结构1内对应每一台千斤顶8的位置布设测点,根据沉降监测值调整顶力大小,调整过程中加强对地铁结构1的监测。千斤顶8每一加载级别为5T,加载速率<5T/半小时。待沉降数值稳定后,紧固初衬结构的型钢立柱11与型钢顶梁12的螺栓13,并加设钢楔,闭合初衬,及时进行初衬壁后回填注浆。
图3中,隧道开挖时先开挖左洞,待左洞初衬贯通后,开挖右洞。右洞贯通后,全部千斤顶安装到位,视地铁结构变形监测情况决定是否需要进行同步顶升。如沉降控制情况正常,则施作防水和二衬结构。先将该段底板二衬14全部做完,再施工侧墙和顶板二衬,且将纵向施工步距缩短以配合千斤顶8逐个断面拆除。每次拆除两个断面的千斤顶,二衬的侧墙和顶板向前施作一步,待二衬结构达到设计强度后再拆除最后两个断面的千斤顶,循环进行,千斤顶卸载速率应<5T/半小时。中隔壁不拆除,绑扎纵向分布筋后浇筑中墙混凝土。
图4中,型钢顶梁处节点图,7为钢格栅,8为千斤顶,9为型钢,17为加劲板。
图5为图4的剖面图,其中8为千斤顶,9为型钢,17为加劲板。
Claims (8)
1.一种新建隧道零距离下穿既有地铁结构控制变形的方法,包括以下步骤:
步骤一:在新建隧道开挖面临近既有地铁结构的隧道时,对开挖断面两侧及底部一定范围内的土体进行全断面超前注浆预加固;
步骤二:开挖新建隧道内的土体,及时施作初衬结构,初衬结构主要采用间隔布置钢格栅,并在其表面喷射混凝土的形式,初衬结构在布置千斤顶的位置采用型钢立柱、型钢顶梁和底钢梁的形式;
步骤三:在新建隧道初衬结构的侧墙上对应上部既有地铁结构的若干位置布置千斤顶,并在千斤顶与既有地铁结构底板之间设置型钢立柱和型钢顶梁,使千斤顶的顶升力均匀地传给既有地铁结构;
步骤四:在既有地铁结构内对应每台千斤顶的位置布置测点,根据既有地铁结构的沉降监测值实时调整顶力大小,保证既有地铁结构的安全,同时在调整千斤顶顶升力的过程中加强对既有地铁结构的监测;
步骤五:待沉降变形稳定后,紧固初衬结构的型钢立柱与型钢顶梁的螺栓,闭合初衬结构,及时进行壁后回填注浆,使初衬结构与既有地铁结构的隧道底板密贴;
步骤六:待初衬结构贯通后,立即施作新建隧道的防水和二衬结构。
2.如权利要求1所述的一种新建隧道零距离下穿既有地铁结构控制变形的方法,其特征在于步骤一中进行全断面超前注浆预加固时,注浆区域各侧距隧道断面不小于2m。
3.如权利要求1所述的一种新建隧道零距离下穿既有地铁结构控制变形的方法,其特征在于步骤二中新建隧道的开挖采用台阶法开挖,并保留核心土,台阶长度≤3m。
4.如权利要求1所述的一种新建隧道零距离下穿既有地铁结构控制变形的方法,其特征在于步骤三中布置千斤顶的具体过程为:在待开挖到预设千斤顶位置时,将此处的钢格栅换为型钢,底钢梁采用宽翼板的型钢,以加大与地基的接触面积。
5.如权利要求4所述的一种新建隧道零距离下穿既有地铁结构控制变形的方法,其特征在于布置好千斤顶后,采用千斤顶施加一定的预顶力,以压实初衬结构下方的地基土,使千斤顶与型钢顶梁、型钢顶梁与既有地铁结构顶紧,此处的型钢顶梁不做喷射混凝土,同时,应保证千斤顶施加的预顶力不超过加固后的地基土承载力,从而避免地基土发生过大变形。
6.如权利要求4所述的一种新建隧道零距离下穿既有地铁结构控制变形的方法,其特征在于在初衬结构中,各型钢的连接处均设有连接板,型钢立柱与型钢顶梁连接处的连接板采用螺栓连接,其他部位的连接板除采用螺栓连接外,还要沿连接板周边进行围焊,除型钢顶梁外,其它型钢断面与钢格栅断面均采用纵向连接钢筋连接,保证初衬结构的纵向整体性,然后在型钢立柱顶部侧面布置千斤顶。
7.如权利要求4所述的一种新建隧道零距离下穿既有地铁结构控制变形的方法,其特征在于所述千斤顶具备单独顶升和同步顶升的功能。
8.如权利要求1所述的一种新建隧道零距离下穿既有地铁结构控制变形的方法,其特征在于步骤六中施作二衬结构时,千斤顶可浇入二衬结构内或拆除。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101817562A CN101858222B (zh) | 2010-05-25 | 2010-05-25 | 一种新建隧道零距离下穿既有地铁结构控制变形的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101817562A CN101858222B (zh) | 2010-05-25 | 2010-05-25 | 一种新建隧道零距离下穿既有地铁结构控制变形的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101858222A CN101858222A (zh) | 2010-10-13 |
CN101858222B true CN101858222B (zh) | 2012-03-21 |
Family
ID=42944355
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010101817562A Expired - Fee Related CN101858222B (zh) | 2010-05-25 | 2010-05-25 | 一种新建隧道零距离下穿既有地铁结构控制变形的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101858222B (zh) |
Families Citing this family (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102155233B (zh) * | 2011-04-21 | 2013-07-10 | 上海市城市建设设计研究院 | 一种隧道开挖施工方法 |
CN102287195B (zh) * | 2011-05-13 | 2014-09-17 | 中铁四局集团第二工程有限公司 | 浅埋暗挖大跨度隧道下穿既有高速铁路施工方法 |
CN103410522A (zh) * | 2013-08-27 | 2013-11-27 | 中铁十三局集团第四工程有限公司 | 浅埋暗挖法连续近距离下穿铁路桥的施工方法 |
CN103899323B (zh) * | 2014-05-06 | 2016-01-27 | 中铁二十五局集团轨道交通工程有限公司 | 一种盾构穿越铁路站场的施工方法 |
CN104695479B (zh) * | 2015-01-14 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | 一种连接民建地下室与地铁通道的施工方法 |
CN105809246B (zh) * | 2016-02-25 | 2018-02-02 | 东南大学 | 一种基于bp‑时间序列融合的地铁结构变形预报方法 |
CN106640090B (zh) * | 2017-02-28 | 2018-01-02 | 安徽理工大学 | 邻近既有井筒条件下新建煤矿深立井地面预注浆监控系统 |
CN108952771A (zh) * | 2017-05-27 | 2018-12-07 | 中铁建大桥工程局集团第三工程有限公司 | 一种下穿既有刚性构筑物零变形施工方法 |
CN107036515B (zh) * | 2017-06-08 | 2023-03-28 | 浙江工业大学 | 模拟台阶法隧道施工引发地表变形的试验装置及试验方法 |
CN107747492B (zh) * | 2017-11-10 | 2024-06-21 | 中铁二十四局集团安徽工程有限公司 | 可伸缩式十字初期支护结构及其变形动态控制方法 |
CN108397199A (zh) * | 2018-01-03 | 2018-08-14 | 中铁广州工程局集团有限公司 | 一种近距离下穿引水洞的隧道施工方法 |
CN109798121B (zh) * | 2019-03-22 | 2020-11-24 | 中建八局轨道交通建设有限公司 | 暗挖隧道密贴下穿既有结构底板的施工方法 |
CN110107303A (zh) * | 2019-04-19 | 2019-08-09 | 同济大学 | 浅覆土盾构下穿高速铁路的变形控制方法 |
CN110630284B (zh) * | 2019-09-28 | 2024-02-13 | 广州地铁设计研究院股份有限公司 | 密贴下穿既有地铁车站施工的沉降主动控制结构及方法 |
CN111734423A (zh) * | 2020-07-30 | 2020-10-02 | 中铁隆工程集团有限公司 | 一种下穿机场航站楼的暗挖隧道初期支护方法 |
CN113605933A (zh) * | 2021-07-13 | 2021-11-05 | 山东大学 | 一种近距离下穿地铁车站暗挖通道注浆加固方法 |
CN113605902B (zh) * | 2021-08-26 | 2024-03-29 | 山东省交通规划设计院集团有限公司 | 一种下穿铁路路基隧道施工方法 |
CN115467366B (zh) * | 2022-08-17 | 2024-05-31 | 湖北工业大学 | 一种基坑施工主动补偿邻近运营隧道变形的施工方法 |
CN115341576B (zh) * | 2022-09-19 | 2023-06-27 | 中铁第六勘察设计院集团有限公司 | 一种基坑开挖诱发下伏隧道隆起变形的控制方法及装置 |
CN115928798B (zh) * | 2023-03-13 | 2023-05-23 | 北京城建设计发展集团股份有限公司 | 超小净距长距离斜交穿越轨道交通既有地下结构的方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4388021A (en) * | 1981-08-26 | 1983-06-14 | Richard Weiss | Method of and device for making canalization by advancing under pressure a string of sewer pipes |
CN1932244A (zh) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | 双圆盾构近距离穿越建筑物或构筑物的施工方法 |
CN101126318A (zh) * | 2007-09-28 | 2008-02-20 | 中铁二局股份有限公司 | 三线并行下穿铁路干线隧道的盾构施工方法 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3446640B2 (ja) * | 1998-12-14 | 2003-09-16 | 鹿島建設株式会社 | 柔構造式沈埋トンネルおよびその構築工法 |
JP2001336382A (ja) * | 2000-05-30 | 2001-12-07 | Kajima Corp | トンネルの構築方法およびトンネル |
-
2010
- 2010-05-25 CN CN2010101817562A patent/CN101858222B/zh not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4388021A (en) * | 1981-08-26 | 1983-06-14 | Richard Weiss | Method of and device for making canalization by advancing under pressure a string of sewer pipes |
CN1932244A (zh) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | 双圆盾构近距离穿越建筑物或构筑物的施工方法 |
CN101126318A (zh) * | 2007-09-28 | 2008-02-20 | 中铁二局股份有限公司 | 三线并行下穿铁路干线隧道的盾构施工方法 |
Non-Patent Citations (2)
Title |
---|
杨广武等.《盾构法隧道下穿既有结构三维数值模拟分析》.《中国铁道科学》.2009,第30卷(第6期),54-59. * |
黄建玲等.《邻近暗挖地铁建筑物安全评价方法》.《中国铁道科学》.2009,第30卷(第2期),77-81. * |
Also Published As
Publication number | Publication date |
---|---|
CN101858222A (zh) | 2010-10-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101858222B (zh) | 一种新建隧道零距离下穿既有地铁结构控制变形的方法 | |
CN101440708B (zh) | Pba浅埋暗挖近距离大断面三洞分离岛式结构施工方法 | |
CN105064397B (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法 | |
CN101550698B (zh) | 盾构隧道上方基坑施工方法 | |
CN108487252A (zh) | 一种深基坑明挖顺作施工方法 | |
CN105041349A (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的暗挖施工方法 | |
CN112253133B (zh) | 上软下硬岩体大断面暗挖隧道安全高效施工方法 | |
CN103696784B (zh) | 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法 | |
CN106979021B (zh) | 大断面黄土隧道开挖及初期支护快速封闭成环方法 | |
CN108868778A (zh) | 一种大型地下结构非开挖修建方法 | |
CN104594361B (zh) | 一种工字型围护桩以及围护结构兼做主体结构的施工方法 | |
CN107675628A (zh) | 城市道路框架桥上穿运营地铁下穿运营铁路顶进施工方法 | |
CN109763838A (zh) | 适用于钻爆法隧道的装配式仰拱结构及其拼装方法 | |
CN104652279A (zh) | 一种新建框架桥上穿既有地铁结构箱涵顶进施工方法 | |
CN209510325U (zh) | 一种采用预制装配仰拱的钻爆法隧道结构 | |
CN105089670B (zh) | 一种在并行区间盾构隧道基础上扩挖地铁车站施工方法 | |
CN105201516A (zh) | 一种地铁车站主体结构及其四联拱pba暗挖施工方法 | |
CN105089680A (zh) | 一种沿空留巷轻质高强混凝土砌块墙体及其施工工艺 | |
CN102031785A (zh) | 永久结构板带代替临时围檩的基坑支护技术 | |
CN109667587A (zh) | 采用预制装配仰拱的钻爆法隧道结构 | |
CN105507170A (zh) | 钢筋混凝土盖板涵的强化方法 | |
CN205036380U (zh) | 一种四联拱pba暗挖地铁车站主体结构 | |
CN101215840A (zh) | 飞机式基础加固予力工法 | |
CN105156130B (zh) | 一种隧道施工免支护安全施工方法 | |
CN106869198B (zh) | 一种利用井字梁加固杆塔基础加固松散土质下陷空区方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120321 Termination date: 20120525 |