CN101824787A - Waterproof shock-absorption road surface structure and construction method thereof - Google Patents

Waterproof shock-absorption road surface structure and construction method thereof Download PDF

Info

Publication number
CN101824787A
CN101824787A CN 201010132658 CN201010132658A CN101824787A CN 101824787 A CN101824787 A CN 101824787A CN 201010132658 CN201010132658 CN 201010132658 CN 201010132658 A CN201010132658 A CN 201010132658A CN 101824787 A CN101824787 A CN 101824787A
Authority
CN
China
Prior art keywords
layer
basic unit
absorption
waterproof shock
road surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010132658
Other languages
Chinese (zh)
Other versions
CN101824787B (en
Inventor
马银华
易志坚
杨庆国
何小兵
赵朝华
谷建义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Jiaotong University
Original Assignee
马银华
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 马银华 filed Critical 马银华
Priority to CN201010132658XA priority Critical patent/CN101824787B/en
Publication of CN101824787A publication Critical patent/CN101824787A/en
Application granted granted Critical
Publication of CN101824787B publication Critical patent/CN101824787B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a waterproof shock-absorption road surface structure and a construction method thereof. The structure of the road surface comprises a surface layer, a base layer, a drainage underlayer and a road bed from top to bottom; a waterproof shock-absorption functional layer is arranged between the surface layer and the base layer; the waterproof layer, the base layer and the drainage underlayer are separated naturally; and a water-permeable filter layer is arranged between the drainage underlayer and the road bed. The construction method is realized by arranging the road bed, the water-permeable filter layer, the drainage underlayer, the waterproof layer, the base layer, the waterproof shock-absorption functional layer and the surface layer from bottom to top. The road surface structure can effectively prevent the damage of the road surface and the road bed by the water on road surface and the underground water; meanwhile, the road surface structure has good shock absorption function and remarkably prolongs the actual service life of the road.

Description

Waterproof shock-absorption road surface structure and job practices thereof
Technical field
The present invention relates to a kind of road structure and job practices thereof, especially a kind of waterproof shock-absorption road surface structure and job practices thereof.
Background technology
In fields such as road, airfield runway and urban operating mechanisms, pavement life shortens a great problem that has become in the construction.Cause the reason of road surface early damage, the lost of life to have many.Wherein, studies show that " water is the dead enemy ".According to the source of water, the road surface damage by water is bad can be divided into two kinds of the bad and underground water damages of road table damage by water.
Road table damage by water is bad, mainly be show the way the table water (as rainwater) enter surface layer inside by surface layer hole, seam or crack, cause the surface material damage by water bad, water further infiltrates basic unit, cause basic unit to move the water erosion damage, and between surface layer and basic unit, form non-homogeneous coming to nothing and non-homogeneous supporting, for asphalt concrete pavement, the moving water of interlayer washes away the adhesion stress that also can weaken surface layer and basic unit, is unfavorable for that asphalt concrete pavement is stressed.When water further infilters into roadbed down again, if subgrade drainage is bad then to make it be immersed in water for a long time, roadbed material intensity and bullet mould reduce, and easily cause the roadbed unstability, then cause basic unit's depression, fracture, cause surface layer purt mud phenomenon, depression and rupture failure to occur at last.Solve road table damage by water bad aspect, existing road surface has the measure that porous draining basic unit is set between surface layer and basic unit, the road table water that infiltrates basic unit is discharged beyond the road surface, has obtained certain effect.
Underground water damages, and is meant big roadbed soil of humidity or the higher area of groundwater table, and the water in roadbed soil, roadbed bottom or the cut slope enters the pavement destruction that road structure inside causes by capillarity or side direction seepage flow.Underground water corrodes basic unit for a long time, weakens the bulk strength of subbase, basic unit, reduces the bullet mould of base material, and influence of dynamic water also can quicken basic unit's destruction simultaneously, thereby causes top course depression, rupture failure.In addition, when underground water enters road structure inside, under the continuous extruding of carload especially heavy duty, also can attach a small amount of roadbed fine grained soils, cause the roadbed fine grained soils to run off, the roadbed bulk strength reduces and influences the road structure bearing capacity, and the roadbed fine grained soils also can cause the road surface purt mud phenomenon frequently to occur with the subsidiary rising of water, the fine grained soils that rises also can stop up the drainage blanket passage, causes impeded drainage.In addition, at northern extremely frigid zones, underground water also can cause the frost heaving failure of roadbed, has aggravated the reduction of service life of road surface.Exist countless capillary tubies in the subgrade soils, underground water can rise to roadbed inside by the capillary tube in the roadbed, especially in the winter time, and when the atmosphere subzero temperature imports into underground, Free water in the face of land is the glaciation crystal at first, along with the continuation decline of temperature, the outermost layer of water of hydration also begins to freeze, and ice crystal is enlarged gradually, and in soil layer, form ice band, the freezing back of moisture volume will increase, and the soil body is swelled along with expanding, and frost heaving occur.Particulate is many more in soil, and the capillary tube of formation is just many more, and is also big more to the frost heave influence of roadbed.Therefore must effectively stop the structural damage of underground water road pavement.
The existing measure that stops underground water to enter ground mainly contains: the first, drainage blankets such as gravel, honeycombed cement stabilization gravel are set, and this measure can reduce capillary tube, controls phreatic rising quantity.But still have part water to continue to rise to road structure inside by capillarity.Simultaneously, in the higher highway section of groundwater table, because roadbed is in dampness for a long time, the continuous vibration effect of traffic load will make that the roadbed soil property is softening, soil particle attenuates, and the subsidiary roadbed fine grained soils of underground infiltration rises under load vibration extruding.The roadbed fine grained soils rises to bed course and brings two adverse consequences: the one, and the roadbed fine grained soils runs off, and causes subgrade soils intensity to reduce, and causes pavement depression and destroys; The 2nd, the roadbed fine grained soils rises and fills the hole of drainage blanket, easily causes bedding course drainage not smooth, and owing to the bed course porosity diminishes, capillary tube attenuates, it is big that rise waterborne becomes, and strengthened the capillarity of water, and underground water is easier to rise to basic unit even surface layer by capillarity.Basic unit on the bed course all is stabilized with inorganic binder pellet semi-rigid type base basically, himself be difficult to stop fully the infiltration of water, and drying shrinkage and warm draw line ubiquity, these are carried secretly by capillarity to underground water undoubtedly, and the roadbed fine grained soils rises to basic unit together and surface layer provides passage, causes basic unit, surface layer damage by water evil idea and mud pumping phenomenon thus.Simultaneously, the construction quality of honeycombed cement stabilization gravel class drainage blanket requires high, and the system of mixing of drainage blanket compound is high especially to the requirement of water supply volume, and is if water supply volume is too small, loose easily when rolling compound; If water supply volume is excessive, segregation phenomenon then appears easily, and construction control is bad, will influence its drainage effect, and porosity reduces provides capillary channel.The second, in the winter of northern extremely frigid zones,, adopt usually and change the way of banketing for solving the roadbed frost heaving failure, promptly water good stability, non-heaving soil or weak swelling soil change the top of filling out roadbed, as sand, gravel, slag etc.Adopt this measure can alleviate the frost heave degree of roadbed greatly, but the problem that exists is that because the rising of capillary water, underground water still can cause the frost heaving failure of road structure inside.Even drainage blanket is set again, capillary water also can infiltrate in the bed course and congeal into ice, and causes the bed course frost heaving.Bed course generation frost-heaving deformation, basic unit be must be subjected to and its vertical direction and the tangential constraint of interlayer given, this constraint is strong more, the restraint forces that bed course is subjected to is just big more, correspondingly, the reaction force that bed course gives basic unit is also just big more, and this reaction force comprises extruding force and interlayer tangential shearing or the frictional force (to basic unit, this shearing or frictional force performance be basic unit bottom tension) of bed course for basic unit.Semi-rigid sub-base material has high compression strength, can resist the compressive stress that extruding force produces, but, the tensile strength of semi-rigid sub-base material is less, the interlayer tangential force makes basic unit's tension, and then can cause adverse effect to basic unit, even when this tensile stress reaches its tensile strength, base course crack occurs, cause pavement destruction.In addition, for the rigid pavement structure, when for example being cement concrete pavement, because cement concrete material fragility is bigger, the surface layer rigidity is big, there be non-homogeneous coming to nothing and non-homogeneous supporting in interlayer when contacting with basic unit, under the vibratory impulse effect of heavy load, surface layer is stressed unfavorable, and reduce fatigue life, when especially basic unit is semi-rigid type base or rigid base, surface layer and basic unit are very stiff and demanding, and the low-cycle fatigue failure under the high stress level takes place down easily for surface material and base material antivibration scarce capacity, heavily loaded vibratory impulse, pavement destruction, and then infiltrate basic unit and roadbed provides passage for road table water.
Therefore need a kind of waterproof that has, the road structure and the job practices thereof that have vibration-damping function simultaneously, can effectively stop from bottom to top underground water and top-down road to show the destruction that water road pavement structure causes, and can also improve surface layer support conditions, enhancing surface layer antivibration ability, prolong service life of road surface.
Summary of the invention
In view of this, the purpose of this invention is to provide a kind of waterproof shock-absorption road surface structure and job practices.The objective of the invention is to be achieved through the following technical solutions: a kind of waterproof shock-absorption road surface structure, comprise surface layer, basic unit, drainage blanket and roadbed from top to bottom, the waterproof shock-absorption functional layer is set between described surface layer and the basic unit, fluid-tight waterproofing course is set between basic unit and the drainage blanket, waterproofing course and basic unit, the equal natural separation of drainage blanket are provided for filtering the permeable filtration beds of fine deposit between drainage blanket and the roadbed.
Further, described waterproof shock-absorption functional layer is that thickness is the finished product thin layer soft material of 0.2mm~1.0mm;
Further, described waterproof shock-absorption functional layer is waterproofing geomembrane, composite plastic woven cloth or plastic sheeting;
Further, described waterproofing course is the finished product thin layer soft material of thickness 0.1mm~0.5mm;
Further, described waterproofing course is waterproofing geomembrane, composite plastic woven cloth or plastic sheeting;
Further, described permeable filtration beds is the geotechnological layer of cloth of permeable filtration of thickness 0.5mm~2mm;
Further, described surface layer is bituminous concrete composite cover, portland cement concrete surface layer, roller compacted concrete surface layer, modified concrete surface layer or fibrous concrete surface layer; Described basic unit is flexbile base, semi-rigid type base or rigid base; Described drainage blanket is pellet bed course, organic binder stable granulate bed course, stabilized with inorganic binder pellet bed course or mangcorn sarking;
Technical scheme of the present invention also comprises: a kind of job practices of waterproof shock-absorption road surface structure, and the making order is followed successively by from bottom to top: the first, tamping road bed; The second, the smooth permeable filtration beds of laying on roadbed; The 3rd, making drainage blanket on smooth permeable filtration beds; The 4th, treat to re-lay waterproofing course after the complete moulding of drainage blanket making, make natural separation between drainage blanket and the waterproofing course; The 5th, on smooth waterproofing course, repave and build basic unit, make natural separation between basic unit and the waterproofing course; The 6th, smooth laying waterproof shock-absorption functional layer in basic unit; The 7th, making surface layer on smooth waterproof shock-absorption functional layer, thus form complete road structure.
Beneficial effect of the present invention is: first, between roadbed and drainage blanket, be provided with permeable filtration beds, can guarantee underground water rise enter drainage blanket and discharge beyond the road surface in, the roadbed fine grained soils can be blocked effectively or particle is brought into drainage blanket by underground water, avoid the loss of roadbed fine grained soils or particle, reduce pavement depression, also can avoid roadbed fine grained soils or particle to stop up the hole of drainage blanket, thereby influence draining.Second, be provided with between drainage blanket and the basic unit can with the flexible film class waterproof layer material of drainage blanket and basic unit's natural separation after, at first, having avoided waterproofing course contacts with basic unit and the direct of drainage blanket, the interlayer contact surface is more smooth relatively, reduced the frictional force between basic unit and the drainage blanket greatly, made when winter, water entered bed course generation frost-heaving deformation, the tangential effect of contraction of the interlayer of bed course and basic unit greatly alleviates, help bed course and basic unit is stressed, and can also avoid the damage of waterproof layer material.Secondly, because film class waterproofing course has certain adaptation deformation ability, can play the effect of stress absorption and compatible deformation, it is stressed to be beneficial to basic unit.Once more, because the setting of waterproofing course, stoping underground water further to rise to basic unit and surface layer fully, when effectively solving the underground water damage, pavement disease and the destruction problem that cause because of the underground water frost heave winter will significantly be reduced, simultaneously, can also stop road table water to enter roadbed fully, avoid the roadbed damage by water and the mud pumping phenomenon that cause thus by bed course.At last, owing to effectively stoped phreatic rising, because quality control on construction is bad causes under the situation that porosity reduces, can prevent that roadbed fine grained soils or particle from stopping up the existing hole of drainage blanket at drainage blanket, can not cause porosity further to reduce even stop up, the 3rd, in the job practices of the present invention, owing to after treating that drainage blanket is completed into, re-lay waterproofing course, so guaranteed the natural separation of drainage blanket and waterproofing course, played the effect in front for the water vent of bed course.The 4th, owing to be provided with the waterproof shock-absorption functional layer, can effectively stop road table water to penetrate into the destruction that inner road pavement structure causes, show by the drop-weight impact experiment simultaneously, compare with the road surface of water vibration-damping function layer in the air, the top course anti-vibrating and impact ability that adopts the present invention to build can improve more than 50%.
Other advantages of the present invention, target and feature will be set forth in the following description, and to a certain extent, based on being conspicuous to those skilled in the art, perhaps can obtain instruction from the practice of the present invention to investigating hereinafter.
Description of drawings
Below in conjunction with drawings and Examples waterproof shock-absorption road surface structure of the present invention and job practices thereof are described further, accompanying drawing is a structural representation of the present invention.
The specific embodiment
As shown in the figure, waterproof shock-absorption road surface structure of the present invention is followed successively by surface layer 1, waterproof shock-absorption functional layer 2, basic unit 3, waterproofing course 4, drainage blanket 5, permeable filtration beds 6 and roadbed 7 from top to bottom.Surface layer 1 is one of bituminous concrete composite cover (being specially the surface layer of the composite construction of making asphalt concrete layer on the cement concrete layer), portland cement concrete surface layer, roller compacted concrete surface layer, modified concrete surface layer or fibrous concrete surface layer; Waterproof shock-absorption functional layer 2 is one of waterproofing geomembrane, composite plastic woven cloth or plastic sheeting; Described basic unit 3 is one of flexbile base, semi-rigid type base or rigid base; Described waterproofing course 4 is one of waterproofing geomembrane, composite plastic woven cloth or plastic sheeting; Described drainage blanket 5 is one of pellet bed course (the pellet bed course is bed courses such as common sand grains, rubble), organic binder stable granulate bed course, stabilized with inorganic binder pellet bed course or mangcorn sarking (the mangcorn sarking is the various mangcorn sarkings between pellet, organic binder stable granulate and the stabilized with inorganic binder pellet); Described permeable filtration beds 6 is the geotechnological layer of cloth of permeable filtration; Be the natural separation state between waterproofing course 4 and basic unit 3, the drainage blanket 5.
Concrete job practices of the present invention is: the first, tamping road bed 7; The second, the smooth permeable filtration beds 6 of laying on roadbed 7; The 3rd, making drainage blanket 5 on smooth permeable filtration beds 6; The 4th, treat to re-lay waterproofing course 4 after the complete moulding of drainage blanket 5 makings, make natural separation between drainage blanket 5 and the waterproofing course 4; The 5th, on smooth waterproofing course 4, repave and build basic unit 3, make natural separation between basic unit 3 and the waterproofing course 4; The 6th, smooth laying waterproof shock-absorption functional layer 2 in basic unit 3; The 7th, making surface layer 1 on smooth waterproof shock-absorption functional layer 2, thus form complete road structure.
Embodiment one, described surface layer 1 is the portland cement concrete surface layer, waterproof shock-absorption functional layer 2 is the composite plastic woven cloth of thickness 0.2mm, basic unit 3 is a semi-rigid type base, waterproofing course 4 is the waterproofing geomembrane of thickness 0.1mm, drainage blanket 5 is an organic binder stable granulate bed course, and the geotechnological layer of cloth of permeable filtration that permeable filtration beds 6 is thickness 0.5mm can making waterproof shock-absorption road surface structure of the present invention according to aforementioned job practices.
Embodiment two, described surface layer 1 is the bituminous concrete composite cover, waterproof shock-absorption functional layer 2 is the waterproofing geomembrane of thickness 1.0mm, basic unit 3 is a flexbile base, waterproofing course 4 is the plastic sheeting of thickness 0.5mm, drainage blanket 5 is a stabilized with inorganic binder pellet bed course, and the geotechnological layer of cloth of permeable filtration that permeable filtration beds 6 is thickness 1.25mm can making waterproof shock-absorption road surface structure of the present invention according to aforementioned job practices.
Embodiment three, described surface layer 1 is the fibrous concrete surface layer, waterproof shock-absorption functional layer 2 is the plastic sheeting of thickness 0.6mm, basic unit 3 is a flexbile base, waterproofing course 4 is the waterproofing geomembrane of thickness 0.3mm, drainage blanket 5 is the pellet bed course, and the geotechnological layer of cloth of permeable filtration that permeable filtration beds 6 is thickness 2mm can making waterproof shock-absorption road surface structure of the present invention according to aforementioned job practices.
Explanation is at last, above embodiment is only unrestricted in order to technical scheme of the present invention to be described, although the present invention is had been described in detail with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, can make amendment or be equal to replacement technical scheme of the present invention, and not breaking away from the aim and the scope of technical solution of the present invention, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (8)

1. waterproof shock-absorption road surface structure, comprise surface layer (1), basic unit (3), drainage blanket (5) and roadbed (7) from top to bottom, it is characterized in that: between described surface layer (1) and the basic unit (3) waterproof shock-absorption functional layer (2) is set, between basic unit (3) and the drainage blanket (5) fluid-tight waterproofing course (4) is set, waterproofing course (4) and basic unit (3), drainage blanket (5) be natural separation all, is provided for filtering the permeable filtration beds (6) of fine deposit between drainage blanket (5) and the roadbed (7).
2. waterproof shock-absorption road surface structure according to claim 1 is characterized in that: described waterproof shock-absorption functional layer (2) is the finished product thin layer soft material of thickness 0.2mm~1.0mm.
3. waterproof shock-absorption road surface structure according to claim 1 and 2 is characterized in that: described waterproof shock-absorption functional layer (2) is waterproofing geomembrane, composite plastic woven cloth or plastic sheeting.
4. waterproof shock-absorption road surface structure according to claim 1 is characterized in that: described waterproofing course (4) is the finished product thin layer soft material of thickness 0.1mm~0.5mm.
5. according to claim 1 or 4 described waterproof shock-absorption road surface structures, it is characterized in that: described waterproofing course (4) is waterproofing geomembrane, composite plastic woven cloth or plastic sheeting.
6. waterproof shock-absorption road surface structure according to claim 1 is characterized in that: described permeable filtration beds (6) is the geotechnological layer of cloth of permeable filtration of thickness 0.5mm~2mm.
7. waterproof shock-absorption road surface structure according to claim 1 is characterized in that: described surface layer (1) is bituminous concrete composite cover, portland cement concrete surface layer, roller compacted concrete surface layer, modified concrete surface layer or fibrous concrete surface layer; Described basic unit (3) is flexbile base, semi-rigid type base or rigid base; Described drainage blanket (5) is pellet bed course, organic binder stable granulate bed course, stabilized with inorganic binder pellet bed course or mangcorn sarking.
8. the job practices of the described waterproof shock-absorption road surface structure of claim 1, it is characterized in that: making is followed successively by in proper order: the first, tamping road bed (7); The second, go up the smooth permeable filtration beds of laying (6) at roadbed (7); The 3rd, go up making drainage blanket (5) at smooth permeable filtration beds (6); The 4th, treat to re-lay waterproofing course (4) after the complete moulding of drainage blanket (5) making, make natural separation between drainage blanket (5) and the waterproofing course (4); The 5th, on smooth waterproofing course (4), repave and build basic unit (3), make natural separation between basic unit (3) and the waterproofing course (4); The 6th, go up smooth laying waterproof shock-absorption functional layer (2) in basic unit (3); The 7th, go up making surface layer (1) in smooth waterproof shock-absorption functional layer (2), thereby form complete road structure.
CN201010132658XA 2010-03-25 2010-03-25 Waterproof shock-absorption road surface structure and construction method thereof Expired - Fee Related CN101824787B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010132658XA CN101824787B (en) 2010-03-25 2010-03-25 Waterproof shock-absorption road surface structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010132658XA CN101824787B (en) 2010-03-25 2010-03-25 Waterproof shock-absorption road surface structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN101824787A true CN101824787A (en) 2010-09-08
CN101824787B CN101824787B (en) 2012-05-23

Family

ID=42688939

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010132658XA Expired - Fee Related CN101824787B (en) 2010-03-25 2010-03-25 Waterproof shock-absorption road surface structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN101824787B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103541287A (en) * 2013-10-21 2014-01-29 马银华 Pavement structure with comprehensive waterproof reinforced roadbed as well as construction method of pavement structure
CN103556558A (en) * 2013-10-21 2014-02-05 马银华 Pavement construction with hierarchically completely encapsulated roadbed and construction method thereof
CN104878678A (en) * 2015-06-04 2015-09-02 深圳市华威环保建材有限公司 Construction method for water-permeable and water-retaining water-permeable pavement structure
CN105113351A (en) * 2015-08-06 2015-12-02 中国水利水电第六工程局有限公司 Concrete pavement structure in alpine region and construction method thereof
CN105133463A (en) * 2015-10-16 2015-12-09 武汉大学 Permeable pavement structure based on geobag reinforcing technology
CN107847102A (en) * 2015-08-05 2018-03-27 美利肯公司 The installation of multi-part car mat
CN109281235A (en) * 2018-11-29 2019-01-29 西南交通大学 A kind of volcanic slag railway bed and its process for constructing
CN109797621A (en) * 2019-01-17 2019-05-24 江苏瑞沃建设集团有限公司 A kind of high-strength composite road surface and its construction technology
CN110438862A (en) * 2019-08-22 2019-11-12 长安大学 A kind of assembled Plastic Base Asphalt Pavement structure and its construction technology
CN113463458A (en) * 2021-08-04 2021-10-01 江苏阔景建设工程有限公司 Stable road structure and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112127216B (en) * 2020-09-30 2021-12-03 武汉理工大学 Prefabricated assembly type asphalt substrate type ballastless track and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004031501A1 (en) * 2002-10-01 2004-04-15 Dodge-Regupol, Incorporated Noise and vibration mitigating mat
CN1587526A (en) * 2004-08-30 2005-03-02 邢台路桥建设总公司 New road surface structure layer
CN201372397Y (en) * 2008-10-09 2009-12-30 深圳市海川实业股份有限公司 Permeable road surface structure
CN201722579U (en) * 2010-03-25 2011-01-26 马银华 Waterproof vibration-reducing pavement structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004031501A1 (en) * 2002-10-01 2004-04-15 Dodge-Regupol, Incorporated Noise and vibration mitigating mat
CN1587526A (en) * 2004-08-30 2005-03-02 邢台路桥建设总公司 New road surface structure layer
CN201372397Y (en) * 2008-10-09 2009-12-30 深圳市海川实业股份有限公司 Permeable road surface structure
CN201722579U (en) * 2010-03-25 2011-01-26 马银华 Waterproof vibration-reducing pavement structure

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103541287A (en) * 2013-10-21 2014-01-29 马银华 Pavement structure with comprehensive waterproof reinforced roadbed as well as construction method of pavement structure
CN103556558A (en) * 2013-10-21 2014-02-05 马银华 Pavement construction with hierarchically completely encapsulated roadbed and construction method thereof
CN103556558B (en) * 2013-10-21 2015-06-24 重庆交通大学 Pavement construction with hierarchically completely encapsulated roadbed and construction method thereof
CN104878678A (en) * 2015-06-04 2015-09-02 深圳市华威环保建材有限公司 Construction method for water-permeable and water-retaining water-permeable pavement structure
CN107847102A (en) * 2015-08-05 2018-03-27 美利肯公司 The installation of multi-part car mat
CN105113351A (en) * 2015-08-06 2015-12-02 中国水利水电第六工程局有限公司 Concrete pavement structure in alpine region and construction method thereof
CN105133463A (en) * 2015-10-16 2015-12-09 武汉大学 Permeable pavement structure based on geobag reinforcing technology
CN109281235A (en) * 2018-11-29 2019-01-29 西南交通大学 A kind of volcanic slag railway bed and its process for constructing
CN109797621A (en) * 2019-01-17 2019-05-24 江苏瑞沃建设集团有限公司 A kind of high-strength composite road surface and its construction technology
CN110438862A (en) * 2019-08-22 2019-11-12 长安大学 A kind of assembled Plastic Base Asphalt Pavement structure and its construction technology
CN110438862B (en) * 2019-08-22 2024-03-15 长安大学 Assembled plastic base asphalt pavement structure and construction process thereof
CN113463458A (en) * 2021-08-04 2021-10-01 江苏阔景建设工程有限公司 Stable road structure and construction method thereof

Also Published As

Publication number Publication date
CN101824787B (en) 2012-05-23

Similar Documents

Publication Publication Date Title
CN101831855B (en) Waterproof pavement structure and construction method thereof
CN101824787B (en) Waterproof shock-absorption road surface structure and construction method thereof
CN201722578U (en) Pavement structure provided with water-permeable filter layer on roadbed
CN201722580U (en) Waterproof pavement structure
CN109235179B (en) Drainage-protecting pavement structure for reducing urban heat island effect and construction method thereof
CN201722579U (en) Waterproof vibration-reducing pavement structure
CN108677715B (en) A kind of highway bridge subgrade and pavement and its construction method
CN205368926U (en) Garden way supercrust structure that water permeability is strong
CN103541287B (en) Pavement structure with comprehensive waterproof reinforced roadbed as well as construction method of pavement structure
CN207130558U (en) A kind of roadbed filling structure
CN208649826U (en) The pervious asphalt road of Collapsible Loess District
CN203668784U (en) Subgrade with all-sided waterproof function
CN112746542A (en) Waterproof asphalt pavement structure and construction method thereof
CN113463458A (en) Stable road structure and construction method thereof
CN201258447Y (en) Asphalt concrete pavement water damage prevention composite structure for moist area
CN205171297U (en) Two anti - drainage roadbed structure that strain
CN103556558B (en) Pavement construction with hierarchically completely encapsulated roadbed and construction method thereof
CN208803316U (en) A kind of shallow water position highway waterproof roadbed
CN207749382U (en) A kind of drainage pavement structure in sponge city
CN109972467B (en) Construction waste road cushion layer and pouring method thereof
CN209636588U (en) A kind of inside has the reinforcement subgrade and pavement of geotechnological water-permeable pipe
EP0385971A1 (en) Method for forming road and ground constructions
RU2283910C2 (en) Heat-insulation layer of road structure
CN215164278U (en) Waterproof asphalt pavement structure
CN201103129Y (en) Underlayer structure of red mud tailings reservoir

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHONGQING JIAOTONG UNIV.

Free format text: FORMER OWNER: MA YINHUA

Effective date: 20150813

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150813

Address after: 400074 Chongqing Nan'an District University Avenue, No. 66

Patentee after: CHONGQING JIAOTONG University

Address before: 400074 School of civil engineering and architecture, 66 school Avenue, Nan'an District, Chongqing

Patentee before: Ma Yinhua

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120523